piling md

download piling md

of 23

Transcript of piling md

  • 8/17/2019 piling md

    1/23

    : PROJECT SITE :

    HIDCO CONVENTIONCENTRE,

    NARKELBAGAN, KOLKATA,

    WEST BENGAL

    PROJECT UNDERTAKEN BY:

    LARSEN & TOUBRO LTD.

  • 8/17/2019 piling md

    2/23

    The com!e" #$ %'h$ ()om $he

    e%$)#%ce

  • 8/17/2019 piling md

    3/23

    P!#% o( $he *ho!e )o+ec$

    Schem#$c -#')#m

    D/C PILING

    PREFACE:

     The report is prepared after the training andobservation done at Project-site of WBHIDCOCo%0e%$o% Ce%$)e, being an engineer trainee underGeo$)e#$ L$-. 

     The project is undertaken by L#)1e% & To23)oL$-. A part of piling works is being conducted byGeo$)e#$ L$-.

     The start date of the construction project was

    16.06.01! " the e#pected end date is 1$.0%.016.&ver '600 piles are to be constructed a(ong which

    $00 nu(ber of pilling is conducted by Geo$)e#$ L$-.

    All of the( are done by D/C !%' (ethods.

  • 8/17/2019 piling md

    4/23

     The whole project report is subdivided in the

    following sections)

    1. *ntroduction. &bjectives and classi+cation of piles

    and piling (ethods,. Principle of / piling!. Apparatus used$. ield procedure / piling

    6. /onclusion

  • 8/17/2019 piling md

    5/23

    1. *T2&3/T*&

    Piles are the columnar structure, the most common type of 

    deep foundation, that safely transfer loads from the super structure to more competent subsurface strata by means of friction, end bearing or a combination of both. Piles can bebroadly classified based on the following parameters.

    1. Method of installation of piles – Driven (displacement) pilesor bored (replacement) piles.

    . !ype of material used for piling – "oncrete, steel, timber piles etc.

     #mong these, concrete piles can be classified further as pre$cast and cast in situ concrete piles. !hough there are a varietyof piling options, the most common type of piles used for ma%ority of construction wor&s in 'ndia are bored cast in situconcrete piles.

  • 8/17/2019 piling md

    6/23

    . &bjectives and classi+cation of piles and

    piling (ethods

    unctions of piles)

     The (ajor uses of piles are)1. To carry vertical co(pression load' eg. bearing

    piles' friction pile. 4*5. 1. To resist uplift pressure' eg. tension piles or

    uplift piles or anchor piles. 4*5. ,. To resist hori7ontal or inclined loads' eg. 8atter

    piles. 4*5. ,

  • 8/17/2019 piling md

    7/23

    etting up piles

      epending up on the setting up principle' pilescan be of two types' eg. D1!#ceme%$$4e and Re!#ceme%$ $4e' each has its own

    advantages and disadvantages. or -1!#ceme%$!%' me$ho-' piles are driven into the groundpushing the soil out of its way. isplace(ent piling isgood for conta(inated sites where it costs a lot to(ove the soil out.

      3sing the )e!#ceme%$ !%' me$ho-, (uckis dug out and replaced with the pile. uch bigger piles

    can be casted by replace(ent (ethod.

    Direct Mud Circulation (DMC !%' me$ho-or si(ply / Piling (ethod is an e#a(ple ofreplace(ent piling (ethod. This (ethod is the principlesubject of interest in this report.

     The advantages of displace(ent piling are)-

  • 8/17/2019 piling md

    8/23

    • 9elf testing as driven to refusal or :set:

    • o pile arising to dispose of 

    • ;ittle disturbance

    •;i(ited access

    • ?ectively vibration free

    • *nstalled into non cohesive and water bearing soils

  • 8/17/2019 piling md

    9/23

    ground level' water jet strea(s are used and then a

    typical chisel cuts the relatively softer soil. 8ore holes

    of several depths 4for e#a(ple 10(' 1$(' 0(' $('

    ,0(' etc. and dia(eter 4for e#a(ple $00(( $0(('1000(( etc. are dug as per design re@uire(ents. *t

    can be understood @uite clearly that the nearby soil can

    collapse. To prevent the collapse so(e special safety

    (easures are considered during the operation which

    will be discussed in later sections.

