Planning and Development Committee West Corridor Update May 10, 2007.
Transcript of Planning and Development Committee West Corridor Update May 10, 2007.
Planning and Development Committee
West Corridor UpdateMay 10, 2007
Since March Meeting
RTD received a request in early April from the jurisdictions to postpone five VE items until the May board meeting.
•Federal Bridge
•Ped Bridges & Bike Path through the Park
•Single Track to Jeffco
•Changes to Drainage Plan
•Sheridan Station/Bridge
In Addition
•Auraria has request additional review time for the Auraria station changes
•Denver has requested RTD look at moving the Decatur station – as part of a Transit Oriented Development (TOD) opportunity.
Federal Blvd. Bridge
Action: Further analysis with the CM/GC determined the barrel vault structure type is not feasible in this location. This is no longer a VE item.
Current proposed structure type will be precast concrete box girder.
Status: Need concurrence from CDOT and Denver on new design, CDOT on increased cost of bridge replacement.
Ped Bridges and Bike Path in Parks
Original VE proposal was to eliminate the three pedestrian bridges through the park section in Denver. Also proposed to change the bike path material from concrete to asphalt.
Action:
Park Pedestrian bridges won’t be eliminated and bike paths won’t be changed.
RTD to cover $1 M of ped bridges
Park Mitigation Funds to cover $1 M of ped bridges
Park Mitigation Funds to cover delta of $.5M for bike path
Status – These VE proposals with stated changes are going to the RTD board on May 15
Single Track from DFC to Jeffco
Single Track is an RTD operational issue, not a service level issue for Jeffco
RTD was planning 15 minute frequencies with double track, no change with single track
Ridership forecasts don’t warrant a change in headways until after ???
Headways of 10 minutes could be attainable with additional passing track east of Colfax– estimated cost $3 million (2006$)
5 minute headways require double track, and additional bore under I-70 (estimated in Year ????) RTD will ensure that CDOT not preclude second bore if and when I-70 is rebuilt at this location.
Original plan was to bring all drainage improvements in the corridor to the 100 year eventIssue: RTD cannot afford this in all locations and has proposed alternatives
VE proposal to consider changes to design criteria
– Will adhere to local jurisdiction and UDFCD design standards as a minimum
– Maintain track and station operational effectiveness
– Not impact adjacent property or public safety
–Meet the requirements of the 100 year FEMA flood plan
Changes to Drainage Plan
Drainage Plan
Status:•Met with stakeholders on March 27
•Met with Denver and UDFCD on April 10 and May 8th to focus on resolution
•Continue to work with affected parties to discuss specific concerns
•Meetings continue to focus on individual area drainage issues
The original plan was to raise Sheridan Blvd and place light rail under the road, with the station directly below Sheridan Blvd.
Challenge: The VE proposal is to leave Sheridan at its current location and build light rail on a bridge over the top of Sheridan, with the station on the west approach to Sheridan Blvd.
VE proposal has been modified to increase clearance over Sheridan to allow future CDOT roadway improvements. VE savings reduced from $10.5 M to $7.7 M.
Sheridan Station
$7.7 M funding shortfall for Sheridan$3.5 M from Park Mitigation Funds possible$4.2 M gap
Possibilities for Funding the Gap1.Money could be recouped from sale of the
property necessary to build Sheridan over2.Additional cost savings are being discussed
on bridge traffic control and construction methodology
Requires further discussion with stakeholders (Denver, CDOT) and the RTD Board
Sheridan Station
StatusMet with CDOT, Denver and Lakewood on April 30 to discuss Sheridan alternatives and funding options. Follow up meeting on May 14.
Sheridan Station
Auraria StationRTD, Denver and AHEC need further discussion on station location vis-à-vis overall Campus Master Plan
DecaturRTD and Denver are discussing relocating the station as part of a TOD opportunity. Discussions ongoing on cost implications. Possible private funding opportunity.
Auraria and Decatur
Value Engineering Status
The RTD Board will take action on 37 VE items on May 15. RTD will continue to work with the stakeholders on these remaining items. These items will go to the RTD board at the June 19 meeting.
•Single Track to Jeffco
•Changes to Drainage Plan
•Sheridan Station/Bridge
•Auraria Station
•Decatur Station
West Corridor Schedule
Mar-Jun ‘07 Stakeholder design workshops (inc. VE)
May ‘07- Rail Removal/Utility RelocationApr ’08
May 15 RTD Board action on 37 of the 41 VE items
May 16 Groundbreaking Event/Rail removal
May 19 RTD Board retreat Review of FasTracks program including West Corridor budget
June 19 RTD Board action on remaining 4 items
Schedule
July ‘07 Informal Design Review (VE items only)
Aug ‘07 Draft EA released for comment& EA Public Hearing
Sept ‘07 EA Finalized and submitted for approval
Oct ‘07 FONSI from FTA
Nov ‘07 90% Design Submittal
Nov ‘07 FFGA Application Submittal
Early ’08 Guaranteed Maximum Price Due
Spr/Sum’08 Full Construction Begins
Schedule Con’t