PLANNING & SCHEDULING BYAL-LATIFIA
Mazhar AnwaarSaleh Al-Garni
January 23, 2010
CEM – 510 TERM PROJECT
![Page 2: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/2.jpg)
OUTLINE
Project Objectives
Research Methodology
Contractor Introduction
Project Management System
Planning & Scheduling Techniques
CPM Technique
Monitoring & Control Techniques
Effectiveness of Management Techniques
Conclusions
Q & A
Wrap Up
![Page 3: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/3.jpg)
PROJECT OBJECTIVES
How contractor is doing Planning & Scheduling? Is he following industry accepted methods and procedures? How dynamic P&S for various project phases? How variance is identified against plans? How effectively plans are used to monitor and control the variance?
![Page 4: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/4.jpg)
RESEARCH METHODOLOGY
Brief Interviews
Detailed Interviews
QuestionnaireDevelopment,
Distribution and Collection
![Page 5: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/5.jpg)
CONTRACTOR INTRODUCTION
Al-Latifia Trading and Contracting
Founded: 1987 Headquarter: Riyadh Operations: Throughout the KSA Size: Over 7000 Employees The growth is mainly attributed to its broad project experience and skilled technical resources.
![Page 6: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/6.jpg)
STRENGTHS & DIVERSITY
Kingdom-wide Mobilization
Highly Qualified Professionals
Physical Resources
Fabrication Capability
Project Diversity
![Page 7: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/7.jpg)
Al-Latifia Corporate Structure
Corporate Finance
Accounting and Control
Treasury
Strategy and Performance Mgmt. HR
Legal Council
Communications and PR
Procurement and ContractsPlanning
Cost Control
Project Management
Engineering
Quality Control and HSE
General Manager
Internal Audit
Construction / Operations
Planning and Project Control
FinanceHR and
Administration
IT
Tendering and Estimation
Purchasing and Logistics
Commercial
ORGANIZATIONAL BREAKDOWN STUCTURE
![Page 8: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/8.jpg)
Typical Project Organizational Structure
Quality Supervisors HSE SupervisorsProcurement EngineersPlanning Engineers
Cost Control Engineers
Electrical Lead
Mechanical Lead
Civil Lead
Project Manager
Secretarial Support
Construction Manager
Planning Manager
Quality Manager HSE ManagerProcurement
Manager
Structural Lead
Contract Administrator
IT Support
HSE Engineers
Discipline Engineers
Engineering
Manager
Quality Engineers
Sub -Contractors
ORGANIZATIONAL BREAKDOWN STUCTURE
![Page 9: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/9.jpg)
GOSI Granada SR. 1.54 billion contract – 42 Months Duration A business and residential complex for the General Organization for Social Insurance (GOSI), in Riyadh. The project includes:
• Six high-rise towers• Large underground parking facility• A business center other buildings and amenities.
Saudi Aramco Corporate Data Center SR. 714 Million Contract – 27 Months Duration A strategic project for Saudi Aramco and for the Kingdom of Saudi Arabia. The biggest data center for any producing company Construction of apx. 6000 square metes raised floor divided into four data halls. Complex mechanical & electrical systems.
MAJOR PROJECTS
![Page 10: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/10.jpg)
SOME RECENT PROJECTS
Sofitel Hotel Al-Khobar
Dar Al-Yam Printing Facility
El-Khereiji Office and Commercial Complex:
SABB Regional Offices
![Page 11: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/11.jpg)
PROJECT MANAGEMENT SYSTEM
As per the PMBOK Project Management (PM) is application of knowledge, skills, tools, and techniques to project activities to achieve required objectives.
Al-Latifia planning is divided into two phases: Bid Planning: Done for the bidding of the projects through corporate office Project Planning: Done after the award of the project by the project manager & his team
Al-Latifia project managers and their teams are responsible:
For the development of Project Plans as per the client requirements.
The project plan covers all the aspects of project management including scope, time, cost, resources, quality, HSE, communication and procurement planning.
![Page 12: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/12.jpg)
PLANNING AND SCHEDULING TECHNIQUES Every project plan is to answer the basic questions:
What to be done? Scope Management When it needs to be done? Time ManagementWhat it cost to do? Cost ManagementWho & How will do? Resources Management
Al-Latifia planning and scheduling techniques are more focused around Critical Path Method (CPM) and its requirements.
