Pitfalls of Testing and Commissioning

43
Pitfalls in Data Centre Testing and Commissioning

description

Pitfalls of Testing and Commissioning

Transcript of Pitfalls of Testing and Commissioning

  • Pitfalls in Data

    Centre Testing and

    Commissioning

  • Two Projects Compared PROJECT A PROJECT B

    Data Centre Handed over with minor defects to be rectified during DLP

    Data Centre Handed over with very large list of outstanding defects to be addressed during User fit out stage and DLP

    Completed on time 4 weeks past contract completion date

    Commissioning runs smoothly Major discussion argument and some conflict during commissioning.

    Commissioning proceeded to plan Incidents included 3 fires one flooding power lost to adjacent area of the site.

    Design concepts validated by commissioning process

    Urgent re-design of some systems needed to correct design flaws.

    Major Equipment deliveries received on time Major Equipment deliveries delayed requiring re-scheduling of the construction program.

    Operations and maintenance manuals handed over on time to Future Facility Managers

    Manuals rejected and undergoing review and resubmission

    WHICH ONE IS YOUR PROJECT ?

    Which one represents Successful Commissioning?

  • TWO PROJECTS

    Project 1 - Successful

    Management happy

    Contractors happy

    Construction team congratulated

    BUT

    Experience shows commissioning often throws

    up unexpected problems

    How thorough was the actual commissioning?

  • TWO PROJECTS

    Project 2 also successful

    Program allowed float between contractor hand over and occupancy of the Data Centre

    Potential Operational problems were identified AND RECTIFIED before Data Centre became

    operational.

    Operations staff now know exactly how the Data centre will perform

    When finally received the Manuals are known to be accurate.

  • COMMISSIONING Now that you have your new data centre

    designed and under construction how do you

    know it will perform as you need it to?

    COMMISSIONING is your opportunity to see

    how your Data Centre will perform under

    extreme conditions

    MAKE THE MOST OF THIS OPPORTUNITY

    YOU PROBABLY WONT GET ANOTHER ONE

  • A Commissioning Model

    What is the appropriate model for data centre

    commissioning?

    One accepted regime is the:

    American Society of Heating Refrigeration and

    Air Conditioning Engineers (ASHRAE) model

    for Commissioning

  • A Commissioning Model

    ASHRAE have identified five categories of

    Formal Commissioning Activities.

    Level 1 Factory Acceptance Test

    Level 2 Field Component Verification

    Level 3 System Construction Verification

    Level 4 Site Acceptance Testing

    Level 5 Integrated Systems Testing

  • Shop drawings

    Not highlighted by ASHRAE but is critical to a

    successful project.

    The shop drawings are the foundation that a

    successful commissioning is built on.

    This is the first opportunity to ensure the suppliers

    have got it.

  • ASHRAE Level 1 Factory acceptance testing

    Often abbreviated as FAT

    Also referred to as Factory Witness Test when the test is performed in the presence of an owners representative.

    This test primarily is product testing

    To ensure compliance with Manufacturers advertised specifications, ratings and characteristics.

    For many items of equipment these activities come under the manufacturers QA systems.

  • Testing takes the form of Type testing

    Sample testing

    Often the testing is mandated or covered by Australian or International Standards

    It is common to request copies of the test reports in

    the contracts for minor items

    ASHRAE Level 1 Factory acceptance testing

  • Major plant items are often, and should be, witness

    tested (generators, UPS, switchboards, chillers etc.)

    Manufacturers standard tests may not be adequate

    Tests often need to be augmented by owner-defined functional performance or aesthetic requirements.

    Attendance can be costly particularly when

    equipment is manufactured overseas. Must be included in the budget.

    Dont treat this as an overseas junket!

    ASHRAE Level 1 Factory acceptance testing

  • ASHRAE Level 2 Field component verification

    This is essentially a contractor activity and is generally covered

    under the contactors quality Assurance purchasing activities.

