Pipeline Project GK-Teras Paper update
-
Upload
trianasmoro -
Category
Documents
-
view
218 -
download
0
Transcript of Pipeline Project GK-Teras Paper update
-
8/7/2019 Pipeline Project GK-Teras Paper update
1/17
-
8/7/2019 Pipeline Project GK-Teras Paper update
2/17
16/10/2010
2
Overview
Gunung Kembang Pipeline Project,SSE Block Indonesia
PT Medco E&P Indonesia
Operation Areas
SULAWESIKALIMANTAN
SUMATRA
Merangin
SimenggarisBengaraTarakan
Senoro-Toili
NunukanSembakung
Bangkanai
Yap en
Block AUS Gulf of Mexico
OmanLibya
CambodiaYemen
Tunisia
PAPUA
JAWALematang
SS Extension/Kampar
Rimau
Jakarta
Jeruk
Bawean
-
8/7/2019 Pipeline Project GK-Teras Paper update
3/17
16/10/2010
3
South Sumatra Working Area
Project Background& Scope of Work
Gunung Kembang Pipeline Project,SSE Block Indonesia
-
8/7/2019 Pipeline Project GK-Teras Paper update
4/17
16/10/2010
4
Project BackgroundPT Medco E&P Indonesia has commitment to supplyadditional gas of 15 BBTUD (13.5 MMSCFD) tocustomers, and Gunung Kembang field need to deliver up o .
The existing Gunung Kembang (GK) Teras pipelinehas capacity of 20 MMSCFD
Upgrading the pipeline capacity of GK-Teras toaccomodate the additional gas up to15 MMSCFD
Project Scope of Work
Installation 8 SP 9Teras pipeline 15 km (Segment -1)
Installation 6 Gunung Kembang-SP 9 pipeline 17 km(Segment-2)
River Crossing Keruh (108 m) and Tarum (204 m)
Testing and Certification
The schedule : December 2009 to August 2010
-
8/7/2019 Pipeline Project GK-Teras Paper update
5/17
16/10/2010
5
Pipeline Schematic SSE Block
New Pipeline Project GK-Teras
Pipeline Engineering
Gunung Kembang Pipeline Project,SSE Block Indonesia
-
8/7/2019 Pipeline Project GK-Teras Paper update
6/17
16/10/2010
6
Engineering Code & Standards
ASME B31.8 : Gas Distribution and Transportation
ASME B16.5 : Pipe Flanges and Flanged Fittings, Steel,
Nickel Alloy and other Special Alloy
API RP 14C : Recommended Practice for Analysis,
Design, Installation, and Testing of BasicSurface Safety Systems
API RP 1104 : Welding of Pipeline and Related Facilities
Pipeline Capacity
Pipeline Capacity
8"(existing)
8"(new)
8" and 6"(new)
1Option 1G. Kembang = 830 psigTeras = 620 psig
20 MMSCFD 20 MMSCFD - 40 MMSCFD
2Option 2G. Kembang = 830 psigTeras = 620 psig
20 MMSCFD - 15 MMSCFD 35 MMSCFD
DescriptionNoo a
Capacity
-
8/7/2019 Pipeline Project GK-Teras Paper update
7/17
16/10/2010
7
Design Parameters
Description Data
Fluid GasFluid density 21.10 lb/ft3 (337.99 kg/m3)Maximum operating pressure 850 psig (5.86 Mpa)Maximum operating temperature 120 F (48.89 C)
Pipeline Detail and Material Selection
