PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

31
FRAMINGHAM PLANNING BOARD 150 CONCORD STREET, FRAMINGHAM, MA 01702 MEMBERS OF THE PLANNING BOARD: CHRISTINE LONG, CHAIR - LEWIS COLTEN, VICE CHAIR - VICTOR ORTIZ, CLERK - SHANNON FITZPATRICK - JOSEPH NORTON 1 To: Mary Ellen Kelley, CFO and Jennifer Pratt, Assistant CFO/CPO From: Amanda Loomis, AICP, Planning Board Administrator RE: 480 Franklin Street, allocation of funds Date: March 8, 2019 On January 11, 2018, the Planning Board approved the project at 480 Franklin Street for Site Plan Review; Special Permits for Land Disturbance & Stormwater Management, Reduction in Off-street Parking, Dimensional Off-street Parking Facility regulations; Public Way Access Permit; along with Inclusionary Housing with conditions. Such conditions included the requirement for the Baystone Development, LLC (“the Applicant”) to provide a monetary contribution for the completion of the Dudley Road/Mt Wayte Bicycle Path (condition provided below). 41. To promote the decrease use of the personal automobile and support the reduction in the required number of off-street parking spaces the Applicant shall contribute $25,000 to the completion of the Dudley Road/Mt Wayte Bicycle pathway that will run along the property frontage on Mt Wayte. On January 15, 2019, the Planning Board deposited the $25,000 received the Applicant for compliance with Condition 41 of the Planning Board Decision. Such funds were deposited into the general fund and require appropriation for use by the Department of Public Works (DPW). On February 21, 2019, the Planning Board discussed the funds received from the Applicant and concurred to request the City Council to appropriate said funds for use by the DPW. Therefore, based on the February 21, 2019, Planning Board discussion and compliance with the Planning Board’s decision. The Planning Board requests that the City Council appropriate the funds received from the Applicant for use by DPW as stated in the Planning Board’s decision. Thank you and please let me know if you have any questions. Enclosures: Planning Board Decision for 480 Franklin Street, January 11, 2019 Planning Board Meeting Minutes, February 21, 2019 Deposit of Funds Letter and Documents, Re; 480 Franklin Street, Condition 41 Compliance, dated January 15, 2019

Transcript of PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Page 1: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

FRAMINGHAM PLANNING BOARD 150 CONCORD STREET, FRAMINGHAM, MA 01702

MEMBERS OF THE PLANNING BOARD: CHRISTINE LONG, CHAIR - LEWIS COLTEN, VICE CHAIR - VICTOR ORTIZ, CLERK - SHANNON FITZPATRICK - JOSEPH NORTON

1

To: Mary Ellen Kelley, CFO and Jennifer Pratt, Assistant CFO/CPO From: Amanda Loomis, AICP, Planning Board Administrator RE: 480 Franklin Street, allocation of funds Date: March 8, 2019

On January 11, 2018, the Planning Board approved the project at 480 Franklin Street for Site Plan Review; Special Permits for Land Disturbance & Stormwater Management, Reduction in Off-street Parking, Dimensional Off-street Parking Facility regulations; Public Way Access Permit; along with Inclusionary Housing with conditions. Such conditions included the requirement for the Baystone Development, LLC (“the Applicant”) to provide a monetary contribution for the completion of the Dudley Road/Mt Wayte Bicycle Path (condition provided below).

41. To promote the decrease use of the personal automobile and support the reduction in the required number of off-street parking spaces the Applicant shall contribute $25,000 to the completion of the Dudley Road/Mt Wayte Bicycle pathway that will run along the property frontage on Mt Wayte.

On January 15, 2019, the Planning Board deposited the $25,000 received the Applicant for compliance with Condition 41 of the Planning Board Decision. Such funds were deposited into the general fund and require appropriation for use by the Department of Public Works (DPW). On February 21, 2019, the Planning Board discussed the funds received from the Applicant and concurred to request the City Council to appropriate said funds for use by the DPW. Therefore, based on the February 21, 2019, Planning Board discussion and compliance with the Planning Board’s decision. The Planning Board requests that the City Council appropriate the funds received from the Applicant for use by DPW as stated in the Planning Board’s decision. Thank you and please let me know if you have any questions. Enclosures:

Planning Board Decision for 480 Franklin Street, January 11, 2019

Planning Board Meeting Minutes, February 21, 2019

Deposit of Funds Letter and Documents, Re; 480 Franklin Street, Condition 41 Compliance, dated January 15, 2019

Page 2: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Cc: Diane Connors, Department of Public Works Eric Johnson, City Engineer, Department of Public Works Nancy Lomas, Accounting Department

Page 3: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

PERMIT I ~RAMINGHAM~~~ I~~~~ FRAMINGHAM PLANNING BOARD ,~ (~L/~N " ~UIL~) ' C~f~OW

~ftl ~ ~!~ t~ ; " ~ E i 1~;~ 150 CONCORD STREET, FRAMINGHAM, MA 01702

MEMBERS OF THE PLANNING BOARD: CHRISTINE LONG, CNAIR - LEWIS COLTEN, VICE CHAIR -VICTOR ORTIZ, CLERK -SHANNON FIRPATRICK -JOSEPH NORTON

To: Nancy Lomas

From: Amanda Loomis

Date: January 15, 2019

Re: 480 Franklin Street, Condition 41 Compliance

Please see the attached AD9 for a check #1052 from Baystone Farm Pond, LLC that was deposited today

into account 51757000-484020 in the amount of $25,000.

Please create a separate mitigation account for these funds for use in accordance with the Planning

Board's January 11, 2018, Decision Condition Number 41.

41. To promote the decrease use of the personal automobile and support the reduction in the requirednumber of off-street parking spaces the Applicant shall contribute $25,000 to the completion of theDudley Road/Mt Wayte Bicycle pathway that will run along the property frontage on Mt Wayte.

These deposited funds will require appropriation from the City Council for use by the Department of

Public Works (DPW).

If you have any questions or request additional information, please contact me at 508-532-5450.

Thank yo .

Page 4: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

TOWN Of FRAMINGHAM

SCHEDULE OF DEPARTMENTAL PAYMENTS TO TREASURER

No. 175 Dept. Planning Board Date 1/15/2019

FROM WHOM REV CODE SOURCE KEY ORG ACCOUNT AMOUNTChecks TOTAL

P8593 Plannin Board 593 Accounts 51757000 484020

PBANR A royal Not Re wired Fees Plannin Brd 01750005 432104

PBCOP Co ies-Ma B Laws Fees Plannin Board 01750005 432002

PBFLFE FIIin Fees Plannin Board 01750005 432100

PBMISC Misc Non-Recurrin Revenue Plannin Brd 01750005 484000

PBODR Other De artmental Revenue Plan Board 01750005 437000

PBPBIC Public Access Permits Plannin Board 01750005 445031

PBPHRE Tele hone Reimbursement Plannin Board 01750021 53401

PBPHRL Lon Distance Reimbursement Plan Board 01750021 53403

PBSCEN Scenic Wa Fees Plannin Board 01750005 432105

PBSITE Site Plan Fees Planing Board 01750005 432106

P8516N Si n WaiverA lications 01750005 432107

PBSPCL S ecial Permit Plannin Board 01750005 445030

PBSPCL S ecial Permit Plannin Board 01750005 445030

PBSREG Subdivision Re ulations Plannin Board 01750005 432102 $

PBSUB Sub Division Fees Plannin Board 01750005 432103

CKtt1052 8a stone Farm Pond LLC PBBOND Planni~ Board Bond Accounts 51757100 484020 $25,000.00 $ 25 000.00

PBBOND Plannin Board Bond Accounts 51757100 484020 $

PBBOND Plannin Board Bond Accounts 51757100 484020 $

PBBOND Plannin Board Bond Accounts 51757100 484020 $

PBBOND Plannin Board Bond Accounts 51757100 484020

PBBOND Plannin Board Bond Accounts 51757100 454020 $

P8593 Plannin Board 593 Accounts 51757000 484020 $

PB593 Planning Board 593 Accounts 51757000 484020 $ -

Fee for 480 Franklin Street -Condition of Plannin Board Decision $

$ -

Total $ 25,000.00 $ 25,000.00

No. 175 Date 1/15/2019

The above is a detailed list of moneys collected by me, amounting in the aggregate to

Twenty-five thousand dollars 00/100------------------- - Dollars,

for the period ,which

have paid to the Town Treasurer, whose receipts I hold therefor.

`N2,r(/ ~ o ,r v Name

Received by Treasurer's Office

~y

Page 5: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

City of FraminghamPlanning Board ,. ~..150 Concord StreetRoom 205Framingham, MA 01701

TO Mr. Roy S. MacDowell III

Baystone Farm Pond, LLC

21 Center Street

Weston, MA 02493

INVOICE N 19-1DATE: JANUARY 5, 2019

QTY DESCRIPTION UNIT PRICE LINE TOTAL

Pursuant to Condition 41 of the Planning BoardDecision regard9ng 480 Franklin Street: the

1 Applicant shall contribute $25,000 to theX25,000.00 $25,000.00

completion of the Dudley Road/My Wayte Bicyclepathway.

