For Immediate Release:
Friday, May 20, 2016 Contact:
Annalysce Baker
470.891.2992
Plan Ahead to Survive Summer 2016 Road Construction
Georgia DOT Announces Active Season Statewide
ATLANTA – It’s springtime in Georgia. And summer is right around the corner – the time for lazy days,
for cookouts and for fun. It’s when we welcome visitors and hit the road with family and friends for outings
and vacations. It’s also the season for road construction.
Today Georgia Department of Transportation announced plans for one of the busiest summer construction
seasons Georgia has seen in years, with more than 470 active construction and maintenance projects along
interstates and state routes across Georgia.
While Georgia DOT is doing its part to limit impacts to the public, motorists should prepare for longer than
normal traffic delays.
“This summer’s construction and maintenance activities will ultimately save taxpayers millions of dollars.
Performing maintenance now prevents major repairs later. It also results in less wear and tear on vehicles,”
said Georgia DOT Commissioner Russell R. McMurry, P.E. “We ask you to plan ahead and know before
you go. By knowing what work we are doing and where we are doing it, you can minimize your travel time
and your frustration.”
In Metro Atlanta, construction of the Georgia Express Lanes network continues with construction of the
Northwest Corridor Express Lanes project that adds reversible lanes on portions of I-75 and I-575 in Cobb
and Cherokee counties; the addition of reversible, barrier-separated I-75 South Metro Express Lanes and
ITS infrastructure in Henry and Clayton counties; and 10 miles of construction to begin late this summer for
the I-85 Express Lanes Extension.
Other Metro Atlanta projects include:
Major resurfacing and maintenance of a six-mile stretch of I-75 from SR 54 in Clayton County
through the Downtown Connector to the Brookwood Interchange is expected to be awarded in June.
In Fulton, Cobb and Douglas counties resurfacing on I-20 from Hill Street to Thornton Road and
operational improvements at the I-20 EB/I-285 interchange.
Reconstruction of the Atlanta Road Bridge and Orchard Road Bridge over I-285 in Cobb County.
Roundabout construction at I-285 at Riverside Drive in Fulton County.
Ramp meter installation at interchanges on I-20 on the west side of Atlanta from SR 5 to SR
139/MLK Jr. Drive in Fulton, Cobb and Douglas counties.
Summer maintenance and ongoing construction projects affect all regions of the state.
In Northwest Ga., there is resurfacing on I-75 in Catoosa County from US 41 to the Tennessee state
line. Carroll County has concrete rehabilitation on I-20 from SR 1/US 27 to SR 61.
Visit us on Facebook or Twitter.
Visit us on Facebook or Twitter.
In Northeast Ga., Forsyth County has widening and reconstruction on GA 400 from McFarland
Parkway interchange to SR 369/Browns Bridge Road.
In East Central Ga., there are sign replacements at 22 locations on I-20 in Newton and Richmond
counties.
In West Central Ga., new interchange construction just broke ground on I-85 at Poplar Road in
Coweta County.
In Southeast Ga., reconstruction and rehabilitation of an interchange at I-95 and SR 251 in McIntosh
County continues. In Chatham County, bridge preservation projects at 22 locations on I-95 are
scheduled for completion within 12 months.
Ongoing projects in Southwest Ga. include resurfacing I-75 from Southwell Road to SR 32 in Tift
and Turner counties; and rehabilitation and replacement of portions of bridge deck on I-75 at Old
Clyattville Road in Lowndes County.
For details on these and the other major projects across Georgia, visit 511ga.org.
Here’s how you can survive summer construction:
Plan ahead. Before you get into your car – call 511 or visit 511ga.org for real-time information about
statewide road conditions. There’s also a link to 511 on Georgia DOT’s homepage at dot.ga.gov.
For the statewide list of summer construction projects, visit
www.dot.ga.gov/Documents/2016SummerConstructionProjectList.pdf.
Seek commute options like carpooling, GRTA, MARTA or county transit.
Be flexible - if your employer agrees, consider telework, compressed work week or flextime. Visit
Georgia Commute Options at www.gacommuteoptions.com.
Drive Alert and Arrive Alive – always buckle up, stay off the phone and no texting, and drive alert
with no distractions.
Obey the rules in work zones – Pay Attention, Slow Down, and Watch for Workers. Keep in mind
that work zones are not always stationary. Mobile work zones include litter pickup, mowing and
sweeping.
