Pipeline Project GK-Teras Paper update

download Pipeline Project GK-Teras Paper update

of 17

Transcript of Pipeline Project GK-Teras Paper update

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    1/17

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    2/17

    16/10/2010

    2

    Overview

    Gunung Kembang Pipeline Project,SSE Block Indonesia

    PT Medco E&P Indonesia

    Operation Areas

    SULAWESIKALIMANTAN

    SUMATRA

    Merangin

    SimenggarisBengaraTarakan

    Senoro-Toili

    NunukanSembakung

    Bangkanai

    Yap en

    Block AUS Gulf of Mexico

    OmanLibya

    CambodiaYemen

    Tunisia

    PAPUA

    JAWALematang

    SS Extension/Kampar

    Rimau

    Jakarta

    Jeruk

    Bawean

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    3/17

    16/10/2010

    3

    South Sumatra Working Area

    Project Background& Scope of Work

    Gunung Kembang Pipeline Project,SSE Block Indonesia

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    4/17

    16/10/2010

    4

    Project BackgroundPT Medco E&P Indonesia has commitment to supplyadditional gas of 15 BBTUD (13.5 MMSCFD) tocustomers, and Gunung Kembang field need to deliver up o .

    The existing Gunung Kembang (GK) Teras pipelinehas capacity of 20 MMSCFD

    Upgrading the pipeline capacity of GK-Teras toaccomodate the additional gas up to15 MMSCFD

    Project Scope of Work

    Installation 8 SP 9Teras pipeline 15 km (Segment -1)

    Installation 6 Gunung Kembang-SP 9 pipeline 17 km(Segment-2)

    River Crossing Keruh (108 m) and Tarum (204 m)

    Testing and Certification

    The schedule : December 2009 to August 2010

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    5/17

    16/10/2010

    5

    Pipeline Schematic SSE Block

    New Pipeline Project GK-Teras

    Pipeline Engineering

    Gunung Kembang Pipeline Project,SSE Block Indonesia

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    6/17

    16/10/2010

    6

    Engineering Code & Standards

    ASME B31.8 : Gas Distribution and Transportation

    ASME B16.5 : Pipe Flanges and Flanged Fittings, Steel,

    Nickel Alloy and other Special Alloy

    API RP 14C : Recommended Practice for Analysis,

    Design, Installation, and Testing of BasicSurface Safety Systems

    API RP 1104 : Welding of Pipeline and Related Facilities

    Pipeline Capacity

    Pipeline Capacity

    8"(existing)

    8"(new)

    8" and 6"(new)

    1Option 1G. Kembang = 830 psigTeras = 620 psig

    20 MMSCFD 20 MMSCFD - 40 MMSCFD

    2Option 2G. Kembang = 830 psigTeras = 620 psig

    20 MMSCFD - 15 MMSCFD 35 MMSCFD

    DescriptionNoo a

    Capacity

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    7/17

    16/10/2010

    7

    Design Parameters

    Description Data

    Fluid GasFluid density 21.10 lb/ft3 (337.99 kg/m3)Maximum operating pressure 850 psig (5.86 Mpa)Maximum operating temperature 120 F (48.89 C)

    Pipeline Detail and Material Selection

    Description GK - SP9 Segment SP9 - Teras Segment

    Pipe material CS API 5L Gr. B Sch. 40 CS API 5L Gr. B Sch. 40Outside Diameter 6.625 inch (168.275 mm) 8.625 inch (219.075 mm)Wall thickness 0.28 inch (7.112 mm) 0.322 inch (8.18 mm)

    Length of pipe 17 km 15 kmCorrosionProtection Polyethylene Wrapping Tape Polyethylene Wrapping Tape

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    8/17

    16/10/2010

    8

    Schematic Drawing

    River Crossing

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    9/17

    16/10/2010

    9

    Road Crossing

    Cleaning

    Commissioning

    Dewatering

    Hydrostatic Testing

    Gauging

    Gas In

    Drying and Purging

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    10/17

    16/10/2010

    10

    Construction ProjectManagement

    Gunung Kembang Pipeline Project,SSE Block Indonesia

    Project Management Process

    Source: Project Management Body of Knowledge (PMBOK)

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    11/17

    16/10/2010

    11

    Initiating Issued Project Service Agreement ( PSA ) between

    Technical Services Division (project executor) andpera on sse wner

    PSA consists of: Project Objective

    Project Scope of Work Project Schedule

    Project Budget

    Project Organization

    Planning

    Master Schedule

    SegmentSegment- -11 on early May 10on early May 10

    SegmentSegment- -22 on early Sept 10on early Sept 10

    Using existing material from other lower-priority projectsCombination 8 15 km Segment -1 & 6 17 km Segment-2

