PL 338 - Wireline Logging Program Development Well, Lundin ...

18
Effective Date: 6/3/2016 PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID: Page 1 Uncontrolled when printedconfirm the correct revision is used Baker HughesCompany Confidential PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Baker Hughes Norway, Service Order Number: 8146478 11

Transcript of PL 338 - Wireline Logging Program Development Well, Lundin ...

Page 1: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 1

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1

Baker Hughes Norway, Service Order Number: 8146478

11

kiny
Thommessen - Bilag
Page 2: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 2

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Table of Contents

1 General Information .................................................................................................................. 4 1.1 Objectives, Requirements and Recommendations for Wireline Logging ......................................................... 4 1.1.1 Wireline Logging Objectives .................................................................................................................................. 4 1.1.2 General Requirements for Wireline Logging ......................................................................................................... 4 1.1.3 Recommendations to Follow During Logging ........................................................................................................ 5

2 Well Information ........................................................................................................................ 6 2.1 Well Design ............................................................................................................................................................. 7 2.2 Wireline Personnel ................................................................................................................................................. 7 2.3 Run Numbering System......................................................................................................................................... 7 2.4 Communication ...................................................................................................................................................... 8 2.5 Data ....................................................................................................................................................................... 10

3 File Naming Convention ......................................................................................................... 10

4 Wireline Run Detail ................................................................................................................. 11 4.1 Proposed Logging Sequence .............................................................................................................................. 16 4.1.1 Continuous Logged Runs .................................................................................................................................... 16

5 Risk Deployment Management .............................................................................................. 17

5.1 Tension Simulation .............................................................................................................................................. 17 5.2 Stuck Tool Procedure .......................................................................................................................................... 17

Appendix A. ................................................................................................................................... 18 5.3 Service Mnemonics .............................................................................................................................................. 18

6 Detailed Guidance for RPM ........................................................... Error! Bookmark not defined. 6.1 Objectives for RPM run............................................................................................... Error! Bookmark not defined.

Revision History

Revision Comment Date Changed by

1.0 Initial DRAFT 02.09.16 Paul

Brzezinski

1.1 Updated contacts, Updated Logging Sequence for RPM

05.09.16 Chris Gauci

Page 3: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 3

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Page 4: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 4

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

1 General Information

The well will be drilled by the Rowan Viking drilling rig. Wireline logging will be carried out in the 9 5/8in and 7in. casing only.

1.1 Objectives, Requirements and Recommendations for Wireline Logging

1.1.1 Wireline Logging Objectives

To carry out all actions without harm to personnel or the environment.

Run Schlumberger Isolation scanner as CIS to identify

Good casing cement outside the 9 5/8in casing

Run INTeX SBT logs to identify:

Good casing cement outside the 9 5/8in casing and in liner

Run 60 arm Multi Finger Caliper to identify:

Casing wear in packer setting area in the 9 5/8in casing, and in the 7in liner

Verify Production Packer setting depth in 7in liner with good cement bond and no casing wear

Run Reservoir Saturation Tool (RPM).

Run RPM tool in 7in liner to provide a base line Saturation Log

1.1.2 General Requirements for Wireline Logging

All equipment preparation and mobilization to be in compliance with Baker Hughes policies and procedures as defined in BHOS and WS Managing the Job Cycle.

All Wireline cables will be seasoned.

Upon completion of drilling and casing/cementing operations and prior to commencement of wireline operations, survey data, casing details, well fluid data and cement information and other data as required should be delivered to the wireline unit by the Wellsite geologist. The reference log for depth correlation, GR or Casing Tally should be provided by Lundin.

A summary of the logging suite identifying each tool in the string in the correct sequence including all auxiliary tools, knuckles, centralizers, stand offs etc will be provided as a tool diagram before deployment.

Tool sketch shall be provided in all log plots.

All corrections and remarks on the logging runs shall be provided.

