Pitfalls of Testing and Commissioning
description
Transcript of Pitfalls of Testing and Commissioning
-
Pitfalls in Data
Centre Testing and
Commissioning
-
Two Projects Compared PROJECT A PROJECT B
Data Centre Handed over with minor defects to be rectified during DLP
Data Centre Handed over with very large list of outstanding defects to be addressed during User fit out stage and DLP
Completed on time 4 weeks past contract completion date
Commissioning runs smoothly Major discussion argument and some conflict during commissioning.
Commissioning proceeded to plan Incidents included 3 fires one flooding power lost to adjacent area of the site.
Design concepts validated by commissioning process
Urgent re-design of some systems needed to correct design flaws.
Major Equipment deliveries received on time Major Equipment deliveries delayed requiring re-scheduling of the construction program.
Operations and maintenance manuals handed over on time to Future Facility Managers
Manuals rejected and undergoing review and resubmission
WHICH ONE IS YOUR PROJECT ?
Which one represents Successful Commissioning?
-
TWO PROJECTS
Project 1 - Successful
Management happy
Contractors happy
Construction team congratulated
BUT
Experience shows commissioning often throws
up unexpected problems
How thorough was the actual commissioning?
-
TWO PROJECTS
Project 2 also successful
Program allowed float between contractor hand over and occupancy of the Data Centre
Potential Operational problems were identified AND RECTIFIED before Data Centre became
operational.
Operations staff now know exactly how the Data centre will perform
When finally received the Manuals are known to be accurate.
-
COMMISSIONING Now that you have your new data centre
designed and under construction how do you
know it will perform as you need it to?
COMMISSIONING is your opportunity to see
how your Data Centre will perform under
extreme conditions
MAKE THE MOST OF THIS OPPORTUNITY
YOU PROBABLY WONT GET ANOTHER ONE
-
A Commissioning Model
What is the appropriate model for data centre
commissioning?
One accepted regime is the:
American Society of Heating Refrigeration and
Air Conditioning Engineers (ASHRAE) model
for Commissioning
-
A Commissioning Model
ASHRAE have identified five categories of
Formal Commissioning Activities.
Level 1 Factory Acceptance Test
Level 2 Field Component Verification
Level 3 System Construction Verification
Level 4 Site Acceptance Testing
Level 5 Integrated Systems Testing
-
Shop drawings
Not highlighted by ASHRAE but is critical to a
successful project.
The shop drawings are the foundation that a
successful commissioning is built on.
This is the first opportunity to ensure the suppliers
have got it.
-
ASHRAE Level 1 Factory acceptance testing
Often abbreviated as FAT
Also referred to as Factory Witness Test when the test is performed in the presence of an owners representative.
This test primarily is product testing
To ensure compliance with Manufacturers advertised specifications, ratings and characteristics.
For many items of equipment these activities come under the manufacturers QA systems.
-
Testing takes the form of Type testing
Sample testing
Often the testing is mandated or covered by Australian or International Standards
It is common to request copies of the test reports in
the contracts for minor items
ASHRAE Level 1 Factory acceptance testing
-
Major plant items are often, and should be, witness
tested (generators, UPS, switchboards, chillers etc.)
Manufacturers standard tests may not be adequate
Tests often need to be augmented by owner-defined functional performance or aesthetic requirements.
Attendance can be costly particularly when
equipment is manufactured overseas. Must be included in the budget.
Dont treat this as an overseas junket!
ASHRAE Level 1 Factory acceptance testing
-
ASHRAE Level 2 Field component verification
This is essentially a contractor activity and is generally covered
under the contactors quality Assurance purchasing activities.
It includes inspection or testing of products and goods upon
delivery to site to ensure that:
The products delivered match those purchased and tested during factory acceptance
Products match the order
Goods delivered have not been damaged during shipment
Goods delivered have not been altered
Goods delivered are these witnessed during FAT
-
ASHRAE Level 2 Field component verification
As an end user you do not directly participate this
level of testing but must ensure that it does occur.
You can influence, often unintentionally and
adversely, this level of commissioning via:
Demanding construction program
Contract requirements
Cash flow requirements - EOFY or other contract payment dates
-
ASHRAE Level 3 System Construction verification
Includes field inspections and certifications that the components are assembled into systems as required by the
plans and specification.
This typically is the defects inspections and certification stage of a project that is generally well understood within
the construction industry.
In many standard construction projects this is the highest level of commissioning that is carried out as part of the final
completion and certification of a construction project.
-
ASHRAE Level 3 System Construction verification
The builders and consultants are generally comfortable and familiar with their roles at this level.
They also will generally fall into the standard practices and routines that they are familiar with.
As a client you may not be as familiar with these standard practices
These standard acceptance practices
generally wont be rigorous enough for a high reliability installation such as a data centre.
-
ASHRAE Level 3 System Construction verification
It is important to understand the roles that are played
out here The designers generally certify the designs
The installers certify that they believe they have built the installation to the design
The building hand over process relies on these certifications.
The project management team ensure and certify that the work is complete and in accordance with the Contract. The designers often have a
role in this inspection regime.
The important word here is contract. You will get no more and no less than what the contract asks for.
-
ASHRAE Level 4 Site acceptance testing
Most often referred to as SAT
SAT includes demonstration that related components
equipment and ancillaries of a defined system
operate and function to the acceptance criteria.
This level of commissioning is often only performed
on the more critical systems including: Mechanical Services
Electrical Services
Fire Services
Communications (sometimes Level 3)
-
ASHRAE Level 4 Site acceptance testing
It should include:
Normal modes of operation
Maintenance mode of operation
Checking safeties
Checking monitoring and control functions
Checking performance
-
ASHRAE Level 4 Site acceptance testing
The construction and Project Management Teams
are comfortable and familiar with their roles at this
level.