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    12/17

    16/10/2010

    12

    Planning - OrganizingForming the project team (internal), creating a WBS, andallocating resources (manpower, equipment & material)

    Work Breakdown Schedule (WBS)Work Breakdown Schedule (WBS) :a) Engineering (8%)b) Land acquisition (20%)c) Procurement (25%)

    d) Construction andCommissioning (45%)

    e) Handover (2%)

    ro ec xecu onro ec xecu on ra egy nra egy nonon--In-house EngineeringIn-house Project ManagementIn-house Material ProcurementSeparately Service Contract: Fabrication, NDT, Equipment, Hydrostatic

    Executing

    Pipeline Sections for ConstructionPipeline Sections for Construction

    8 Segment-1 on stream early May 20106 Segment-2 : Part 1 started construction on April 2010

    Part 2 started construction on June 2010

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    13/17

    16/10/2010

    13

    Controlling S Curve ProjectWEIGHTFAC TO R W 0 W 1 W 2 W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 W 11 W 1 2 W 1 3 W 14 W 1 5 W 1 6 W 1 7 W 1 8 W 19 W 2 0 W 2 1 W 1 8 W 19 W 2 0 W 2 1 W 2 2 W 2 3 W 24 W 2 5 W 2 6 W 2 7 W 28 W 2 9 W 3 0 W 3 1 W 3 2 W 33 W 3 4 W 3 5

    % 7 / 12 1 4 /1 2 2 1 /1 2 2 8/ 1 2 4 / 1 11/ 1 1 8 / 1 2 5 / 1 1 / 2 8 / 2 1 5/ 2 2 2 / 2 1 / 3 8 / 3 1 5 / 3 2 2 / 3 2 9 / 3 5 / 4 1 2 / 4 1 9 / 4 2 6 / 4 3 / 5 1 0 /5 1 7 / 5 2 4 / 5 3 1 / 5 7 / 6 1 4 /6 2 1 / 6 2 8 / 6 5 / 7 1 2 /7 1 9 / 7 2 5 / 7 1 / 8 8 / 8 1 5/ 8 2 2 / 8 2 9 / 8

    1 ENGINEERING 8,001,1 Survey 1 Lot 0,80 0 ,4 8 0, 321.2 Basic Design 1 Lot 1,20 0, 18 0, 54 0,40 0,081.3 Drawing 1 Lot 1,20 0, 11 0, 20 0,26 0,29 0, 22 0,10 0, 021.4 MTO 1 Lot 1,60 0,24 0, 72 0,53 0, 111 ,5 A s Bu il t Dr aw in gS P IX -T er as 1 L ot 1,60 0 ,96 0 ,6 41 ,6 A s Bu il t Dr aw in gG K- SP IX 1 L ot 1,60 0, 48 0, 88 0, 24

    2 LANDACQUISITION 20,002 ,1 L an d ac qu is it io n an d So zi al i ta ti on 1 Lo t 20,00 0,80 1,40 2,00 2,40 2,60 2,80 2,60 2,20 1,40 1,00 0,40 0,40

    3 PROCUREMENT 25,00

    Des-09 Jun-10 Jul-10 Agust-10N O. DE SCR IP TI ON Q TY & UN IT

    Mei-10 Apr-10Jan-10 Mar-10Feb-10

    3 ,1 C ontracting 0,203 .1 .1 W el di ng , He av yE qu ip me nt 1 L ot 0,10 0,00 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,00 0,00 0,003 .1 .2 R iv er C ro ss in gS . Ta ru m 1 L ot 0,10 0,00 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,00 0,00 0,003,2 Materials 24,80

    3 .2 .1 P ip e 6" A PI 5 L Gr .B S ch . 40 E RW 1 .4 50 J ts 7,44 0,45 1,12 1, 34 1,56 1, 49 0, 97 0,37 0,153.2.2 Pipe8"API5LGr.BSch.40ERW 1.250 Jts 9,10 1, 36 4,09 3,00 0, 643.2.3 Instrument 1 Lot 1,49 0,06 0,13 0,19 0,22 0,28 0,22 0,18 0,12 0,04 0,033.2.4 PipeFittings 1 Lo t 2,48 0,10 0,22 0,32 0,37 0,47 0,37 0,30 0,20 0,07 0,053.2.5 Closure12" 2 Ea 0,73 0,03 0,07 0,09 0,11 0,14 0,11 0,09 0,06 0,02 0,013.2.6 Closure10" 2 Ea 0,50 0, 03 0, 07 0,09 0,10 0, 10 0,06 0, 02 0, 013.2.7 WrappingTape 2.400 Roll 3,07 0,18 0,46 0, 55 0,65 0, 61 0, 40 0,15 0,06

