Planning Research Corporation - Records Collections › work › 03 › 130688.pdfThe Raymark site...
Transcript of Planning Research Corporation - Records Collections › work › 03 › 130688.pdfThe Raymark site...
proPlanning Research Corporation
proPRC Engineering Planning Research CorporationSuns SUO- -==-- — ' ._. ":"'-' "" •••••••"-"'•'-!" : ;— -- — - -j -- .--• - --- - — - - • "~-~— ---"'303 Easi W.acKe? Drive ."."''"_.r:"~ "!!": " " J" ----=••-- ---_ - ; -••• -*-••--Cnioago_ IL..606D1 — _'j;i....L".r_"_"."V..."~": '..."- -••; — 2L1_- T ™ - - _ • ;;•; - "—";::- /
TWX 9 ra;_2"i 51 1.2 . :"Cable -CONTOWENG
RAYMAEK CORPORATION
FOCUSED FEASIBILITY STUDY
FINAL REPORTPrepared for
U.S* ENVIRONMENTAL PROTECTION AGENCYOffice of Waste Programs Enforcement
Washington, D.C. 20460
Work Assignment No.EPA RegionSite No.'Date PreparedContract No.PRC No.Prepared By
Telephone No.
94334783-20-S568-01-7037 '15-0940-93PRC EnvironmentalManagement, Inc.312/938-0300
So [ ,"; n o n I U u o J D
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY - _ _ _ _ _ _ 1
1. INTRODUCTION
1.1 Site Background Information ' 1-1
1,1.1 General 1-1
1.1.2 Raymark Site l-l
1.2 Nature and Extent of Problem 1-2
1.3 Focused Feasibility Study Objectives - 1-6
1.4 Focused Feasibility Study Assumptions 1-7
1.4.1 General Assumptions 1-7
1.4.2 Hydrogeologic Analysis ; - 1-9
1.4.3 Public Health Risk ' 1-10
1.4.4 Environmental Risk Assessment 1-10
1.4.5 Cost Analysis - 1-11
1.4.6 Post Closure, Long Term . - - 1-11Monitoring Plan
2. IDENTIFICATION AND INITIAL SCREENING OFREMEDIAL ACTION TECHNOLOGIES
2.1 General Response Actions 2-1
2.2 Evaluation of Response Actions - - 2-1
2.2.1 No Action 2-1
2.2.2 Capping 2-2
2.2.3 Containment Barrier . 2-2
2.2,4 Groundwater Pumping and Treatment : ^ "2-4
2.2.5 Alternative Water Supply - 2-8
2.3 Results of Response Actions Evaluations - 2-9
2.4 Development of Remedial Alternatives 2-10
i OG.535
3. REMEDIAL ACTION ALTERNATIVES
3.1 General Description of Technologies 3-1
3.2 Remedial Action Alternatives 3-7
4. ANALYSIS OF REMEDIAL ACTION ALTERNATIVES
4.1 Introduction 4-1
4.2 Pumping of Contaminated Groundwater 4-2
4.3 Carbon Adsorption ,., ... 4-17
4.4 Air Stripping -• • ~ •- 4-22
4.5 Surface Water Discharge 4-28
4.6 Reinjection of Treated Water - 4-31
4.7 Closure Plan and Post-Closure 4-42Monitoring Plan
4.8 -Cost Analysis 4-43
4.9 Summary of Alternative Analyses 4-54
5. REFERENCES 5-1
fiRi00337
LIST OF FIGURES
Figure __ _____ . _ _ _ _ _ . _._._.. _ _. . _____ __ _ Pa
1-1 Location Map of Raymark Site, Hatboro Wells, and 1-3Warminster Heights Wells.
1-2 Locations of Sampling Wells (NUS Corp.,' 1985). 1-8
2-1 Groundwater Table Elevation 09/24/82 (after Luborsky, 1984). 2-7
2-2 Flow diagram of Remedial Option Technologies. 2-11
4-1 Drawdown calculations for various distances and times for a 4-8single recovery well. Hydrogeologic conditions are T =12,000 gal/day/ft, 24,000 gal/day/ft and Q 50, 100, 200gpm.
4-2 Aquifer water level configuration at 1,000 days under the 4-9conditions T = 12,000 gal/day/ft, Q = 50 gpm, with arecovery well(s) centered on the Raymark site (10 ftcontour intervals).
4-3 Aquifer water level configuration at 1,000 days under the 4-10conditions T - 24,000 gal/day/ft, Q - 50 gpm, with arecovery well(s) centered on the Raymark site (10 ftcontour intervals).
4-4 Aquifer water level configuration at 1,000 days under the . 4-11conditions T »• 12,000 gal/day/ft, Q = 100 gpm, with arecovery well(s) centered on the Raymark site (10 ftcontour intervals).
4-5 Aquifer water level configuration at 1,000 days under the ... 4-12conditions T « 24,000 gal/day/ft, Q = 100 gpm, with arecovery well(s) centered on the Raymark site (10 ftcontour intervals).
4-6 Aquifer water level configuration at 1,000 days under the 4-13conditions T » 12,000 gal/day/ft, Q « 200 gpm, with arecovery well(s) centered on the Raymark site (10 ftcontour intervals).
4-7 Aquifer water level configuration at 1,000 days under the 4-14conditions T * 24,000 gal/day/ft; Q = 200 gpm, with arecovery well(s) centered on the Raymark site (10 ftcontour intervals).
4-8 Conceptual Flow Diagram for Carbon Adsorption Process. 4-18
4-9 Conceptual Flow Diagram for Air Stripping Process. 4-23
111fifiiOD333
4-10 Aquifer .water level configuration at 1,000 days under the 4-34conditions T = 12,000 gal/day/ft, Q = 50 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located midway between the Raymark site and H-17(10 ft contour intervals).
4-11 Aquifer water level configuration at 1,000 days under the 4-35conditions T = 24,000 gal/day/ft, Q = 50 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located midway between the Raymark site and H-17(10 ft contour intervals).
4-12 Aquifer water level configuration at 1,000 days under the 4-36conditions T = 12,000 gal/day/ft, Q - 100 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located midway between the Raymark site and H-17(10 ft contour intervals).
4-13 Aquifer water,level configuration at 1,000 days under the 4-37conditions T = 24,000 gal/day/ft, Q = 100 gpm, with arecovery well(s) centered on the Raymark site and injectionwel-L(s) located midway between the Raymark site and H-17(10-ft contour intervals).
4-14 Aquifer.water level configuration at 1,000 days under the 4-38conditions T = 12,000 gal/day/ft, Q = 200 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located midway between the Raymark site and H-17(10 .ft contour intervals).
4-15 Aquifer water level configuration at 1,000 days under the 4-39conditions T =-24,000 gal/day/ft, Q - 200 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located midway between the. Raymark site and H-17 (10ft contour intervals).
4-1.6 -Aquifer water level-configuration at 1,000 days under the 4-40conditions T - 12,000 gal/day/ft, Q = 100 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located at Fischer-Porter FP14 (10 ft contourintervals).
4-17 Aqui_fer.iwater level- configuration at 1,000 days under the 4-41conditions T = 24,000 gal/day/ft, Q - 100 gpm, with arecovery well(s) centered on the Raymark site and injectionwell(s) located at Fischer-Porter FP14 (10 ft contourintervals).
D f *i i'1 oh I u u o
LIST OF TABLES
Table __ _ . : . . . . : . . - . - • Pa_1
2-1 Remedial Alternatives 2-12
3-1 Descriptions of Remedial Alternatives 3-8
4-1 Values of hQ-h(ft) for various values of time and 4-6distance from the main pumping well with T = 12000gal/day/ft and Q - 50 gal/min (a), 100 gal/min (b),and 200 gal/min (c) .
4-2 Values of ho-h(ft) for various values of time and 4-7distance from the main pumping well with T = 24000 . .gal/day/ft and Q - 50 gal/min (a), 100 gal/min (b),and 200 gal/min (c).
4-3 Estimated Costs for On-site Groundwater Pumping 4-16
4-4 Carbon Adsorption Process Design.Criteria 4-20
4-5 Estimated Costs for Carbon Adsorption Treatment 4-21
4-6 Summary of Air Stripping Process Design Criteria 4-26
4-7 Estimated Costs for Air Stripping Treatment 4-27
4-8 Estimated Costs for Installation of Discharge 4-jPiping to Culvert
4-9 Estimated Costs for Injection Well 4-33
4-10 Remedial Alternatives Cost Analyses 4-45
4-11 .. . Summary of the Comparison of Alternatives - 4-56
v
Executive Summary _ „___ ....„_„„. .. _, _._ ~-i.. _~~....,,....,.-
The goal ofr this Focused Feasibility Study (FFS) is to review,
describe.and identify those remedial.alternatives that can be
implemented to abate the trichloroethylene (TCE) contamination of
Hatboro Borough's drinking water. The remedial alternatives were
formulated and then evaluated based on their cost-effectiveness
and their ability to meet all applicable environmental, public
health, institutional, and technical requirements. It is not the
intent, of the FFS to recommend a specific remedial alternative
for implementation.
Six general response actions were identified and evaluated. These
remedial actions include the following:
o No action;
o Capping;
o Installing a containment barrier;
o On-site "g'roundwater pumping and treatment;
o Off-site grbundwater pumping and treatment; and
o Providing an alternate drinking water supply.
After initial screening, two response actions were selected for
further considerations: 1) On-site groundwater pumping and
treatment and 2) Off-site groundwater pumping and treatment. On-
site treatment .would be located at the Raymark site. Off-site treat-
ment would be located at the individual contaminated Hatboro
water wells. Hydrogeological data were then evaluated to deter- _ ..
mine.the feasibility of.the pumping/treatment remedial action.
A R i C G 3 ' i _ l
Proven treatment processes were also evaluated to select
appropriate (cost-effective and environmentally sound) treatment
methods.
Carbon adsorption and air stripping were identified as the
treatment technologies best suited for the removal of TCE from -
the contaminated groundwater. The treated Water would then be
either discharged to a surface water body (creek or culvert) or
reinjected into the aquifer.
Based on the selected pumping/treatment response action, ten
remedial alternatives (Table 3-1) were identified. A detailed
analysis was performed on each proposed alternative, based on the
following factors:
o Technical adequacy;
o Environmental and public health impacts;
o Institutional issues; and . .: .
o Costs.
The estimated capital costs and operation and maintenance expenses
for each alternative were computed for comparisons among the ten
alternatives.
[2]
f i R I G C 3 l _ 2
CHAPTER 1
INTRODUCTION
1.1 - - -Site Background Information . . ... . .
l.-l.l -General . ..---„, - - - • •- ,-,——-• - -..—,-..-•—•
In 1979, samples of some of the public drinking water wells in
Hatboro Borough showed concentrations of trichloroethylene (TCE)
as high as 500 micrograms per liter. Subsequently, the Environ-
mental Protection Agency (EPA) began investigations in October,
1979 .into the contamination of the Hatboro Borough, Pennsylvania
water supply by TCE. ":"" ""•-
1.1.2 Rayjnarfc S ite ™ - - : - - • - -
The Raymark site is located on Jacksonville Road in Hatboro
Borough, Montgomery County, Pennsylvania. There is one manufac-
turing building on" the site. - -
The Milford Rivet & Machine Company, a subsidiary of Raymark
Corporation, owned and operated the facility until 1981. In
October 19.81-, Milford sold the property to the Telford Industrial
Development Authority. In November. 1981, Mr. Manuel N. Stamatakis
entered into an Installment Sale Agreement with the Authority to
purchase the facility. The plant is presently leased to Penn
Fasteners for the manufacture of rivets and fasteners.
In the production o.f metal rivets, Milford Rivet utilized a
degreaser. for_. non-porous ferrous and non-ferrous parts. The
1-1 * p t n ~ c-t.H ft i C U o S-
rivets and fasteners were degreased using 30, to 40 gallons per
day of Perm-a-clor, a solvent containing TCE. Milford has indi-
cated that the degreasing system was a closed loop system with
all waste solvent returned to the supplier for reclamation
(Walker, 1979).
Former plant personnel have stated that TCE was stored in outside
above ground tanks and that metal cleaning drums used for the
degreasing operation were located above a concrete pit (Aitken,
1982) .
Aerial photos of the site taken in 1950, 1965 and 1970 showed that
four lagoons were located behind the manufacturing plant. The lagoons
reportedly were used for wastewater neutralization and storage from
1943 to 1972. According to plant personnel, the lagoons were orig-
inally installed with clay liners. It was reported that when the
lagoons were removed from service in 1972, the material above the liner
was excavated and removed from the site, and the lagoons were then
filled with clean material to grade (Betz-Converse-^Murdoch, 1982).
It was reported that, as of 1980, TCE is no longer used on the plant
site ( Wassersug, 1982).
1.2 Nature And Extent Of Problem
The Hatboro Borough drinking water supply wells near the Raymark site
have shown TCE contamination. Figure 1-1 is a map indicating the
relative locations of the Raymark (Penn Fastener) site and the drinking
water wells.
1-2r n • p -, -. -, —H r. ; u o o 4 4
A HATBO.RO WELLS
• OBSERVATION WELLS
• SAMPLING WELLS - .=_-__. - , - _ - - = -
O WARMfNSTER HEIGHTS WELLS . . •-. F1QURE I-3 RAYMARK WELL LOCATION MAP OF RAYMAffK SITE,
HATttftO WCLL3 AND WAftMINSTER HEIGHTS WELLSNOT TO SCALE-.. .__.." . f, , , ^. .- f , I
_________;____________ _________, • ^.- •' , , t • ~_.n—————————————————————-1-3 ————————————————————— Htt i U o u 'f
The following data indicate the maximum concentrations of TCE in
the contaminated water from some of the Hatboro wells (Aitken,
1982 and Gilmore, 1982.)
Name Of Well TCE Concentration (ppb) __ _ _
HI . .-190H2 ' 110K3 38H7 8K12 6H14 297H16 108H17 729
Due to the TCE contamination in the well water supply, the above
eight Eatboro municipal wells were temporarily taken_out of
service in 1979. The TCE concentrations in most of these wells
were significantly higher than the suggested no adverse response
level (SNARL) of 4.5 ppb (U.s'. EPA, 1985), exposing the users of
these Hatboro wells to potential health risks.