Above all - Expect the Unexpected.
“As we move through this summer construction season, we ask that you please ‘pardon our progress,’”
McMurry said. “Your dollars are working to build a better Georgia; our workers are working to build a
better Georgia, too. Please watch out for them in your travels.”
Every day Georgia DOT employees work on roadways in close proximity to travel lanes. Whether they’re maintenance,
construction or HEROs, it’s dangerous. Fifty-eight Georgia DOT personnel and many more motorists, passengers and
contractors’ workers have been killed in work zone crashes since 1973. When you drive in a work zone, obey the rules: Pay
Attention - Slow Down - Watch for Workers. It can make the difference between life and death. Visit
www.dot.ga.gov/DS/SafetyOperation/Workzone.
1 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
DISTRICT 1 (Northeast Georgia) Mohamed Arafa 678-721-5284
County Project Name/ Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe
Dawson Intersection Improvements and VDS on SR 400 @ SR
53
SR 400 SB allowed between 7:00 pm to 5:30
am M-Thur. Single lane closures allowed
9:00 pm Sat. to 9:00 am Sun.
Comp: 5/10/17
Forsyth Widening and Reconstruction on SR 400 From McFarland Road Pkwy Interchange to SR369/
Brown Bridge Road
Southbound lane closures allowed from 9pm
to 5am, M – Th; Northbound lane closures
allowed daily from 9pm to 12pm Comp: 10/1/18
Forsyth/
Gwinnett Widening and Reconstruction SR 20 @ Chattahoochee
River @ Forsyth Co. Line
Lane Closures allowed 9:00 am to 4:00 pm
and 7:00 pm to 6:00 am, M – F.
Single lane closures allowed 10:00 am to
4:00 pm and 7:00 pm to 8:00 am, Sat. and
Sun
Comp: 5/31/2018
Forsyth Widening and Reconstruction on SR 20/Buford Hwy
Beg. at Samples Rd. and Ext. to James Burgess Rd.
Single lane closures allowed weekdays from
7pm to 6am and from 8pm to 8am on
weekends Comp: 5/31/19
Gwinnett Operational Improvements of I-85 NB from SR 140 to
Indian Trail Lilburn Rd
Lane closures allowed between 10 pm to 5am
Monday to Friday and between 10 pm Friday
to 6 am on Weekends Comp: 1/22/16
Gwinnett Resurfacing and Maintenance on SR 13 from Old
Peachtree Rd to SR 20 No lane closures between 6-9 am & 4-8 pm
M-F and 8am-9pm Sat. &Sun. Comp: 9/30/16
STATEWIDE SUMMER CONSTRUCTION PROJECTS / 2016
2 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
Gwinnett Patching and Milling and plant mix SR 13 from SR 20
West of Sawnee Ave. No Lane closures between 6-9am & 4-8 pm
M-F and 8am-9pm Sat. & Sun. Comp: 10/31/16
Gwinnett Widening and Construction of SR 20 East of Burnette
Trail to Peachtree Ind. Blvd
Single lane closures between 7:00 pm to 6:00
am Mon. Thur. and between 8pm and 6 am
on Weekends Comp: 6/1/17
Gwinnett Express Lanes I-85 N of Old Peachtree to Hamilton
Mill Rd
Lane closures allowed 8:00 pm to 5:00
am, Sun. - Thur. and between 8 pm and
9 am on Weekends; limited lane closures
allowed during daytime hours
Comp: 6/26/18
Hall Widening and reconstruction of SR 347/Friendship Rd
beginning at I-985/SR 419 and Ext. to SR 211
Lane closures allowed 9:00 am to 2:30 pm
and 6:00 pm to 6:00 am, Mon. - Thu. and
some closures on weekends.
Comp: 6/30/16
Barrow/
Gwinnett
Milling and Plant Mix Resurfacing, Shoulder
Rehabilitation of SR 8 from South of Stanley Court to
NE of Barrow County Line No lane closures 6-8:30am & 4:30-8 pm M-F Comp: 9/30/16
Clarke Resurfacing and Mai of SR 10/US78 from Gaines
School Rd to Oglethorpe County Line
No lane closures 6am -8pm m-f and no lane
closures between 3pm Friday -9am Monday
on UGA home game weekends Comp: 8/31/16
Oconee Widening and Reconstruction and Installation of
Intersection VDS of Mars Hill Rd from Hog Mtn. Rd
to SR 8/SR 316 – Phase I
Single lane closures and flagging operations
allowed 9:00 am to 4:00 pm and 7:00 pm to
6:00 am, M – F.