TOTAL $25, 000.00

Make checks payable to The City of Framingham

Page 6: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

- -- ~i~i~r96h~11~~'r11~i.~.tW~i7~6nl;l~Pwn .3=(~l~l~i~i~~-1v~.4rol~i-;til4h~Ull~it121ipr t.,;vl,l~li~,~~l_.;Lii..~J.1~i11.Y~~ lnJw;~nl.f~- :-I _...-.. -. '---- -. ,, t ,i~}, ;.

1052 ~~~~►YST'OPdE FARM POND LLC

21 CENTER STREETWESTON, MA 02493

(781)894-9898

SAFlTAWDER BAPIK, NA60-7269/2313

1 /9/2019

PAY TO THE City Of FI'al71111gh8tT1. I ~ '"25,000.00ORDER OF

Twenty-Five Thousand and 00/100*****~*~«**~*~~~~,~~*~~~~*~**~,~~~~***,~~~**~,r*~~~~****~~*~***~~**,+,~~****~*~~***~*******DOLLARS,,, _ __ a E, ~ ~ :. ~ ~ :,-.... ~~,, r~J̀ City of Framingham,_

_ Planning Board-.~ ' 150 Concord Street7 Room 205

Framingham, MA 01702 ; „,_` ,~r.~~iu~c~

planning Board Condition #41 (bike path contribution — — ~— ~V~

BAYSTONE FARM POND LLC 1052City of Framingham ;' ~ i' 1/9/2019

Date ~~ Type Reference Original Amt. Balance Due Discount Payment1/5/2019 Bill 19-1 25,000.00 25,000.00 25,000.00

Check Amount 25,000.00

*Santander - Checkin Planning Board Condition #41 (bike path contrib 25,000.00

Page 7: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

r ~ -----------------------------------._......-------

~1 i i' ~~ r~r~~ti~1N~~~~4Framingham Planning Board y~ i

Memorial Building •Room 205 • 150 Concord Street PERMIT~FRAMINGHAM ~~ ~~~ f ~ ~~~~'~J ~~~1e~

Framingham, MA 01702-8373 plan •build •grow ~ .~}~ q~}~~ ~~'

(508) 532-5450 • [email protected] 4°~,m~'~ tUT Cramp

Planning Board Members Planning Board Staff:Christine long, Chair Amanda L. Loomis, AICP, Planning Board AdministratorLewis Colten, Vice Chalr Nathaniel Eames, Associate PlannerVictor Ortiz, Clerk Raphaela Morals-Peroba, Community Outreach CoordinatorThomas F. Mahoney

Stephanie Mercandettl

FRAMINGHAM PLANNING BOARD -Notice of Decision

Regarding the Application of Baystone Development, LLCfor the Property Located at 480 Franklin Street

Decision dated January 11, 2018

Notice is hereby given in accordance with M.G.L. c. 40A, Section 15 that in the applications of BaystoneDevelopment, LLC for Board Site Plan Review; Special Permits for Land Disturbance & StormwaterManagement, Reduction in Off-street Parking, Dimensional Off-street Parking Facility Regulations; PublicWay Access Permit; along with Inclusionary Housing. The opening public hearing was held on November30, 2017, notice of the opening public hearing was published in "MetroWest Daily Newspaper" onNovember 16, 2017 and November 21, 2017. Continued public hearings were held on December 7, 2017,December 21, 2017, and January 11, 2018

The project will include the construction of new 210 new residential units, and amenities building, anda 60 seat restaurant, the project further includes off-street parking, affordable housing units,landscaping, and other associated site improvements. The property is zoned Light Manufacturing (M-1), with an Assessor's Parcel ID of 111-50-2385-000

On January 11, 2018, the Planning Board APPROVED the application Site Plan Review; Special Permitsfor Land Disturbance & Stormwater Management, Reduction in Off-street Parking, Dimensional Off-street Parking Facility Regulations; Public Way Access Permit; along with Inclusionary Housing for theproperty located at 480 Franklin Street a DECISION was filed in the office of the City Clerk on January12, 2018.

For additional information please see the Planning Board's webpage at www.framinghamma.gov.

Christine Long, ChairFRAMINGHAM PLANNING BOARD

Any appeal from the Decision shall be made pursuant to G.L. Ch. 40A, Sec. 17 and must be filed withintwenty (20) days after the date of filing of the Decision in the office of the Town Clerk. The Notice ofDecision can be found in the MetroWest Daily Newspaper and on the Massachusetts NewspaperPublishers Association's (MNPA) website.

Page 8: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Framingham Planning Board

Memorial Building •Room 205 • 150 Concord Street

Framingham, MA 01702-8373

(508) 532-5450 • [email protected]

"~ ~ «~ ~

GITY ~PERMIT~FRAMWGHAM ~-

(~ ~ 0!8 JAIplan •build •grow ~~'~.

~~'S OFFICE

t 2 P 3= 5~ Town Clerk Stamp ~

Planning Board Members Planning Board Staff:

Christine Long, Chair Amanda L. Loomis, AICP, Planning Board Administrator

Lewis Colten, Vice Chair Nathaniel Eames, Associate Planner

Victor Ortiz, Clerk Raphaela Morals-Peroba, Community Outreach Coordinator

Thomas F. MahoneyStephanie Mercandetti

FRAMtNGHAM PLANNING BOARD -Notice of Decision

Regarding the Application of Baystone Development, LLC

for the Property Located at 480 Franklin Street

Decision dated January 11, 2018

Notice is hereby given in accordance with M.G.L. c. 40A, Section 15 that in the applications of Baystone

Development, LLC for Board Site Plan Review; Special Permits for Land Disturbance & Stormwater

Management, Reduction in Off-street Parking, Dimensional Off-street Parking Facility Regulations; Public

Way Access Permit; along with Inclusionary Housing. The opening public hearing was held on November

30, 2017, notice of the opening public hearing was published in "MetroWest Daily Newspaper" on

November 16, 2017 and November 21, 2017. Continued public hearings were held on December 7, 2017,

December 21, 2017, and January 11, 2018

The project will include the construction of new 210 new residential units, and amenities building, and

a 60 seat restaurant, the project further includes off-street parking, affordable housing units,

landscaping, and other associated site improvements. The property is zoned Light Manufacturing (M-

1), with an Assessor's Parcel ID of 111-50-2385-000

On January 11, 2018, the Planning Board APPROVED the application Site Plan Review; Special Permits

for Land Disturbance & Stormwater Management, Reduction in Off-street Parking, Dimensional Off-

street Parking Facility Regulations; Public Way Access Permit; along with Inclusionary Housing for the

property located at 480 Franklin Street a DECISION was filed in the office of the City Clerk on January

12, 2018.

For additional information please see the Planning Board's webpage at www.framinghamma.gov.

Christine Long, ChairFRAMINGHAM PLANNING BOARD

Any appeal from the Decision shall be made pursuant to G.L. Ch. 40A, Sec. 17 and must be filed within

twenty (20) days after the date of filing of the Decision in the office of the Town Clerk. The Notice of

Decision can be found in the MetroWest Daily Newspaper and on the Massachusetts Newspaper

Publishers Association's (MNPA) website.

Page 9: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Framingham Planning Board

Memorial Building •Room 205 • 150 Concord Street

Framingham, MA 01702-8373

(508) 532-5450 • planning [email protected]

Planning Board Members;Christine Long, ChalrLewis Colten, Vice ChairVictor Ortfz, ClerkThomas F. MahoneyStephanie Mercandettl

~ ~ ,.~ s~op:i. 'F

~ aor,I

DECISION OF THE FRAMINGHAM PLANNING BOARD

ON THE APPLICATION OF BAYSTONE DEVELOPMENT, LLC

FOR THE PROPERTY LOCATED AT 480 FRANKLIN STREET

DECISION DATED JANUARY 11, 2018

General Property InformationProject Number: PB-23-17

Property Address: 480 Franklin StreetAssessor's Information: 111-50-2385-000Zoning District: Light Manufacturing (M-~)

Application InformationApplication(s): Site Plan Review; Special Permits for Land Disturbance & Stormwater Management, Reduction in Off-streetParking, Dimensional OfF-street Parking Facility Regulations; Public Way Access Permit; along with Inclusionary HousingDate applications) were filed with the Planning Board: November 13, 2017Date applications) were filed with the Town Clerk: November 13, 2017

General Project Contact InformationApplicant Name and Address: Baystone Development, LLC, 21 Center Street, Weston, MAProperty Owner Name and Address: Framingham Franklin, LLC, PO Box 166, Shrewsbury, MAProject Contact Name: Peter Barbieri, Esquire, Fletcher Tilton, 161 Worcester Road, Suite 501, Framingham, MAEngineering Company: Bohler Engineering, 352 Turnpike Road, Suite 201, Southborough, MA