Description GK - SP9 Segment SP9 - Teras Segment
Pipe material CS API 5L Gr. B Sch. 40 CS API 5L Gr. B Sch. 40Outside Diameter 6.625 inch (168.275 mm) 8.625 inch (219.075 mm)Wall thickness 0.28 inch (7.112 mm) 0.322 inch (8.18 mm)
Length of pipe 17 km 15 kmCorrosionProtection Polyethylene Wrapping Tape Polyethylene Wrapping Tape
-
8/7/2019 Pipeline Project GK-Teras Paper update
8/17
16/10/2010
8
Schematic Drawing
River Crossing
-
8/7/2019 Pipeline Project GK-Teras Paper update
9/17
16/10/2010
9
Road Crossing
Cleaning
Commissioning
Dewatering
Hydrostatic Testing
Gauging
Gas In
Drying and Purging
-
8/7/2019 Pipeline Project GK-Teras Paper update
10/17
16/10/2010
10
Construction ProjectManagement
Gunung Kembang Pipeline Project,SSE Block Indonesia
Project Management Process
Source: Project Management Body of Knowledge (PMBOK)
-
8/7/2019 Pipeline Project GK-Teras Paper update
11/17
16/10/2010
11
Initiating Issued Project Service Agreement ( PSA ) between
Technical Services Division (project executor) andpera on sse wner
PSA consists of: Project Objective
Project Scope of Work Project Schedule
Project Budget
Project Organization
Planning
Master Schedule
SegmentSegment- -11 on early May 10on early May 10
SegmentSegment- -22 on early Sept 10on early Sept 10
Using existing material from other lower-priority projectsCombination 8 15 km Segment -1 & 6 17 km Segment-2
-
8/7/2019 Pipeline Project GK-Teras Paper update
12/17
16/10/2010
12
Planning - OrganizingForming the project team (internal), creating a WBS, andallocating resources (manpower, equipment & material)
Work Breakdown Schedule (WBS)Work Breakdown Schedule (WBS) :a) Engineering (8%)b) Land acquisition (20%)c) Procurement (25%)
d) Construction andCommissioning (45%)
e) Handover (2%)
ro ec xecu onro ec xecu on ra egy nra egy nonon--In-house EngineeringIn-house Project ManagementIn-house Material ProcurementSeparately Service Contract: Fabrication, NDT, Equipment, Hydrostatic
Executing
Pipeline Sections for ConstructionPipeline Sections for Construction
8 Segment-1 on stream early May 20106 Segment-2 : Part 1 started construction on April 2010
Part 2 started construction on June 2010
-
8/7/2019 Pipeline Project GK-Teras Paper update
13/17
16/10/2010
13
Controlling S Curve ProjectWEIGHTFAC TO R W 0 W 1 W 2 W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 W 11 W 1 2 W 1 3 W 14 W 1 5 W 1 6 W 1 7 W 1 8 W 19 W 2 0 W 2 1 W 1 8 W 19 W 2 0 W 2 1 W 2 2 W 2 3 W 24 W 2 5 W 2 6 W 2 7 W 28 W 2 9 W 3 0 W 3 1 W 3 2 W 33 W 3 4 W 3 5