A time breakdown of logging operations shall be maintained by the wireline lead Field Service Engineer with all details of any lost time recorded on the time breakdown and the duration agreed with the Lundin representative.

A written description of all tool problems encountered will be presented to the Lundin representative offshore.

In the event of tool failure, initial failure report and subsequent follow-up will be provided by Baker Hughes onshore using the First Alert problem resolution system.

A main and repeat pass have to be logged for all services where applicable. Both main and repeat passes must be presented on the log

Page 5: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 5

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

The Lundin wireline supervisor will maintain an independent time breakdown with a written description of the logging operations for each log run. This shall include the string length and the logging speed used and an appraisal of the service quality of all personnel and equipment used.

1.1.3 Recommendations to Follow During Logging

The raw curves on the log presentation should be free from spikes.

Any decision to re-log a zone due to poor/no data will come from the Lundin Wellsite geologist following a recommendation from the logging engineer.

Repeat sections will be performed after the main pass. The Wellsite geologist and logging engineer will decide on a repeat section 60m or longer, based on section of interest seen in the main pass. All tools need to be acquiring data across the chosen 60m interval. Repeatability should be within tolerance allowing for variations for statistical tools and pad contact tools.

Gamma ray curves should be free from non-repeating spikes.

All necessary corrections should be applied on every log before delivery.

Page 6: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 6

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

2 Well Information

Well Name, Field and Type 16/1-A-1 Edvard Grieg Water Injector

Rig/Installation Rowan Viking

Wireline company Baker Hughes

Permanent Datum MSL

Rotary Table-MSL (datum) 72.2 m

Water depth (MSL-seabed) 109.0 m

Wellhead location

UTM 6522936.20 m N 456611.73 m E

Lat/long 58° 50' 33.907'' N / 2° 14' 53.690'' E

Geodetic Datum UTM Zone 31N, ED50

Wellbore designator 16/1-A-1

Estimated TD m MDRT 4508 m MDRT (2350 m TVDRT)

Bit size in 8.5”

Max deviation °planned 70° - Deviated S-shaped (42° through reservoir)

Mud type and weight SG CARBO-SEA OBM 1.15 SG

Estimated temp. °C 92°C (BH static)

Maximum Estimated reservoir pressure bar

194bar

Formation water NaCl ppm 55000ppm

Hydrogen Sulphide ppm 0ppm

Nominal Hole Diameter

Depth

[m MD RT]

Nominal Casing

Diameter

[in]

Casing Grade / Weight

[ppf]

Drift / Minimum

[in]

17-1/5-in. 2161 13.375-in P-110 / 72.0 12.25

12.25-in 750 10.75-in P-110 / 60.7 9.66

12.25-in 750-3854 9.625-in P-110 / 53.5 8.535

8-1/2-in. 3804-4506 7-in SM13CrS110 6.059

Page 7: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 7

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

2.1 Well Design

Depths below are prognosed and should not be used on log headers. The actual numbers are available from the Wellsite geologist.

2.2 Wireline Personnel

The Baker Hughes Wireline standard crew requirements per shift,

1 x Field Service Engineer

1 x Lead Operator

1 x Operator (Welltec cross trained personnel)

2.3 Run Numbering System

A run reference consists of a run number and a trip number. The run number increases with every job/rig-up on a well for a series of logs. The trip number increases with every descent of a logging run into the well i.e. miss-runs will increment the trip number.

Run 1 Trip 1

Page 8: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 8

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Refers to the first descent into the well on the first job on the well – for instance the first run in the 12.25” section.

Run 1 Trip 2

Refers to the second descent into the well on the first job on the well.

Run 2 Trip 1

Refers to the first descent into the well on the second job on the well – for instance the first run in the 8.5”. section

2.4 Communication

All communications from the Wellsite to Lundin should be routed through the Lundin Wellsite geologist AND the Lundin drilling supervisor.

