Piling of a flyover (AUST 2.2 A)
-
Upload
shakhawat-hossain-mehran -
Category
Design
-
view
770 -
download
0
description
Transcript of Piling of a flyover (AUST 2.2 A)
WELCOME
Presentation on
FLYOVER PILING
Prepared by: (GROUP-5)12.01.03.008; 12.01.03.016;12.01.03.019; 12.01.03.025;12.01.03.026; 12.01.03.032;12.01.03.035; 12.01.03.038;
08.02.03.020;
Course Teacher:Md. Arman ChowdhuryWahid Hasan
What is Pile?
• It is a long slender foundation member made either of timber,structural steel or concrete to transfer the load of the structure in deep foundation.
Fig- Pile
Why do we use Pile?W
eak
Soil
Bed Rock
Structure
Dee
p Fo
unda
tion
PILE
Advantage of Piling
• To take the structure deep into the ground and hence preventing over turning.
• To provide a strong bedrock soil (i.e. higher bearing capacity) for the structure and transfer the total load of the structure.
• To distribute the weight of the structure over a large area.
• To prevent unequal settlement.
Types of pile
Depending on their function:
• Bearing piles• Friction piles• Sheet piles• Anchor piles• Batter piles• Fender piles• Compaction piles
Depending on their materials:
• Timber piles• Concrete piles• Composite piles• Steel piles
Casting of a Flyover Pile(cast in situ)
(Location- Mouchak Mogbazar Flyover)
•At first, the locations of piles are fixed by theodolite surveying.
1. Excavation Started
2. If utility pipes are found during excavation, then the location point of pile is changed
3. No utility within 2 meter
Hydraulic Rig machine Cutting Bucket
•After excavating 6m temporary steel case is placed and then bentonite is used.
• Excavation continues according to design using rotary rig machine
•Using hose pipe to remove Bentonite mixed water after excavation process is completed
Making of Steel Case
•Process of making the vertical reinforcements in circular arrangement
•Circular rings are used to make stirrups and to maintain perfect circular arrangement
Stirrups
Completion of steel case
Thread Coupler
•It is used to join the inner rebars
Punching machine Plane coupler
After applying pressure
(N.B: These two couplers are used for the very first time in our country)
Circular CC block
weiring
welding
•Placing of steel case
Placing of trimmy pipe Started casting
•After completion of casting
Top head of the pile is removed Removed pile heads
Load test of pile :
•Load test is done by using hydraulic jack Load test continued (each block weighs 1 ton)
One layer BFS to level the surface of the pile cap
Casting on the BFS After Casting on the BFS
Placing of reinforcement after initial casting of pile cap
Chair
Completion of placing reinforcement of pile cap
Completion of casting of pile cap
Observations:
• The water that they used to admix the bentonite was recycled for next use also.
•They maintained the weiring and welding properly to make steel case strong enough to carry the load.
•When they broke the pile head, it should be above 6” from the ground surface. But in some cases accidently, they couldn’t manage to do so. Therefore, they placed an extra layer of CC of 6” which shouldn’t be as it couldn’t take the load properly.
THANK YOU…
Do you have any Questions?