Studies conducted on the toxicity of TCE indicate that it
produces liver and kidney damage and central nervous system
disorder in mammals. Other studies have reported that TCE has
carcinogenic and mutagenic characteristics? hence decontamination
of groundwater is necessary to protect the health of Hatboro's
residents. The following computed excess lifetime cancer risks
from the National Academy of Science Model.are based on assuming a
human drinking 2 liters of TCE contaminated water per day for seventy
years (U.S. EPA, 1985):
1-4r D'T ="- - ' • • • /•* n i u u c •>_ b
TCE Concentration p __ . . .Excess Risk
4.5 ppb -one excess cancer per millionpersons
45 ppb . " . ten excess cancers per millionpersons
75 ppb _ " . approximately twenty excess cancersper million persons.
Although Milford Rivet & Machine Co.'claimed that the degreasing
system utilizing TCE was a closed loop system, the presence of
TCE in the soil on the Raymark site and in the groundwater under
the site, has been established and documented. The soil analyses
performed by Betz - Converse --Murdoch, Inc. (BCM) (1982)
indicated the following TCE concentrations:
Quantity of TCESample.No. .-. -: Depth Col-lected (ft) .(micrograms/kilogram)
1A — -----—- - " - - " - - - - 3 - ' ' 640IB - - 9 . .___ 502A . .:...-- ~-3 .- ; . <52B - - ..—--—. - - - - - - - - - 7 " ' - - - - - i:i3 6 200
Samples 1A and IB were taken next to the production building at
the site of the former above ground TCE storage tanks. Samples
2A- and 2B were taken behind the waste treatment plant where
the waste holding/neutralization lagoons were located. Sample
No. 3 was taken near EPA well (No. 10).
The BCM report speculated that soil contamination was due to
"occasional minor spills or splashing during the filling of the
above - ground tanks and washing of the material downward by
subsequent__precipitation." The report also identified the possi-
X""3 p- r\ ; <•". ~. ,— f —,
Afi i U U O H ?
bility of "some carry-over of TCE to the holding or neutraliza-
tion lagoons".
In the fall of 1984, five sampling wells (R1-R5) were installed
by EPA west and northwest of the Raymark site (NUS, 1985).
Samples collected from the sampling wells and Raymark_._well (PF1)
on October 29, 30, and 31, 1984, indicate a maximum TCE concen-
tration in groundwater of 4100 ppb (Figure 1-2) . The data also
indicate that the direction of the contaminated groundwater flow
is from the Raymark site towards the Hatboro water.wells HI, H2,
H3, H7 and H17 (See Section 2.2.4 for further discussion).
Hatboro Borough has installed air stripping equipment on two of
their water wells (H12 and H17). Construction is underway to
install an air-stripper on another water well (H14).
1.3 Focused Feasibility Study Objectives
The Focused Feasibility Study (FFS) addresses several proven
remedial measures that may be implemented tb safeguard the
residents utilizing the Hatboro well system,against human health
threats posed by TCE in the drinking water supply.
The study objectives were developed in consultation with the U.S.
EPA and form the basis of this report. The study objectives are
as follows:
o Based on review of existing data from EPA, develop andscreen response actions;
o Develop and analyze remedial alternatives; and
1-6. -*1 " •"' * ni u u 0 *r O
o Review remedial alternatives with respect tocost and non-cost considerations.
The technical development and review of the remedial action
alternatives will focus on those alternatives which have been
successfully implemented at other sites.
1.4 Focused Feasibility Study Assumptions
To complete the development and analysis of remedial action
alternatives for the Raymark site, the following assumptions were
madd and- utilized.
•, _ _ — _ .1.4.1 .-"""": - General Assumptions
1. The Raymark site will continue to be used for industrial
purposes.
2. PRC has been provided with all existing and accurate site
analytical data.
3. Groundwater treatment facilities can be installed on the
Raymark site.
4. An injection well can be installed midway between the Raymark
site and Hatboro"well H17.
5. Regulatory agencies will, have access to the site.
1-7r. n ; /-. .-.AR! 0001*9
rgI
inCO
fr0uw
1-8AH i uOotxQ
1.4.2 Hydrogeologic Analysis Assumptions
1. The hydrogeologic conditions such as the potentiometrie
level in the aquifer and flow directions are as described
in Luborsky (1984).
2. The groundwater system in the vicinity of the Raymark site
can be considered to be approximately in a steady .state
condition; i.e., groundwater withdrawals are approximately
balanced by infiltration recharge. This assumption
effectively means that the drawdowns produced by the Hatboro
wells are constant.
3. For calculation purposes, the groundwater system is under
confined, infinite aquifer conditions; i.e., the assumptions
inherent .in..the development of the Theis (1935) non-
equilibrium equation are applicable. For practical pur-
poses and scoping calculations, this assumption simply means*that the storage coefficient or storativity of the aquifer
utilized-in the calculations is on the order of 10~4.
Although the resultant calculated response is equivalent to
that of a confined aquifer, it is recognized that portions
of the aquifer., may well be under water table conditions (as
interpreted and discussed by Luborsky, 1984). The storage
coefficients of 10~4 to 10~5 reported from pumping tests in
the aquifer (Rima et al. 1962) may reflect the influence and
significance of fracturing in the aquifer, (resulting in a -
A R i U U 3 5 1
relatively low interpreted storativity particularly during
.early-time test data analyses). A storage coefficient of
this magnitude is consistent with measurable drawdowns/
radius of influences of approximately 2500 feet (Sloto and
Davis, 1983).
1.4.3 Public Health Risk Assumptions
1. During implementation of the remedial action, workers and
the general public will have access to the site.
2. New drinking water wells will not be constructed between
Raymark Site and the existing Hatboro water, wells.
3. The air strippers which were designed by Gilmore &
Associates to treat the contaminated water from the
Hatboro wells can achieve an effluent TCE concentration of
4.5 ppb or less.
4. The maxiumum TCE level in the contaminated groundwater under
the site is 4100 ppb.
5. The desired treatment level for TCE in groundwater is 4.5
ppb.
1.4.4 Environmental Risk Assessment Assumptions
1. Pumping.of groundwater will be permitted.
2. Relocation of nearby residents will not be required.
3. The Raymark site is situated in an industrial area and
there are no endangered species present.
1-10AR 1 GO 352 :
4. There are no wildlife sanctuaries in the area.
5. There are no vulnerable ecosystems in the area.
6. ..: Commercial "resources around the site will not be affected.
7. Historical or .archaeological resources will not be
affected. - - - - - -— -
8. The groundwater will remain-contaminated under the no action
alternative even though two air-strippers are in operation and
another is under construction to treat the contaminated well
water at these Hatboro wellheads (H12, H14 and H17).
1.4.5 ~-":=" Cost Analysis Assumptions
1. The lifetime/operation of the treatment facilities is 15
years; the facilities can be financed at a discount rate of
10 percent.
2. The cost estimates prepared by Gilmore & Associates, Inc.
for the off-site air strippers at Hatboro contaminated water
wells are accurate.
1.4.6 Post Closure, Long-Term Monitoring PlanAssumptions
1. - Implementation of the recommended remedial alternative will
proceed on-site for a period, of 15 years.
2. Site inspections and sampling will continue for a period of
30 years. - :
UK i U U J 0
CHAPTER 2
IDENTIFICATION AND INITIAL SCREENING OF REMEDIALACTION TECHNOLOGIES
2-1 General Response Actions
The following general response actions were identified based on
the information available for the Raymark site:
o No action;
o Capping;
o Containment barrier;
o Groundwater pumping/treatment on-site;
o Groundwater pumping/treatment off-site; and
o Alternative drinking water supply.
2-2 Evaluation of Response Actions
2.2.1 No Action
The no action option is not an acceptable alternative since the .
main objective of remedial action is to decontaminate the
groundwater. This option, however, is included in the above
general response action list as a baseline for subsequent
comparisons. The endangerment assessment conducted by EPA
concluded that if no action is taken, there is imminent and
substantial endangerment to the public (Luborsky and Molholt,
19S5). Thus, the no action option is an unacceptable alternative
2-1 - - _ : . . . _ : _ .A R I 0 U 3 5
2.2.2 -Capping ~ . _ "... _ _ _ _ _ _ _ _ _ _ _ - _
Capping a site, is an effective procedure for reducing infiltra-
tion of precipitation into the unsaturated soil region thereby
reducing further off-site migration of TCE contamination. Since
the soil at the Raymark. site is contaminated with TCE, capping
the site may be beneficial. Capping can effectively be achieved
by covering the native., site soil with either clay, synthetic
membranes, asphalt, concrete or other,impermeable materials.
Assuming that the soil is not capped and the groundwater is being
pumped and treated, both infiltration and planned watering of the
surface could enhance migration of TCE into the saturated zone
where it can be -intercepted and treated. Alternately, if the
soil is capped and the groundwater is being pumped and treated,
the TCE already in the soil could remain bound in the soil matrix
indefinitely and. may be a perpetual source of groundwater supply
contamination. More importantly, however, the Raymark site is
currently used for industrial activities and would continue to be
used as such; hence, soil capping would only hinder future activ-
ities at the site. Therefore, soil capping is not deemed to be
an adequate option for.achieving the'FFS objectives and will not
be considered further.
2.2.3 Containment Barrier . :
Containment barriers are generally used to prevent further migration
or flow of contaminated groundwater to undesired zones. These
barriers can be placed downgradient, upgradient or in a circum-
2-2 -
ferential manner. Materials and construction options include
soil-bentonite slurry walls, cement-bentonite slurry walls,
vibrated beam cut-off walls, grout curtains and steel sheet
piling. The feasibility of this option depends on the areal
extent and depth of contamination, and on the geology of the area.
Groundwater analyses (see Figure 1-2) show that TCE has already
contaminated a relatively large area; hence, use of containment
barriers may not be effective at this time.• Moreover, use of a
barrier does not eliminate the possibility of contaminant leaks
due to barrier failure or other unpredictable factors during the
implementation process. More importantly, the depth of contami-
nated ground water (at least 300 feet below ground surface) arid
geologic conditions (arkosic sandstone) eliminate the possibility
of slurry trenches, vibrated beam cut off walls, plasticized
concrete and chemical admixes due to high costs and technical
infeasibility. (The maximum depth of emplacement of any of the
above is less than 100 feet.)
The area immediately beneath the site would require, intensive
hydrogeologic investigation to identify structure or fracture
zones similar to those postulated by Satterthwaite Associates
(1931) and SMC-Martin (1980). The postulated -(op. cit.) fracture
zones are associated with the highest transmissivities in the
aquifer and appear to provide interwell connections between some
of the Hatboro wells. These fracture zones would need to be
grouted in order to reduce the permeability in these preferred
flow zones. The hydrogeologic, geophysical and geologic investi-
A K i 0 0 3 5 6
gations necessary to identify these.zones and the confirmatory
testing and monitoring ..necessary to evaluate the grouting's
effectiveness are not considered to be cost effective. In addition,
the. reliability and degree of certainty associated with such
investigations is not high. Therefore, containment barriers have
been eliminated from further consideration.
2.2.4 Groundwater Pumping and Treatment
Groundwater pumping and treatment involves conveyance of the
contaminated groundwater to the surface followed by removal of
TCE to a desired level. Pumping could be performed on-site at
Raymark site and/or off-site at Hatboro water wells, depending
on the affected area. The treated (decontaminated) water may be
relnjected into the aquifer, discharged to a surface water body,
or utilized in a pub'lic water system.
The decision for interception, withdrawal and subsequent treat-
ment of groundwater depends mainly on the concentration and
toxicity of the pollutant and direction of groundwater flow.
Assessment of the hydrogeologic system based on historical water
well records (Luborsky, 1984) and examination of local topography
as a further indication of the configuration of the water table
indicate that from about 1954 to 1969, the general direction of :
groundwater flow from the Raymark site has been toward the west-
southwest and Hatboro municipal wells HI, H2, H3 and H7. In
1969, Hatboro well H17 was drilled. Pumping in Hatboro well H17
has caused drawdown in Hatboro wells HI, H2, and H3, suggesting
2-4 ARS00357
that groundwater flow from the Raymark site has also developed a
significant northwesterly component of.flow toward H17 due to
the installation and pumping of H17. Analysis of groundwater for
TCE has shown concentrations in excess of 4,000 ppb (Dreish,
1984) between the Raymark site and the Hartboro wells. Since it
has been demonstrated that TCE is toxic (Luborsky and Molholt,
1985), the groundwater must be decontaminated or an alternative
water supply must be located.
Pumping groundwater creates a cone of depression (drawdown)
around the point of withdrawal; hence, groundwater will flow
toward the point of pumping. As groundwater is removed from the
aquifer, it can subsequently be decontaminated. Pumping and
removal of contaminated water beneath the site is technologically
feasible and reliable. It may also control contaminant migra-
tion. However, the relative effectiveness of. such pumping is
highly dependent on the transmissivity of the aquifer beneath the
site. If sufficiently high transmissivity is not present beneath
the site, the relative effectiveness, in terms of the areal
extent of the remedial pumping, will be affected. A discussion
of th* relative effectiveness of pumping under various transmiss-
ivity conditions and pumping rates is provided in Chapter 4.
A review of the available data was conducted in order to deter-
mine the feasibility and effectiveness of on-site groundwater
pumping and treatment as a remedial alternative at the Raymarksite. Technical reports reviewed included Satterthwaite Associ-
2-5 AR I 00358
ates Inc. (1981), Luborsky (1984), Sloto and Davis (1983), SMC-
Martin (1980), Greenman (1955), Hall (1934), and Rima, et.
al. (1962). Based on a technical review of the above reports,r
the groundwater flow regime as presented in Luborsky (1984) is
considered representative of the site conditions.