University of Georgia Home Football Games
Lane Closures No lane closures, flagging
operations, or any other activity will be
allowed that affects traffic between 3:00 pm
the Friday before the game until 9:00 am the
Monday after the game throughout the
Project.
Comp: 5/26/18
3 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
Franklin,
Stephens Widening and Reconstruction of SR 17 from South of
Franklin Line to North of Scott Rd and 2 bridges
Lane closures allowed 8:30 am to 4:30 pm
Fri. and 7:00 pm Fri. to 6:00 am Mon.
SR 17 (Multilane Lane) Single lane closures
allowed 8:30 am to 4:30 pm and 7:00 pm to
6:00 am, Mon. through Thur.
Comp: 5/31/16
Stephens Widening and Reconstruction on SR 17/SR 17 Alt.
from Scott Rd to Memorial Drive
Lane closures allowed 8:30 am to 4:30 pm
Fri. and 7:00 pm Fri. to 6:00 am Mon.
SR 17 (Multilane Lane) Single lane closures
allowed 8:30 am to 4:30 pm and 7:00 pm to
6:00 am, Mon. through Thur.
Comp: 4/30/16
DISTRICT 2 (East Central Georgia) Kyle Collins 478-553-3361
County Project Name/ Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe
Lincoln SR 43 @ Soap Creek E of Lincolnton Bridge
An 8.3-mile off-site detour in place for up to
18 months. Drivers on SR 43 will use SR
220, Chamberlain S Ferry Road, SR 47 and
SR 43 connector as detour routes.
7/31/17
Richmond Resurfacing & Maintenance of SR 4/ Deans Bridge
Road from W of CR 67/Morgan Rd to SR 10 (Gordon
Highway)
No lane closures and work allowed between
6:30 a.m. to 8:30 a.m. and 4 p.m. to 6 p.m.
Sunday through Saturday.
2/28/17
Jasper Resurfacing & Maintenance of SR 11 from SR 16/SR
83 (Southern Avenue) to Newton County Line
No lane closures and work shall be allowed
between 6 a.m. to 8 a.m. and 3 p.m. to 5 p.m.
Sunday through Saturday.
2/28/17
Johnson Bridge Replacement over Little Ohoopee River on
State Route 171 located North of Kite in Johnson
County
Traffic will be maintained with the addition
of an on-site detour bridge during
construction. 7/31/2017
Newton Bridge Replacement over the Yellow River on SR 36 Traffic will use SR 162 and SR 212 as an off- 5/31/18
4 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
14 miles south of Covington Bridge. site detour until the bridge is complete. Local
traffic will be allowed along SR 36 up to the
construction zone.
Richmond Resurfacing and Maintenance of SR 121 from S of CR
1503/Tobacco Rd to CR 199/Lumpkin Rd
No closures between 6:30 a.m. to 8:30 a.m.
or from 4 p.m. to 6 p.m. Sunday thru
Saturday.
TBD
Newton Widening of SR 142 from I-20 at Hazelbrand Road to
Alcovy Road and includes widening Harland Drive to
just east of Avenue of Champions.