Legal Ad &Public Fi~arin~ InformationMetroWest Daily News Run dates of the Legal Ad. (14 days prior) November 16, 2017 and(7 days prior) November 21, 2016Date of abutter/7 Abutting municipalities/parties of interest mailing; November 16, 2017Date of opening public hearing: November 30, 2017

w~

Continued Public Hearings: December 7, 2017, December 21, 2017, January 11, 2018

PLANNING BOARD PLAN APPROVAL INFORMATIONDate of Plan reviewed and approved by the Planning Board: November 8, 2017, revised through January 2, 2018

Zoning Board of AppealsThe Zoning Board of Appeals granted the Applicant a Use Variance, Variance for height, a Variance for more than oneprincipal use, and a Special Permit for a restaurant on September 12, 2017 (stamped with the Town Clerk on September15, 2017).

m

Page 10: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Framingham Planning Board pERMIT~ FRAMINGHAM

Memorial Building •Room 205 • 150 Concord Street

Framingham, MA 01702-8373 plan ~~ i~uilcl ~~ gt~ow

(508) 532-5450 ■ [email protected]

Planning Board Members:Christine Long, ChairLewis Colten, Vice ChairVictor Ortiz, ClerkThomas F. MahoneyStephanie Mercandetti

DECISION OF THE FRAMINGHAM PLANNING BOARD

ON THE APPLICATION OF BAYSTONE DEVELOPMENT, LLC

FOR THE PROPERTY LOCATED AT 480 FRANKLIN STREET

DECISION DATED JANUARY 11, 2018

General Property InformationProject Number: PB-23-17Property Address: 480 Franklin StreetAssessor's Information: 111-50-2385-000Zoning District: Light Manufacturing (M-1)

Application InformationApplication(s): Site Plan Review; Special Permits for Land Disturbance & Stormwater Management, Reduction in Off-street

Parking, Dimensional Off-street Parking Facility Regulations; Public Way Access Permit; along with Inclusionary HousingDate applications) were filed with the Planning Board: November 13, 2017Date applications) were filed with the Town Clerk: November 13, 2017

General Protect Contact InformationApplicant Name and Address: Baystone Development, LLC, 21 Center Street, Weston, MAProperty Owner Name and Address: Framingham Franklin, LLC, PO Box 166, Shrewsbury, MAProject Contact Name: Peter Barbieri, Esquire, Fletcher Tilton, 161 Worcester Road, Suite 501, Framingham, MAEngineering Company: Bohler Engineering, 352 Turnpike Road, Suite 201, Southborough, MA

Leal Ad &Public Hearing InformationMetroWest Daily News Run dates of the Legal Ad: (14 days prior) November 16, 2017 and(7 days prior) November 21, 2016Date of abutter/7 Abutting municipalities/parties of interest mailing: November 16, 2017

Date of opening public hearing: November 30, 2017Continued Public Hearings: December 7, 2017, December 21, 2017, January 11, 2018

PLANNING BOARD PLAN APPROVAL INFORMATIONDate of Plan reviewed and approved by the Planning Board: November 8, 2017, revised through January 2, 2018

Zoning Board of AppealsThe Zoning Board of Appeals granted the Applicant a Use Variance, Variance for height, a Variance for more than oneprincipal use, and a Special Permit for a restaurant on September 12, 2017 (stamped with the Town Clerk on September15, 2017).

Page 11: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

PROJECT DESCRIPTION

The project at 480 Franklin Street is a multi-use development that will include the construction of three

residential buildings that will be comprised of 210 residential units; an amenity building that will support the

residents of the project, and a 60-seat restaurant. The residential portion of the project will provide ten percent

of the units as affordable in compliance with Section V.H of the Framingham Zoning By-Law/Ordinance. The

project will be supported by 354 off-street parking spaces for the 210 residential units and 25 off-street parking

spaces to support the 60-seat restaurant.

The property is approximately 6.7 acres of land, located in the Light Manufacturing (M-1) Zoning District. The

Applicant filed an application with the Zoning Board of Appeals to request a Use Variance for the construction of

210 residential units; a Variance for height to allow the construction of four story, 59-foot buildings, a Variance

for more than one principal use, and a Special Permit for the construction of a restaurant within a residential

project. Such request for zoning relief was granted by the Zoning Board of Appeals on September 12, 2017.

PUBLIC HEARING

The Framingham Planning Board held a series of public hearings for the project at 480 Franklin Street. The

opening public hearing was held on November 30, 2017. Continued public hearings were held on December 7,

2017, December 21, 2017, and January 11, 2018. Planning Board members present during the public hearing

included the following: Christine Long, Chair; Lewis Colten, Vice-Chair; Victor Ortiz, Clerk; Thomas Mahoney; and

Stephanie Mercandetti (absent on December 7, 2017; December 21, 2017; and January 11, 2018). During the

course of the public hearing process, the following individuals appeared on behalf of the Applicant: Peter R.

Barbieri, Esquire, Fletcher Tilton PC; Roy MacDowell, Baystone Development, LLC; John Kucich, P.E., Bohler

Engineering; Jason S. Sobel, P.E., PTO E, Green International Affiliates, Inc. (Traffic); Matt Marotta, Icon

Architecture, Inc.

Summary of Minutes

On November 30, 2017, the Planning Board opened the public hearing, read the legal ad into the record, and started the

public hearing process.

On November 30, 2017, Attorney Barbieri provided an overview of the project, past permitting history, and the recent

Zoning Board of Appeals (ZBA) Decision granted for the property. Attorney Barbieri stated that approximately 1,000sf of

the property was located within the 125 foot wetlands buffer and would require review by the Conservation

Commission. Attorney Barbieri also noted that currently approximately 7 percent of the site is classified as open space,

however, post- construction the site will contain 30 percent open space. The project team including Mr. Kucich (site

design and engineering), Mr. Mirva (architecture), Mr. Sobel, and Mr. Marotta presented project details regarding their

respective expertise.

Mr. MacDowell stated that a force main was installed outside of the utility easement and that as part of the project it

would be relocated into the easement at the expense of the Applicant.

On December 7, 2017, Mr. MacDowel) provided an overview of a recent meeting with the Department of Public Worl<s

(DPW). Mr. MacDowell stated that DPW provided traffic information for the abutting roadways. Mr. MacDowell's

project team presented on traffic, architectural renderings, and other site designs.

On December 21, 2017, Mr. MacDowell provided the Planning Board with an overview of the updates made to the

project since the last public hearing. Mr. MacDowell requested that Mr. Kucich and Mr. Marotta provide an overview of

the site plan and architecture amendments made to the project.

Page 12: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Mr. Kucich stated that the site had approximately 23 percent (after amendments the project will include 30.1 percent

which was stated during a public hearing) ofthe total land area as green space. Mr. Kucich noted that recent

amendments to the site plan, which included infiltration basins for each building, resulted in an increase in open space

and infiltration, Mr. Marotta provided an overview of the revised architecture, the removal of the townhouses, the

addition of an amenities building, and other associated architectural improvements.

Mr. Marotta stated that the removal of the townhouses and the relocation of said residential units to the rear building

allowed for the construction of a 10,000sf amenities building. The new amenities building would include a fitness center,

the leasing office, a community room, theater room, and a patio area.

The Planning Board provided the following comments

Stephanie Mercandetti

o November 30, 2107: Ms, Mercandetti provided comments regarding the need to break up the massing and

utilization of step backs to break up the bulk of the project. It was noted that pedestrian connections are

plentiful throughout the site but need to connect the townhouses to the rest of the project. Ms. Mercandetti

requested clarification regarding snow storage. Ms. Mercandetti requested clarification regarding the locations

of the affordable units.

• Christin Long

o November 30, 2017: Ms. Long stated that the architectural renderings for the site needed to be revised and the

use of brick or stone should be incorporated and that the project should not look monotonous or like a

"stepford" housing project. Ms. Long noted several other developments that have made good use of materials

and architectural details to provide a more residential, unique look rather than a look of a subdivision. Ms. Long

requested a fiscal impact statement for the project. Ms. Long asked that the applicant work with the abutting

property owners, particularly the owner of the Wine Vault to ensure that access is provided to their sites and

cooperation and good will is extended to those abutters. Ms. Long requested for the removal of the bollards

between the Wine Vault property and 480 Franklin Street. Ms. Long requested that the Applicant look into how

to deal with access onto Mt Wayte to prevent traffic issues.

o December 7, 2017: Ms. Long stated the need for a traffic peer review consultant. Thomas Mahoney requested

that if the number were run with an ITE, then enough data would be provided to have a limited review. Justify

the use of the 2013 and 2017 numbers with a focus on the intersection at Franklin Street and Dudley Road.

Victor Ortiz questioned the queuing that would occur at the intersection and the distance before traffic would

blocl<the intersection on Dudley Road.

~ Lewis Colten

o November 30, 2017: Mr. Colten stated that just getting the site improved is much appreciated. Mr. Colten stated

his concern regarding the type of project, leaving people needing to get into a vehicle to get places and that the

project needed more commercial amenities. Mr. Colten stated that he liked the inclusion of the restaurant. Mr.