Based on the available data, groundwater from beneath the
Raymark site flows"primarily in a northwesterly direction
towards the pumping Hatboro well H17. The strong influence of
pumping from Hatboro well H17 is evidenced on the groundwater
table contour map (Figure 2-1) from Luborsky (1984). It is clear
from the directions of groundwater flow on the contour map that
contaminated groundwater from beneath the Raymark Site will enter
the Hatboro well H17 under the assumption that H17 continues to
pump at the rate,which results in the drawdown cone shown on
Figure 2-1. One remedial measure that may eliminate groundwater
contaminant movement from beneath the Raymark Site to the Hatboro
municipal wells is to recover and treat the contaminated ground-
water on-site. - - -- —- - - - - -
It is-possible that the .recovery well(s) installed on the Raymark
site may not be capable of creating a sufficient drawdown
influence to reduce substantially the amount of TCE contamination
that would eventually reach Hatboro. well H17. If the extent of
influence of the on-site recovery system is limited due to low
transmissivity, it may possibly be advantageous to install
injection well(s), using the pumped and treated water from the
2-6aft i n ,~i *"* r" nn I QJo59
LEGEND* 0 RAYMARK SITE SCALEWATER DRAtNAGE .(xx 200O FEET200 WTER level ELECTION _
« HATBORO HELL CONTOUR KTERVAL* »0
FIGURE 2-1: Groundwater Table Elevation 09/24/82 (afterLuborsky, 1984).
2-7 ARi'30360
recovery wells as a hydraulic barrier between the Raymark site
and the nearest .Hatboro municipal wells (H17 and H16) in order to
enhance the area of-influence of the recovery wells. These
alternatives - are discussed in detail in Chapter 4.
The available treatment technologies for removal of volatile organic
compounds from groundwater include reverse osmosis, aeration and
carbon adsorption. Treatment by reverse osmosis and similar
technologies have been tested. The results indicate that these
technologies are .not reliable and have difficulty obtaining a
high removal efficiency (Morris and Donovan, 1983). Currently,
carbon adsorption and aeration are the two most widely used
technologies.for the removal of organic chemicals (O'Brien and
Stenzel, 1984). In addition, the aeration system has proved to
be a reliable-and cost effective technology for the removal of
volatile organic compounds from contaminated water (McCarty,
1983). Since aeration and carbon adsorption are proven methods
for removing volatile organic-compounds from contaminated water,
these-two treatment technologies will be fully discussed and
evaluated in Chapter 3. -
2.2.5- Alternative Water Supply
Providing an alternative drinking water supply for residents that
normally obtain :their water from the contaminated wells is
another option to prevent, any further health risk to the general
public. ___When "TCE was discovered in eight of the Hatboro
municipal wells in 1979, the Hatboro Water Authority stopped-
2~5 A R i O G S B i
using the affected wells and built an interconnecting pipeline to
the Philadelphia Suburban Water Company (PSWC) for conveying
water to Hatboro when the water production from the other
uncontaminated Hatboro wells could not meet the demand. However,
this action would force the Authority to depend on PSWC for an
adequate water supply. The Hatboro Water Authority does not want
to lose its independent status in supplying water to. the general
population in the Hatboro Borough. Therefore, this is not an
acceptable option and has been eliminated from further consideration.
2.3 Results Of Response Actions Evaluations
Based on the evaluation of the six identified response actions,
the following conclusions have been reached.
1. No action is an unacceptable response action.
2. Capping the site will not solve the problem of ground-
water contamination and may hinder future use of the area.
3. A containment barrier is not viable at this .time since
the drinking water supply has already been contaminated. The
geologic conditions under the site precludes the effective use of
a containment barrier.
4. Provision of an alternate drinking water supply is
eliminated from consideration because Hatboro Water Authority
does not want to lose its independent status in supplying water.
2—9 P M i • • ' • r oA lil u u o 6 2
5. "Groundwater pumping and treatment, on-site and/or
off-site, is essential for the protection of the public health
and the environment.
2.4 Development Of Remedial Alternatives
Figure 2-2 presents the remedial option technologies appropriate
for consideration. For the treatment system on the Raymark site,
the contaminated groundwater could be treated by aeration, carbon
adsorption, or a combination of the two technologies. The treated
water could either be discharged into a suitable surface-water
body -or be relnjected into the ground. For the treatment units
at the Hatboro water wells, the Hatboro Water Authority has
selected aeration as the preferred technology for treating the
contaminated water from the Hatboro wells. Air-strippers have
already.been installed at wells H12 and H14, and an air-stripper
is being installed at well H17.
A review of. these options and their various combinations resulted
in the identification of eleven remedial alternatives, including
the no action alternative. These alternatives, which will
undergo a .detailed analysis in Chapter 4, are summarized in Table2-1. - r " --=--"- • • - - - - - - - - -
. ^ r _i U U 0 0 J
GROUND WATER PUMPING
ON-SITE
AERATION
OFF-SITE
CARBON
ADSORPTION
AERATION
AND CARBON
ADSORPTION
DISCHARGETO
SURFACEWATER
AERATION
REINJECT INTO
GROUND
DISCHARGETO
EXISTINGWATERSYSTEM
Figure 2-2: Flow diagram of Remedial Option Technologies
2-11
r D T - , x £ LH U i U w U -t
TABLE 2-1 -REMEDIAL ALTERNATIVES
Number • ----- ' - -—- =:--~ ------ "•=-""-- Description
1 No action.
2 - Pump out,groundwater on-site, treat by aerationand discharge to" a. surface water.
3 Pump out groundwater on-site/ treat by aerationand reinject into the aquifer.
4 Pump out groundwater off-site, treat by aerationand discharge to the existing water distributionsystem.
5 - Pump outTgrouhdwaten on-site and off-site, treatby aeration and discharge to. a surface water andthe. existing water,distribution system, respectively.
6 - -"- ""~~ "~Pump~r out groundwater on-site and off-site, treatby aeration and reinject into the aquifer anddischarge to the existing water distribution sys-tem, respectively. ~
7 Pump out groundwater on-site, treat by carbonadsorption and discharge to a surface water.
8 Pump out groundwater on-site, treat by carbonadsorption and reinject into the aquifer.
9 Pump out groundwater on-site, treat by carbonadsorption and discharge to a surface water. Pumpout groundwater off-site, treat by aeration anddischarge to the existing water distribution system.
10 " ~"~ Pump out groundwater on-site, treat by carbonadsorption and reinject into the aquifer. Pumpout groundwater off-site, treat by aeration anddischarge to the existing water distribution system.
11 Pump out groundwater on-site and off-site,treat by aeration and carbon adsorption, anddischarge the on-site treated water to a surfacewater or reinject into the aquifer. The effluentfrom the off-site treatment will be dischargedinto the existing water distribution system.
2-12 . ,' p | ft i; 355- •-> *-• u w
CHAPTER 3
REMEDIAL ACTION ALTERNATIVES
3.1 General Description of Technologies •_ _ _ . . „ _ _
In Chapter 2, remedial alternatives for decontaminating the
groundwater at the Raymark site were presented. In this chapter,
a brief discussion of the technologies and a more detailed
description of the alternatives will be presented.
Irrespective of the alternative, the .first task calls for pumping
the contaminated groundwater out of the aquifer. This can be done
on-site, off-site or at both locations. On-site interception,
pumping and treatment of groundwater is necessary to curtail the
migration of contaminated water towards the drinking water wells at
Hatboro. Off-site pumping and treatment is necessary to decontami-
nate the groundwater and should protect the general public served
-by the Hatboro Borough Water Authority from consuming contaminated
water.
On-site and off-site pumping refers to the removal of
contaminated groundwater using wells installed specifically for
the purpose of pumping. Pumping of.groundwater creates a cone of
depression around the withdrawal point. Groundwater will flow
toward this cone of depression which, under favorable hydrogeolo-
gical conditions, will include the contaminated area around the
cone of depression. Further migration of.the contaminant to
uncontaminated zones can then be minimized. Periodic water
sampling and analysis would provide data on the concentration of
3-1 A R I G Q 3 5 6
the contaminant in the groundwater over time. However, the TCE
concentration observed in the pumped water may not be representa-
tive of the TCE concentration which would occur in the ground-
water under non-pumping conditions. Therefore, simple monitoring
of pumped water and cessation of pumping after predetermined
concentrations are achieved, may not be an adequate approach for
setting the criteria to stop pumping. The uncertainties with
this approach are partially attributable to the current inade-
quate understanding of the hydrogeochemical controls on organic
chemical migration in groundwater systems. A partitioning of.
virtually all- organic contaminants between the solid phase (i.e. ,
aquifer ..materials such as sand, silt, organic matter, etc.) and
the liquid phase (i.e. , the flowing groundwater) is usually
encountered-in any groundwater system.. This partitioning is
described in its simplest form in; terms of a partitioning coefficient
which, in the case of.organic chemicals, appears to exhibit a
relatively._str_o_ng relationship to the organic content of the
solid material (Schwarzenbach and Westall, 1981). The
partitioning coefficient"describes the equilibrium sorption and
desorption of the contaminant, under the assumption that local
equilibrium between solid and liquid phases is maintained at all
times. However, if the groundwater is flowing relatively quickly
(e.g., under pumping conditions), the equilibrium rate of
desorption (or transfer from the solid to the.liquid phase) may
be too slow to accommodate the rate of groundwater movement past
the sorption sites. Therefore, under pumping conditions, it may
"appear" .that the aquifer._is "decontaminated" based -on the
groundwater chemical analyses, when in fact, if the pumping
3-2 - A R i G u
ceased and the rate of water movement were reduced, the concen-
tration of the contaminant in the groundwater would increase
again, due solely to the kinetics of the desorption mechanisms.
These factors should be considered and quantitatively
evaluated in the development of decontamination or "cease
pumping" criteria. Continued periodic pumping and sampling is
recommended in section 4.7.
As stated in Chapter 2, aeration (air stripping) and carbon
adsorption are suitable for the removal of brganics, in general,
and volatile organics, in particular. Air stripping of volatile
organic compounds from water is achieved by bringing the water
and air into intimate contact. The different types of aeration
systems suitable for air stripping include diffused aeration,
mechanical aeration, spray tower, trayed tower, and packed tower
(countercurrent flow and cross flow). As contact is made between
the air and water, the volatile organic compound in the water is
transferred to the air and thus, is removed from the water. The
removal rate depends on the rate of transfer of the volatile
organic from the liquid to the gaseous phase. This is a function
of the diffusion coefficient of the material being air stripped.
Other factors which influence this change of phases include the
air to water ratio and the Henry's law constant.
Henry's law constant (H) is the proportionality constant between
the amount of a volatile substance in the gas phase above a liquid
and the amount of the substance dissolved in the liquid at equili-
3-3f f-\ • t-s F~ i" -/*" OA K I U U u 0 O
brium and at a given temperature., Thus, if the partial pressure of
the gas and the concentration in the liquid phase are expressed in
the same unit (e.g., mg/m3), Henry's law constant will be
dimensionless. Henry's .law. constant for TCE at 20°C is approx-
imately 0.42 (McCarty, 1983).
In general^ "the higher the Henry's law constant, the higher the
tendency for the volatile organic compound to move from the
liquid phase into the gaseous phase.
The countercurrent packed tower is generally used for removal of
volatile"organics from contaminated water because it is the most
efficient configuration for mass transfer (McCarty, 1983).
Therefore, only this contacting scheme will be considered
further. The countercurrent packed tower employs a column filled
with a set of packing materials such as rashig rings, berl
saddles, intalox saddles, pall rings or other durable packing
material that will increase the area of contact, between the air
and water. As water flows down the column, air will rise up in
the tower and the .volatile organic compound will be stripped
from the water and transferred into the air stream, resulting in
the decontamination of the water. Air to water.ratio, tower
height and diameter of the column can be selected to achieve the
desired contaminant removal level.
Carbon adsorption has also proved to be a suitable technology for the
removal of organic compounds from water and wastewater. The
efficiency of this process, like many other mass transfer opera-
T — 4. f r~, i "•• - ~ • r~ ,~iM K i U o o o 9
tions, depends on the contaminant/adsorbant equilibrium relation-
ship, mass transfer rate and contact time. Generally, a
packed column is used to provide intimate contact between the
contaminanted water and the carbon media. The process of adsorption
occurs when the contaminant in the water .migrates and is adsorbed
onto the carbon. As such, the properties of both the
contaminated water and carbon influence the mass transfer rate.
The mass transfer rate in general, is controlled by the mass
transfer resistance in the liquid phase (water) and solid phase
(carbon). The extent of adsorption is controlled by the
equilibrium relationship between the contaminant and the carbon.
The equilibrium relationship can readily be used to esti-
mate the quantity of carbon needed for a given treatment level.
As the water flows through a carbon column, adsorption occurs,
removing the targeted contaminants from the water. As the
contaminants are removed, the removal capacity of the carbon is
reduced. As this process continues, the carbon reaches a
saturation point and one or more of the contaminants start to
break through. When the treatment efficiency is reduced to an
unacceptable level, the column can then be removed from service
and the carbon regenerated for the next operating cycle.. Carbon
columns can be arranged in series or in parallel. When two or ...
more column are used in series, the first column can be used
beyond the breakpoint concentration because the second column will
then operate as the primary treatment unit., Sampling between the
columns will indicate when the carbon in the first column is
3-5
flftiOUo/0
approaching exhaustion..., JWith a .suitable piping arrange-
ment, each of the carbon columns can alternate as the lead
column, allowing one or more of the columns to be in use while
the exhausted column is undergoing regeneration. A furnace is
normally utilized for carbon regeneration. If thermal regenera-
tion is judged to be inappropriate due to- the possibility of ... . ..
generating air emissions in violation of the Clean Air Act, the .
spent carbon, can be disposed of in a-landfill.
Recently, a pilot treatment system using carbon adsorption
followed by aeration (induced draft stripper) was used to remove
volatile organic "compounds from contaminated water (O'Brien and
Stenzel, 1984). Since this type of treatment system has not yet
been fully developed and evaluated, it is eliminated from further
consideration.