% 7 / 12 1 4 /1 2 2 1 /1 2 2 8/ 1 2 4 / 1 11/ 1 1 8 / 1 2 5 / 1 1 / 2 8 / 2 1 5/ 2 2 2 / 2 1 / 3 8 / 3 1 5 / 3 2 2 / 3 2 9 / 3 5 / 4 1 2 / 4 1 9 / 4 2 6 / 4 3 / 5 1 0 /5 1 7 / 5 2 4 / 5 3 1 / 5 7 / 6 1 4 /6 2 1 / 6 2 8 / 6 5 / 7 1 2 /7 1 9 / 7 2 5 / 7 1 / 8 8 / 8 1 5/ 8 2 2 / 8 2 9 / 8
1 ENGINEERING 8,001,1 Survey 1 Lot 0,80 0 ,4 8 0, 321.2 Basic Design 1 Lot 1,20 0, 18 0, 54 0,40 0,081.3 Drawing 1 Lot 1,20 0, 11 0, 20 0,26 0,29 0, 22 0,10 0, 021.4 MTO 1 Lot 1,60 0,24 0, 72 0,53 0, 111 ,5 A s Bu il t Dr aw in gS P IX -T er as 1 L ot 1,60 0 ,96 0 ,6 41 ,6 A s Bu il t Dr aw in gG K- SP IX 1 L ot 1,60 0, 48 0, 88 0, 24
2 LANDACQUISITION 20,002 ,1 L an d ac qu is it io n an d So zi al i ta ti on 1 Lo t 20,00 0,80 1,40 2,00 2,40 2,60 2,80 2,60 2,20 1,40 1,00 0,40 0,40
3 PROCUREMENT 25,00
Des-09 Jun-10 Jul-10 Agust-10N O. DE SCR IP TI ON Q TY & UN IT
Mei-10 Apr-10Jan-10 Mar-10Feb-10
3 ,1 C ontracting 0,203 .1 .1 W el di ng , He av yE qu ip me nt 1 L ot 0,10 0,00 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,00 0,00 0,003 .1 .2 R iv er C ro ss in gS . Ta ru m 1 L ot 0,10 0,00 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,00 0,00 0,003,2 Materials 24,80
3 .2 .1 P ip e 6" A PI 5 L Gr .B S ch . 40 E RW 1 .4 50 J ts 7,44 0,45 1,12 1, 34 1,56 1, 49 0, 97 0,37 0,153.2.2 Pipe8"API5LGr.BSch.40ERW 1.250 Jts 9,10 1, 36 4,09 3,00 0, 643.2.3 Instrument 1 Lot 1,49 0,06 0,13 0,19 0,22 0,28 0,22 0,18 0,12 0,04 0,033.2.4 PipeFittings 1 Lo t 2,48 0,10 0,22 0,32 0,37 0,47 0,37 0,30 0,20 0,07 0,053.2.5 Closure12" 2 Ea 0,73 0,03 0,07 0,09 0,11 0,14 0,11 0,09 0,06 0,02 0,013.2.6 Closure10" 2 Ea 0,50 0, 03 0, 07 0,09 0,10 0, 10 0,06 0, 02 0, 013.2.7 WrappingTape 2.400 Roll 3,07 0,18 0,46 0, 55 0,65 0, 61 0, 40 0,15 0,06
4 CONSTRUCTIONWORK+ COMMISIONING 45,008"TERAS-SP IX SEGMENT(15 Km) 18,00
4,1 CivilWork 6,304 .1 .1 P re par ing the ROW 1 5 Km 2,21 0,33 0, 99 0,73 0, 154 .1 . 2 P ig L /R F ou nd at io n Te ra s & SP I X 1 L ot 0,63 0, 19 0, 35 0, 094.1.3 Ditching 15 Km 0,95 0,14 0,43 0, 31 0,074 .1 .4 B ac kf il li ng & Co mp ac ti ng 1 5 K m 2,52 0, 38 1,13 0, 83 0, 184,2 Mechanical Work 0,90
4.2.1 F abr ic at e &I ns ta ll P ig L/ R 8" 1 L ot 0,90 0 ,2 7 0 ,4 95 0 ,1 354,3 PipelineWork 9,00
4 .3 .1 R iv er C ro ss in gS . Ke ru h 1 L ot 1,80 0, 27 0,81 0, 594 0, 126 04.3.2 Stringing 1.250 Jts 0,45 0, 14 0, 25 0, 074 .3 . 3 Wel di ng & X -R ay C he ck in g 1 .2 50 J ts 4,23 0, 55 1,18 1, 44 0, 85 0,214 .3 .4 W ra pp in g& Ho li da yT es t 1 5 K m 0,90 0,12 0, 25 0, 31 0,18 0,054.3.5 Lowering 15 Km 0,45 0, 14 0, 25 0, 074 .3 .6 F lu sh in g& Hy dr ot es ti ng 1 L ot 0,45 0,454.3.7 Dewatering 1 Lot 0,36 0,364.3.8 Drying 1 Lot 0,36 0,364,4 Instrument Work 0,90