MacDowell stated that they didn't even want to include the restaurant since the retail market is constantly

changing. Mr. Colten stated that he would rather see a taller building design with more green space. Mr. Colten

made a comment regarding the materials and colors of the buildings, noting that they were devastating and that

some fenestration was used but needed a lot more work.

Page 13: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

o Mr. Colten requested a break down in the unit count. Mr. MacDowell stated that there were 16 studios, 82 1-

bredrooms, 102 2-bedrooms, and 10 3-bedrooms, Mr. Colten requested the cost of the units. Mr. MacDowel)

stated that they would range from $1,400 to $2,800, Mr. Colten requested clarification regarding the traffic

relative to the project. Mr. MacDowell stated that residential traffic peals at different times rather than peaks

typical of retail traffic.

o On December 7, 2017: Discussion of placement of a crosswalk occurred. Lewis Colten stated that people would

walk anywhere, regardless of a formal crosswalk. Mr. Colten stated that the project needs to include a well-

defined crosswalk and pedestrian area. Ms, Long stated that people are going to walk where they want and did

not want to create avehicle/pedestrian conflict by placing a crosswalk in the middle of the parking lot. Mr.

MacDowell stated that it would be safer not to have the crosswalk across the parking lot.

o On December 21, 2017: Lewis Colten stated his appreciation for the amendments made to the architecture. Mr.

Colten requested clarification as to what would be located in the amenities building. Mr. MacDowell stated that

the amenities building would include the leasing office which would be staffed, a fitness center, club space,

dining area, and other things that are typically associated with a club. Mr. MacDowell further stated that

everything that was previously located in the amenities area next to the pool has been relocated to the new

amenities building. Mr. Colten reviewed the textures of the residential building.

• Victor Ortiz

o November 30, 2017: Mr. Ortiz stated that safety was his main concern. Mr. Ortiz requested clarification as to

how pedestrians would travel between the two properties. Mr. Ortiz questioned if the underground parking met

all the safety codes, Mr. MacDowell stated that they did. Mr. Ortiz requested clarification regarding the

circulation of the site and the use of the underground parking. Mr. Ortiz stated his concern regarding access to

the site from Mt Wayte.

• Thomas Mahoney

o November 30, 2017: Mr. Mahoney questioned if the Applicant was amendable to including a "Do Not Block the

Box" in front of the property entrance on Mt. Wayte. Mr. Mahoney questioned about the deactivation of the rail

line and it they would be amenable of it being a rail trail and give access to the tenants. Mr. MacDowell stated

that a condition could be put into the decision. Mr. Mahoney thanked the Applicant for the additional green

space. Mr. Mahoney requested that the Applicant consider warm mix asphalt for the project.

On November 30, 2017, December 7, 2017, December 21, 2017, and January 11, 2018 the Planning Board

opened the floor for public comment. Public comments were made on November 30, 2017, December 7, 2017,

December 21, 2017, and January 11, 2018. Public comments can be found in the Planning Board minutes for the

respective date.

FINDINGS

Having reviewed the application, plans, and reports filed by the Applicant and its representatives; having

considered the correspondence from the Department of Public Works (DPW), Inspectional Services (Building

Department), the Fire Department, the Police Department, the Division of Community &Economic

Development, the Conservation Commission, the Board of Health, and comments received during the TRT

Meeting and the public hearing process, the Planning Board makes the following findings:

1. Major Site Plan Review (Section VI.F of the Framingham Zoning By-Law)

a. Retain Community Character (Section VI.F.6.a)

Page 14: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

The proposed Project is consistent with the land use goals for residential use in thenearby Central Business District, as well as the Project Review Guidelines and DesignStandards discussed previously.

b. Traffic, parking, and public access (Section VI.F.6.b)

i. The existing transportation infrastructure can accommodate the Project in a safe andefficient manner. The Project will provide adequate vehicle and pedestrian access andwill not require any on-street parking as there is adequate off-street parking. Threeexisting curb cuts will be eliminated. The Project will result in a significant decrease inthe volume of traffic as compared to a commercial use of the site.

ii. The Planning Board's Peer Review Consultant (WSP) reviewed the project for traffic,

WPS states in their Traffic Engineering Peer Review of Proposed Redevelopment (datedJanuary 11, 2018) report,

1) "As indicated, based on the trip generation and slightly different commutingpatterns for residential use versus retail use, WSP recommends a spot analysisof the weekday AM peak hour operations at the intersection of Franklin Streetat Mt. Wayte Avenue. The proponent has provided additional analysis verifyingthat the off site location with the most significant project impact will operate aswell as was previously estimated (LOS D) during the AM peak hour."

2) "The 2017 TIAS provides a comparison of the total number of trips expected tobe generated by the proposed project and WSP concurs that the total numberof trips will be less than was previously proposed for the site during theweekday PM and Saturday peak hours. In addition, during the weekday PM andSaturday peak hours, the proposed development will generate fewer trips thanwere visiting the site during the 2013 traffic counts."

iii. In accordance with Section VI.F.6.b.5) of the Framingham Zoning Ordinance, theApplicant shall mitigate all derogations in Level of Service (LOS) caused by the projectthrough traffic improvements or a cash payment for mitigation procedures. TheApplicant has agreed to donate a contribution of $25,000 to the City to be held by thePlanning Board for the sole purpose and use of constructing the multi-use pathwayalong Mt Wayte Avenue. Such contribution will provide funding for makingimprovements that will connect the project to Cushing Parl</Loring Arena/KeefeTechnology School and Bowditch Field.

iv. The project has requested a decrease in the required number ofoff-street pari<ingspaces, pursuant to Section IV,B of the Framingham Zoning By-Law.

1) The project requires 445 off-street parking spaces for the development (two off-street parking spaces per unit and one off-street parking space for every threeseats of the restaurant, in addition to one off-street parking space for every twoemployees of the restaurant).

2) The project has been designed to provide 354 off-street parking spaces for the210 residential units (1.7 off-street parking spaces per unit).

3) The project includes 25 off-street parking spaces for the 60 seat restaurant uses.

Page 15: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

4) The total project will include 379 off-street parking spaces.

~ v. The Planning Board's Peer Review Consultant (WSP) reviewed the proposed off-street

parking. WPS states in their Traffic Engineering Peer Review of ProposedRedevelopment (dated January 11, 2018) report,

1) "The site has proposed 357 parking spaces, significantly higher than required as

calculated in the 2017 TIAS. WSP verified the calculation for peak parkingdemand for the residential portion of the development and agrees that the

residential portion of the development will provide more parking than isnecessary"

2) "the peak parking demand of the 2,800 square foot, 60 seat high turnover

restaurant. Based on ITE's Parking Generation, the peak parking demand for the

restaurant will be 40 spaces which is higher than the 25 spaces provided. Overall

the parking supply on site will be adequate."

vi. The off-street parking demand indicates that there is overall off-street parking capacity

on-site, if a reduction in the required number ofoff-street parking spaces was granted.

However, to ensure the separation of the commercial vs. residential uses, the Applicant

agrees to provide designated off-street parking signage for the commercial use during

specific times of peak use.

vii. The Applicant is installing five bicycle racks that accommodate 34 bicycle racks for the

residential component and two bicycle racks that accommodate 10 bicycles for the

restaurant use.

viii. In accordance with Section VI.F.5.c,1) of the Framingham Zoning By-Law, the Applicant

shall construct and/or repair sidewalks along the street frontage of the property as part

of the project and shall be ADA compliant, Given that the property does not have anysidewalks along Mt Wayte Avenue and new sidewalks have been constructed by the City

at the intersection and along Franklin Street. The Applicant has agreed to install a new

sidewalk along Mt Wayte from the new sidewalk at the intersection of Mt Wayte-Franklin Street up to the new sidewalk at the railroad bridge on Mt Wayte.

c. Environmental Impact (Section VI.F.6.c)

The proposed stormwater management system will meet the criteria set forth in the

Mass. DEP Stormwater Technical Handbook. The Project has reduced the peak rate of

runoff, volume of runoff and will improve the water quality and quantity leaving the site

with the use of Best Management Practices.

d. Health (Section VI.F.6.d)

The Project has been designed to minimize adverse air-quality impact, noise, glare andodors.

e. Public services and utilities (Section VI.F.6.e)

i. The municipal services system surrounding the site will adequately service the site.

ii. All municipal services necessary to meet the needs of the proposed use must beadequate and sufficient. Based on the Applicant's meeting and consultation with the

D

Page 16: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

City of Framingham's Department of Public Worl<s, the municipal services systemsurrounding the site will adequately service the site.

iii. Adequate and appropriate facilities will be provided for the proper operation of theproposed use, including adequate off-street parking. The proposed Project will provideadequate access and includes off-street parking at grade and below grade, totalingthree hundred fifty-three (353) parking spaces. Utility services, stormwatermanagement and landscaping are also provided as required.

f. Land Use Planning (Section VI.F.6.f)

i. The proposed Project is consistent with the land use goals of the nearby Central

Business Zoning District, as well as the guidelines outlined in the Planning Board's

Project Review Guidelines.

ii. The Applicant has secured Variances and a Special Permit from the Zoning Board of

Appeals for the use of the site for multi-family residential purposes (two hundred ten

units), a swimming pool, a restaurant (sixty seats) and for building heights of four

stories, fifty-nine feet.

iii. The use or structure is consistent with the intent of the district in which the use is

proposed, and with the Purpose and Intent of this By-Law, as a result of the receipt of

the Zoning Board of Appeals' Decision.

iv. The use or structure as developed will not create a hazard to abutters, vehicles orpedestrians. The proposed Project will eliminate three (3) curb cuts, and the design ofthe parking facility allows for proper emergency vehicle access.