After., the groundwater is decontaminated, the next step is the
disposal of the treated., water. The on-site decontaminated water
can either, be discharged to a surface water or reinjected into
the ground. Discharge to surface water depends on the treatment
level selected and,.access "to a suitable surface water body. If
the decontaminated water is disposed off-site, this action must
be in compliance with Pennsylvania's .environmental laws. A National
Pollutant Discharge Elimination System (NPDES) permit will be
required for off-site disposal to a surface water.
3-6A R I 0 0 3 7 I
Reinjection of the decontaminated groundwater can be considered
when (1) it improves the overall treatment strategy, (2) there is
no surface water near the site, and, (3) the treated water cannot
be reused in a manufacturing process. This option involves
construction of injection wells. The feasibility of reinjection
depends on site hydrogeologic conditions and the associated
costs.
3.2 Remedial Action Alternatives
Tables 3-1 lists the alternatives developed in Chapter 2 and
provides a brief description for each alternative. The alterna-
tive numbers correspond to those in Table 2-1. Alternative 11 has
been eliminated from further consideration since the treatment
technology is still in the development stage. In the next chap-*
ter, a detailed analysis of the remaining alternatives will be
presented.
3-7
ARS00372
TABLE 3-1DESCRIPTIONS OF REMEDIAL ALTERNATIVES
Alternative Number ~"T Description
The no action alternative calls for doing nothingabout the problem. This option is included toto provide a baseline condition for comparisonwith the developed remedial alternatives.
The second alternative requires pumping out thegroundwater on-site and treatment by an aerationsystem. The treated water is "then discharged to asurface water.
In "the third alternative, the groundwater that ispumped out on-site is treated by aeration.However, instead of discharging to a surfacewater, the treated water is reinjected off-siteinto the aquifer. '
This alternative calls for pumping the groundwateroff-site at the Hatboro wells and providingaeration treatment with subsequent discharge tothe. existing water distribution system.
"Alternative five calls for treatment of thegroundwater both on-site and off-site. Thisrequires pumping followed by aeration treatment.The on-site and off-site treated water volumes arethen discharged to a surface water and the exis-ting water distribution system, respectively.
Unlike alternative .five, the on-site treatedwater is reinjected into the ground, while thetreated water from the off-site treatment isdischarged to the existing water distributionsystem. At both sites, aeration constitutes themethod of treatment process to be applied.
Alternative seven requires on-site pumping ofgroundwater followed by carbon adsorptiontreatment. The treated water is then dischargedto a surface water.
Alternative eight is similar to alternative sevenexcept that the treated water is reinjected intothe aquifer.
flR 100373
9 In alternative nine, groundwater is pumped out on-site and off-site. Pumping on-site is followed bytreatment by activated carbon and the treatedwater is discharged to a surface water. Thecontaminated water from the off-site wells istreated by aeration and then discharged to theexisting water distribution system.
10 In this alternative, groundwater is pumped outon-site and off-site and is treated separatelyby carbon adsorption and aeration, respectively.Following treatment, the on-site treated water isinjected into the aquifer while the off-sitetreated water is discharged into the existing waterdistribution system. '
3-9 A R I 0 0 3 7
CHAPTER 4
ANALYSIS OF REMEDIAL ACTION ALTERNATIVES
4.1 Introduction,, . : . _J,i~J,.,. :..J.-. -.. -.,,-*^.-,--- -----
This chapter,presents a detailed analysis of the ten remedial
action alternatives described in Chapter 3. Each alternative is
examined with .regard to technical feasibility, environmental and
public health impacts, institutional requirements, and costs.
The no action alternative is presented as a baseline for compar-
ison with the other .nine alternatives.
With the exception of the no action alternative, each remaining
alternative is composed of .three or more .of the following
remedial action technologies:
o Pumping of groundwater;
o Air.stripping;
o Carbon adsorption;
o' Surface water discharge; and
o ..-injection well disposal of treated groundwater.
As described in Chapters 2 and 3, these treatment technologies
were selected based on each technology's respective abilities to
meet the remedial-action objective; i.e., the abatement of TCE
contamination in the Hatboro underground municipal drinking
water, supply. . . . . . . - - •• --~-
This chapter ..is- organized in nine sections. The first six sect-
ions provide detailed descriptive evaluations of the respective
4-1 ARi00375
treatment technologies. Each evaluation identifies and considers
the adverse and beneficial effects of each technology. The
technical adequacy, relative potential for protection of the
environment and public health, and the institutional effects are
determined and examined. Estimated costs for the construction
and operation of an integrated treatment/disposal system are also
provided. -
Following the six descriptive evaluations, a section is provided
on the estimated costs for each of the nine remedial alterna-
tives. Since each alternative is a combination of several _____ _____
remedial action technologies, the costs previously developed for
the individual treatment technologies were .appropriately combined
to determine the costs for implementing each, alternative.
The last section of the chapter includes a:summary table delinea-
ting the cost information in present-worth, dollars for each
remedial action alternative, as well as the significant impacts
and issues of each remedial action alternative for.comparison.
4.2 Pumping of Contaminated Groundwater
The relative effectiveness of the groundwater recovery .scheme at
the Raymark site is dependent primarily on the transmissivity of
the Stockton aquifer beneath the site and the transmissivity
between the site and Hatboro pumping wells H16 and H17. Wells
H16 and H17 are the two municipal wells which are most directly
affected by contaminated groundwater from beneath the Raymark
site, under the present conditions.&R100376
4-2
It was assumed for calculation purposes that the transmissivity
of the stockton aguifer .was in the 12,000 to 24,000 gallons per
day per-foot (gpd/ft) range (Luborsky, 1984). Sloto and Davis
(1983) report a "radius of influence" of water supply wells of
2,500 feet. A conservative maximum radius -of influence of 2,000
feet was chosen for the following calculations. Given an aquifer
with the above hydraulic characteristics, effective long-term
pumping rates (of one recovery well or the combination of several
wells) on the order of 50 to 200 gallons per minute (gpm) were
assumed. (An effective pumping rate refers to the long-term
average pumping of, one or more recovery wells; i.e., 12 hours
pumping at 200 gpm, followed by 12 hours recovery, followed by 12
hours pumping at 200..gpm, -yields an effective long-term pumping
rate of 100 gpm). For .illustration purposes, a single recovery
well installed at the Raymark site was assumed.
A matrix of time and distance drawdown calculations was
performed, based on the.premise that the assumptions inherent in
the development of the Theis (1935) non-equilibrium equation for
transient groundwater flow are applicable. Given the available
data, the premise is essentially substantiated, with the excep-
tion of major fractures or fracture zones. If a major fracture
zone does exist between the Raymark site and well H17 the
following'"would need to be addressed:
o Is it p.ossible to utilize existing-hydraulic or chemical
data to establish, the existence of a major fracture zone
and, if so, to establish the likelihood of an
4~3 flR!G0377
interconnection to the Hatboro wells?
o Is the fracture zone highly permeable and does it provide
direct connection to the pumping municipal wells?
o Would it be possible to utilize the fracture zone as a
"collector" zone, essentially creating a major hydraulic
influence by pumping the fracture and effectively reducing
the impact of the contamination from the Raymark site on
the Municipal wells?
The existing chemical data (i.e. TCE concentrations in wells Rl
through R5, H2, FP13, and PF1) shown on Figure 1-2 suggest that
the TCE contamination is relatively widespread between Rl and R5-
along the railroad right of way. There does not appear to be
any positive indication, from these chemical data and from the
attempted pumping of these wells (which provided relatively low
yields), of the existence of a significant or .permeable fracture
- related feature in this area. If a fracture zone is encountered
at the site or between the site and the pumping wells, further
more detailed evaluation will -be necessary. The matrix of
drawdown calculations utilize the following input.
Transmissiviti.es (gal/day/ft) = 12,000 and 24,000Storage coefficient = 10~4Radial Distances (feet) - 50, 200, 400, 800, 1,600, 2,000Times (days) = 10, 100, 300, 500, 1,000, 2,000Effective pumping rates (gpm) « 50, 100, 200
4-4 fiRi00378
The results of the calculations using a single recovery well are
presented in Tables '4-1 and 4-2, and are shown on Figures 4-1
through 4-7. The time-drawdown curves for various radial
distances are presented in Figure 4-1* The effect after 1,000
days of pumping on .the groundwater flow system is shown on Figures
4-2 through 4-7 for the two transmissivities and the three
pumping rates. The effect of the single recovery well on the
flow regime is calculated and presented on these figures using
the base conditions on Figure 2-1 and employing the principle of
superposition (Bear, 1979). It is obvious from these figures
that the effect of a recovery well at the Raymark site is to
reduce the.steepness of the drawdown cone centered on Hatboro
well H17, but not to develop a significant reversal of flow. In
actuality, a small drawdown cone would develop around the Raymark
well under certain pumping/transmissivity conditions. The extent
of the influence of the drawdown will, however, be somewhat
limited. Water elevations within the Raymark well are approxi-
mated, from the" calculations and are shown in Figures 4-2 through
4-7 for each of the hydrogeologic conditions.
Time Distance 50 200 400 800 1600 2000(days) (ft,)
10 7.09 5.31 4.68 4.06 3.33 3.11100 7.74 6.41 5.78 5.16 4.43 4.21300 8.26 6.92 6.30 5.61 . 4.94 4.73500 8.52 7.21 6.52 5.85 5.21 4.911000 8.83 7.51 6.88 6.29 - 5.53 5.302000 9,17 7.83 7.21 6.52 5.87 5.63
10 14.18 10.62 9.36 8.12 - 6.67 6.22100 15.47 12.82 11.56 10.30 8.86 8.42300 16.52 13.85 12.61 11.22 -9.88 9.45500 17.04 14.42 13.03 11.70 10.43 9.821000 17.67 15.01 13.75 12.59 11.06 10.622000 18.34 15.66 14.42 —13.04 11.74 11.26
4-1(b)
10 28.36 21.24 18.72 16.24 13.34 12.44100 30,94 25.64 23.12 2'0.60 17.72 16.84300 33.04 27.70 25.22 22.44 19.76 18.90500 .34.08 28.84 26.06 23.40 20.86 19.641000 35.34 30.02 27.50 25.18 22.12 21.242000 36.68 31.32 28.84 26.08 23.48 22.52
Table 4-1: Values of hQ-h(ft) for various values of time anddistance from the main pumping well with T = 12000gal/day/ft and Q - 50 gal/min (a) , 100 gal/min (b) ,and 200 gal/min (c) .
4-6
A R l G u 3 8 Q
8°° 160° 2000
10 " " 3.49" ~2.82~ "2.51 1.16 1.83 1.72
100 4r°4 3-37 3V06 """2.71 2.38 2.27
300 ~:4'30 3.65 ::3V30 2.98 2.64 2.56500 4:42 3.75 ' : 3.43 3.11 2.76 2.66
1000 4'58 3.98 3. 62 3.26 2.92 2.822000. 4.78 - - - 4 . 0 9 - -3175 ' """3.«""" 3.12 2.98
4-2(a)
10 6'98 5'63 5-01 ...4.32 3.65 3.44100 8-08 6'73 6.11 5.42 4.77 4.54300 8'60 7.31 -6.60 5.96 5.29 5 11500 8'84 "7-51 '6.87. 6.21 5.51 5.31
1000 9Vlf "^-83 "~"7.23"": 6.52 5.B5 5.64
2000 9/56 8'18 7-50 6.86 6.24 5.96
4-2(b)
10 13.94 "11.26 10.02 8.64 7.30 6.88100 16.16 13.46 12.22 10.84 9.54 9.08300 17.20' 14.62 13.20 11.82 10.58 10.22500 17.68 15.02 13.74 , 12.42 11,02 10.62
1000 -—18~.37 15.66 14.46 13.04 11.60 11.282000 20.12 - 16.36 15.00 13.72 12.48 11,92
4-2(c)Table 4-2: Values of h'o-h(ft) for various values of time and
distance from the main pumping well with T = 24000gal/day/ft and Q = 50 gal/min (a), 100 gal/min (b),and 200 gal/min (c).
4-7 AT ; n ~ n •>, i.fM uu38 I
<0
3=7.000i'12000
?000
- - - 4 0
JO-
H, - hCO
Q.1UOOO1.2*000
ZOOO zoo°
Figure 4-1. Drawdown calculations for various distances andtimes for a single recovery well. Hydrogeologicconditions are T = 12,000 gal/day/ft, 24,000 gal/day/ft, and Q = 50, 100, 200 gpm.
Q = 50 gpm= 12,000 gal/day/ft
t = 1000 days
WATER DRAINAGE. ^ ^ --Q (OQtf 2QOQ200-. -.« HATBORO I.SIT" ~" ". 1 M"'- ' CONTOUR
FIGURE 4-2. Aquifer water level configuration at 1,000 daysunder,the conditions T = 12,000 gal/day/ft, Q = 50gpm, with a recovery well(s) centered on the .Raymarksite (10 ft contour intervals),
A R i 0 0 3"8 3
Q = 50T =24,000 gal/day/ftt ="1000 days
\0° 13
RAYMARK SITESURFACE WATER DRAINAGEWATER l&Tel.' ELEVATIONHATBORO WELL CONTOUR INTERVAL'
FIGURE 4-3. Aquifer water level configuration at 1,000 "daysunder the conditions T = 24,000 gal/day/ft, Q ==. 50gpm, with, a recovery well(s) centered on the Raymarksite (10 ft contour intervals).
4-10 -• . . f. p t ,, - -i /> M t i u o u o 4
Q = 100 gpmT, = 12,000 gal/day/ftt = 1OOO days
-—— SURFACE. WATER DRAINAGE^ „ . .i -, , ... o inoo ?non200 WATER level ELEVATION uw " iuuu1.2 .HATBORO .WELL . . . . . . - CONTOUR JNTFRxar ;' IP'
FIGURE 4-:4. Aquifer w ter level configuration at 1,000 daysunder the conditions T =• 12,000 gal/day/ft, Q = 100gpm, with a recovery well(s) centered on the Raymarksite (10 ft contour intervals).