      After the bore hole is dug and the collapse of

    subsoil around the hole is safely prohibited' areinforce(ent cage is entered into the borehole and

    concrete is +lled fro( the botto( of the hole with the

    help of pipes' typically designed for this operation'

    called the Tre(ie pipes. 3sually concrete is left B days

    to harden and gain full strength' but so(eti(es using

    ad(i#tures they are prepared within 1 days.

    !.  Apparatus used*.  / rig

    •  T T2*P& 9C9T>

      ain shear leg) it is the longer leg than the other

    two that carries the load.

     The length is .$(.

      The length can be adjusted. Dith the help of

    0(( dia pins

  • 8/17/2019 piling md

    10/23

      The side shear legs) there are two side shear

    legs' 6.,( long and they (ainly support the tripod

    syste(.

     The side legs (ust be placed at least 1.$( away

    fro( the centre of the piles.

    • 8A9> /;

     These are standard * section' c( thick and there

    are grooving in it that holds the shear legs onto theground with the help of base cannel pin.

    • 9;*P &=>2 D>;

    ia(eter !$0(( Thickness $0((&peration The rope slips over this

    wheel or Pulley

    • 9;*P &=>2 D>>; 2

    ia(eter E $00((

  • 8/17/2019 piling md

    11/23

    • 9.&. D>; P*

    ia(eter 6$((;ength 00((&peration This is very i(portant pin'

    because it holds the 9.&.

    Dheel with the tripod

    syste( and the entire

    vertical loads act on it.

    • P;35>

    *nside ia(eter E $0((

    • 939P>9*& P;AT> F this is called into action if

    so(ehow the chisel is stuck in the borehole.

    Pulleys are attached here and the chisel is pulled

    out.

     

    9uspension Plate

  • 8/17/2019 piling md

    12/23

    • A* 9A2 ;>5 P* F 0(( dia.

    **. Dinch

    /apacity , Ton 4&ther capacities can

    be of 1 Ton .$ Ton $ Ton

    .$ Ton etc.riven wheel dia(eter %00((

    ***. iesel engine

    • 39> * D*/< 4239T& AG>

    u(ber of

    cylinder

    ! ,

    iesel

    consu(ption

    .1 litHhr 1.$ litHhr

    obil

    consu(ption

    4fresh engine

    0.$ lit per days 0.$ lit per days

    obil

    consu(ption

    4older engine

    0.$ lit per 1

    hours

    0.$ lit per 1

    hours

    • 39> * P3P 4G*;&9G>2 AG>

    u(ber of cylinder iesel consu(ption 1.$ litHhrobil consu(ption $0(l per 1 hours

    *=. 8ailer or 9lush Pu(p

  • 8/17/2019 piling md

    13/23

    ;ength

    00((*nside ia(eter !$0((

    Deight 0.$ Ton

    =. 5uide casing

    ;ength

    $0((*nside ia(eter

    $$0(( Thickness of casing ,0((

     Thickness of collar 0((

    =*. /hisel or /hopper

     Thickness of sheet B0((

    *nside ia(eter

  • 8/17/2019 piling md

    14/23

    !00((;ength

    $00((

    u(ber of no77le !

     

    .  / rod

    ;ength 4( . ,

    ,.$ia(eter 4(( %$ $

    6$ Thread length 4(( 10 Thread type Tapered* of tapered king end

    4((

    B0

    * of @ueen end 4(( 10

      Tapered thread end of / rods

  • 8/17/2019 piling md

    15/23

    B.  2ope

    ia(eter F 0((

    %.  Tre(ie pipe

    * $ inch& 6 inch

     Thickness of sheet 1((

    10.  =ertical pu(p

    Power source >lectrically operatedPower 10

  • 8/17/2019 piling md

    16/23

    =ertical Pu(p in 8entonite tank

    1.  Dash vat This is where the (uck (i# with water gets stored'

    the (uck gets precipitated and the water beco(es

    reusable.

    1,.  Tre(ie fork

    3sed to insert the tre(ie pipes and taking out /

    rods.