2. Special Permit for Land Disturbance and Stormwater Management

The site is currently developed and covered with approximately ninety-three percent (93%)impervious surfaces. During construction, the Project will utilize temporary sediment controlsuch as dust control, installation of a construction fence, silt fence and/or wattles along the

perimeter. Silt sacks will also be installed in the existing catch basin adjacent to the site. All

construction debris will be disposed of in accordance with all Federal, State and Local

Regulations.

b. The existing on-site drainage system currently does not have proper stormwater controls. The

Project will control stormwater runoff. The proposed Project will meet and exceed the criteria

i. The site is currently developed, and there are no endangered species, wildlife habitats,natural landscape features, scenic views or historic resources associated with the site.

3. Inclusionary Housing (Section V.H of the Framingham Zoning By-Law/Ordinances)

The Applicant agrees to provide 21 Affordable Housing Units (AHU) in compliance with therequirements set forth in Section V,H of the Framingham Zoning By-Law/Ordinance. Such unitsshall be evenly dispersed throughout the site to blend within the project and not placedtogether as a cluster to be identified as such.Prior to the issuance of a building permit, the Applicant shall provide a site plan that depicts the

location of the AHUs.4. Public Way Access Permit

7

Page 17: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

a. The Owner is proposing to eliminate the three existing curb cuts. The use of two of the existing

driveways will not create a condition that is unsafe or endangers the public safety and welfare.

b. The Applicant agrees to work with the Department of Public Works (DPW) to determine and

install a "Do not block the driveway" sign is appropriate for the Mt Wayte driveway intersection.

Based on the findings as shown in the submitted documentation and as presented during the public hearing

process, the site plan and the proposed project complies with the requirements of Framingham Zoning By-Law

(Sections II.B, IV.B, IV.E, V.F, V.H, VI.E, and VI.F) and the Framingham General By-Laws (Article VI, Section S),

being consistent thereof.

CONDITIONS OF APPROVAL

The Planning Board finds that the Application and Plans submitted by the Applicant comply with all applicable

provisions of Framingham's Zoning By-Law and General By-Laws relevant to this review. Accordingly, the

Planning Board votes are pursuant to relevant provisions of these By-Laws. Therefore, said approval from the

Planning Board is subject to the following conditions:

General Provisions

1. Prior to the commencement of authorized site activity, the Applicant and the general contractor shall

meet with Planning Board Administrator, Building Commissioner, and the Framingham's Town Engineer

to review this approval.

2. Prior to the commencement of authorized site activity, the Planning Board Office shall be given written

notice within not less than 48-hours. If activity on the Property ceases for a period of longer than 30

days, then written notice shall be given within not less than 48 hours to the Planning Board Office prior

to restarting work.

3. Prior to the commencement of authorized site activity the Applicant shall provide to the Planning Board

Office the name, address and emergency contact telephone number of the individual or individuals who

shall be responsible for all activities on site and who can be reached 24 hours a day, seven days a week.

4. A copy of this Decision shall be Kept on the Property in a location that is highly visible and accessible.

5. Prior to the issuance of any Department of Inspectional Services (Building Department) permit, an

electronic copy of the approved signed Site Plan shall be provided to the Planning Board Office for

distribution to municipal departments in order to be reviewed for compliance with this Decision. The

Site Plan shall be revised if necessary to reflect the conditions of this Decision. In the event of a

discrepancy between the Decision and the Site Plan, the Decision shall tale precedence.

6. No material corrections, additions, substitutions, alterations, or any changes shall be made in any plans,

proposals, and supporting documents approved and endorsed by the Planning Board without the

written approval of the Planning Board. Any request for a material modification of this approval shall be

made in writing to the Planning Board for review and approval by the Planning Board or the Planning

Board's Administrator and shall include a description of the proposed modification, reasons the

modification is necessary, and any supporting documentation.

7. Following notice to the project manager for the Project, members or agents of the Planning Board shall

have the right to enter the Site and to gather all information, measurements, photographs and/or other

materials needed to ensure compliance with this approval. Members or agents of the Planning Board

Page 18: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

entering onto the Site for these purposes shall comply with all safety rules, regulations, and directives of

the Applicant and the Applicant's contractors.

S. The Applicant shall record this Decision with exhibits) at the Middlesex South Registry of Deeds prior to

the issuance of a building permit after the required appeal period has lapsed in accordance with M.G.L.,

c. 40A, Section 17. The Applicant shall submit proof of recording to the Planning Board. Failure to record

the decision or comply with the conditions of approval herein shall render this Decision null and void.

9. This approval for requires Site Plan Review; Special Permits for Land Disturbance & Stormwater

Management, Reduction in Off-street Parking, Dimensional Off-street Parking Facility Regulations; Public

Way Access Permit; along with Inclusionary Housing shall lapse within three years from the date that the

Decision is recorded at the Middlesex South Registry of Deeds, not including such time required to

pursue or await the determination of an appeal from the grant thereof if a substantial use thereof has

not sooner commenced except for good cause as determined by the Planning Board.

10. The failure to comply with the Framingham Zoning By-Laws, Framingham General By-Laws and/or the

terms of this Decision may result in revocation of the permit for requires Site Plan Review; Special

Permits for Land Disturbance & Stormwater Management, Reduction in Off-street Parking, Dimensional

Off-street Parking Facility Regulations; Public Way Access Permit; along with Inclusionary Housing,

issued hereunder. The Planning Board shall by first class mail send the owner written notification of any

failure to comply with the Framingham Zoning By-Laws, the Framingham General By-Laws, the Planning

Board Rules &Regulations, and/or the terms of this Decision. If the owner believes that it is not in

violation, it may request and will be granted an opportunity to attend a Planning Board meeting to try to

resolve the alleged violation. If within 30 days from the date of mailing of said notice, the owner has not

resolved the matter with the Planning Board or remedied the alleged violation, it shall be grounds for

revocation of the approvals issued hereunder. At the expiration of the 30 day period, the Planning Board

after a duly noticed public hearing, including notice to the owner by first class mail, may revoke the

approvals issued hereunder if it finds by afour-fifths vote that there has been a violation of the By-law

and/or the terms of this Decision and that the owner has failed to remedy it; alternatively, the Planning

Board may continue the public hearing, or by a four-fifth vote extend the time period in which the

violation may be corrected.

Site Construction

11. The Applicant shall perform daily cleanup of construction debris, including soil, on municipal streets

within 200 yards from the entrance of the site driveways caused by the site construction.

12. Outside construction hours are limited to 7:00 AM - 5:30 PM Monday through Friday and 8:00 AM - 4.00

PM on Saturday. Absent emergency conditions, no construction is permitted on Sunday or holidays. No

equipment on-site shall be started and allowed to warm up prior the start of the allowed construction

hours. No vehicles are to arrive at the construction site before the designated construction hours, which

includes no vehicle parking, standing or idling on adjacent public streets. Oversized deliveries of

construction materials shall occur after peak traffic hours.

13. Any work within the public right of way shall be required to have a police detail during the duration of

said work for the purpose of public safety.

14. In the event of blasting or compaction during the construction phase, the Developer's Blasting Operator

shall provide no less than ten days' advance notice of the commencement of blasting operations by

Page 19: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

certified mail to those property owners entitled to a pre-blast inspection pursuant to MassachusettsComprehensive Fire Code: 527 CMR 1.00 et seq.

a. Copies of said mailing shall be furnished to the Planning Board and the Framingham FireDepartment.

b. Copies of the blasting monitoring reports, noting any vibrations in excess of that allowable byregulation, shall be mailed to the above-referenced property owners, Planning Board and theFramingham Fire Department at the termination of blasting operations.

c. The Blasting Operator shall provide notice to the Planning Board and the Framingham FireDepartment of any reported damage to real property.

15. The Developer's Blasting Operator shall post a Blasting and/or Compaction Notice Sign in a conspicuouslocation along the roadway to inform the public of the proposed blasting for the property. Applicantshall notify all abutting residents of such blasting and/or compacting event at the time said notice isposted in a conspicuous location.