They also will generally fall into the standard practices and routines that they are familiar with.
This activity usually falls within the agreed contract completion time.
Level 4 testing can be rushed if the construction falls behind program.
The various parties involved are focused on their particular
systems and tend to commission and test in isolation of the
other systems.
-
ASHRAE Level 4 Site acceptance testing
THIS IS THE FINAL STAGE FOR
MOST PROJECTS INCLUDING
MANY DATA CENTRES
-
ASHRAE Level 5 Integrated system testing
The Functional performance testing of interrelated components and
systems to respond as intended to expected and unexpected anomalies.
There is no industry recognized formula for this level
This level of testing is expensive
This level of testing goes beyond demonstrating contract compliance
This level of testing can, and probably will, expose design problems
This is one way that design and construction of a complex high
reliability systems such as Data Centre Infrastructure can be
validated
-
ASHRAE Level 5 Integrated system testing
Why perform level 5 testing?
Testing to level 4 only tests the systems in isolation.
Testing to level 4 is often performed with some systems incomplete.
Testing to level 4 will only demonstrate that the systems conform to the design, it does not validate the design.
Are the systems properly integrated? Will the generating set support the UPS?
Does the monitoring system properly communicate with and record alarms for the critical sub-system?
Allows operation and maintenance personnel to learn how the system operate and interact.
-
ASHRAE Level 5 Integrated system testing
For Level 5 testing to be successful it needs
Careful planning
Good programming
The right participants
For Level 5 Commissioning to be successful you need buy in
by all parties. You need to allocate:
Time
Money
Resources
-
Manuals
Also not highlighted by ASHRAE but is critical to
successful operation of a data centre.
Accurate manuals are required to ensure trouble free
operation and timely maintenance of the data centre.
Incorrect manuals and as-built drawings can have
disastrous consequences years after completion .
-
Commissioning Overview
-
Two Projects Compared PROJECT A PROJECT B
Data Centre Handed over with minor defects to be rectified during DLP
Data Centre Handed over with very large list of outstanding defects to be addressed during User fit out stage and DLP
Completed on time 4 weeks past contract completion date
Commissioning runs smoothly Major discussion argument and some conflict during commissioning.
Commissioning proceeded to plan Incidents included 3 fires one flooding power lost to adjacent area of the site.
Design concepts validated by commissioning process
Urgent re-design of some systems needed to correct design flaws.
Major Equipment deliveries received on time Major Equipment deliveries delayed requiring re-scheduling of the construction program.
Operations and maintenance manuals handed over on time to Future Facility Managers
Manuals rejected and undergoing review and resubmission
WHICH ONE IS YOUR PROJECT ?
Which one represents Successful Commissioning
-
Commissioning Overview LEVEL 1 FACTORY ACCEPTANCE
-
Commissioning Overview LEVEL 1 FACTORY ACCEPTANCE
What to look for: Basic operation almost always okay
What is missing usually interface with other services
Conformance with Australian Standards Particularly relevant for overseas suppliers
Rigorousness of FAT regime
Review of non-witnessed test results prior to despatch
-
Commissioning Overview LEVEL 1 FACTORY ACCEPTANCE
Will the equipment fit?
-
Commissioning Overview LEVEL 2 COMPONENT VERIFICATION
Beware of negative influences by artificial contract
dates!
-
Commissioning Overview LEVEL 3 SYSTEM VERIFICATION
This is a contractor activity that is determined by the
construction contract
Once the contracts are in place you will have very
little opportunity to influence it
Building works predominantly complete
Requires co-ordination between trades to avoid
abortive works
-
Commissioning Overview LEVEL 3 SYSTEM VERIFICATION
SAFETY
-
Commissioning Overview LEVEL 4 SAT
These tests are defined during the original contract.
You can influence Level 4 commissioning by ensuring
that the specifications and contracts clearly spell out
the acceptance testing. Cost
Program
REMEMBER THIS LEVEL OF COMMISSIONING
CONFIRMS THAT THE INSTALLATION MEETS THE
ORIGINAL DESIGN.
-
Commissioning Overview LEVEL 4 SAT
Systems MUST be complete
-
Commissioning Overview LEVEL 5 Integrated System Testing
The decision on performing IST is totally in the
customers hands
It will probably be the only opportunity to observe how
the data centre will respond under extreme stress
Not industry standard
-
Commissioning Overview LEVEL 5 Integrated System Testing
Pifalls Contractors not on board or interested in IST consider moving IST
outside contract completion date
Testing before the data centre is complete
Monitoring system must be complete
Who does the ITPs? Must be someone who understands the design
Takes a lot of time
Contractors are typically only concerned with completing construction to the design documents
Designers often only test scenarios they have designed for
Consider peer reviewer or independent commissioning agent but get them involved early they need to have time to assess and understand the design
-
Commissioning Overview LEVEL 5 Integrated System Testing
Pifalls Load in the data hall
How big a load
How many load banks
Consider many small load banks to avoid heat damage and fire system activation
Issues identified
-
KEY POINTS
PLANNING
Decide on your commissioning needs
Level 1 involvement
Level 5
Allow sufficient Budget
Allow time for commissioning
-
KEY POINTS
PEOPLE
Involve the Designers
Involve the user/owners
Involve the facility managers
Consider an independent commissioning agent
Make sure the team has
Skills
Experience
Collaboration
-
KEY POINTS
DOCUMENTATION
Contract requirements
Define responsibilities
Workshop Drawings
Manuals
The Testing Script (ITPs)
-
KEY POINTS
RELATIONSHIPS
Collaboration
Communication
Expectations
Everyone must be engaged
-
KEY POINTS
COMPLETION
Works must be complete
and
Previous Level Testing must
be Complete
-
Questions