Page 9: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 9

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Bård Fjellså Production Drilling Manager [email protected] 916 44 064

John Zerbi Drilling Manager [email protected] 468 53 779

Sindre Hernes Drilling Superintendent [email protected] 917 86 141

Trym Elseth Lead Drilling Engineer [email protected] 951 21 669

Synnøve Rygh Lead Completion Engineer [email protected] 480 75 287

Hilde Sørensen Senior Completion Engineer [email protected] 992 48 925

Åge Svinøy Senior Drilling Engineer [email protected] 481 42 964

Grete Skotte Exploration Geologist [email protected] 970 45 885

Øyvind Stirø Petrophysicist [email protected] 906 20 525

Odd Aasheim Operations Geologist [email protected] 907 79 961

Brian Jacobsen Senior Completion Engineer [email protected] 915 69 777

Torje Tvedt Completion Engineer [email protected] 41104171

Chris Gauci BHI account manger [email protected] 91592179

Paul Brezinski BHI operations manager [email protected] 91892563

Ian Leslie Regional Advisor, Well Integrity [email protected] +44 7972 211-074

Gul Shahid Technical Advisor (CH Evaluation)

[email protected] +44 7412618113

Page 10: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 10

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

2.5 Data

Distribution of wireline data from the rig will be done through the Welllink Wireline remote witness and WellLink data distribution and retrieval services. These services can be accessed by logging on to www.bakerhughesdirect.com and navigating to the required sites. Email distribution of data will only be used as a backup to the Welllink Wireline system.

During logging, an activity log entry should be recorded on the chat page approximately every hour from the start of rig-up. If the operation delays, or is expected to delay, for a period longer than an hour, the wireline engineer will note this in the chat page explaining the reason for the delay. This will ensure that progress can be determined clearly by those monitoring the job through Welllink Wireline.

Access to Welllink Wireline and WellLink is controlled through a per-well access list maintained by Baker Hughes’ Beacon Centre staff. Required additions to or deletions from this list can be can be communicated through [email protected]

3 File Naming Convention

A file naming convention, consisting of six distinct fields will be used to name all log data files sent to Lundin.

A ‘_’ (underscore) character will be used to separate fields within the file name and a ‘-‘(dash) will be used to separate records within a field. The descriptions of field names are provided in the following table with an example file name.

16_1-A2_T2_6in_Run-1A_03-Jun-2015_DOWN_TTRM-ZDL-CN-DSL.zip

Field Description Field Example(s)

Well name NPD well name with ‘/’ replaced by ‘_‘ 16_1-A01

Bit Size Nominal bit size in decimal formatted inches 7in

Run and Descend Number

Run and Descend number formatted as Run-XY where ‘X’ and ‘Y’ are the run number and descend letter respectively.

Run-1A

Date Date of the first rig-up for the job (Run) formatted as “DD-MMM-YYYY” i.e. all trips on a job has the same date

03-Jun-2015

Log Direction Logging direction – one of up, down or stationary

UP, DOWN, STATIONARY

Service Mnemonics

Mnemonics of all services for which data is contained in the file, separated by a ‘-‘.

GR-INTeX-CCL-GR-SBT-VDL-CCL-GR-MFC

Page 11: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 11

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

4 Wireline Run Detail

Run No. Run Summary

Run 1A SCH CH-Welltec Tractor-SCH Isoscanner (BH CIS) (Cement evaluation in 9 5/8in csg)

Run 1B BH CH-Welltec Tractor-GR-INTeX-CCL-GR-SBT-VDL-CCL-GR-MFC 60 Arm (Cement evaluation in 9 5/8in and 7in casing and casing mechanical integrity in 7in casing)

Run 1C BH CH-Welltec Tractor-GR-RPM

.

Page 12: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 12

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Run No. Run 1A

Services BH CIS, Welltec Tractor, Schlumberger Isoscanner

Tool String SCH CH-Welltec Tractor-SCH Isoscanner (BH CIS)

Interval(s) 1. Log main log from 10 m above 7” PBR @ 4xxx m to 37xx m MD.