Our project focus was to study time, cost and resources planning features of Al-Latifia.
![Page 13: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/13.jpg)
WHAT IS CITICAL PATH METHOD?
A PM methodology designed to effectively plan and control a project.
It Offers a structured approach to project planning and control features.
A network analysis technique used to predict project duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility.
![Page 14: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/14.jpg)
CPM TECHNIQUE
Al-Latifia is applying CPM, while utilizing various tools and techniques:
Work Breakdown Structure Network Modeling Durations & Resources Estimation Schedule Development & Analysis Budgeting and Costing
![Page 15: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/15.jpg)
WORK BREAKDOWN STRUCTURE
Breaking the project down into smaller elements.A greater probability that every major and minor activity is accounted for.
Significance Responsibility matrix Costing Risk analysis Organizational structure Control (including contract administration)
Use of typical WBS templates form historical data of previous projects .
![Page 16: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/16.jpg)
16Developed by: ITSU Graphics/PPOD/Project Support & Controls Department
WORK BREAKDOWN STRUCTURE
![Page 17: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/17.jpg)
17Developed by: ITSU Graphics/PPOD/Project Support & Controls Department
WORK BREAKDOWN STRUCTURE
![Page 18: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/18.jpg)
NETWORK MODELING, ESTIMATION OF TIME AND RESOUCRES
Primavera (P3) with PDM network are used for scheduling.
Historical information used for the estimation of activities durations and resources.
Historical productivity records are used to assess the time and resources requirements. Resource leveling is done for the optimization of manpower and equipments (Contradiction)
![Page 19: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/19.jpg)
SCHEDULE DECVELOPMENT & ANALYSIS
Identification of CP and near CPs Verification of Milestones and Project Completion
Dates Baseline schedule submission for approval (Control
Sch.) No specific method used for schedule analysisSignificance: Benchmark the project actual progress against the
plan. Impact of late starts and early starts Trade-offs between resources and time Evaluation of performance
![Page 20: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/20.jpg)
BUDGETING & COSTING
Once a project is awarded to Al-Latifia:
Budget assigned from higher management. Project Manger responsible for Managing and controlling the cost. Assigned Budget = Direct + Indirect + POHs Assigned Budget formulate the basis of control.
Significance :
What is included and what is not included Cash flow plan, with progress payments & overdraft
![Page 21: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/21.jpg)
MONITORING & CONTROL TECHNIQUES
Generally to achieve Control: Cost, schedule, and technical objectives are clearly documented, realistically derived, and deliberately managed.
Type of Controls:
Schedule Control Cost Control
![Page 22: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/22.jpg)
MONITORING & CONTROL TECHNIQUES
Schedule Control
Weekly update of schedules Variance Analysis. Weekly meetings to:
o Monitor the progress o Reasons for variance
Corrective actions Recovery plan implementation
![Page 23: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/23.jpg)
MONITORING & CONTROL TECHNIQUES
Cost Control
Project Budget as Basis of Cost Control Weekly update as per actual Cost Variance Analysis Identification of Variation Causes Corrective actions to Eliminate the variance Recovery plan implementation
![Page 24: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/24.jpg)
EFFECTIVENESS OF MANAGEMENT TECHNIQUES
Structured PM techniques - Enhanced control through WBS Segmenting projects into logical control points Variance tracking - Earned value method
For each project - Variance thresholds
Recovery plan in case it happens.
Utilization of enough time and resources on planning.
Planning & Scheduling - CPM technique utilizing P3 PP
![Page 25: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/25.jpg)
CONCLUSION
System Development Under progress - Implementation of ERP, and ISO Certification.
Al-Latifia is growing at fastest pace and also improving its systems and procedures.
More focused in optimization of project time line and budgets.
Careful planning, vigilant monitoring & controls with simple tools and techniques. (WBS, Schedules, S-Curves, Manpower HG, Procurement Plan etc.)
![Page 26: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/26.jpg)
Q & A
Any Question Please!!
![Page 27: PLANNING & SCHEDULING BY AL-LATIFIA Mazhar Anwaar Saleh Al-Garni January 23, 2010 CEM – 510 TERM PROJECT.](https://reader035.fdocuments.us/reader035/viewer/2022062314/56649da65503460f94a91f78/html5/thumbnails/27.jpg)
Thank You