4-11ARi DO'585
Q =100 gpmT = 24,000 gal/day/ftt =1000 days'
RAYMARK SITE ~ -iSURFACE WATER DRAINAGE „.
z o o WHTER level ELEVATION ' , ,« HATBORO WELL CONTOUR l^^^FRVAl ; 10'
FIGURE 4-5. Aquifer water level configuration at 1,000 daysunder the conditions T = 24,000 gal/day/ft, Q = 100gpm, with a recovery well(s) centered on the Raymarksite (10 ft contour intervals).
4-12 AR100386
Q = 200 gpm= 12,000 gal/day/ft
t = 1OOO days
LEGZftD.-- ---ffl RAYMARK SITE ... ... _. .._.:.._. ______________———————— ——-.—— "SURFACE. WATER DRAINAGE '" .. . " _" J~~———loOO 2OOO FEET
200 WATER level ELEVATION '12 .HATBORO .WELL _. _ . . .. • _ .... .CONTOUR INTERVAL - '0
FIGURE.4--&. Aqtrifer water level configuration at 1,000 daysunder:the conditions T = 12,000 gal/day/ft, Q = 2009ptt/. with a recovery well(s) centered on the Raymarksite (10: .ft contour intervals) .
4-13
Q = 200 gpmT = 24,000 gal/day/ftt = 1OOO days
RAYMARK SITE '_.——- SURFACE WATER DRAINAGE200 WATER level ELEVATION« HATBORO WELL " CONTOUR INTERVAL:
FIGURE 4-7, Aquifer water level configuration at_ 1,000 daysunder the conditions T = 24,000 gal/day/ft, Q » 200gpia, with a recovery well(s) centered on the Raymarksite (10 ft contour intervals).
4-14r t h l Q u o
Pumping of the contaminated groundwater should not pose any
adverse impact on the environment..and.public health. As
previously discussed, the drawdown due to the recovery well
should not affect the water production from the Hatboro wells.
The contaminated groundwater would be pumped to a holding tank
where it would be transferred to an air stripper or carbon adsorber
for removal of TCE. Public exposure to the contaminated
groundwater.'would be minimal during the pumping phase of the
remedial action.
An approval from the Delaware River Basin Commission is required
for withdrawal of groundwater when the daily average gross
withdrawal during any calendar month exceeds 100,000 gallons. An
application has to be submitted to the Commission (1981) for approval
under Section 3.8 of the Delaware River Basin Compact. Since
Hatboro Borough and Warminster Height Township are located within
the Groundwater Protected Area, Section 10.3 of the Compact which
establishes more stringent conditions for groundwater withdrawal
is applicable. Under this more stringent regulation, a protected
area permit is required .when the average groundwater withdrawal
rate.is more than 10,000 gallons per day over a 30-day period
(Delaware River Basin Commission, 1982).
Table 4-3 presents: the estimated-costs associated with pumping of
the contaminated groundwater. • • ~ : ~
4-15 flfiiOG389
Table 4-3
Estimated Costs for On-site Groundwater Pumping
Capital Cost
Pumping Well . $ 16,500Pump 1,600Electrical 2,000Instrumentation 83,000Monitoring Wells (3 @ $2500) 7,500
4-16
Subtotal $ 110,600
Contingency (20%) 22,200
Subtotal $ 132,800
Engineering, Administration,and Contractor Fees (20%) 26,600
Total - . $ 159,400
Annual Operation And Maintenance Costs
Maintenance $ 4,000Utilities (@ 6 cents/KWH) 5,300Labor
(7 hours/week @ $18/hour) 6,600
Subtotal . $15,900
Contingency (20%) 3,200
Total . $ 19,100
nfs '- o nu U j u
4.3 Carbon Adsorption
Over the years, granular activated carbon systems have been used
successfully for the treatment of water and wastewater conta-
minated with ,-organics. The technology and methodology tiave been
fully developed arid have.been found both dependable and reliable.
This technology involves the concentration of the pollutant onto
the carbon media. Spent carbon can be used repeatedly after
regeneration, which is normally accomplished in a furnace. In
other similar treatment facilities, this treatment process has
not generated a negative public response and has not been found
to endanger the public or .the environment.
Design of a.carbon adsorption unit involves laboratory study of
the contaminant/adsorbant equilibrium and rate behavior. The
contaminant/adsorbant equilibrium relationship dictates the -
optimum capacity achievable and is a function of the affinity
between the contaminant and the carbon. The equilibrium data can
then be used to determine the carbon dosage for a particular
treatment system. The rate behavior indicates how fast the
pollutant.is .being removed from the contaminated medium and
determines the required size (contact -time) of the carbon unit.
The proposed on-site carbon adsorption treatment system would
consist of two identical standard carbon columns as depicted in
Figure 4-8. .This arrangement will allow the lead column to be
operated to exhaustion to insure optimum use of the carbon. The
design criteria are presented in Table 4-4. The proposed system
would" be capable _qf treating the contaminated water at the rates
of 50, 100 and 200"gpm. " "~
4-17
A K i 0 0 3 9 i
QZLJOUJ
cr zLJt-UJ
CL < O——CXJ"I-
<to
O_JL.
>
<Z£ O2 OO ECO C_?
O.
kl J =Q.
O 3Em z>o: _j< Oo o
OT R!•00-c Swp B wasoE 5^ £<5<CO
I* 2Spftb!•
IICO
C3Hfe
< UJ
4-18PRC ENGINEERING
« n i U J b S 2
The two columns can be operated either in series as one system
with lead.and lag columns or in parallel as two individual
columns. Each carbon column contains approximately one truck load
(approximately 20,000 Ibs) of carbon.
An important part of the treatment process is the sampling of the
influent and effluent. Three sampling points are shown in Figure
4-8. The first sampling point is essential to determine the
groundwater concentration of TCE prior to treatment. This
information will eventually be used to determine when to termi-
nate treatment. Data -from the second sampling point will
indicate when the carbon in the first column is exhausted and
requires regeneration or replacement. The results from the third
sampling point will indicate if the effluent treatment goal is
being met. The operating data from the first column can be used
to estimate when, breakthrough will occur in the second column.
The estimate of carbon usage indicates that the carbon needs to
be replaced approximately every four months. This estimate is
based on equilibrium data from the literature (O'Brien and
Stenzel, 1984). It should be noted, however, that breakthrough
will likely occur sooner than predicted because the actual column
capacity will be less than that derived from the laboratory_study
(batch isotherm data). Hence, a more refined estimate of the
carbon's replacement, frequency can be determined when actual
operational data become available. Table 4-5 presents cost esti-
mates for the proposed' carbon'adsorption system.
4-19Mi j u'uob'3
Table 4-4
Carbon Adsorption Process Design Criteria
Column diameter ~ ; 10 ft.
Height of packing 10 ft.
Contact time 30 min.
Hydraulic loading • 2 gpm/ft2
4-20
Table 4-5
Estimated Costs for Carbon Adsorption Treatment
Capital Cost . _ . _ _ _ _ . "~ ..." M " ./";;" ' " " ".'
Adsorption Column (2 units) $ 160,000Pump (3 units) 11,000Piping _. _ _ _ . _ _ _ . . . _ _ _ _ . . .___.__...... ... 3,000Electrical, Instrumentation . 6,000Structures . . . . . . . . _ _ . .
Holding well, Building 20,000
Subtotal - . . . - - . $ 200,000
Contingency (20%) 40,000
Subtotal $ 240,000
Engineering, Administration,and Contractor Fees (20%) 48,000
Total $ 288,000
Annual O & M Costs _ _ _
Electric-power (@ 6 cents/KWH) $ 10,000Replacement of carbon (4 cycles/year) 64,000Laboratory costs . . : - . - : .
(4 samples/month @ $300/sample) 14,400Operating labor
(10 hours/week @ $18/hour) 9,400Maintenance 3,000
Subtotal $ 100,800
Contingency (20%) 20,200
Total . . . . . . . $ 121,000
4"21 - An I 00395
4.4 Air-Stripping - _ ~ " . . " " . "
Air stripping or aeration .involves removal of volatile organic
compounds from the contaminated groundwater by transferring the
compounds into the gaseous phase. This technology has been demon-
strated to be feasible in both pilot and full scale treatment
systems for the removal of TCE from contaminated water (McCarty,
1983; O'Brien and Stenzel, 1984; McCoy and Associates, 1984).
These reports suggest that the air/water ratio can be varied to
achieve a desired removal level. As stated earlier, air strip-
ping results in the transfer of the organic contaminant from one
phase to another. Therefore, both environmental and public
health impacts must be considered. ___... _ _ . _ " .
Under, the assumptions of the maximum pumping rate (200 gpm) and
groundwater TCE concentration (4100 ppb), the maximum possible
TCE emission rate"during continuous operation is .40 Ib per hr.
Pennsylvania Air Pollution Control Regulations (Pennsylvania
Code, Title 25, Chapters"121-141) list no general emission limits
for volatile-organic compounds (VOC). However, any new or modi-
fied source that emits amounts greater than 50 tons per year,
1000 pounds per day, or 100 pounds per hour is considered signi-
ficant and is subject to special permitting and emission offset
requirements _ as described in Section 127.63. Comparison of ..the
maximum possible TCE emission .rate of,., 0,40 Ib/hr-with these
levels that are considered significant suggests that air
emissions from the air stripping process will have little impact
to the environment and the public.
ARI 00396
PRC ENGINEERING . 4-23 A R I O D 3 9 7
The important "considerations for designing an air stripper include
the following:
1) Air to water ratio;2) Henry's law constant; - -3) Influent contaminant concentration;4) Desired effluent contaminant concentration or treatment
efficiency;5) Height of packing;6) Type of packing; and7) Diameter of the column.
Given, the contaminant to be removed, Henry's law constant, type of
packing, and influent and desired effluent concentrations, an air
stripping column can be designed.
A schematic diagram of the on-site areation treatment process is
shown in Figure 4-9, The proposed treatment process would
require two identical stripping columns operating in series.
Table 4--6 contains a summary of the design criteria for the on-
site-air .stripping systems at the .three pumping rates being
considered "(i.e., 50 gpm, 100 gpm, 200 gpm). Analysis of the TCE
concentration in the influent and •effluent to the stripping -
columns will be required to determine when to terminate treatment-
and, more importantly, if the treatment process is performing as
designed. Table 4-7 presents a summary of cost estimates for
the on-site air stripping systems sized for the three water flow
rates. - ^ ; - --- -'- ----- :'- - -
The following estimated costs for Installing air-strippers for
the off-site treatment systems at the contaminated Hatboro wells
were prepared by Gilmore and Associates, Inc.
4-24 ARI00398
Well Air Stripper Cost
HI, H2, H3 $200,000
H7 . 130,000
H16 . 175,000
AR1003594-25
Table 4-6
Summary of Air Stripping Process Design Criteria
Pumping Rate .. .. r : ... „.:..-> n rr,™™ -i ™200 gpm 100 efpm 50 gpmColumn Diameter.. — — - . :3ft 2.5ft l.5ft
Height of Packing - — " ~ T 20 ft : . 20 ft "" 20 ft
Air-:: wate . Ratio 3 0 ; . ! 30r. x " 30 . _
Air Flow ———— ""-•- ---- — soo s flT" "' 400 'fln "" 200 scfm
influent Concentration 4100 ppb 4100 ppb 4100 ppb
Effluent concentration <4.5 ppb <4.5 ppb <4.5 ppb
4-26
A R I O Q 4 Q Q
Table 4-7
Estimated Costs for Air Stripping Treatment
Capital Cost
Pumping Rates 200 gpm _ 100_gpm 50 gpm
Stripping column (2 units)Tower, Packing, Blower $ 70,000 $ 50.,000 $ 36,000
Pump (3 units) 10,500 .10,500 9,000Piping 3,000 3,000 3,000Electrical, Instrumentation 6,000 6,000 .6,000StructuresHolding well. Building 20,000 20,000 20,000
Subtotal $ 109,500 $ 89,500 $ 74,000
Contingency (20%) 21,900 17,900 14,800
Subtotal $ 131,400 $ 107,400 $ 88,800
Engineering, Administration,and Contractor fee (20%) 26,,300 21,500 17,800
Total $ 157,700- $ 128,900 $ 106,600
Annual O £ M Costs
Electrical power @6 cents/KWH $ 10,000 $ 10,000 $" 5,000
Laboratory costs (4 samples/month @ $300/sample) 14,400 14,400 14,400
Operating labor (10 hours/week 6 $18/hour) 9,400 9,400 9,400
Maintenance and supplies 3,000 . 3,000 3,000
Subtotal $ 36,800 $ 36,800 $ 31,800"
Contingency (20%) 7,400 7,400 6,400
Total $ 44,200 $ 44,200 $ 38,200
4.5 " - -Surface Water Discharge ,_ .. .
The effluent from the various proposed treatment unit(s) would be
suitable for discharge to a surface water. Based on existing
information, there are two potential receiving points. An
unnamed creek is located approximately 2600 feet northwest of the
site and a culvert .is located approximately 600 feet from the
site. Further investigation of the sewer system in the vicinity
of the site will be required to select the appropriate point of
discharges ~- -•-•-.:—— ^ :. ~"~ - - - '- ---~^^~ ---
In accordance ""with the Pennsylvania Clean Streams Law and Chapter
92 of the Pennsylvania Water Resources Rules, an NPDES permit
will be-.required from the Department of Environmental Resources
in order to discharge the treated.groundwater to the surface
water- near ...the site. . . . - • • • • - - •
Article 3, Section 2 of the Rules 'of Practice and Procedure
(Administrative Manual - Part II)' issued by the Delaware River
Basin Commission (1981) states that "Any project which may have a
substantial effect on the water resources of the basin, ..,,
shall be submitted to the Commission for a determination as to
whether the project will have a substantial effect on the water
resources of the .basin ...". Therefore, an application to the DRBC
will also be required for surface water discharge .
The TCE concentration in the treated water is anticipated to be
4.5 ppb or.less. As discussed in Chapters 2 and 3, at this
concentration there will be a reduced risk to the environment and
4'28
public health.