    4 CONSTRUCTIONWORK+ COMMISIONING 45,008"TERAS-SP IX SEGMENT(15 Km) 18,00

    4,1 CivilWork 6,304 .1 .1 P re par ing the ROW 1 5 Km 2,21 0,33 0, 99 0,73 0, 154 .1 . 2 P ig L /R F ou nd at io n Te ra s & SP I X 1 L ot 0,63 0, 19 0, 35 0, 094.1.3 Ditching 15 Km 0,95 0,14 0,43 0, 31 0,074 .1 .4 B ac kf il li ng & Co mp ac ti ng 1 5 K m 2,52 0, 38 1,13 0, 83 0, 184,2 Mechanical Work 0,90

    4.2.1 F abr ic at e &I ns ta ll P ig L/ R 8" 1 L ot 0,90 0 ,2 7 0 ,4 95 0 ,1 354,3 PipelineWork 9,00

    4 .3 .1 R iv er C ro ss in gS . Ke ru h 1 L ot 1,80 0, 27 0,81 0, 594 0, 126 04.3.2 Stringing 1.250 Jts 0,45 0, 14 0, 25 0, 074 .3 . 3 Wel di ng & X -R ay C he ck in g 1 .2 50 J ts 4,23 0, 55 1,18 1, 44 0, 85 0,214 .3 .4 W ra pp in g& Ho li da yT es t 1 5 K m 0,90 0,12 0, 25 0, 31 0,18 0,054.3.5 Lowering 15 Km 0,45 0, 14 0, 25 0, 074 .3 .6 F lu sh in g& Hy dr ot es ti ng 1 L ot 0,45 0,454.3.7 Dewatering 1 Lot 0,36 0,364.3.8 Drying 1 Lot 0,36 0,364,4 Instrument Work 0,90

    4 .4 .1 Ins ta ll Ins tr um ent 1 Lo t 0,90 0 ,5 4 0 ,364,5 COMMISIONING 1 Lo t 0,45 0,454,6 INSPECTION& CERTIFICATION 1 Lo t 0,45 0, 27 0 ,1 8

    6"GK- SPIXSEGMENT(20Km) 27,004,1 CivilWork 9,45

    4 .1 .1 P re par ing the ROW 1 7 Km 4,25 0, 47 0,94 1,15 1,02 0,51 0,17

    4 .1 .2 Pi gL /R F ou nd at io nG K& SP I X 1 Lo t 0,95 0, 28 0, 52 0, 144.1.3 Ditching 17 Km 1,42 0,21 0,64 0,47 0,104 .1 .4 B ac kf il li ng & Co mp ac ti ng 1 7 K m 2,84 0,85 1,56 0,434,2 Mechanical Work 1,35

    4.2.1 F abr ic at e &I ns ta ll P ig L/ R 6" 1 L ot 1,35 0 ,8 1 0 ,5 44,3 PipelineWork 13,50

    4 .3 .1 R iv er C ro ss in gS . Ta ru m 1 L ot 3,92 0,59 1,77 1,30 0, 274 .3 .2 R oa dCr os si ng SP VIII 1 Lo t 0,80 0, 24 0, 44 0, 124.3.3 Stringing 1.450 Jts 0,68 0, 20 0, 37 0, 104 .3 . 4 Wel di ng & X -R ay C he ck in g 1 .4 50 J ts 2,70 0,16 0,41 0, 49 0,57 0,54 0,35 0,14 0,054 .3 .5 W ra pp in g& Ho li da yT es t 1 7 K m 2,03 0,26 0,57 0,69 0,40 0, 104.3.6 Lowering 17 Km 1,35 0,41 0,74 0,204 .3 .7 F lu sh ing & Hy dr ot es ti ng 1 L ot 0,68 0,684.3.8 Dewatering 1 Lot 0,68 0,684.3.9 Drying 1 Lot 0,68 0,684,4 Instrument Work 1,35

    4 .4 .1 Ins ta ll Ins tr um ent 1 Lo t 1,35 0 ,8 1 0 ,5 44,5 COMMISIONING 1 Lo t 0,68 0,684,6 INSPECTION& CERTIFICATION 1 Lo t 0,68 0,68