16, Said Blasting Notice Sign shall be posted at least ten days prior to any blasting on-site and abuttersnotified by mail within 500' of the property. The Developer's Blasting Operator shall encourage theabutting properties within 500' of the property boundaries to have their homes inspected at theexpense of the Applicant prior to the commencement of blasting and/or compaction. Such reports shallbe provided to the Developer's Blasting Operator prior to the commencement of blasting.

Environment

17. All stormwater and erosion control management shall be checked prior to the start and finish of eachworkday.

18. The Applicant shall check all stormwater features prior to and at the end of each construction day. In theevent a multiple day storm event occurs, the project manager shall check on the stormwater features toensure they are functioning properly and have not exceeded their capacity. Any repairs, adjustments, ordeficiencies shall be made immediately.

19. The Applicant shall provide appropriate erosion control methods such as silt fences and straw wattlesaround the stockpiles in case of a storm event, in addition to the temporary dust control requirements.

20. The Applicant shall provide straw wattles and other erosion control methods at the base of the drivewayduring off-construction hours to prevent runoff and erosion from getting onto the public way.

Snow Storage/Sidewalk/Walkway21. Snow storage shall not obstruct sight lines so as to preserve public safety.22. Snow storage shall be on-site in the snow storage areas designated on the Endorsed Site Plans. In

addition, the Applicant must remove excess snow from the site as may be deemed necessary withinforty-eight hours after the snowfall ends, in the interest of public safety.

23. Bicycle racks and sidewalk amenities shall be installed in locations, which shall not restrict or limitmovements for all users throughout the site.

24. In the event that the Applicant has to remove, cut, or modify the sidewalk along the property frontage.The Applicant shall replace said section with the same material.

25. Sidewalks throughout the site shall be constructed to be accessible by all pedestrian users.

10

Page 20: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

26. The Applicant shall provide handicap accessible ramps with rumble warning strips at the access drives.

27. The sidewalks and walkways shall be kept clear of snow, and all other impediments and/or litter

throughout the year. In the event of snow, the sidewalks and walkways shall be cleared within 48 hours

of a snow event. Snow shall not be stored on or impede access/use of sidewalks and walkways.

28. The Applicant agrees to maintain any plantings or physical landscape features at a height of two feet or

less above the adjacent roadway grade where such plantings are located within the driveway sight lines.

29. The Applicant has agreed to install a new sidewalk along Mt Wayte from the new sidewalk at the

intersection of Mt Wayte-Franklin Street up to the new sidewalk at the railroad bridge on Mt Wayte.

Inclusionary Housing30. The Applicant shall provide 21 Affordable Housing Units (AHU) pursuant to Section V.H of the

Framingham Zoning By-Law/Ordinance. Such units shall be evenly dispersed throughout the site to

blend within the project and not placed together as a cluster to be identified as such.

31. Prior to the issuance of a building permit, the Applicant shall provide a site plan that depicts the location

of the AHUs.Framingham Department Review

32. The Applicant shall comply, in all material respects, with all directives requested in the correspondence

from the Department of Public Wori<s dated December 7, 2017.

33. The Applicant shall comply with the requirements set forth in the Department of Public Health's

correspondence dated December 18, 2017 (RE; Departmental Project Review/444-480 Frani<lin Street,

Framingham, MA —from Samuel Wong, Director of Public Health, Director of Public Health).

34. The Applicant shall agree to meet with the Fire Department post Planning Board approval to ensure the

building meets Fire Code. The Applicant further agrees to comply with the Framingham Fire

Department's request for fire safety and shall meet with the Fire Department periodically prior to the

start and during the construction of the project.

35. The Applicant shall comply with the requirements set forth by the Building Commissioner, as stated in

the November 29, 2017 letter of correspondence.

36. The Applicant shall comply with the requirements set forth in the Conservation Commission's

correspondence dated December 21, 2017 (Subject: Planning Review — 444 — 480 Franklin St —from

Robert McArthur, Conservation Administrator).

Special Provisions/Periodic Conformance Reporting and Review

37. The Applicant shall provide the following performance guarantees for the Project.

a. The Applicant shall provide the Planning Board with atwo-year landscape maintenance

schedule. The Applicant shall further provide the name and contact information for said

landscaper/landscape company that will be maintaining the project for two years after the

issuance of the final use and occupancy permit. The Applicant shall place a performance bond

equal to the landscaper/landscape company's quote for the two years of maintenance.

b. Upon completion of the project and prior to the request for a final use and occupancy permit,

the Applicant shall provide the Planning Board with "As Built Plans" which shall be reviewed by

the Planning Board Administrator, for certification.

38. Prior to the issuance of a final use and occupancy permit, the Applicant shall submit an as-built plan

stamped by a Professional Engineer registered in the Commonwealth of Massachusetts certifying that all

11

Page 21: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

improvements are completed in accordance with the approved Site Plan in a form acceptable to

Framingham Department of Public Work's Engineering &Transportation Division (DPW). The as-built

plan shall be submitted in both hard copy and electronic formats (PDF and AutoCAD). The AutoCAD file

must conform to the current form of the Mass GIS Standard for Digital Plan Submission to Municipalities

or other standard requested by the Framingham DPW. The plan shall include, but not be limited to, site

utility improvements and tie-in dimensions to all pipes and connection points. The as-built information

shall be delivered to DPW a minimum of 5 business days in advance of the Applicant seeking a final

certificate of occupancy sign-off to allow time for DPW review and approval of submitted information.

The Applicant shall also submit a statement certifying that all conditions of approval of this decision

have been met and site improvements are complete.

39. The Applicant shall to install a "STOP" sign at the exit points of both driveways.

40. The Applicant shall inform the abutting residential neighbors as to when construction will commence

and provide them with contact information in the event an issue arises.

41. To promote the decrease use of the personal automobile and support the reduction in the required

number ofoff-street parking spaces the Applicant shall contribute $25,000 to the completion of the

Dudley Road/Mt Wayte Bicycle pathway that will run along the property frontage on Mt Wayte.

42. The Applicant shall reconstruct the sidewalk along Mt Wayte, across the street from the project site for

100 feet from the intersection of the Mt Wayte -Franklin Street intersection.

43. The Applicant shall install a bus stop in accordance with the requirements of the MetroWest Regional

Transportation Authority (MWRTA).

44. The Applicant shall join the MetroWest Transportation Management Association. The Applicant shall

designate a Transportation Coordinator to implement a Transportation Demand Management Program

to promote vehicle trip reduction measures including, but not limited to, ridesharing, bicycle use, public

transportation, and monetary incentives. The Transportation Coordinator shall provide copies of the

TDM Report filed with the Commonwealth of Massachusetts.

45. The Applicant shall male reasonable efforts to provide two off-street parking spaces for a car share

program. The Applicant agrees that the inclusion of a car share opportunity will further enhance the

City's goals oftransit-oriented development while further easing existing parking demands on-site.

46. The Applicant agrees to work with the local and regional transportation system to provide alternative

public transportation options within the area. Such options may include, the placement of a bicycle

share program, etc.

47. All signs and pavement markings to be installed within the Project site shall conform to the applicable

standards of the Manual on Uniform Traffic Control Devices (MUTCD).

48. The Applicant shall incorporate outdoor seating for the restaurant use; such additional shall be made

through a letter to the Planning Board and an updated site plan.

49, Prior to the issuance of a building permit, the Applicant shall submit finalized architectural renderings.

No additional vote of approval is required for the acceptance of any minor architectural changes by the

Planning Board as recommended by the Administrator.

12

Page 22: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

50. The Applicant shall conduct apost-development traffic monitoring program in order to validate the tripprojections for the Project and to evaluate operating conditions at the Franklin Street-Mt Wayte Avenueintersection. The monitoring program will include the following elements:

Obtaining traffic volume information over a continuous seven day, weeklong period at thedriveways serving the Project

b. Performing manual turning movement and vehicle classification counts during specially weekdaymorning (7:OOam to 9;OOam) peak periods and peak evening hours. project driveways on MtWayte Avenue and Franklin Street, in addition to the intersection of Franklin Street-Mt WayteAvenue intersection

c. Performing a traffic operations analysis (Level of Service, motorist delays and vehicle queuing) atthe monitored locations for the weekday morning and evening peak hours.

The monitoring program will be performed atone year and three years after the move in of the firsttenant. The results of the monitoring program will be summarized in a report provided to the PlanningBoard Administrator within 2-months after the completion of the data collection effort. The report willdocument the traffic volumes associated with the Project and will include operating conditions and themotor vehicle crash history at the monitored locations. If the measured traffic volumes associated withthe Project exceed the traffic volume projections in the Applicant's Traffic Impact Study by more than 20percent on a regular and sustained basis during the monitoring period the Applicant will identify andundertake reasonable corrective measures, for traffic associated with the project. These reasonablecorrective measures may include without limitation:

• Adjustments to the traffic signal timing at the Mt Wayte-Franklin Street intersection

51. The Applicant shall install off-street parking signage to designate commercial off-street parking spaceuse during specific hours of operation. During all other times, the off-street parking spaces can beshared between the two uses.