Discharging the treated groundwater to a surface water body
requires the installation of an effluent line from the on-site
treatment unit to the point of discharge. For cost estimation
purposes, it was assumed that the treated water can be discharged
by gravity into the culvert. Table 4-8 presents the capital
costs for installing 600 feet of discharge piping for the three
flow rates considered.
a f~- , -=- — *
A t-, i U u 4 0 3
Table 4-8
Estimated Costs for Installation of Discharge Piping to Culvert
Capital Cost _ ~_ - - - - . - - - ^^- —— -_- - •• ------- - •_ -
Pumping Rate , ., ; 2o0gpm 100gm 50gpB
Materials ... _ . _..,.. 3 9 i«n *-,«-,«Installation ' 5 2,160 $1,830 $1,470installation '5,200
Subtotal S 7,360 " ' "$6,530 "" $5Contingency (20%) 1/500 . i^oo i,'
Subtotal ....,§ 8,860 $7,830 $7,100
Engineering 5 Contractor" 1/800 " 1,570 1,400
Total $10,660 $9,400 $8,500
Note: The pipeline requires little or no maintenance; there-fore, no annual operation and.maintenance cost is provided
4~30
4.6 Reinjection of Treated Water __-
A slightly larger area of influence and contaminated groundwater
recovery can be achieved by reinjecting the pumped and treated
recovery well water at a point, for instance, midway between the
Raymark site and Hatboro well H17 (Figures 4-10 through .4-15).
The area of influence of the recovery well, under pumping/injec-
tion conditions, would be about 10 to 20 percent larger than for
the recovery well alone. The water elevations shown in Figures
4-10 through 4-15 surrounding the Raymark well and proposed
injection well were estimated by superimposing elevated-water level
data for the injection well on drawdown data for the Raymark well.
A further scenario using an effective injection/withdrawal rate
of 100 gpm and an injection well located at FP14 (Figure 1-2)
upgradient of Raymark, was also calculated.' The results of this
scenario are presented in Figures 4-16 and 4-17 for two transmis-
sivities (12,000 gpd/ft and 24,000 gpd/ft) and a contour interval
of 10 ft. The result of such an injection/withdrawal system would
be to increase the gradient toward the Raymark well, effectively
reducing the time required to decontaminate the aquifer upgradient
of Raymark. However, under these conditions there would be
essentially no effective "zone of influence" between the Raymark
site and Hatboro well H17; that is, the decontaminated zone would
be primarily upgradient of Raymark. Since this scenario does not
adequately address the source of contamination or the area of
aquifer .beneath and between the Raymark site and well H17, it is
not cons idered further.
4-31 . .._._ .A R i O u i i Q S
The costs associated with the development of the injection well
are provided in Table 4-9.
An NPDES permit from the Pennsylvania Department of Environmental
Resources and approval from the Delaware River Basin Commission
are required for injecting the treated water back into the aquifer.
ARI00406
Table 4-9
Estimated Costs for Injection Well
Capital Cost
Gravity Injection Well . $ 16,500Piping 17,000
4-33
Subtotal $ 33,500
Contingency (20%) 6,700
Subtotal $ 40,200
Engineering, Administrationand Contractor Fee (20%) 8,000
Total $ 48,200
Annual O&M Costs
Maintenance _ , $3,300Labor (7 hours/week @ $18/hour) 6,600
Subtotal $ 9,900
Contingency (20%) 2,000
Total $ 11,900
A R 1 Q Q I . 0 7
.160= 50 gpm
T = 1?,000 gal/day/ftt = 1600 days
—— -—— -SURFACE WATER DRAINAGE" " . . . . . . .200 -WATER level ELEVATION . IOO° 20QO FEET« - HATBORO: WELL '': : ". CONTOUR INTERVAL ; _!Q1_© PROPOSE£"INJECTION WELL .. ' ......
FIGURE-4-10. Aquifer water level configuration! 1,000 daysunder;.the conditions T = 12,000 gal/day/ft, Q = sogpm, with(a recovery well(s) centered on the Raymarksite and injection well(s) located midway betweenthe Raymark site and H-17 (10 ft contourintervals).
Q = 50 gpm\eO T = 24,000 gal/day/ft
t = 1QQO days "
RAYMARK SITET'SURFACE WATER DRAINAGE . -.. £~————^——r"lBoO FEETWATER level ELEVATION : - - -
12 HATBORO WELL CONTOUR INTERVAL/0 PROPOSED INJECTION WELL ...... ' _ . -'
FIGURE 4-11. Aquifer water level configuration at 1,000 daysunder the conditions T » 24,000 gal/ day/ft, Q •= 50gpm, with a recovery well(s) centered on the Raymarksite and injection well(s) located midway betweenthe Raymark site and H-17 (10 ft contourintervals) .
4-35
Q = 100 gpmI" = 1?,000 gaf/day/ftt = 10OO days
__.._RAYMARK,— ••—— SURFACE WATER DRAINAGE200 WATER level ELEVATTON ' ~ " ' ° I00° ZDO°« HATBORCrWELl" ,._T..:. . . . _' -.-CONTOUR INTERVAL> _IQ1© PROPOSED:w " "" ™'~"1""
FIGURE 4-12. Aquifer water level configuration at 1,000 daysunder the conditions T = 12,000 gal/day/ft, Q = 100gpm, with a recovery well(s) centered on the Raymarksite and injection well(s) located midway betweenthe Raymark site and H-17 (10 ft contourintervals).
gpm000 gal/day/ft
days
- RAYMARK SITE \.._ ~" _______________—-.——-:SURFACE WATER DRAINAGE . - ;._ £ JJJ^:rToQO .FEET._?£?<? WATER level. ELEVATION ' _« HATBORO WELL CONTOUR INTERVAL-——]Q_© PROPOSED INJECTION WELL
FIGURE 4-13. Aquifer water level configuration at 1,000 daysunder the conditions T = 24,000 gal/day/ft, Q - 100gpm, with a recovery well(s) centered on the Raymarksite and injection well(s) located midway betweenthe Raymark site and H-17 (10 ft contourintervals).
4-37 A R i Q Q l j
Q - 200 gpm ,t\oT = 12,000 gal/day/ftt = 10OO days
.RAYMARK, SITE.. ...SURFACE WATER DRAINAGE200 WATER level ELEVATJON' " ° I00° 2000. FEET!? ..HATB.ORO WELL !! . _ ^ CQNTOUR INTERVAL * __!0___© - PROPOSE JN JECTJON'VVELL ! " . - . "
FIGURE 4-14. Aquifer water level configuration at 1,000 days underthe conditions T = 12,000 gal/day/ft, Q = 200 gpm,with a recovery well(s) centered on the Raymark siteand injection well(s) located midway between theRaymark site and H-17 (10 ft contour intervals).
4-38 A R 1 0 Q U 1 2
Q = 200 gpmT = 24,000 gal/day/ftt =^1000days
_______ __ RAYMARK SITE0 PROPOSED ———— SURFACE WATER DRAINAGE ; J ——————^QQ FttT
INJECTION WELL ZOO WATER level ELEVATION . . . ; . ' . . . . . _ . "= '« HATBORO WELL CONTOUR INTFRva.! .i 1Q
FIGURE 4-15. Aquifer water level configuration at 1,000 daysunder the conditions T 24,000 gal/day/ft, Q « 200gpm, with a recovery well(s) centered on the Raymarksite and injection well(s) located midway betweenthe Raymark site and H-17 (10 ft contourintervals).
Q = 100 gpmT = 12,000 gal/day/ftt = 1OOO days
SITESURFACE WATER DRAINAGE.WATER level ELEVATIONHATB;ORO WELL ' . . . . _ .FISCHER PORTER WELL #14
FIGURE..4-16.. Aquifer water level configuration at 1,000 days underthe conditions T = 12,000 gal/day/ft, Q = 100 gpm,with a recovery well(s) centered on the Raymark siteand injection well(s) located" at Fischer-Porter FP14(10 ft contour intervals).
4-40
Q = 100 gpmT = 24,000 gal/day/ftt » 10OO days
RAYMARK SITE — - ' ' .___ SURFACE WATER DRAINAGE J—————^00 2OOO FEET200 WATER leeei. ELEVATION ;tz HATBQRO WELL CONTOUR INTERVAL1 _JO-___® FISCHER PORTER WELL*W
FIGURE 4-17. Aquifer water level configuration at 1,000 daysunder the conditions T = 24,000 gal/day/ft, Q - 100gpm, with a recovery well(s) centered on the Raymarksite and injection well(s) located at Fischer-PorterFP14 (10 ft contour intervals).
• f l f i l O O i . 1 5
4.7 Closure Plan and Post-Closure Monitoring .Plan
Implementation of any of ~the~proposed remedial actions with the
exception of the no action alternative requires continuous
monitoring during and after the remedial activities.
The following is a description of a closure and post-closure
monitoring plan which can be implemented at the site.
o Two upgradient wells should be installed in off-site
locations in order to monitor the water,quality of
the groundwater before it flows under the site.
One well should be located south of the site and the . ..
other east of the site. • These wells can be sampled
once a month to provide.groundwater background
information. If the treated water is reinjected into
the aquifer, a third monitoring well should be
installed between the injection well and Hatboro well
H-17 to monitor the water quality downgradient of the
barrier... - - " ......_...... .._-—--,---- ------ -----
o "Each month, two sets of samples should be collected
and analyzed for TCE concentrations. Each set of the
samples should, consist of a sample of untreated influent to
the air. stripper and a sample of treated effluent froin
the air stripper.. The average concentrations of the
respective samples will be the. monthly TCE concentra- .
tions for-the influent and effluent. If the monthly
concentrations of TCE in the infuent falls to or below
"42 R n I n r, I f rflR 1 Guk 1 b
4.5 ppb for twelve consecutive months, on-site treatment
can stop. However, monthly sampling to determine TCE
concentrations at the monitoring wells between the
injection well and H-17 should continue to determine
the effectiveness of the remedial activities. These
monitoring activities should continue for 30 years.
4-S Cost Analysis
Each proposed remedial action alternative is composed of three of
the five treatment technologies that were discussed in the
previous sections. The estimated costs for construction, opera-
tion and maintenance for these treatment technologies were iden-
tified in their respective sections. Sources of cost information
include equipment manufacturers, technical literature, and Means
cost data (1985).
These costs were used to compute the present worth of each alter-
native. The capital cost for each alternative is the sum of the
capital costs of the individual selected treatment technologies.
However,"the operation and maintenance cost for each alternative
is not the total of the 0 & M costs of the treatment technolo-
gies. The labor requirement for each alternative was evaluated
to insure optimum utilization of operators and maintenance
personnel. For all alternatives, labor requirements were
reduced to reflect economies of scale.
Since air stripping columns have already been purchased by the
Authority for three of the Hatboro contaminated wells, the cost
4-43
OR i nnu 7
estimates for the off-site treatment did not include capital
costs for these three air strippers. However, an estimated
annual operation, and maintenance cost was included for the
recurring costs to decontaminate the drinking water supply.
In computing the present worth of the annual operation and main-
tenance costs/ a 15 year project life was assumed with no net
salvage value and a discount rate of 10 percent. These costs are
order-of-magnitude estimates with an accuracy of_+50 percent.
The costs for -the ten alternatives on a present worth basis are
presented in Table 4-10. Capital .costs were assumed to be
incurred at the beginning of the first year and 0 & M costs paid
at the end of each year.
4-44
^ f i i O u ^ i f f
Table 4-10 . _ .
Remedial Alternatives Cost Analyses
Alternative 1
No Action . $ .0
Alternative 2 __
On-Site, Pumping/AerationTreatment/Discharge To Surface Water
Capital Costs _
Flow Rate 200 gpm 100 gpm 50 gpm
Pumping $159,400 $159,400 $159,400Aeration 157,700 128,900 106,600Discharge To Surface Water 10,700 9,400 8,500
Total $327,800 $297,700 $274,500
Annual Operation and Maintenance Costs _ , . „ _ _ , .
Utilities $ 15,300 $ 15,300 $ 10,300Laboratory Analyses 14,400 14,400 14,400Maintenance 7,000 7,000 7., 000Labor 9,400 9,400 9,400
Subtotal $ 46,100 $ 46,100 $ 41,100
Contingency (20%) 9,200 9,200 8,200
Total $'55,300 $ 55,300 $"49,300
Present Worth O & M Costs(15 years £ 10 percent) $420,600 $420,600 $375,000
Total Present Worth $748,400 $718,300 $649,500
4-45 o w i n f: T. i Q
Table 4-10, continued
Alternative'. 3
On-Site, Pumping/AerationTreatment/Reinjection
Capital Costs __ __ , _____ .,; __.__,.._. ,_.-. .._..,» .......
Flow Rate ., 200 gpm 100 gpm 50 qpm
Pumping „ . — _"-._-. :__.;. "__._ r$i59,400 $159,400 $159,400Aeration 157,700 128,900 106,600Reinjection 48,200 48,200 48,200
Total : - - - - - - """$365,300 $336,500 $314,200'
Annual Operation and Maintenance Costs
Utilities - " $ 15,300 $ 15,300 $ 10,300Laboratory Analyses. ^ 14,400 14,400 14,400Maintenance - -10,300 10,300 10,300Labor : . . . - • : - : 9,400 9,400 9,400
Subtotal —$ 49,400 $ 49,400 $ 44,400
Contingency (20%) 9,900 $ 9,900 $ 8,900
Total -:$ 59,300 $ 59,300 ' $ 53,300
Present.Worth O & M Costs(15.years"©.10 percent) . $451,000 $451,000 $405,400
Total Present Worth - $816,300 $787,500 $719,600Value -" -,---- =s==s=!==c==s= ._—————— ___....
4-46
f i R i 00^20
Table 4-10, continued
Alternative 4 _ _ _ _ .. . _
Off-Site, Pumping/AerationTreatment/Discharge ToWater Distribution System
Capital Costs
Air Strippers for^1'Hatboro Well 1, 2, 3 $200,000Hatboro Well 7 130,000Hatboro Well 16 175,000
Total $405,000
Hatboro Borough has purchased air strippers for wells12, 14 and 17. Therefore, no capital costs for theseunits were included in this cost estimate.