Lane closures allowed weekdays from 6:00
am to 8:00 am and 4:00 pm to 7:00 pm. TBD
Newton,
Richmond
Replace and upgrade existing signage on I-20 @
twenty-two locations between Newton and Richmond
counties
Work to be completed utilizing shoulder
closures TBD
Newton SR 36 @ CR 181/Flat Shoals/Steel Rd and CR
506/Henderson Mill Realignment of Henderson Mill Road (CR 508)
Traffic will be maintained on existing
roadways during construction. 8/31/17
DISTRICT 3 (West Central Georgia) Kimberly Larson 706-646-7532
County Project Name/ Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe
Henry/Clayto
n
I-75 South Metro Express Lanes Add toll lanes and reversible lanes along I-75 South of
Atlanta at SR155/ McDonough Rd. and ends at
SR138/Stockbridge Highway
Weeknight: 9 p.m. - 5 a.m. northbound only Weeknight: 9 p.m. - 7 a.m. southbound only Weekends Continuously from Friday at 9
p.m. until Monday morning
Comp: 01/2017
Coweta/
Fulton/
Meriwether/
Troup
Replace striping and RPMs on I-85 from N of SR 219 in Troup County to S of SR 92 in
Fulton County
Lane closures limited to nighttime only
between 8 pm and 7 am NTP: 3/2/2016 Comp: 12/31/2016
Coweta New Interchange on I-85 @ CR 103/Poplar Rd No traffic interruptions on I-85 weekdays
from 6am to 9am (northbound) and weekdays
from 4pm to 7pm (southbound)
NTP: 5/5/2016 Comp: 5/31/2021
Bibb Replace Lighting on I-75 from SR 247 to Minimal lane closures but work will be NTP: 4/1/2016
5 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
CR 85/Arkwright Rd performed in close proximity to travel lanes Comp: 5/31/2017
Fayette Resurfacing and Maintenance on SR 85 from SR 92 to
Clayton County Line No traffic interruptions on weekdays from
7pm to 7am. NTP: None Comp: 1/31/2017
Henry Resurfacing and Maintenance on SR 81 from SR 20 to
Newton County Line Weekday single lane closures from 7pm to
6am NTP: Comp:
Butts Resurfacing and Maintenance on SR 16 from SR 42 to
I-75 Nighttime lane closures between 8 pm and 7
am NTP: 4/19/2016 Comp: 2/28/2017
Spalding Resurfacing and Maintenance on SR 155 from SR 3 to
Poplar Road Nighttime lane closures between 8 pm and 7
am NTP: Comp:2/28/2017
Muscogee Resurfacing and Maintenance on SR22 Spur from SR
1 to Reese Road
Daily lane closures from 7pm to 6am NTP: Comp:2/28/2017
Houston Resurfacing and Maintenance on SR 247 from Houston
Lake Road to SR 247/Watson Blvd Lane closures allowed daily from 7 pm – 6
am NTP: 10/21/2015 Comp: 7/31/2016
Bibb Resurfacing and Maintenance on SR 11/US 129 from
Barnes Ferry Road to point north of SR 247 Single and double lane closures nightly from
8 pm to 6 am. NTP: 4/5/2016 Comp: 1/31/2017
Coweta Resurfacing and Maintenance on SR 16 beginning east
of US 29 / SR 14 and extending to the Spalding County
line Contractor currently working 24/7, E.R. Snell
NTP: 9/4/2015 Comp:6/30/2016 Work Began:
3/14/2016 DISTRICT 4 (Southwest Georgia) Juanita Birmingham 229-391-5463 County Project Name/ Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe
Tift & Turner Resurfacing I-75 from S of CR 204/Southwell Rd in
Tift County to S of SR 32 in Turner County
No lane closures from 7 am to 7 pm Ramp closures allowed 10 pm to 5 am Sunday – Thursday work schedule Daily nighttime lane closures expected
Completion date
1/31/2017
Coffee
Widening & reconstruction on SR 135 from SR
31/US441 E to SR 32; including Railroad separation construction of bridge over CSX railroad and Iron
Road
No lane closures 6-9 am and 3:30-7 pm Completion date
5/31/2020
6 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
Tift Interchange reconstruction on I-75 at Exit 66/Brighton
Road
Interchange closed, off-site detour; I-75 N &
S inside lanes closed, expected to reopen
June. Occasional nighttime lane closures
expected
Completion date
11/30/2016
Lowndes I-75 at Exit 13/Old Clyattville Road **Exit to Wild Adventures Theme Park Bridge
Old Clyattville Road traffic narrowed to one
lane each direction; I-75 South detour when
bridge spans are removed & replaced
Completion date
9/30/2016
Lanier SR 64 at Five Mile Creek and Ten Mile Creek Bridge Off-site detour Completion date
10/31/2017
Grady SR 112 at Sapp Creek Bridge Replacing 1950 bridge
Off-site detour Completion date
5/31/2016
Brooks
Widening & Reconstruction on SR 133 from CR
276/Troupeville Road to CR 10/Pauline Church Road **Governor’s Road Improvement Program (GRIP)
corridor
Traffic shifts to newly-constructed lanes Completion date
6/30/2016
Colquitt Widening & Reconstruction on SR 133 from CR
388/Hawthorne Drive to SR 35/E Moultrie Bypass **GRIP corridor
Traffic shifts to newly-constructed lanes Completion date
7/31/2016
Brooks &
Colquitt
Widening & Reconstruction on SR 133 from CR 1/Old
Quitman Adel Road in Brooks Co. to CR 256/Old
Berlin Road in Colquitt Co. **GRIP corridor
Traffic shifts to newly-constructed lanes Completion date
4/30/2018
Randolph
Widening & Reconstruction on US 27/SR 1 from CR
153/Carnegie Vilulah Road to S of the Cuthbert Bypass
**TIA project
Traffic shifts to newly-constructed lanes Completion date
12/27/2016
DISTRICT 5 (Southeast Georgia) Jill Nagel 912-530-4425
County Project Name/ Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe Chatham/Bry Reconstruction/ Rehabilitation I-95 (2 loc.) and I-16 (2 Lane closure restrictions: I-95 no single lane 30-60 days
7 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
an/Camden loc.)