52. The Applicant agrees to work with the Department of Public Works to determine and provide "Do notblock the driveway" signage is appropriate at the Mt Wayte driveway intersection.

13

Page 23: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

VOTES

The Planning Board voted four in favor, zero opposed, and zero in abstention to grant a Public Way AccessPermit for Baystone Development, LLC's application for the property located at 444 — 480 Franklin Street,zoned Light Manufacturing.

Public Way Access Permit (Article VI, Section 8)

Christine Long ........................yes

Lewis Colten ... . . .................... .yes

Victor Ortiz ...........................yes

Thomas Mahoney ......................yes

The Planning Board voted four in favor, zero opposed, and zero in abstention to grant an approval withconditions a Special Permit for Reduction in the Required Number of Parking Spaces and Special Permit forRelief to Off-Street Parking Dimensional Design Standards for Baystone Development, LLC's application for theconstruction of a two hundred ten (210) unit multi family residential project with a restaurant with off-streetparking, landscaping, stormwater management system, residential space, inclusionary housing units andassociated site improvements for the property located at 444 — 480 Franklin Street.

Special Permit for Reduction in the Required Number of Parking Spaces (Section IV.B) &

Special Permit for Relief to Off-Street Parking Design Standard, (Section IV. B. 3. g.)

Christine Long .... . . . ................ .yes

LewisColten ..........................yes

Victor Ortiz ...........................yes

Thomas Mahoney . . ....... . ........... .yes

The Planning Board voted four in favor, zero opposed, and zero in abstention to grant an approval withconditions a Special Permit for Land Disturbance (Section V. F.J for Baystone Development, LLC's applicationfor the construction of a two hundred ten (210) unit multi family residential project with a restaurant with off-street parking, landscaping, stormwater management system, residential space, inclusionary housing unitsand associated site improvements for the property located at 444 — 480 Franklin Street.

Special Permit for Land Disturbance and Stormwater Management (Section V. F.)

Christine Long .... . ....... . ........ . . .yes

LewisColten ..........................yes

Victor Ortiz .......... . ....... . . . ......yes

Thomas Mahoney ......................yes

14

Page 24: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

The Planning Board voted four in favor, zero opposed, and zero in abstention to grant an approval withconditions for Major Site Plan Review (Section Vl. F.) related to Baystone Development, LLC's application forthe construction of a two hundred ten (210) unit multi family residential project with a restaurant with off-street parking, landscaping, stormwater management system, residential, inclusionary housing units andassociated site improvements for the property located at 444 — 480 Franklin Street, zoned LightManufacturing.

Major Site Plan Review (Section VI. F.)

Christine Long ..... . ............ . .....yesLewisColten ..........................yesVictor Ortiz ... . .......... . ............yesThomas Mahoney ...... . . ..............yes

By: / ,~'rChristi ong, Chair Framingham Planning Board

Date o ignatur anuary 11, 2018

15

Page 25: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

EXHIBITS

Not attached unless indicated

The Applicant has filed with the Planning Board various plans and reports required under the requirements of

the Framingham Zoning By-Laws/Ordinances and the Framingham General By-Laws. During the review process,

the Applicant and its professional consultants also submitted revisions to plans in response to requests by the

Planning Board and by the various town departments that reviewed the Project. All of these plans, reports and

correspondence are contained in the Planning Board's files and are hereby incorporated into this Decision by

reference.

1, Form A —Application Cover Letter for the property at 480 Franklin Street (PB-23-17), stamped with the

Town Clerl<on November 13, 2017

2, Form E-1—Site Plan Review Application for the property at 480 Franklin Street (PB-23-17), stamped with

the Town Clerl< on November 13, 2017

3. Form I —Special Permit Application for the property at 480 Franklin Street (PB-23-17), stamped with the

Town Clerl< on November 13, 2017

4. Form J —Special Permit for Land Disturbance and Stormwater Management for the property at 480

Franklin Street (PB-23-17), stamped with the Town Clerk on November 13, 2017

5. Form P —Cover Letter for General By-Law Applications for the property at 480 Franklin Street (PB-23-

17), stamped with the Town Clerk on November 13, 2017

6. Form Q—Public Way Access Permit Application for-the property at 480 Franklin Street (PB-23-17),

stamped with the Town Clerk on November 13, 2017

7. Development Impact Statement for Baystone Development, LLC, 480 Franklin Street, Framingham, MA,

dated November 2017

8. Drainage Report for Baystone Development, proposed 444-480 Franklin Street, Framingham, MA,

prepared by Bohler Engineering, November 8, 2017

9. Site Development Plans for Batstone Development, 444-480 Franklin Street, Town of Framingham, ,

prepared by Bohler Engineering, dated November 8, 2017, revised through January 2, 2018

10. Architectural renderings prepared by ICON Architecture, dated November S, 2017, revised through

January 11, 2018

11. Traffic Impact and Access Stduy, proposed 444-480 Franklin Street Development, Framingham, MA,

prepared for Baystone Development, prepared by Green International Affiliates, Inc,, Dated November

2017

12. Letter of information from Fletcher Tilton, RE: 444-480 Franklin Street, dated December 5, 2017

13. Letter of response from Bohler Engineering, Re: Response to Comments, Baystone Development, 480

Franklin Street, Framingham, MA, dated January 2, 2108

14. Letter of response from Bohler Engineering, Re: Baystone Development — 480 Franklin Street,

Framingham, dated January 2, 2018

The Planning Board received correspondence various municipal Departments who review the project. The

previously mentioned correspondence is contained in the Planning Board files and is incorporated herein by

reference.

1. Form B —Building Department Recognition Form —Inspectional Services Division, dated November 3,

2017

16

Page 26: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

2. Town of Framingham Planning Board —Special Permit and Site Plan Review Checklist for Application

Submittal, for the property at 480 Franklin Street (PB-23-17), stamped with the Town Clerk on

November 13, 2017

3. Framingham Planning Board —Public Way Access Permit and Modification to a Scenic Way Permit

Checklist for Application Submittal for the property at 480 Franklin Street (PB-23-17), stamped with the

Town Clerk on November 13, 2017

4. Framingham Planning Board —Notice of Public Hearing, Property Located at 444-480 Franklin Street,

advertised in the MetroWest Daily Newspaper on November 16, 2017 and November 21, 2017, stamped

with the Town Clerk on November 13, 2017

5. Interoffice Memo, Project Review Request and Timeline, Re: Departmental Project Review —Project

Loaded to ACCELA for 480 Franklin Street (PB-23-17), dated November 13, 2017

6. Peer Review Traffic Report, prepared by WSP, Re: Traffic Engineering Peer Review of Proposed

Redevelopment, dated January 11, 2018

7. Letter of comment from the Town of Framingham, Department of Public Health, Re: Departmental

Project Review/PB-23-17/444-480 Franklin Street, Framingham, dated December 18, 2017

8. Correspondence of comment received via ACCELA from the Framingham Police Department, dated

December 6, 2017

9. Correspondence of comment received via ACCELA from the Framingham Fire Department, dated

November 29, 2017

10. Correspondence of comment received via ACCELA from the Framingham Department of Inspectional

Services (Building Department), dated November 29, 2017

11. Letter of comment from the Department of Public Works, Re: Baystone Development — 480 Franklin

Street, Framingham, dated December 7, 2017

12. Letter of comment from the Framingham Division of Community &Economic Development, Re:

Departmental Project Review, 480 Franklin Stree, dated December 18, 2017

13. Letter of comment from the Town of Framingham, DPW —Conservation &Open Space, Subject: Planning

Review — 444-480 Franklin St, Dated December 21, 2017

17

Page 27: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

~J~ 1 1 `J~l ~,I'4 i~~i ~il i:d i~lil~~lii

.. 1 ~ _ ~-. +n I 1 4 L~ ~~ ~ i~ i ~ t..

i ~I. .. i

(, , ~--', '~; , ,'°, MEMORIAL BUILDING-ROOM 205 ~ ~'~"~PERMIl` FI~~MINGHAM~~MIINGHAM 150 CONCORD STREET, FRAMINGHAM, MA 01702

MASSACHUSETTS 508.532.5450 - [email protected] ~ PLAN ~ BUILD •GROW

PLANNING BOARDCHRISTINE LONG, CHAIR AMANDA LOOMIS, PLANNING BOARD ADMINISTRATOF

LEWIS COLTEN, VICE CHAIR NATHANIEL EAMES, ASSOCIATE PLANNEF

VICTOR ORTIZ, CLERK

SHANNON FITZPATRICK

JOSEPH NORTON MINUTES

FEBRUARY 21, 20'I9, ABLONDI ROOM, 7:OOPM

Present for the Public Hearing: Christine Long, Chair; Lewis Colten, Vice-Chair; Victor Ortiz,

Clerk; Shannon Fitzpatrick, and Joseph Norton

Christine Long, Chair, read the agenda into the record and called the Planning Board meeting

to order at 7:00 p.m. on Thursday, February 21, 2019.