    It includes inspection or testing of products and goods upon

    delivery to site to ensure that:

    The products delivered match those purchased and tested during factory acceptance

    Products match the order

    Goods delivered have not been damaged during shipment

    Goods delivered have not been altered

    Goods delivered are these witnessed during FAT

  • ASHRAE Level 2 Field component verification

    As an end user you do not directly participate this

    level of testing but must ensure that it does occur.

    You can influence, often unintentionally and

    adversely, this level of commissioning via:

    Demanding construction program

    Contract requirements

    Cash flow requirements - EOFY or other contract payment dates

  • ASHRAE Level 3 System Construction verification

    Includes field inspections and certifications that the components are assembled into systems as required by the

    plans and specification.

    This typically is the defects inspections and certification stage of a project that is generally well understood within

    the construction industry.

    In many standard construction projects this is the highest level of commissioning that is carried out as part of the final

    completion and certification of a construction project.

  • ASHRAE Level 3 System Construction verification

    The builders and consultants are generally comfortable and familiar with their roles at this level.

    They also will generally fall into the standard practices and routines that they are familiar with.

    As a client you may not be as familiar with these standard practices

    These standard acceptance practices

    generally wont be rigorous enough for a high reliability installation such as a data centre.

  • ASHRAE Level 3 System Construction verification

    It is important to understand the roles that are played

    out here The designers generally certify the designs

    The installers certify that they believe they have built the installation to the design

    The building hand over process relies on these certifications.

    The project management team ensure and certify that the work is complete and in accordance with the Contract. The designers often have a

    role in this inspection regime.

    The important word here is contract. You will get no more and no less than what the contract asks for.

  • ASHRAE Level 4 Site acceptance testing

    Most often referred to as SAT

    SAT includes demonstration that related components

    equipment and ancillaries of a defined system

    operate and function to the acceptance criteria.

    This level of commissioning is often only performed

    on the more critical systems including: Mechanical Services

    Electrical Services

    Fire Services

    Communications (sometimes Level 3)

  • ASHRAE Level 4 Site acceptance testing

    It should include:

    Normal modes of operation

    Maintenance mode of operation

    Checking safeties

    Checking monitoring and control functions

    Checking performance

  • ASHRAE Level 4 Site acceptance testing

    The construction and Project Management Teams

    are comfortable and familiar with their roles at this

    level.

    They also will generally fall into the standard practices and routines that they are familiar with.

    This activity usually falls within the agreed contract completion time.

    Level 4 testing can be rushed if the construction falls behind program.

    The various parties involved are focused on their particular

    systems and tend to commission and test in isolation of the

    other systems.

  • ASHRAE Level 4 Site acceptance testing

    THIS IS THE FINAL STAGE FOR

    MOST PROJECTS INCLUDING

    MANY DATA CENTRES

  • ASHRAE Level 5 Integrated system testing

    The Functional performance testing of interrelated components and

    systems to respond as intended to expected and unexpected anomalies.

    There is no industry recognized formula for this level

    This level of testing is expensive

    This level of testing goes beyond demonstrating contract compliance

    This level of testing can, and probably will, expose design problems

    This is one way that design and construction of a complex high

    reliability systems such as Data Centre Infrastructure can be

    validated

  • ASHRAE Level 5 Integrated system testing

    Why perform level 5 testing?

    Testing to level 4 only tests the systems in isolation.

    Testing to level 4 is often performed with some systems incomplete.

    Testing to level 4 will only demonstrate that the systems conform to the design, it does not validate the design.

    Are the systems properly integrated? Will the generating set support the UPS?

    Does the monitoring system properly communicate with and record alarms for the critical sub-system?

    Allows operation and maintenance personnel to learn how the system operate and interact.

  • ASHRAE Level 5 Integrated system testing

    For Level 5 testing to be successful it needs

    Careful planning

    Good programming

    The right participants

    For Level 5 Commissioning to be successful you need buy in

    by all parties. You need to allocate:

    Time

    Money

    Resources

  • Manuals

    Also not highlighted by ASHRAE but is critical to

    successful operation of a data centre.

    Accurate manuals are required to ensure trouble free

    operation and timely maintenance of the data centre.

    Incorrect manuals and as-built drawings can have

    disastrous consequences years after completion .