restrictions, Double lane restrictions - no
closures between 7am-7pm
Chatham Widening with interchange construction on SR204 to
West of King George Blvd.
SR 204 lane closure restrictions for peak
hours: Eastbound 7a.m.-9 a.m. Westbound
4p.m.-7p.m. no restrictions on weekends
except for holidays
Work started5/14 Completion date 01/31/20171
McIntosh Reconstruction/ Rehabilitation on I-95/SR 405 at SR 251
Lane closure restrictions: I-95 no single lane
restrictions, Double lane restrictions 7am-
7pm, SR 251 no LC btw 6am-9am and 4pm-
6am
Work started
09/29/2014 Competition date 04/30/17
Ware,
Charlton,
Bryan and
Camden
Bridge Preservation on SR 4 & SR 25 at 17 bridge
locations 2 bridges over Ogeechee River work only on
weekends from Fri 6pm through Mon 6am 12 month contract
Chatham Bridge Preservation on I-95 at 22 bridge locations I-95 Lane closure restrictions: no single lane
restrictions, Double lane restrictions 7am-
7pm 12 month contract
Chatham I-95@SR 21 Diverging Diamond Interchange (DDI)
Nighttime construction on SR 21 and ramps
for the duration of the project until this fall 3-
day closure and detour at the interchange
before opens to traffic. No lane closures on I-
95 mainline.
1/24/2017
DISTRICT 6 (Northwest Georgia) Mohamed Arafa 678-721-5284
County Project Name/ Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe
Cobb/ Cherokee
Northwest Corridor Express Lanes Adding toll lanes and reversible lanes along I-75 from
Akers Mill Road to Hickory Grove Road and along I-
575 from I-75 to Sixes Road
Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
October 2018
Haralson Bridge Construction on SR 120 @ Beach Creek E of
Tallapoosa No part of SR 120 over Beech Creek shall be
detoured or closed for duration of 3.5 years
8 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
construction activities
Catoosa Resurfacing and Maintenance on I-75 from SR 3/US
41 to Tennessee State Line
Mainline and Ramps: Single Lane Closures 2
or more Lanes 7:00 pm thru 6:00 am Mon
thru Fri, 7:00 pm Fri to 6:00 am Mon.
Doubles with 3 or more lanes 10:00 pm thru
6:00 am Mon thru Sun. Single Ramp: 10:00
pm thru 6:00 pm Mon thru Sun.
11 months
Floyd Bridge Rehabilitation on SR 1 @ six locations;
SR 20 @ six locations and SR 61 @ one location.
Single Lane Closures will be allowed from
9:30 am to 3:30 pm Monday thru Friday or
from 8:00 pm Friday to 5:00 am, Monday
thru Sunday.
12 months
Gordon Roadway Project on South Calhoun Bypass from SR
53 @ CR 31 E to SR 53 @ CR 64
Do not install lane closures, pace traffic or
move equipment or materials on SR53 or
US41 between the hours of 6:00 am to 9:00
am and 4:00 pm to 7:00 pm, Monday thru
Friday.
5 years
Carroll Concrete Rehabilitation on I-20 from SR 1/US 27 to
SR 61
Stage I: Allowable times for Single Lane
Closures, East and West: 9:00pm Mon thru
5:00 am Tues, 9:00pm Tues thru 5:00am
Wed, 9:00pm Wed thru 5:00am Thurs,
9:00pm Thurs thru 5:00am Fri, 9:00pm Fri
thru 5:00am Mon. Stage 2 & 3 Ramps:
9:00pm Fri to 5:00am Mon.