Annual Operation and Maintenance Costs _ _ __
Utilities (6 units @ $1200/month each) $ 86,400Laboratory Analyses (6 units @ $25OO/ .._ . 15,000
year each)Maintenance (6 units @ $3000 each) 18,000Labor (6 hours per week per unit @ $18/hr) 33,700
Subtotal $ 153,100
Contingency (20%) 30,600
Total $ 183,700
Present Worth O & M Costs(15 years @ 10 percent) $1,397,200
Total Present Worth Value — --— $1,802,200
(1) Capital costs are based on estimates prepared by Gilmore &Associates, Inc. for the Hatboro Borough Authority in August,1983.
Table 4-10, continued
Alternative' 5
On-Site, Pumping/Aeration Treatment/Discharge to Surface Water; Off-Site,Pumping/Aeration Treatment/DischargeTo Water Distribution System
Capital Costs _._..,„__„„.„., ... ,,-_ ,.._--,..,.,„-,.. . ...... .
Flow Rate - ~- - —— 200" gpm ."" 100 gpm 50 gpm
Pumping _, " " $159,400 $159,400 $159,400Aeration*1' 562,700 533,900 511,600Discharge To Surface Water ; 10,700 9,400 8,500
Total : --"'• $732,800 * $702,700 $679,500
Annual Operation and Maintenance costs
Utilities ; $ 101,700 $ 101,700 $ 96,700Laboratory Analyses 29,400 29,400 29,400Maintenance _ : .25,000, 25,000 25,000Labor -..I..,-:..--- ^"""--- — — -"43,100 43,100 43,100
Subtotal -- --$199,200 " " $ 199,200 $ 194,200
Contingency (20%) 39,800 39,800 39,000
Total _- $ 239,000 " $ 239,000 ?233,200
Present Worth 0 & M Costs(15 years""@^10 percent) $1,818,000 $1,818,000 $1,774,000
Total Present Worth $2,550,800 $2,520,700 $2,453,500T7-* T 11 n — • _ - ._ - ——4 ^ —. ^ -. ^ ^__-_______—______ -
(l) Capital costs for the air strippers for Hatboro wells 1, 2, 3, 7and 16 are included.
4-48
Table 4-10, continued
Alternative 6
On-Site, Pumping/Aeration Treatment/Reinjection; Off-Site, Pumping/AerationTreatment/Discharge To Water DistributionSystem
Capital Costs • .
Flow Rate 200 gpm 100 gpm 50 gpm
Pumping $159,400 $159,400 $159,400Aerationt1) 562,700 533,900 511,600Reinjection 48,200 48,200 48,200
Total $770,300 $741,500 $719,200
Annual Operation and Maintenance Costs __ .. _
Utilities $ 101,700 $ 101,700 $ 96,700Laboratory Analyses 29,400 29,400 29,400Maintenance 28,300 28,300 28,300Labor 43,100 43,100 ._ 43,100
Subtotal $ 202,500 $ 202,500 $ 197,500
Contingency (20%) 40,500 40,500 39,500
Total $ 243,000 $ 243,000 $ 237,000
Present Worth 0 & M Costs(15 years © 10 percent) $1,848,000 $1,848,000 $1,803,000
Total Present Worth $2,618,300 $2,589,500 $2,522,200V cL^ LL& ^ ^ —* «-*—_ _™,_,_— ^ ^ -i ~
(1) Capital costs for the air strippers for Hatboro wells 1, 2, 3, 7and 16 were included.
4-49 _ ,- -., 00A r. 1 u J 4 2 3
Table 4-10, continued .
Alternative .7 _. .. . ...—_.„...-_.
On-site, Pumping/Carbon AdsorptionTreatment/Discharge To Surface Water
Capital Costs ......,.„.____...._. .._... - . ... .u.__ _._.._ z . . ..
Flow Rate - ; 200 gpm 100 gpm 50 gpm
Pumping $159,400 $159,400 $159,400Carbon Adsorber .- = 288,000 288,000 288,000Discharge To Surface Water • 10,700 9,400 8,500
Total $458,100 $456,800 $455,900
Annual Operation and Maintenance Costs
Utilities $ 15,300Laboratory Analyses 14,400Maintenance 7/000Carbon Replacement " - "64,000Labor ._..__il_...: " -: .: - 9,400
Subtotal .... - - $ 110,100
Contingency (20%) 22,000
Total $ 132,100
Present Worth 0 & M Costs(15 years @ 10 percent) " $1,005,000 $1,005,000 $1,005,000
Total Present Worth $1,463,100 ... $1,461,800 $1,460,900
The same annual operation and..maintenance costs apply to thecarbon treatment systems for flow rates of 200, 100 and 50 gpm.
Table 4-10, continued
Alternative 8
On-S ite, Pumping/CarbonAdsorption Treatment/Reinjection
Capital Costs
Flow Rate 200, 100 and 50 gpm
Pumping $159,400Carbon Adsorber 288,000Reinj ection 48,200
Total $495,600 .
Annual Operation and Maintenance Costs
Utilities $ 15,300Laboratory Analyses 14,400Maintenance 10,300Carbon Replacement 64,000Labor . 9,400
Subtotal $ 113,400
Contingency (20%) 22,600
Total $ 136,000
Present Worth O & M Costs(15 years @ 10 percent) $1,034,400
Total Present Worth $1,530,000Value =========5=
4-51 - : - _ .*,• n i — -• t r\ r~wri t uu-~i-25
Table 4-10, continued
Alternative 9 _„_- _-~. _.,.-._._.-..; -,:.- ..•---___,_____, ._; ._...,.- ... --- - .- ---
On-Site, Pumping/Carbon AdsorptionTreatment/Discharge To Surface Water;Off--Site, Pump ing/Aeration Treatment/Discharge To Water Distribution System
Capital Costs - ;..__„- .-. . ,.,, _-_:.-\. .: .-.-.: ..-..-.. .- - • —- —
Flow Rate 200 gpm 100 gpm 50 gpm
Pumping * $159,400 $159,400 $159,400Carbon Adsorber : 288,000 288,000 288,000Discharge To Surface Water : 10,700 9,400 8,500Aeration 405,000 405,000 405,000
Subtotal. . . . . . . $ 263,200
Contingency (20%) 52,600
Total ...--—..-.-—- .-$863,100 $861,800 $860,900
Annual Operation and Maintenance Costs
Utilities - _ . _ . . _ . ' _ _ . . . _ . $ -101,700Laboratory Analyses 29,400.Maintenance . . „ , —-. - 25,000Carbon Replacement 64,000Labor - •--'- - 43,100
Total - , .: - $ 315,800
Present Worth O & M Costs(15 -years @ 10 percent) $2,402,000 $2,402,000 $2,402,000
Total .Present Worth $3,265,100 $3,263,800 $3,262,900
The same annual operation and maintenance costs apply to thecarbon treatment systems for flow'rates of 200, 100 and 50 gpm..
... -,,,,.U 0 '^ i 6
Table 4-10, continued
Alternative 10
On-Site, Pumping/Carbon AdsorptionTreatment/Reinjection; Off-Site, Pumping/Aeration Treatment/Discharge To WaterDistribution System
Capital Costs
Flow Rate 200,100 and 50 gpm
Pumping $ 159,400Carbon Adsorbers 288,000Reinjection 48,200Aeration 405,000
Total $ 900,600
Annual Operation and Maintenance -Costs
Utilities $' 101,700Laboratory Analyses 29,400Maintenance 28,300Carbon Replacement 64,000Labor -43,100
Subtotal $ 266,500
Contingency (20%) 53,300
Total 319,800
Present Worth O & M Costs(15 years @ 10 percent) $2,432,000
Total Present Worth $3,332,600Value ==========
4.9 Summary of Alternative Analyses
The summary of analyses, for.-the proposed alternatives is
presented in Table 4-11 which can readily be used to compare the
alternatives. The findings can be summarized in the followingmanner. _ . - . . . . . . . . . ....... ..... ;-. •- -
1. Except for the no action alternative, each remedial
alternative would reduce public health threat to a certain degree.
For the alternatives examined, public health risks would be
reduced to the greatest extent when treatment of the contaminated
groundwater,is performed both on-site and off-site.
2. For the no action alternative, ingestion of TCE contaminated
water ..poses a significant concern regarding the potential adverse
impacts of TCE on the health of the affected population. The
other..remedial alternatives would result in decontaminating the
groundwater and/or retarding any further migration of TCE
contaminated groundwater.
3. The appropriate treatment technologies include aeration and
carbon adsorption, which have proven to be both dependable and
reliable. " Either the aeration or carbon adsorption system can
meet the treatment requirements, hence, the choice between the
two depends solely on economics.
4. Except for the no action alternative, the anticipated public
responses, to the.other alternatives range from marginally accept-
able to highly acceptable. Since ,the overall objectives are to
4~54 ARS'00^28
decontaminate the groundwater and curtail the migration of TCE
contaminated groundwater, the remedial alternative which calls for
(1) pumping the groundwater on-site, along with treatment by
either air stripping or carbon adsorption, and reinjection into
the aquifer and (2) treatment of the water from the Hatboro
contaminated water wells by air stripping will most likely be
highly acceptable to the public. The public response to the
other alternatives will most likely range from moderately accep-
table to marginally acceptable depending on the degrees to which
the respective alternatives can meet the overall -objectives.
ARiCCi.29
r
cy)LU
1-
Z
UJ
IkP- 0T z^ si »fc 103 Jrtf *•- 1 •u
HI-Sh-
U.O
ee.^z3
aUIi ^<a.k»4o""( — 'z<
_1<uX3=-uUJ»-
<"S"
IRON
HE
xLU
_J
UJ-E
CJ
.—103
a-
OOo
1— -</>o0
UJenOa.LUQ£
>"t—«-•23 ---EZOCJ
MzQ£UJuOCJ
.._. _
CERM
S
oCJ
za:u. .o°
^0. •
a.<o .
UJ>•"• -*—*czQiLU1—^
0)^.Q(B4-»aO -U<J<D
.. C".3
"
UJT3 0SJ ***C <+-•<- O
c c0 0CJ —
z raO t~— > U)
< E
LU(J1—
O— oCD4J <u•a uO 3O cf>0 OCO Q_C" " k=5 Ot
•C -o..."••—4-*U(U
~ o-E
----- ———
- • '-X.— .
_.._.. (U- c
•: '. . -"diC_--- • ~ to
' ac
£, o
<n<u
. _.. ... o£
i- - . . O.OJ .C
« ~~ " L
TJ. C ' :!»
-0 ..... .LlQ_f-r I_
' : cc :- o
D)c - - : .. i"~ «
c - - ~oj-- t- ETt --
M
' CO • •—
Q. 4>' :"ut- JJ (_-C ffl .34-* 3 - O
Oi *O
"1 .CNJ
.. . "4y._ . .. -.--3.O"
;"{V, E. 3a.
——
,OJ
- -_, :
-Q.CD4D. ,0>uu"*
enO
C O01 C'
- O (J£_ CJa 4--
C :j_
-UJ-CJ_ . ..*—"W ~ i:
o Ta'"4- -a'03 C«- 3LO) O.~ t_
_ .E • .ca ^4J C-C 3O O(J . c-
O)>0 _"O,
_p ro.4J •— ""
CO COT— ^J -
00 COO OJOJ «
C-a> .4103
OJ-a 4--c .--.3. «o .C- CUi O
- '
>,. 1<uu
- <oC_-
" "o"".TO,o-C.
o'.:. w;
.... 01Q.
-
; „ . . __ _ , .-Jt si^E '
_ ——— - _^3!
"in". ..;P
- " ." c ;---o ,o ,
1) - ' ,.C l-_ ---. ID4 OJ t.
4- " O)ft- O a :— ,OJ _C 3 ETJ * • * - - - " ".•;c a> to3 0 C • --"T
4-> 4J •-- CL, . _ t- ,TO •- t_ 3 .3.3 « -O W O
. . ..•_-.. o ,: " . . _ ...:... (M
-, - ' --:- *1M
i-O 0>4 4-
fflH 4> 3
X c on 4^.Q O t- flJ 3
-™- « o o*J 4-» .c <003 OS O ** "O.0» i- o] (- EU" - «* i- 3 34-> <a 13 a> a.
- f'4)^_» ^
_Q03-ua.4)uu
c"OJ
o1_a.
c
UJot—
t~~bc..o
(_D)
E
iE01
c._o .o4-oco,..4-<
CO00N-
S-.
m"
c_4)4JCB3
-DC3 •O(_CD
. _. _
D)O
Oco<t>
.--.- -un
dwat
i
oD)
- oj• JZ? 4C3 . t_P... 4>
0) C3
T3
4J 0)03 4JC 10•— at
•o03
in - -M
O4)L. C4J, O
« 4-1O (D4-> C_^ 0)CQ a•C '>-0 -Q
- ----- ~
- - - -y
. _ . — . .. ^O
(Q0-
^..... O
co
,:.:;::;_.,!.!o
. _. L .41
.. *J
- ~=1=---- 3
^ = -1
C-. -., O
u
[_. . . 0
JJ ~ — <01 03 .. -A-=.. 3. . .. jg4J f>
O)o . c •; «4- ' >. 0>
J^ — p ... o0 C Q." 34- •— Q. T3— - ft. 3 4)ffl "D « M
Oeo
tfto-d-
o*JC^
*-• 4-10 . 3a; ~u o-. d--c 3 a- 0 E4) t- 3(- D) ...
TUpcao_0)u
*
D>O
C 001 C•> .eO 0(- 0*Q. 4->
EraC • 4-1— i- C
(D Oui *j oCJ C -T
1- — EQ
O t- 4- O4J 4->
C 4-1 UJ • —O CD CJ en— 3 l-4- TJ -Offl c cn o><- 3 4-> 4->a> o D. (c—— - L. Q) CE ro o —
•*-o
o4-1 4-> Ol03 Cni v rtc- tfl-C — C4J i_ (0 •
-C-O
— ' (J «<n c ca t-<U rtJ OJ tUJT 0 — Q.
t- OCJ *J4J
3 0) X C 0)4J J3 O *-
*o *•— *~ CDc w 4-> 4- e_3 ' (D <D U 0)o H- o> t- cn 4JU H- l_ 41 — COro o 4J «j "D 3:
Co,,3JDL.4-)m
"°
4-56 A R i O Q i j S O
•of31
5!c!0]
1— 1
•ijej|Sit-»l
a.UI
O B£UJt- >-< t-a. —*— • zU 5— Z1- Z-E O< U
_)< trtu a:•v of-E UI-E UU SEu. Ot- CJ
_t<t—SELU
3E 3£O asOf U.