I. Minutes —February 14, 2019

Shannon Fitzpatrick moved that the Planning Board approve the minutes of February 14, 2019

with the addition of Ms. Fitzpatrick's comment, as presented. Joseph Norton seconded the

motion. The Planning Board voted to approve the motion. MOTION PASSED 4-0-0.

11. Public Hearings

630 Worcester Road —Application of Union Twist, Inc. for Minor Site Plan Review

Present for the Applicant: Amy McNamee, CEO; Marie St. Fleur, COO; Attorney

Daniel Glissman, Prince Lobel Tye, LLP

Christine Long, Chair, opened the public hearing, read the legal ad into the record,

and turned the floor over to the Applicant.

The Union Twist team introduced themselves for the record and stated that they did

not have any comments.

Ms. Long requested comments from members of the Planning Board. No comments

were provided.

Ms. Long asked for public comment. No public comments were provided.

Lewis Colten moved that the Planning Board close the public hearing. Joseph

Norton seconded the motion. The Planning Board voted in favor of the motion 4-0-

0. MOTION PASSES

Framingham Planning Board Minutes Page 1 of5 February 21, 2019

Page 28: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

Lewis Colten moved that the Planning Board approved the Application for Minor

Site Plan Review, with conditions for the Applicant Union Twist. Joseph Norton

seconded the motion. The Planning Board voted in favor of the motion 4-0-0.MOTION PASSED

1020, 1060, 1062, and 1062A Grove Street and 2, 36, and 40 Winch Street, and 40

Winch Street RR — Application of Winch Millwood Realty Trust II for a four lot

Definitive Subdivision Plan entitled "Paradise Valley" dated December 27, 2018

prepared by Bohler Engineering

Present for the Public hearing: Michael Dryden, Bohler Engineering

Christine Long, Chair, opened the public hearing and requested an update from the

Applicant.

Mr. Dryden noted that minor changes since the last public hearing regarding the two

structures being located on one lot have been made. Mr. Dryden stated that one of

the two structures would be razed and that has been noted on the amended site

plan.

Ms. Long requested comments from members of the Planning Board. No comments

were provided.

Joseph Norton moved that the Planning Board close the public hearing. Lewis

Cotten seconded the motion. The Planning Board voted in favor of the motion 4-0-0. MOTION PASSED

Lewis Cotten moved that the Planning Board to grant the requested waivers.

Joseph Norton seconded the motion. The Planning Board voted in favor of themotion 3-0-1 (Shannon Fitzpatrick). MOTION PASSED

Joseph Norton moved that the Planning Board approve the Application for

Definitive Subdivision Plan Review, with conditions. Lewis Cotten seconded the

motion. The Planning Board voted in favor of the motion 3-0-1 (ShannonFitzpatrick). MOTION PASSED

Amend the Framingham Zoning By-law —Section I.E (Definitions), Section II.B

(Table of Use), Section J (Village B-3 Zoning District), Section IV.E (Dimensional

Regulations), Section VI.G (Variances) To see if the City Council will vote to amend

the Framingham Zoning By-Law by amending the Definitions (Section I.E), amending

the Table of Use (Section II.B) relative to B-3 Zoning, add a new Section II.J Village (B-

3) Zoning District, amend Section IV.E Dimensional Regulation relative to B-3 zoning,

and amend Section VI.G relative to B-3 Zoning.

Amend the Framingham Zoning Map —Village (B-3) Zoning District To see if the City

Council will vote to amend the Framingham Zoning Map to establish a new Village

(B-3) Zoning District in the area of Framingham known as Nobscot (intersection of

Water Street, Edmands Road, and Edgell Road) as shown on the map.

Christine Long, Chair, opened the public hearings for the Village (B-3) District Zoning

and the proposed B-3 Zoning Map amendments and requested a presentation

Framingham Planning Board Minutes Page 2 of 5 February 21, 2029

Page 29: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

regarding the intersection and related traffic improvements for the Nobscot area

from Eric Johnson, City Engineer for the City of Framingham.

Mr. Johnson provided a review of the intersection of Water Street, Edgell Road, and

Edmands Road. Mr. Johnson stated that two of the intersection sides have a very

tight turning radius and two of the intersection sides are very wide. Mr. Johnson

reviewed the widths and noted that the roadways are being modeled so that it will

be constructed correctly. Mr. Johnson further stated that it is necessary to move the

Chapel on the corner in order to perform the work since site lines are obstructed

currently with the building being located on the corner which results in a "no turn on

red" at the intersection today. With the intersection improvements due to the

relocation of the Chapel, the plan would then be to allow a right turn lane on red at

the intersection.

Mr. Johnson reviewed the funding for the intersection improvements which

included the requested funding from both the City and the State. During the

presentation Mr. Johnson stated that the project will cost approximately $3.5 million

dollars and it will be necessary for funding to be supplemented with mitigation

monies since there is a shortfall. Therefore, DPW will be requesting mitigation

monies in the future to help fund the indicated traffic improvements.

Ms. Long requested comments from the Planning Board. The following comments

were provided:

• Joseph Norton requested further details of the intersection construction and

planned improvements.

• Lewis Colten requested clarification regarding light levels and what type of

lighting would be used, and possible right turn on red onto Water Street.

• Shannon Fitzpatrick had no comments at this time.

• Christine Long asked what the expected cost of the project would be, how many

land takings are involved, and if the cost of those takings is part of the expected

cost. Ms. Long asked for clarification on State funding for the project and the

timeline involved.

Ms. Long opened the floor for public comment. No public comments were provided.

Ms. Long thanked Mr. Johnson for the presentation.

Ms. Long continued the public hearings to Thursday, March 7, 2019, at 7:OOpm.

III. Any Other BusinessChristine Long, Chair, stated that the Planning Board recently received the required $25,000

pursuant to the conditions of the Planning Board's Decision for the project at 480 Franklin

Street. Ms. Long stated that the Planning Board voted to allocate those monies to the DPW

on January 11, 2018 and therefore would be sending a request to the City Council to

appropriate the funds for use by the Department of Public Works (DPW).

_..........Framingham Planning Board Minutes Page 3 of 5 February 21, 2019

Page 30: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

IV. Public Hearing

3 and 21 Lockland Avenue —Application of Wayside Youth and Family Support

Network, Inc. for Minor Site Plan Review under Dover Amendment Uses, M.G.L. Ch.

40A, Section 3

Christine Long, Chair, read the legal ad into the record and then continued the public

hearing without testimony at the request of the Applicant to Thursday, April 4, 2019

at 7:OOpm.

• 101 Bishop Street, Application of ABC Supply Company for Minor Site Plan Review

Christine Long, Chair, opened the public hearing and then continued the public

hearing at the request of the Applicant to Thursday, March 7, 2019 at 7:OOpm.

• 15 Pleasant Street Connector, application of Amerco Real Estate Company for Minor

Site Plan Review

Present for the Public hearing: Attorney Brian Levey, Beveridge and Diamond; Daniel

Feeney, Beals and Thomas; and Scott Chase, U Haul

Christine Long, Chair, opened the public hearing and asked for an update from the

Applicant.

Attorney Levey provided a brief review of the process in in Southborough in addition

to the review of the draft decisions provided by both Framingham and

Southborough planners,

Ms. Long stated that the Planning Board has requested a determination from the

City Solicitor regarding the timeline concerned with the advertising of the Corporate

Mixed-use (CMU) District and the Approval Not Required (ANR) plan in relation to

the actual zoning that the project falls under.

Attorney Levey stated that they were disappointed that a vote would not betaken

tonight. Attorney Levey requested that instead of receiving a copy of the City

Solicitor letter of determination that they would like to have a meeting with the City

Solicitor.

Ms. Long continued the public hearing to Thursday, March 7, 2019, at 7:OOpm to

allow enough time to receive the requested information from the City Solicitor.

iv. Any Other Business

Christine Long, Chair, presented the request regarding the Clarks Hill lot releases that was provided

to Planning Board members in their packets.

Joseph Norton moved that the Planning Board approve the release of two lots as requested by the

Applicant of Clarks Hill. Shannon Fitzpatrick seconded the motion. The Planning Board voted in

favor of the motion 4-0-0. MOTION PASSED

Framingham Planning Board Minutes Page 4 of 5 February 21, 2019

Page 31: PLANNING BOARD CHRISTINE LONG CHAIR LEWIS COLTEN …

v. Administrator's Report

vi.

No Administrator Report will be provided.

Member Reports

No Planning Board member reports were provided.

vii. Adjournment

Shannon Fitzpatrick moved that the Planning Board adjourn. Lewis Colten seconded the

motion. The Planning Board voted 4-0-0 to approve the motion. MOTION PASSED

The Planning Board adjourned the meeting of January 2~, 2019, at 7:43pm.~.

~w~

Christine bong, Chair of the Planning Board

t.Dated: ~ ~ ~~~~~"~

__Framingham Planning Board Minutes Page 5 of 5 February 21, 2019