    5 HANDOVER & CLOSEOUT 1 Lo t 2,00 0,66 0,30 0,14 0,90

    GRANDTOTAL 100,000,00 0,48 0,61 2,11 5,39 5,53 6,05 6,63 6,32 5,20 4,25 4,15 4,48 2,97 2,51 1,39 0,61 0,99 1,49 1,52 2,86 2,51 1,94 1,55 1,91 2,22 1,93 2,12 2,78 1,56 1,97 3,09 2,66 2,00 1,25 1,22 0,68 1,35 0,82 0,900,00 0,48 1,09 3,20 8,59 14,12 20,18 26,80 33,13 38,32 42,58 46,73 51,21 54,19 56,70 58,09 58,70 59,69 61,18 62,70 65,56 68,07 70,00 71,55 73,46 75,68 77,61 79,73 82,50 84,07 86,04 89,13 91,79 93,79 95,05 96,26 96,94 98,29 99,10 100,00,00 0,00 3,00 6,00 6,97 6,97 3,49 2,96 3,01 2,07 2,50 1,42 2,12 6,11 5,86 4,47 2,18 2,37 2,72 2,14 1,65 3,50 3,41 2,89 2,76 1,35 1,36 0,88 0,68 0,41 0,84 1,07 0,56 1,19 1,49 0,82 0,58 0,58 1,29 2,310,00 0,00 3,00 9,00 15,97 22,94 26,43 29,39 32,40 34,48 36,98 38,40 40,53 46,64 52,50 56,96 59,15 61,52 64,24 66,38 68,02 71,53 74,94 77,83 80,60 81,95 83,31 84,19 84,87 85,28 86,12 87,19 87,75 88,94 90,43 91,25 91,84 92,41 93,70 96,01

    -0 ,5 1 ,9 5 ,8 7 ,4 8 ,8 6 ,3 2 ,6 - 0, 7 - 3 ,8 - 5 , 6 - 8, 3 -10,7 -7 ,6 - 4 ,2 - 1, 1 0 ,5 1 ,8 3 ,1 3 ,7 2 ,5 3 ,5 4 ,9 6 ,3 7 ,1 6 ,3 5 ,7 4 ,5 2 ,4 1 ,2 0 ,1 - 1, 9 - 4 ,0 - 4 , 9 - 4, 6 - 5 ,0 - 5 , 1 - 5, 9 - 5 ,4 - 4 , 0

    INCREMENTALACTUAL

    PLANNING

    AHEAD/BEHIND

    INCREMENTAL ACCUMULATIVE

    ( + / - ) ACCUMULATIVE

    Controlling - Problem

    1) There was a problem during pig cleaning (segment-1):the pig was stuck for 1 week (April-May).

    2) Legal administration of ROW caused delay:1) the start of the project part-2 for 3 weeks (July)

    2) the completion of the segment-2 for 7 weeks (Sept-Oct).

    3) Material wrapping tape delivery (segment-2) wasdelayed for 5 weeks (July-August) impact to backfillingprogress

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    14/17

    16/10/2010

    14

    Controlling Overcoming

    hydrostatic test.

    2) Local inhabitants invite into the works and negotiationvia local officer.

    3) Provide additional resources (manpower andequipment) for fast track the project.

    Closing - Lesson Learns

    Right of Way Procurement & Project

    (ROW)

    Advance Project

    Socialization toStakeholder

    Process

    Proper Planning

    Strategy

    Conduct cost-benefit analysis

    Maintaincoordination toStakeholder during the projectexecution

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    15/17

    16/10/2010

    15

    Project Benefit &Conclusion

    Gunung Kembang Pipeline Project,SSE Block Indonesia

    Cost Benefit Analysis

    a.a. Engineering ValueEngineering Value

    8 15 km and 6 17 km instead of 8 32 km

    1,970,883.35$ 2,442,316.90$

    8" 15km & 6" 17km8" 32km

    1,970,883.35$ 2,442,316.90$

    8" 15km & 6" 17km8" 32km

    Saving 20% of material cost

    471,433.54$ 471,433.54$

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    16/17

    16/10/2010

    16

    Cost Benefit Analysis (2)b.b. Project Cost (excluding material)Project Cost (excluding material)

    In House vs EPC Contract

    Saving 20% of EPC

    Average ($ / km-inch) TotalIn House 8.387,39 1.862.000,00 EPC Contract * 10.526,53 2.336.889,39

    474.889,39 * f rom other similiar medco's projects

    c.c. TotalTotal sasavingving comparecompared d to EPCto EPC : : 2020%%(engineering, material, construction)

    Opportunity Benefit

    Capacity Pipeline after Segment 1 on stream

    Price: USD 4 / Mbtu

    8" GK-Teras Existing 20

    68" Segment 1 (New) 268" - 6" GK-Teras (New) 35

    Potential capacity gain from on stream Segment 1 = USD 224K4K / day/ day

    PotentialPotential revenuerevenue after after total GKtotal GK TerasTeras onon streamstream = USD= USD 60K60K / day/ day

  • 8/7/2019 Pipeline Project GK-Teras Paper update

    17/17

    16/10/2010

    17

    ConclusionPipeline Gunung Kembang Teras Projecthas been successful delivering gas sales,and met the sectional project time frame

    .

    In-house execution saved 20% comparedto EPC contract with strong contributionfrom Engineering value and ProjectManagement

    By completion of this project is expectedincreasing the potential gas sales revenueup to USD 60,000/day

    Thank You