Pipeline Project News Andrew Emhof Facilities Engineer, Interstate Marketing N ti l F l G S l C National Fuel Gas Suppl y Corp. Empire Pipeline, Inc. PIOGA Technical Conference August 23, 2016

Transcript of Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ......

Page 1: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Pipeline Project News

Andrew EmhofFacilities Engineer, Interstate Marketing

N ti l F l G S l CNational Fuel Gas Supply Corp.

Empire Pipeline, Inc.

PIOGA Technical Conference

August 23, 2016

Page 2: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

National Fuel Gas Company

2 3 T f P d R (1)

Upstream• 2.3 Tcfe Proved Reserves (1)

• 785,000 net acres in Marcellus Shale• 3 million Bbls/year of crude oil

production in California

• $1.2 billion midstream investments since 2010

• Coordinated infrastructure build-out in Appalachia with NFG Upstream

Midstream

in Appalachia with NFG Upstream

• 740,000 Utility customer accounts

Downstream

(1) Total proved reserves are as of September 30, 2015.2

Page 3: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Interstate Marketing Facilities Planning

What do we do?• Determine capacity through existing facilities• Determine capacity through existing facilities

• Meter stations• Compressor stations• Pipeline segments and systems• Pipeline segments and systems

• Evaluate and design expansion projects to create incremental capacity• Act as liaison between Engineering, Gas Control, and Operations• Manage and maintain all capacity postings

3

Page 4: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

2015 Expansion ProjectsEnhancing Outlets for Production

Page 5: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

2015 Expansion Projects

West Side Expansion & Modernization• Capacity: 175,000 Dth/d

• Market:• Range Resources• Seneca Resources

• Interconnects:

Westside Expansion &

• Mercer (TGP Station 219)• Holbrook (TETCO)

• Facilities:• 3 550 HP of new compression

MercerExpansion &

Modernization3,550 HP of new compression

• 23.3 Miles of 24” replacement pipeline

• Placed into service: November 2015

Holbrook

Delivery Point 5

Page 6: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

West Side Expansion & Modernization

6

Page 7: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

2015 Expansion Projects

Northern Access 2015• Capacity: 140,000 Dth/d

• Market:• Lease of Capacity to TGP

• Interconnects: • Niagara (TCPL) Northern

ANiagara (TCPL)g ( )

• Facilities:• 15,400 HP of compression at Hinsdale CS• 7,700 HP of compression at Concord CS• Various M&R facilities

Access 2015

ClermontVarious M&R facilities

• Placed into service: December 2015

Clermont

Delivery Point

7

Page 8: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Northern Access 2015

8

Page 9: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Planned Future Expansion ProjectsMeeting the Demands of an Evolving Market

Page 10: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Future Expansion Projects

Line D Expansion• Capacity: 77,500 Dth/d

• Market:• Increased On-System Demand

• Transportation Path: Lamont (TGP 300 Line) to Erie, PA region

Line D E pansion

North East, g

• Facilities:• 4,140 HP of compression at new Keelor CS• Lamont M&R Upgrades and station

modifications

ExpansionErie

Lamont

Warren

• Satisfied FERC Prior Notice Blanket Requirements in February

• Targeted in-service: April 2017

Delivery Point

10

Page 11: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Line D Expansion: Project Milestones

• Fall 2014: Open season held• 77,500 Dth/d of capacity subscribed

• December 21, 2015: Applied for FERC Prior Notice Blanket Certificate , pp

• February 26, 2016: Received FERC approval

• Summer 2016: Commence initial construction activities• Keelor CS site development

Complete pipeline MAOP remediation work• Complete pipeline MAOP remediation work

• Early Fall 2016: Anticipate PADEP Air Permit

• Fall 2016-Winter 2017: Anticipate construction of mechanical facilities• Installation of new compressors at Keelor CS• Finish Bowen and Lamont upgrades• Commission new facilities

• April 1, 2017: Projected in-service date

11

Page 12: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Line D Expansion: Keelor CS Site Development

12

Page 13: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Future Expansion Projects

Northern Access• Capacity:

• 497,000 Dth/d on NFGSC• 350 000 Dth/d on Empire350,000 Dth/d on Empire

• Market:• Seneca Resources

• Transportation Path: Seneca’s Clermont production area to TGP 200 Line and Chippawa Northern

Chippawa(TCPL)

TGP 200 Line

production area to TGP 200 Line and Chippawa (TCPL)

• Facilities:• 99.0 Miles of 16” and 24” pipeline• New 22 214 HP Pendleton CS

Northern Access

Clermont

• New 22,214 HP Pendleton CS• Enhanced 5,350 HP Porterville CS• Dehydration facility• Various M&R facilities

T t d i i N b 2017• Targeted in-service: November 2017

Delivery Point

13

Page 14: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Northern Access: Project Milestones

• Summer 2014: Open season held• Capacity subscribed by foundation shipper

• Summer 2014-Winter 2015: Conducted environmental and engineering studies

• July 24, 2014: Began FERC Pre-filing process

• March 17, 2015: Submitted initial FERC 7(b)/7(c) applications

• Summer 2015-Winter 2016: Conduct right-of-way negotiations

November 2 2015: Submitted amended FERC 7(b)/7(c) applications• November 2, 2015: Submitted amended FERC 7(b)/7(c) applications• Relocated Pendleton Compressor Station

• February 2016: Submitted NYS DEC 401 Water Quality Certification application

• July 27, 2016: Received FERC Environmental Assessment

• Late October 2016: Anticipate FERC certificate

• Early March 2017: Anticipate NYS Water Quality Certificate and air permits

• March 2017: Anticipate starting construction of facilities

• November 1, 2017: Projected in-service date

14

Page 15: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Northern Access: FERC Environmental Assessment

• EA Issued July 27, 2016• Based on FERC’s analysis, the Northern Access project would have no significant y p j g

environmental impact• NFG and Empire have developed comprehensive construction plan in its 7(c)

application• 69% of total pipeline route co-located with existing facilities69% of total pipeline route co located with existing facilities

• FERC Staff proposed 26 recommendations, including:• Modifications to plan must be submitted to and approved by Director of Office of

Energy Projects• Constructed facilities shall be as shown in EA• Must have at least one Environmental Inspector per construction spread• Must develop environmental complaint resolution procedure

15

Page 16: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Northern Access: Porterville CS Engines

16

Page 17: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Potential Future Expansion ProjectsBroadening Our Reach

Page 18: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Potential Future Expansions

To Iroquois

IGT

Empire North

To TCPL

Line N to REX

Line N to Rover/Nexus

ExtensionSupply North

REX

18

Page 19: Pipeline Project News - National Fuel Gas · PDF filePipeline Project News Andrew Emhof ... • Capacity: 175,000 Dth/d ... the Northern Access project would have no significant

Potential Future Expansions

Empire North Expansion• Open Season held Fall 2015• Currently negotiating precedent agreements

Line N Expansion• Replacement of remaining older-vintage pipeline, increasing System Maximum

Operating Pressure• Expand or develop new interconnections with other pipelines (Columbia DTI• Expand or develop new interconnections with other pipelines (Columbia, DTI,

NEXUS, Rover, TETCO, TGP)• Develop market-area delivery points

Production-related expansions• Replacement/expansion of existing pipelines in Marcellus/Utica Shale fairway• Development of new facilities for delivery to TGP, Transco, or Canada

Additional Capacity to TransCanada Pipeline• Utilizing NFGSC corridors and facilities

19