Phone: (03) 6273 4955 Facsimile: (03) 6273 4977 Email ... Bu… · 6hr fire rated encasement of SHS...
Transcript of Phone: (03) 6273 4955 Facsimile: (03) 6273 4977 Email ... Bu… · 6hr fire rated encasement of SHS...
AINTENANCE SYSTEMS PTYLTD
Museum of Old and New Art – Feature wall incorporating rock bolting.
Red Bridge Campbell Town – Archtec anchoring to upgrade load capacity of this major highway historic bridge – Completely hidden – this bridge has 36 x 5mtr stainless steel anchors placed tangentially to the 3 arches.
St Patrick’s Church at Colebrook – Restoration for Pugin Foundation. Cintec – fully hidden stainless steel anchors support and tie the spire structure and main roof.
C O N T R A C T I N G * * * * I N N O VAT I O N * * * * S P E C I F I C AT I O N
www.maintenancesystems.com.au 34 Derwent Park Road, Derwent Park 7009Phone: (03) 6273 4955 Facsimile: (03) 6273 4977 Email: [email protected]
SPECIALISED ANCHORING, GROUTING and INDUSTRIAL COATING SERVICES
T E C H N I C A L B U L L E T I N N O . 2 4
Hobart Reservoir – Cintec anchors to full height to stabilise wall for 1000 year flood security – This is a heritage site and all anchoring is completely hidden.
S P E C I A L I S E D A N C H O R I N G
NORSKE SKOG – 11 cubic meters of deep pour epoxy grout placement to log feed and debarking mill base plates – This specialised grout for high dynamic loads placed using continuous mixing and pumping technology.
BELL BAY GAS FIRED POWER STATION – The Rolls Royce, turbine and generator set is the main power plant and sits on a tapered grout bed 80 to 30mm over 30mtrs – 6m3 epoxy deep pour grout placed within 1 day – Continuous pour mixing and pumping technology.
TREVALLYN POWER STATION – Vertical inlet tunnel – Precision cementitious grout to lock steel to surrounding concrete.
NYRSTAR – 200 metre holes drilled into embankment required the final 20mtrs to have stainless steel pipe and flange termination grouted in place – Special purpose grouting technology was developed to undertake the works – Picture shows grout being placed with overflow bleed in action.
NYRSTAR – The completed system – 9 outlets – Acids can now be drained out as required and be removed safely.
Demolition grout – great for breaking out dolerite rock – silently – in built up areas – where blasting is not acceptable.
S P E C I A L I S E D G R O U T I N G
6hr fire rated encasement of SHS steel – preparation stage. 6hr fire rated encasement of steel – finished section.
Vermiculite firespray to steel beams providing 120 minute rating to structural steel members.
MONA – Shotcrete – preparation and application. MONA – feature wall – The shotcrete application completed.
Looking for fire protection? We offer a comprehensive range of solutions.
S P E C I A L I S E D C O AT I N G
Extensive Concrete Repair After concrete and steel remediation
ρ Founded 1990 as a specialist Contracting and Consulting company
ρ Focus is the enhancement, protection, maintenance and repair of concrete assets
ρ Provides survey and advice as to correct solutions to client problems
ρ Applies the recommended and agreed solutions in accordance with the relevant standards and product manufacturers specifications
W E O F F E R E X P E R I E N C E , I N N O VAT I O N , Q U A L I T Y , S E R V I C EContact: Stuart Spotswood 0409 495 685 Richard Eveleigh 0419 323 083 Alan Debnam 0418 532 866
O R I G I N E N E R G Y – S E L F S P O I N T Before concrete and steel remediation
Total package works comprising concrete plinths repair, blasting and coating of all tank, pipes and walkways under strict QA and Hazard control.
T E C H N I C A L I N D U S T R I A L PA I N T I N G