     

    $.  ield procedure / piling

    • or e#ecuting / piling (ethod which is

    approved as per *9 %11 under speci+cations ofbored cast in situ piles. The positioning of pointswhere the piles are proposed to set up' arechecked by the surveyor.

    / piling 2ig set-up and initiation of boring

    using the 8ailer

  • 8/17/2019 piling md

    17/23

    • After the point for boring operation is set out by

    the surveyor the tripod is paced such that eachside legs are at least 1.$( away fro( the point'keeping the centre of borehole e#actly in thecentre.

    •  The bailer is then attached with the rope and the

    boring operation is initiated.

    • After bailer reaches its full length into the soil' the

    guide casing is inserted into the hole for fartheroperations.

    *nsertion of the guide casing

     

    •  To prevent the side collapse and caving in' a guide

    casing of $$0(( dia and of $0(( length is

    placed on the top of the bore hole and ha((ered

  • 8/17/2019 piling md

    18/23

    by the bailer to insert it into the soil. This will bewithdrawn after concreting is over.

     

    8oring with /hisel

    •  &nce the guide casing is placed' the boring is

    started with chisel.

    •  The chisel has ! no77les fro( where water jet is

    forced on the hard soil layer as the boring

    progresses.

    Progression of boring and addition of

    / rods

    • / rods are added one after another as the depth

    increases.

    •  The / head are attached on top of the / rods

    which has the plunge which receives the waterfro( delivery hose.

    • The whole syste( is pulled up by the rope and the-9hackle with the help of the winch syste( andthen left to fall free' so that the chisel at thebotto( cuts the soil and the boring progresses.

    •  The loose soil produced by boring' (i#es with

    water and co(es up and is stored in the wash vat'where the soil gets precipitated and the water is

    again usable.

  • 8/17/2019 piling md

    19/23

     Taking out of the / rods and /hisel

    and *nsertion of the reinforce(ent cage• After the boring is co(plete up to the desired

    depth' the / rods are re(oved one by one usingthe / fork and the chisel is also re(oved.

    •  Then the steel reinforce(ent cage is inserted and

    welded where ever there are joints.

     

     /oncreting and +nali7ation of the

    process

    •  The tre(ie pipes are inserted one by one using the

     Tre(ie fork and then the bore hole is washed withthe 8entonite water and the uck is co(pletelyre(oved and the hole is +lled with bentonite slurry.

    •  The Transit (i#er arrives and the

  • 8/17/2019 piling md

    20/23

    •  The T puts concrete (i# into the hopper and the

    valve opens. The bore hole is gradually +lled withconcrete which is co(pacted by gradual vibrationof tre(ie pipes. This +lling of concrete fro( thebotto( is done to avoid segregation of theconcrete (i#.

    • As the concrete +lls the hole fro( botto('

    8entonite slurry escapes the hole. The tre(ie pipesare detached one by one and thus the hole gets+lled co(pletely.

    • After the hole is fully +lled' the concrete is left Bdays to gain full strength. After B days the guidecasing is re(oved and the pile is ready.

    /oncreting

    6.  /onclusion

  • 8/17/2019 piling md

    21/23

    / piling is the (ost co((on piling (ethods used in*ndia. or (oderate si7ed piles' that is !$0(( to1000(( dia(eter and $( to ,0( depth pilesI it isalso (ost convenient and econo(ic way of piling.;arger piles that are of dia(eter up to 1$00(( canalso be founded by this (ethod' but those are not thatconvenient. &ther process like 2educed ud /irculation42/ is also in use.

    LATEST TRENDS IN PILING & FOUNDATION ENGINEERING.

