Pier 1 PACE Upgrade

13
May 2013 Director, Sustainability Programs Aaron Binkley Pier 1 PACE Upgrade

Transcript of Pier 1 PACE Upgrade

Page 1: Pier 1 PACE Upgrade

May 2013

Director, Sustainability Programs

Aaron Binkley

Pier 1 PACE Upgrade

Page 2: Pier 1 PACE Upgrade

Objectives

2

Introduce Prologis and the PACE project at our Pier 1 global headquarters

Highlight what worked and what was a challenge for this project

Page 3: Pier 1 PACE Upgrade

Unmatched Global Platform

3

1. Note: Data as of December 31, 2012 2. Comprises Prologis’ operating, development and other portfolio 3. Source: International Monetary Fund

Platform covers countries representing ~70% of global GDP(2)

Americas Europe Asia Total

Total Prologis’ Share Total Prologis’

Share Total Prologis’ Share Total Prologis’

Share

Total Portfolio(1) – Square Feet / Square Meters (mm) 380 / 35 73% 138 / 13 66% 36 / 3 73% 554 / 51 72%

Development – TEI ($mm) $968 86% $203 90% $921 91% $2,092 89%

Land (acres) 7,614 98% 3,485 100% 170 58% 11,269 98%

Page 4: Pier 1 PACE Upgrade

Corporate Responsibility Initiatives

4

Environmental Stewardship

Social Responsibility

Governance and Ethics

Operations

Lighting upgrades

HVAC

Cool roofs

Daylighting

Water conservation

EPC/Energy Star

Technology pilot projects

Capital Deployment

Certified construction

EPCs

Embodied carbon pilot

Adaptive re-use

ISO 14001

Renewable Energy

Community Engagement

Green Path

Corporate carbon emissions

Education and training

CR Champions

Charitable activities

Prologis Foundation

Volunteering

Space for Good Program

Corporate Governance

Governance practices

Independent directors

Business conduct hotline

Ethics

Code of business conduct

Employee training

Communications

Page 5: Pier 1 PACE Upgrade

Sustainable Development

5

Prologis applies recognized green building standards to development projects with a goal of 100% certification

38 MSF of certified projects

6 rating systems in 11 countries

Page 6: Pier 1 PACE Upgrade

Energy Efficient Upgrades

Energy efficiency investments are the single, most cost-effective way to reduce customer operating expenses

270 million square feet has efficient systems

50 percent of the global operating portfolio

6

Page 7: Pier 1 PACE Upgrade

Renewable Energy

7

83 megawatts of rooftop solar projects in six countries

104 million kWh of energy production potential

Page 8: Pier 1 PACE Upgrade

Pier 1 Upgrade Project Objectives

8

Reduce operating costs

Better manage our environmental footprint

Demonstrate PACE

Retro-commissioning

Lighting upgrade

200kW rooftop solar installation

Page 9: Pier 1 PACE Upgrade

Elements of Overall Energy Savings

9

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Baseline Energy Use

67% Post- Upgrade

26% Energy Use Reductions • Retro-commissioning • Lighting Upgrade

7% Solar

Page 10: Pier 1 PACE Upgrade

Project Evaluation

10

Fortunately

Located in PACE market

Support from City

No mortgage

High energy costs

QECB

Unfortunately

No utility incentives

Triple-net leased building

Don’t “own” the building

Special tenant tax status

QECB

Page 11: Pier 1 PACE Upgrade

Perceived Value vs. Effort

11

Value Effort

QECB

QECB

PACE bond

Owner Equity

PACE bond

Owner Equity

Page 12: Pier 1 PACE Upgrade

Pier 1 and PACE: Works in Progress

12

Page 13: Pier 1 PACE Upgrade

WWW.PROLOGIS.COM

Aaron Binkley Director, Sustainability Programs +1 (415) 733-9554 [email protected]