4 .4 .1 Ins ta ll Ins tr um ent 1 Lo t 0,90 0 ,5 4 0 ,364,5 COMMISIONING 1 Lo t 0,45 0,454,6 INSPECTION& CERTIFICATION 1 Lo t 0,45 0, 27 0 ,1 8
6"GK- SPIXSEGMENT(20Km) 27,004,1 CivilWork 9,45
4 .1 .1 P re par ing the ROW 1 7 Km 4,25 0, 47 0,94 1,15 1,02 0,51 0,17
4 .1 .2 Pi gL /R F ou nd at io nG K& SP I X 1 Lo t 0,95 0, 28 0, 52 0, 144.1.3 Ditching 17 Km 1,42 0,21 0,64 0,47 0,104 .1 .4 B ac kf il li ng & Co mp ac ti ng 1 7 K m 2,84 0,85 1,56 0,434,2 Mechanical Work 1,35
4.2.1 F abr ic at e &I ns ta ll P ig L/ R 6" 1 L ot 1,35 0 ,8 1 0 ,5 44,3 PipelineWork 13,50
4 .3 .1 R iv er C ro ss in gS . Ta ru m 1 L ot 3,92 0,59 1,77 1,30 0, 274 .3 .2 R oa dCr os si ng SP VIII 1 Lo t 0,80 0, 24 0, 44 0, 124.3.3 Stringing 1.450 Jts 0,68 0, 20 0, 37 0, 104 .3 . 4 Wel di ng & X -R ay C he ck in g 1 .4 50 J ts 2,70 0,16 0,41 0, 49 0,57 0,54 0,35 0,14 0,054 .3 .5 W ra pp in g& Ho li da yT es t 1 7 K m 2,03 0,26 0,57 0,69 0,40 0, 104.3.6 Lowering 17 Km 1,35 0,41 0,74 0,204 .3 .7 F lu sh ing & Hy dr ot es ti ng 1 L ot 0,68 0,684.3.8 Dewatering 1 Lot 0,68 0,684.3.9 Drying 1 Lot 0,68 0,684,4 Instrument Work 1,35
4 .4 .1 Ins ta ll Ins tr um ent 1 Lo t 1,35 0 ,8 1 0 ,5 44,5 COMMISIONING 1 Lo t 0,68 0,684,6 INSPECTION& CERTIFICATION 1 Lo t 0,68 0,68
5 HANDOVER & CLOSEOUT 1 Lo t 2,00 0,66 0,30 0,14 0,90
GRANDTOTAL 100,000,00 0,48 0,61 2,11 5,39 5,53 6,05 6,63 6,32 5,20 4,25 4,15 4,48 2,97 2,51 1,39 0,61 0,99 1,49 1,52 2,86 2,51 1,94 1,55 1,91 2,22 1,93 2,12 2,78 1,56 1,97 3,09 2,66 2,00 1,25 1,22 0,68 1,35 0,82 0,900,00 0,48 1,09 3,20 8,59 14,12 20,18 26,80 33,13 38,32 42,58 46,73 51,21 54,19 56,70 58,09 58,70 59,69 61,18 62,70 65,56 68,07 70,00 71,55 73,46 75,68 77,61 79,73 82,50 84,07 86,04 89,13 91,79 93,79 95,05 96,26 96,94 98,29 99,10 100,00,00 0,00 3,00 6,00 6,97 6,97 3,49 2,96 3,01 2,07 2,50 1,42 2,12 6,11 5,86 4,47 2,18 2,37 2,72 2,14 1,65 3,50 3,41 2,89 2,76 1,35 1,36 0,88 0,68 0,41 0,84 1,07 0,56 1,19 1,49 0,82 0,58 0,58 1,29 2,310,00 0,00 3,00 9,00 15,97 22,94 26,43 29,39 32,40 34,48 36,98 38,40 40,53 46,64 52,50 56,96 59,15 61,52 64,24 66,38 68,02 71,53 74,94 77,83 80,60 81,95 83,31 84,19 84,87 85,28 86,12 87,19 87,75 88,94 90,43 91,25 91,84 92,41 93,70 96,01
-0 ,5 1 ,9 5 ,8 7 ,4 8 ,8 6 ,3 2 ,6 - 0, 7 - 3 ,8 - 5 , 6 - 8, 3 -10,7 -7 ,6 - 4 ,2 - 1, 1 0 ,5 1 ,8 3 ,1 3 ,7 2 ,5 3 ,5 4 ,9 6 ,3 7 ,1 6 ,3 5 ,7 4 ,5 2 ,4 1 ,2 0 ,1 - 1, 9 - 4 ,0 - 4 , 9 - 4, 6 - 5 ,0 - 5 , 1 - 5, 9 - 5 ,4 - 4 , 0
INCREMENTALACTUAL
PLANNING
AHEAD/BEHIND
INCREMENTAL ACCUMULATIVE
( + / - ) ACCUMULATIVE
Controlling - Problem
1) There was a problem during pig cleaning (segment-1):the pig was stuck for 1 week (April-May).