2. Repeat log over interval as provided by well site geologist with all sensors.

Remark(s) Depth correlation to LWD GR depth cross referenced to Casing Tally.

Confirm zero point with Lundin witness

Activate Welltec Tractor as required while RIH

Check Pick Up weights every 500m while RIH

Live Data NA

Rush Data NA

Field Logs NA

Geoscience

Processing

NA

Run No. Run 1B

Services Cement Evaluation and Casing Mechanical Integrity

Tool String BH CH-Welltec Tractor-GR-INTeX-CCL-GR-SBT-VDL-CCL-GR-MFC 60 Arm

Interval(s) 1. Set up INTeX and SBT in 9 5/8in casing in Free Pipe

2. Record SBT Normalisation pass

3. Log SBT down in the 9 5/8” from above T.O.C to 4xxx m.

4. Set up INTeX and SBT in 7in liner in Free Pipe

5. Log SBT down in 7in liner 6. Log INTeX up in 7in Liner from 4xxx m. to 100 m past top of cement in 7in liner

7. Log INTeX repeat log from 4xxx m to 3xxx m MD in 7in Liner

8. Set up INTeX in 9 5/8in casing 9. Log up from 4xxx m. to 100 m past top of cement in 9 5/8” 10. Log INTeX repeat log from 4xxx m to 3xxx m MD in 9 5/8in casing 11. RIH to 4xxxm 12. Log MFC in 7in liner and 9 5/8in casing 13. Log MFC repeat log over closest feature in 9 5/8in casing to the Top Logged Interval

Remark(s) 1. This log has to be on depth with LWD GR log and cross referenced to the Casing Tally. Report any discrepancies immediately they are noticed

2. Confirm zero point with Lundin witness

3. Log 60m repeat sections over intervals agreed with Lundin

4.

Live Data To be transmitted to WellLink real time during logging run: Real time Support from regional expert available on line. Data to by QC’ed by onshore prior to POOH

Rush Data To be uploaded to WellLink after logging run (Cased Hole folder):

Field Logs To be produced post job and uploaded to WellLink for approval:

INTeX and SBT Field Log

MFC Field Log

Page 13: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 13

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Geoscience

Processing

INTeX / MFC quick look – Casing wear VS cement quality – delivered within 2-3 hours

Cement Evaluation Report Casing mechanical Integrity Report – delivered within 10 hours

Run No. Run 1C

Services Reservoir Performance Monitor

Tool String BH CH-Welltec Tractor-GR-RPM

Interval(s) 1. Depths to be confirmed

2. Sigma mode main log from 4xxx m (all sensors) to 3xxx 3. RIH for repeat log. 4. Repeat section 60m Interval to be specified d by Lundin

Remark(s) 1. This log has to be on depth with Run 1B

2. Log to be correlated to MWD GR

3. Log in PNC 3D mode from 50 meters below bottom planned perf interval.

4. Stop log at top perforation interval.

5. Log 60 m repeat over zone of interest. – Specified by Lundin

6. If C/O mode required, Log 3 – 5 passed from 4000m up to top of sand around 3972m

Live Data RPM data to be transmitted via Welllink wilreine. Real time technical support to be available. Data to be QC’ed by onshore support prior to POOH

Rush Data Rush log to be uploaded to ‘Cased hole folder’

Field Logs To be produced post job and uploaded to Wellink for approval:

RPM Field Log

Geoscience

Processing

Processed logs to be uploaded to Wellink once completed

Page 14: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 14

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Page 15: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 15

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Service Parameter / Settings Depth Sample Rate

[samples per foot]

Integrity Explorer

(INTeX)

TBC 4 spf

Segmented Bond Tool

(SBT)

Pipe Cmd : 9 5/8in and 7in

Normalised Pad Data 4 spf

Reservoir Performance Monitor

(RPM)