2 years, 11 months
DISTRICT 7 (Metro Atlanta) Annalysce Baker 470-891-2992
County Project Name/Brief Project Description Lane Closure Allowed & Timeframe Project Timeframe
Cobb Operational Improvement Diverging Diamond Interchange SR 3 @ CS 4538/Windy Hill Road
Daytime, Weeknights, Weekends March 2017
9 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
Cobb
Reconstruction/ Rehabilitation on SR 3/US 41 from I-285 WB Ramp to
CS 1782/Spring Rd
Weekday, Weeknight, Weekend TBD
Cobb Reconstruction/ Rehabilitation on Windy Ridge Pkwy from Circle 75 to
Interstate North Pkwy Weekday, Weeknight, Weekend TBD
Cobb Construction of I-285 Multi-use Bridge over I-285 Weekday, Weeknight, Weekend August 31, 2017
Cobb/ Cherokee
Northwest Corridor Express Lanes Adding toll lanes and reversible lanes along I-75 from
Akers Mill Road to Hickory Grove Road and along I-
575 from I-75 to Sixes Road
Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
October 2018
Henry/
Clayton
I-75 South Metro Express Lanes Add toll lanes and reversible lanes along I-75 south of
Atlanta at SR 155/McDonough Road and ends at SR
138/Stockbridge Highway
Weeknight: 9 p.m. - 5 a.m. northbound only Weeknight: 9 p.m. - 7 a.m. southbound only Weekends Continuously from Friday at 9
p.m. until Monday morning
February 2017
Fulton Bridge Preservation on I-85 @ ten locations in Fulton
County
Weekday: 9 a.m. - 4 p.m. Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
December 2016
Clayton/ Fulton
Resurfacing and Maintenance on I-75/ S.R. 401 from
SR 54/ University Avenue to I-285 in Clayton County
and from SR 54/University Avenue to Brookwood
Interchange in Fulton County
Weeknights: 9 p.m. - 5 a.m. Weekends: 9 p.m. - 5 a.m.
Feb 2017
Fulton
Resurfacing and Maintenance on IRENE KIDD
PARKWAY and CLEVELAND AVENUE (from Main
Street to Springdale Road), SYLVAN ROAD (from
Palm Drive to Oakleigh Drive), VIRGINIA AVENUE
(from Harrison Road to Norman Berry Drive), and
Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
December 2016
10 | Page External Master- revised May 19, 2016
Includes major impact projects across the state. Does not include ALL construction projects.
NORMAN BERRY DRIVE (from Cleveland Avenue
to Willingham Drive).
Fulton, Cobb,
Douglas
Resurfacing and Operational Improvement on I-20 @
I-285 from Hill St. to Thornton Rd. Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
December 2016
Fulton Widening of Old Alabama Rd @ SR 141/Medlock
Bridge Road
Weekday: 9 a.m. - 4 p.m. Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
October 2016
Cobb Reconstruction on I-285 @ Atlanta Road Bridge
Project
Weeknight: 9 p.m. - 5 a.m., Weekend: Friday at 9 p.m. to Monday at 5
a.m.
October 2017
DeKalb Reconstruction on I-285 @ SR 155/Flat Shoals Road;
including Noise Barriers
Weeknight: 9 p.m. - 5 a.m., Weekend: Friday at 9 p.m. to Monday at 5
a.m. November 2017
Fulton Resurfacing and Maintenance on SR 139 beginning at
Ralph David Abernathy Rd/Cascade Rd and extending
to the Cobb County line
Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
July 2016
Fulton
I-285 @Riverside Drive The Design-Build project consists of safety
improvements to the existing interchange which will
convert the two existing signalized intersections at
each ramp terminal to roundabouts and provide routine
maintenance on the bridge over I-285.
Weekday: 9 a.m. - 4 p.m. Weeknight: 9 p.m. 0 - 5 a.m.
May 2018
Fulton Intersection Improvements on SR 372 at Crabapple
Rd/Birmingham Hwy Weeknight: 9 p.m. - 5 a.m. Weekend: 9 p.m. - 5 a.m.
May 2020