2) Legal administration of ROW caused delay:1) the start of the project part-2 for 3 weeks (July)
2) the completion of the segment-2 for 7 weeks (Sept-Oct).
3) Material wrapping tape delivery (segment-2) wasdelayed for 5 weeks (July-August) impact to backfillingprogress
-
8/7/2019 Pipeline Project GK-Teras Paper update
14/17
16/10/2010
14
Controlling Overcoming
hydrostatic test.
2) Local inhabitants invite into the works and negotiationvia local officer.
3) Provide additional resources (manpower andequipment) for fast track the project.
Closing - Lesson Learns
Right of Way Procurement & Project
(ROW)
Advance Project
Socialization toStakeholder
Process
Proper Planning
Strategy
Conduct cost-benefit analysis
Maintaincoordination toStakeholder during the projectexecution
-
8/7/2019 Pipeline Project GK-Teras Paper update
15/17
16/10/2010
15
Project Benefit &Conclusion
Gunung Kembang Pipeline Project,SSE Block Indonesia
Cost Benefit Analysis
a.a. Engineering ValueEngineering Value
8 15 km and 6 17 km instead of 8 32 km
1,970,883.35$ 2,442,316.90$
8" 15km & 6" 17km8" 32km
1,970,883.35$ 2,442,316.90$
8" 15km & 6" 17km8" 32km
Saving 20% of material cost
471,433.54$ 471,433.54$
-
8/7/2019 Pipeline Project GK-Teras Paper update
16/17
16/10/2010
16
Cost Benefit Analysis (2)b.b. Project Cost (excluding material)Project Cost (excluding material)
In House vs EPC Contract
Saving 20% of EPC
Average ($ / km-inch) TotalIn House 8.387,39 1.862.000,00 EPC Contract * 10.526,53 2.336.889,39
474.889,39 * f rom other similiar medco's projects
c.c. TotalTotal sasavingving comparecompared d to EPCto EPC : : 2020%%(engineering, material, construction)
Opportunity Benefit
Capacity Pipeline after Segment 1 on stream
Price: USD 4 / Mbtu
8" GK-Teras Existing 20
68" Segment 1 (New) 268" - 6" GK-Teras (New) 35
Potential capacity gain from on stream Segment 1 = USD 224K4K / day/ day
PotentialPotential revenuerevenue after after total GKtotal GK TerasTeras onon streamstream = USD= USD 60K60K / day/ day
-
8/7/2019 Pipeline Project GK-Teras Paper update
17/17
16/10/2010
17
ConclusionPipeline Gunung Kembang Teras Projecthas been successful delivering gas sales,and met the sectional project time frame
.
In-house execution saved 20% comparedto EPC contract with strong contributionfrom Engineering value and ProjectManagement
By completion of this project is expectedincreasing the potential gas sales revenueup to USD 60,000/day
Thank You