    Preamble  *ood, "lothing and shelter are the basic needs of human beings from the beginning of life on earth

    and the human race are vying each other to achieve the same. +ecause of this all the good lands on earth are

    used for horiontal developments during old civiliations and the developments where mainly near -iver +an&s

    and ea ports. +ecause of the shortage of land rban areas vertical growth of buildings have become a

    necessity. !he earlier structures in the world having significant heights are /utab Minar in Delhi and 0eaning

    !ower of Pia in 'taly. !echniues have been evolved after nd 2orld war in 3uropean and #merican countries

    for improving the various types of foundations to ta&e up under ground railway wor& and constructing high rise

    buildings such as ears !ower in "hicago, 2orld !rade "entre in 4ew 5or&, !win !owers in Malaysia and +ur%Dubai !ower in Dubai business district which is above 167 stories and 877 meter above ground level. !o support

    these types of structures deep and large diameter piles are essential which can be done by direct mud circulation

    method or by -otary -igs supported by bentonite slurry system. +oth the methods are approved by +ritish and

    'ndian standards and are used in 'ndia 9 abroad depending on the speed by which the pro%ect has to be

    completed. -otary method has got more speed when compared to DM" method and the disadvantage is that it

    cannot cut through hard roc&s effectively. !he DM" system is widely used '4 'ndia for providing pile foundations

    for buildings up to 67 stories (167 meters) and the piles can be done upto depths of :7 meter from ground level

    and diameters can vary from 677 to 1677mm. !his is cost effective and we recommend this system for 'ndia and

    abroad for diameters from 677mm to 1677mm and depth up to :7 meters.

    Types of Piling  +ecause of the agricultural and 'ndustrial revolution building rules has come in to effect inprominent towns of 3urope and the 1st town planning act of ; is in 1

  • 8/17/2019 piling md

    22/23

    concrete or the safe bearing capacity of the founding strata. 'f the concrete is wea& and the founding strata is

    strong there will be structural failure of the concrete or if it is vise versa the founding strata will fail.

    !he method of piling from place to place will vary such as dia meter, depth etc. and in !rivandrum generally the

    depth is 6 to 7 mtrs, in ;ochi depth from 7 to :7 mtrs etc. 'n ;ochi some of the areas where roc& is not

    available, the pile is rested on coarse sand strata where the 4$value is more than 177. +efore ta&ing a decision

    to rest the pile on sand the thic&ness of the sandy strata should also be analyed, because the sandy strata willbe very thin and if clay strata is under laying the piles will not ta&e the desired load.

    !e"#o$ S"a"emen" % D! Piling

    *or e?ecuting DM" piles (Direct Mud "irculation piles ) method which is approved as per ' 777mm dia depth up to :7 mtrs. !hese types of piling are mainly used for industrial purposes

    where large areas are available for development and time is the main factor. !he capacity of the rigs are

    classified based on torue it can produce and it various from B to C7 and this is designed based on hardness of 

    the roc& it can cut. !he roc& is mainly cut by -otary method using !ungsten carbide bits or diamond bits. 'f the

    roc& is too hard then it is cut by using core barrel using Diamond bits and this is very e?pensive. !he production

    of -otary rigs has to be a minimum of 177 mts per day to cover the cost and if the production is low, then the cost

    will increase. #lso in transporting and deploying these machines wide approach roads are reuired as the

    machine weights from C7 tons to B7 tons and the length of the ;elly bar from 1 mtrs to 16 mtrs. *or residential

    buildings now a days @ydraulically operated rotary rigs are used mounted on lorries and these also give desiredresult and less e?pensive when compared to modern rotary rigs.

    b' !e"#o$ of "es"ing Fo(n$ing S"ra"a!he basic method for ascertaining the strata for founding is standard

    penetration test and if the 4$value is more than 177, then it is considered as reasonably good founding strata for 

    piling.

    )' on)re"e !he concrete mi? used for piling is M6,M>7,M>6 etc. in 'ndia and outside the country MC7 is the

    minimum standard for piling and if goes to M87. !he strength of the concrete as ascertained by cube test after >

    days, Bdays, 1days, 8days, etc. !he wor&ability of the concrete is assessed by ta&ing the slump at site it

    should be from 167 to 187mm.

    $' Pile "es" T#e piles are "es"e$ for "#e follo*ing

  • 8/17/2019 piling md

    23/23

    • 'nitial vertical load test

    • 'nitial lateral load test

    • 'nitial pullout test

    • -outine vertical load test

    • -outine lateral load test

    • -outine pullout test

    • Dynamic load test (4ondestructive)• 'ntegrity test.

     #s per the 'ndian standard 1 times the design load is tested and the settlement of the piles should be below

    1mm.!he relevant ' code is as follow '