> aeLU U
t—_iUJSE V>
\ «
! 3i Bi X 4-.i — Q.
: H o; „ (J£ •«
XC 0»0 0
•M C 063 O C— > _C— O Oa> t. eat Q. 4-1
t_ L. -J
t 0 "«3 O (3
C T3 C
— — S O
w f! 2 —C D> Q. O
O S 0 4J
U J^—— 4J «
-O e [- «Q. -C «- *-•
4J U
€) >. 4)—* —• —jQ — -Qa , to to
>. 4-. C4--—• a. — a.j= c o) ojm o t _ o
X , >.C DJ C C!>o o 0 6M C Q . ! W C O4 ) V C Ol O C— > .*= - -- - : - — > - .c— ' O U -* O O
M c_ 3
C 4-1» 6 TO
O 4> E • O 4 - T Jt_ m co (o L. , i_ (0 c4-1 I_ *J 4J 4) 4 J U 3c ra o. c 4-r - "c ra oo •— « o e o— £-O E O 0 3 O E 01
" - 4 J W C , < 0 " D 4 - I O >—' eo «- C • O ) 4 J C 4-<J3 flj t_ no • • - C 3 C - U C D
*J O) M O) C D)X 1 M O W I - . eft. U M t- -; _*• •*-.-- - 3-O C-- -
i — u i t o u e o Q . -' o *-> to di o. ' ra 4>c. j«: —-— I O J 3 — «—— — D _ . o _ f - - - - • 4 - > C 4 J - <S aj C Q.m a i ' D O o "Da 41 . u o a> 4-* 4^ *^ a.=3 Oa. u
C ... ... - O J O M - O C --; - 3 — C <B — C. 3O . 0 £ . E O 4 - > O O 4J «•- -3 - (0 "O
OJO4OJ
^3 t*i h^ o*1 OJ o _ - - *o r*^ coCO O PO - Sf IA IA l/*l
- 4->t- .= O • O t-
< - . o e i o x t _ 4 - > X ' X ( _ < u . o a t** C ,__(B (00 ** C — - D O . '4J « - » + * " " C 03O « 8 . » - U 3 t - X > B J R I - C O . ' > < 0 C O < 0 3*-• 3 a t x c a i oj (n >— *-" i aj >-. c; v ra 3 •— +j 3 - o — d>
3 « u ^ o c_ aj 4J 4J 3 0) 4-1 J2 O b tfl - 4-> 3 OJ i *J (_ (D
C * QQ ^ 4 T* -- S3 3 ^ O C *~- t/1 4 4 ' C L* 4* ftf C ' TO C. *~ CDQ . 3 M < a t S U H * Q . Q . Q . 3 _ 3 i a n 3 C 3 V 4 ^ a . Q . 3 4 . O O O H -
3 t. c •*- u o •=__? cam r - t - c * - t _ < u < J } t . f u x o j 3 t. c >. TJ «- 3Q . O » O O * J - 3 T . S « i f i S ( f l £ - , Q . O l O O 4 - i < D t _ c n 3 « ^ O- Ol O JD S3 "O W
4-57 AR 10043
w
•0141)31Cl— 14-1CJ01UI
t• l
"i
vt—1-QJroti-l
UJ
XoQ.toUI
Q CsLUJ1- >-< V-Q. «-<
0 3— £
Z O "< (J.
»-i -«t tOu. z— ee-E UJ= - cju a:UI Oi- (J
_j
zUIZ C/)z zO Cfc -*— t (J
Z Oui u
zt—— iUIa= toz
u o;« ui-I Om zra oQ. O —
0 3- -o0 0.%
5to o.o «c0 U _.
UJ
1— --zceUJ1——J
, — . . ' - . -X O . ._ -,, ,--=-... ,. __. ————— -4, •• - - - _.._.._. _——f ^- _- - - - - - - ---._. -.. — .-- .... . ; . . . . . .
TO TO .QC *-• : X TO— a . - . -_,. 4-.O> 4) _c, Q. . ... . . ._ . . _. ._t- 0 D. oiTO 0 —— 0Z < : 35 «_; - - - - - -
^ - >• , . X - -, . . . .c cn - - - . — £?_ b> .,--.o .a o1" o - - ~:- -co c "o " - "" -" "-_-«" c ~o" ^ - --- -- j --j •.-- — - - ---': -"T -- 41 <U C : ~ ~ "«" S> C - . . - . . . . . __i ... ._....... .
— • O U " ,_ o O01 {_ 0 0) [_ _,OS Q. 4J - !=-_: K Q_ ^ - - - - - - - - - - - - . _ - - . .
- • '_._..._. _ _ _ _ _ _ _ _ _ _ .. - .--.= - — _: - - - . - ---_ - _ _. ----- - M c - J -....-_.
I- UJ t_ L ~o O _ - _ . . -^ -..-----—-a* u , • a> oi __ c_ • '____: .- .. :--=.;.-: -.e: 43- w bi "" " ' ""
_ t- n- *_,.-—-" O T3 J- : . . . . - - -- -3 0 L. 43,, u 5 - - - -H- 0) W" - 4Jc 4^ _._..T.._. _.__._ -::c ^, ra . . . . . .c o o . a . t o o c c ' .._....— •- •— 3 • • - - - - .i;'.— a •— ": -~ - - . ' - - - - -• ..?..- —O 4 J T J . ""jO4-" B • - • - - . . - - -£ « c •_. • -- - '.:•'.* w TO t. "" ""• -•4 - " * - 3 — 4 J t _ 4 J 4 J < UC O J O C ,,01 Q. C 4J0 ••_ i- O •- V O (0 'U E O) — .. — .- O E U O 3 , -
. ,*. . . . . - - -. i flj - - o ___ .w E < -e ..._t-- --O ' bL. to u 4-1 a> •;— *j 4-1 oj . . . . ^D) 4J C . /-4->; .^- i.TO . C -~"~ C 3 L;. o> TO J2 01 oe o o o ^. 3 . --- 3 ; (- «o c_. -0 4-*-- » a. .e ..- cM CM c - m : - . - :•*. c_ ai— "- 3 O C i ' - W ""•"" ') .'- o TJ 4 .- x - o ^ c_ 4rf o - ~; '- - '- - -- "to 01 t_ . jd._ - o *j 4> r- - - - ' - ' . " - . :4-J C .-w-OJ 0 c.-Q. . 3-1-." U. w ._ . • ; ..,.,. . . -.-.. ° -ro- ** ^ •-— Q- . Ti. ,,co c to t. - , • .-----3 •— C TO '— c_ r 3 43 01 OS 01 01 - , - .._... .C J 4 J - — 3 - W "D ' fl) O£ .n-!- o — ' Q. ' ".-- -
M , -O -O -O" CM t\J OJ^ «, - ^- ^ . . . . . . " " "__ .__._^_ .__. ._ M M ^
^ ' <- C\j" Mt^ - -, - ^O *Q *^O ""•<r ^ -.- - --:.,.. ^-^--03 Tco eo - . - . , . ,-.-,_. .. ,. ,.,
« o- - - - - - - I - L: ' 2 !i in r. c *-'• - •- • <u TO^^ - « _....._ ........ TO 0 41 t_ 0 X.,s"g — -- •"••^' --§--i" 3-:.§:r
SJ*. « 3 r o" . 33^^ * ? » S S 5 ^ ? =0 "i .- TO •£• .1.1 p-?'.t: 4. S £-2"fi .*» -a - - < - « . s.Q. 3 c. o o c- = _5 'o. 3-« c .0 o "5 «£ fi. § - ? - S o a "1 S ^ x --S :;;==£: -li 2 c £ !s -S 5 ^- 1- £ r ->; ." S 2La^wo^j B. i_ o) a - a i 0 4 - o TO-a w a r o o ^ - o 3 weo - — -, --.:-{>. - - - . . : — - ;
0)... " ~"&
TOX 4-— a.^ OJtn oi— o2= <:
-xC D>0 0
— -*M C O
. « Q> C— > -C '— -o oo L. aid£ Q. 4
Tj. W C
' — 3t- c- O O41 41 t- £_-c 4J 4-1 cn4- C C1_ ._ .. o T.3 O CD4- 4J
C u m- M O C C "— ---•*— (0 «O 4J E >t- oi M TO e_"c a> a C- 4-O «- 4> o aso e u o 3
... ..-o0 O"- 4J 4J (Uj co CT^ 4> j«f O3 • L. Ma .c — c
*J 1- TO
-. a* .c e, 4-- oO 4-1 O r— --3 — • 0 W"D CO C CO t-"<0 QJ TO OJ atfl£ J= 0 — Q.
toN1
«
T—Oo
T5CTO
C-41 C+* 0
- *-< (0 * X —3 I -J _Q 4-.O -O 4-> CO.
C -^ 4-> O t-Q. 3 « to J3 Oe o . oi u M3 t- C t- TO •_]O. O) O 4-i o ffl
o
s41
(0t- 4- "O X41 TO C "w
o 4 ai TO4J Q. TO C- , O XC E 3 4J C V —— 3-D O •- "Q.
Q. C .- — 4) Q.4-« 3 Ot 4-> 01 3O .» O 4J ra C- (fl<U *O C- •— I_ <g— i C O> W 41 _C C_C 3 ' "ffl O Q)—— O 4- M- W 4->41 C- 3 •+- X — (DC- Ol O O -Q 'B 3
4-58 AR I OOU32
LIST OF REFERENCES
Aitken, Robin (1982). Technical Section of Case DevelopmentPlan for Milford Rivet (PA-431).
Bear, J., (1979)„ Hydraulics of Groundwater. McGraw-Hill, Inc.,Israel.
Betz-Converse-Murdoch Inc., (1982). Lette'r report to Ms. SusanL. Gordon, Esquire, Morgan Lewis and Bockius.
Delaware River Basin Commission (1981). Administrative Manual-Part II, Rules of Practice and Procedure.
Delaware River Basin Commission (1982). Ground Water ProtectedArea Regulations Southeastern Pennsylvania.
Dreish, R., (1984). November 26 Letter to D.K. Donnelly, EPARegion 3.
Gilmore & Associates, Inc. (1982). Report on the Estimated TotalCosts For the Removal of Volatile Organic Compounds.
Greenman, D.W., (1955). Ground water resources of Bucks County,Pennsylvania, Pennsylvania Department of Internal Affairs,Topographic and Geol. Surv. Bull. W-ll.
Hall, G.M., (1934). Ground water in southeastern Pennsylvania,Pennsylvania Department of Environmental Resources, Topographicand Geol. Surv. Bull. W-2.
Luborsky, P.G., (1984). A hydrogeologic study of a part of theStockton Formation, Montgomery and Bucks Counties, Pennsylvania.M.Sc. Thesis, Department of Geology, University of Pennsylvania,Philadelphia, Pennsylvania.
Luborsky, P.G. and B. Molholt (1985). Raymark Site Hydrogeologicand Toxicologic Assessment.
McCarty, P.L., (1983). Removal of Organic Substances from Waterby Air Stripping, In: Control of Organic Substances in Water andWastewater, EPA-600/8-83-011, USEPA, Washington, D.C.
McCoy & Associates, (1984). The Hazardous Waste Consultant, Vol.12, No. 6.
Means, R.S. Co., Inc., (1985). Building Construction Cost Data43rd Annual Edition, Kingston, MA.Morris, J.C. and J.F. Donovan (1983). The Impact of OrganicSubstances on Municipal Wastewater Reuse, In: Control of OrganicSubstances in Water and Wastewater, EPA-600/S-83-011, USEPA,Washington, D,C.
5-1 f i R I O
NUS Corp., (1985). A Field Trip Report For Raymark, PreparedUnder TDD No. 8401-02, EPA No. PA-678, Contract No. 68-01-6699.
O'Brien, R.P and M.H. Stenzel (1984). Combining GranularActivated. Carbon and Air Stripping, Public Works, December.
Rima, D.R., Meisler, H., and Longwill, S., (1962). Geology andHydrology _of the Stockton Formation in southeastern Pennsylvania,Pennsylvania Department of Internal Affairs, Topographic andGeol. Surv. Bull. W-14.
Schwarzenbach, R.P. and J. Westall (1981). Transport of Non-Polar Organic Compounds from Surface Water to Groundwater,Laboratory Study, Environmental Science and Technology, Vol. 15,PP.- 3_60-367. _ . . " -
Sloto, R.A. and Davis, O.K., (1983). Effect of Urbanization onthe Water Resources of Warminster Township, Bucks County,Pennsylvania, U.'S. Geol. Surv. Water Resources Investigation 82-4020.
SMC-Martin Environmental Consultants (1980). HydrogeologicStudy of Fischer and Porter Company and vicinity, WarminsterTownship, Bucks County, Pennsylvania. Report prepared for Fischer.and Porter Company, Warminster, Pennsylvania.
Theis, C.V./"(1935). The relation between the lowering of thepiezometric surface and the rate and duration of discharge of awell using -ground water, storage, Trans. Amer. Geophy. Union, 2,pp. 519-524.' ! •
U.S. EPA, (1985), office-of Drinking Water Health Advisory forTrichloroethylene.
Walker/ R., (1979). November 27 Letter to Joseph Armao, Esquire,EPA, Region UI. -
Walter_B. Satterthwaite Associates, Inc., (1981). investigationof test well sites, Hatboro Borough, Montgomery County,Pennsylvania, Report prepared for Hatboro Water Authority,Hatboro, Pennsylvania.
Wassersug, S,, (1982). November 30 Memo to Peter N. Bibko,Regional Administrator, EPA Region III.
5"2 AR.OQL.3U