  • Commissioning Overview

  • Two Projects Compared PROJECT A PROJECT B

    Data Centre Handed over with minor defects to be rectified during DLP

    Data Centre Handed over with very large list of outstanding defects to be addressed during User fit out stage and DLP

    Completed on time 4 weeks past contract completion date

    Commissioning runs smoothly Major discussion argument and some conflict during commissioning.

    Commissioning proceeded to plan Incidents included 3 fires one flooding power lost to adjacent area of the site.

    Design concepts validated by commissioning process

    Urgent re-design of some systems needed to correct design flaws.

    Major Equipment deliveries received on time Major Equipment deliveries delayed requiring re-scheduling of the construction program.

    Operations and maintenance manuals handed over on time to Future Facility Managers

    Manuals rejected and undergoing review and resubmission

    WHICH ONE IS YOUR PROJECT ?

    Which one represents Successful Commissioning

  • Commissioning Overview LEVEL 1 FACTORY ACCEPTANCE

  • Commissioning Overview LEVEL 1 FACTORY ACCEPTANCE

    What to look for: Basic operation almost always okay

    What is missing usually interface with other services

    Conformance with Australian Standards Particularly relevant for overseas suppliers

    Rigorousness of FAT regime

    Review of non-witnessed test results prior to despatch

  • Commissioning Overview LEVEL 1 FACTORY ACCEPTANCE

    Will the equipment fit?

  • Commissioning Overview LEVEL 2 COMPONENT VERIFICATION

    Beware of negative influences by artificial contract

    dates!

  • Commissioning Overview LEVEL 3 SYSTEM VERIFICATION

    This is a contractor activity that is determined by the

    construction contract

    Once the contracts are in place you will have very

    little opportunity to influence it

    Building works predominantly complete

    Requires co-ordination between trades to avoid

    abortive works

  • Commissioning Overview LEVEL 3 SYSTEM VERIFICATION

    SAFETY

  • Commissioning Overview LEVEL 4 SAT

    These tests are defined during the original contract.

    You can influence Level 4 commissioning by ensuring

    that the specifications and contracts clearly spell out

    the acceptance testing. Cost

    Program

    REMEMBER THIS LEVEL OF COMMISSIONING

    CONFIRMS THAT THE INSTALLATION MEETS THE

    ORIGINAL DESIGN.

  • Commissioning Overview LEVEL 4 SAT

    Systems MUST be complete

  • Commissioning Overview LEVEL 5 Integrated System Testing

    The decision on performing IST is totally in the

    customers hands

    It will probably be the only opportunity to observe how

    the data centre will respond under extreme stress

    Not industry standard

  • Commissioning Overview LEVEL 5 Integrated System Testing

    Pifalls Contractors not on board or interested in IST consider moving IST

    outside contract completion date

    Testing before the data centre is complete

    Monitoring system must be complete

    Who does the ITPs? Must be someone who understands the design

    Takes a lot of time

    Contractors are typically only concerned with completing construction to the design documents

    Designers often only test scenarios they have designed for

    Consider peer reviewer or independent commissioning agent but get them involved early they need to have time to assess and understand the design

  • Commissioning Overview LEVEL 5 Integrated System Testing

    Pifalls Load in the data hall

    How big a load

    How many load banks

    Consider many small load banks to avoid heat damage and fire system activation

    Issues identified

  • KEY POINTS

    PLANNING

    Decide on your commissioning needs

    Level 1 involvement

    Level 5

    Allow sufficient Budget

    Allow time for commissioning

  • KEY POINTS

    PEOPLE

    Involve the Designers

    Involve the user/owners

    Involve the facility managers

    Consider an independent commissioning agent

    Make sure the team has

    Skills

    Experience

    Collaboration

  • KEY POINTS

    DOCUMENTATION

    Contract requirements

    Define responsibilities

    Workshop Drawings

    Manuals

    The Testing Script (ITPs)

  • KEY POINTS

    RELATIONSHIPS

    Collaboration

    Communication

    Expectations

    Everyone must be engaged

  • KEY POINTS

    COMPLETION

    Works must be complete

    and

    Previous Level Testing must

    be Complete

  • Questions