PNC 3D

8 spf

Multi-Finger Caliper (MFC)

Hi Resultion – Logging speed 10 m/m Hi Rsolution

Run Number(s)

Services Diagram

Run 1A SCH CH-Welltec Tractor-SCH Isoscanner (BH CIS) Schlumberger

Run 1B BH CH-Welltec Tractor-GR-INTeX-CCL-GR-SBT-VDL-CCL-GR-MFC 60 Arm TRAC_INTEX_SBT_M

FC.pdf

Run 1C BH CH-Welltec Tractor-GR-RPM BHA 318 WT-Baker

RPM.PDF

Page 16: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 16

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

4.1 Proposed Logging Sequence

4.1.1 Continuous Logged Runs

1. Hold Tool Box Talk with all personnel involved with the logging operation.

2. Rig-up the tool strings

3. Perform a function check in with the tools in the derrick.

4. If required install / adjust positioning devices if not done during the rig-up.

5. Zero the tool string on the drill floor, making sure that the correct zero point and delay is used. Note the relevant information on the depth control sheet.

6. If required install radioactive sources in the tool string – all barriers in place and announcements to be made.

7. Continue to RIH, slowing down through restrictions.

8. Perform pick-up weights every 500 m down

9. If required perform before-log verifications.

10. Each run to be correlated depth to LWD GR, Check with tally

11. If required record a down-log while on the way to TD, otherwise RIH directly to TD

12. Log up the main interval as per requirements specified above.

13. If required, stop in the casing shoe and perform after log verifications.

14. Perform repeat log as per Lundin instructions.

15. If the tool string contains RA sources, safely remove the sources per standard operating procedures.

16. Perform required after log verifications if applicable.

17. Rig down the tool string.

18. Ensure all tools and accessories are accounted for. Report any damaged or lost equipment to the log witness, drilling supervisor and operations geologist.

19. Prepare cablehead for the next run.

Page 17: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 17

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

5 Risk Deployment Management

5.1 Tension Simulation

The tension simulation for all runs has been performed with the following deployment risk mitigation measures:

Heavy Duty Wireline (7Q49RTZZ-EEHS, 30 000 lb breaking strength)

Deployment of Welltec Tractor

5.2 Stuck Tool Procedure

In case of a wireline tool string becoming stuck the following procedure will be followed to retrieve the stuck tool string.

1. In case of the tool sticking pull to 55 % of the LWR and hold for 2 min. If there is no sign of the tool moving, slack off completely and immediately proceed with (2).

2. Pull up to 70 % of the LWR and monitor tension carefully for 10 minutes. Inform the Drilling Supervisor as soon as possible that the tool has become stuck.

3. If during (2) there is indication that the tool is moving keep 70 % of LWR pull on the string and monitor the tension. If no further tool movement is observed continue with (4).

4. Slack and pull to 70 % of the LWR. Hold 70 % of the LWR for 5 minutes while closely monitoring the tension.

5. Inform Drilling Supervisor, Town Duty Roster and relevant Town Drilling Personnel.

Page 18: PL 338 - Wireline Logging Program Development Well, Lundin ...

Effective Date: 6/3/2016

PL 338 - Wireline Logging Program Development Well, Lundin Norway AS 16/1-A-1 Job ID:

Page 18

Uncontrolled when printed—confirm the correct revision is used Baker Hughes—Company Confidential

Appendix A.

5.3 Service Mnemonics

Description Mnemonic Service or Measurement(s)

Casing Collar Locator CCL Magnetic Flux Measurement

Gamma Ray GR Natural Gamma Ray

Integrity Explorer INTeX Shear and Flexural Wave measurement

Segmented Bond Tool SBT Compensated Attenuation Measurement

Variable Density Log VDL Variable Density Acoustic Waveform

Multi Finger Caliper MFC 60 Finger Caliper

Reservoir Performance Monitor RPM Saturation log