Philippines LNG: Developing New Import Marketslantaugroup.com/files/ppt_fsru14_sf.pdf ·...

download Philippines LNG: Developing New Import Marketslantaugroup.com/files/ppt_fsru14_sf.pdf · Philippines LNG: Developing New Import Markets Sarah Fairhurst 3rd Annual FSRU Conference,

If you can't read please download the document

Transcript of Philippines LNG: Developing New Import Marketslantaugroup.com/files/ppt_fsru14_sf.pdf ·...

  • Philippines LNG: Developing New Import Markets Sarah Fairhurst 3rd Annual FSRU Conference, Singapore, November 26 2014

    Prepared by:

    Sarah Fairhurst

    [email protected]

  • Agenda

    Understanding Philippiness energy needs and government policy for LNG imports

    Outlining possible terminal projects: Who might win the race to build the terminal?

    Barriers to entry and possible options to manage them

    1

  • Understanding the Philippines Energy Needs: Current Situation

    Fuel mix is currently very diversified with a

    high proportion of renewable and local

    sources

    Gas makes up 25% of the fuel for power

    generation in the country higher if you just

    look at Luzon

    Practically all the gas comes from

    Malampaya a single gas field offshore

    Palawan via long (504km) undersea pipeline

    The Malampaya concession expires in 2024

    and while it may have enough gas for some

    further expansion, this is not considered

    sufficient for more than about 5 years at

    current levels

    2

    After Malampaya what then?

    Coal 43%

    Oil 6%

    Natural Gas 25%

    Geo-thermal

    13%

    Hydro 13%

    Wind 0.1%

    Solar 0.002% Biomass

    0.3%

    2013 Generation Mix

    Source: Philippine DOE (Power Statistics)

  • And although there is a lot of gas currently burnt, much of it is not economic

    The three gas plants all currently run baseload

    However, they ONLY run baseload because of the

    take or pay (ToP) constraints of the contract for

    the sale of gas

    Without these ToP constraints, economically the

    gas-fired plants would run less acting as peaking

    or mid-merit plants

    Between July 2007 and the end of 2013,

    Meralco alone spent an extra US$300m on

    its gas-fired IPPs compared to the cost

    saving it could have got from its coal plants

    3

    3833

    27

    9

    2012

    without

    ToP

    48

    2012

    actual

    42

    80

    60

    40

    20

    0 Geothermal

    Coal

    Natural Gas

    Oil-based

    Hydro

    Wind

    Biomass

    2017

    est

    without

    ToP

    74

    2017

    est

    100

    57

    Luzon generation fuel mix

    Percent

    Source: TLG analysis

    The Philippines has diverted a lot of money from electricity into other things since the

    completion of Malampaya..

  • The Philippines has an event-driven electricity sector much uncertainty and

    variability for both natural and technical reasons

    Note: * Buying price (with 100% surplus)

    Source: PEMC; TLG analysis

    PhP/kWh

    Average monthly WESM spot settlement price* (2007-14)

    4

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    22

    24

    26

    Jan-14 Jul-13 Jan-13 Jul-14 Jul-12 Jan-12 Jul-11 Jan-11 Jul-10 Jan-10 Jul-09 Jan-09 Jul-08 Jan-08 Jul-07 Jan-07 Jan-15

    Low

    hydro

    Gas curtailments

    and low hydro

    Plant forced maintenance

    outages and HVDC link

    maintenance

    Transformer breakdown and San

    Jose substation congestion

    Plant outages and

    coal limitations

    Plant outages

    Gas curtailments

    and plant outages

    Gas scheduled outage

    and plant outages

    ERC-

    regulated

    price

    reduction**

  • Weather effects vary widely each year the system must have the capability to

    deal with strong swings between El Nino and La Nina

    5

    Deg. C

    NOAA Oceanic Nio Index (ONI)

    Source: NOAA

    (2.5)

    (2.0)

    (1.5)

    (1.0)

    (0.5)

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    Jan-5

    0

    Oct-

    51

    Jul-5

    3

    Apr-

    55

    Jan-5

    7

    Oct-

    58

    Jul-6

    0

    Apr-

    62

    Jan-6

    4

    Oct-

    65

    Jul-6

    7

    Apr-

    69

    Jan-7

    1

    Oct-

    72

    Jul-7

    4

    Apr-

    76

    Jan-7

    8

    Oct-

    79

    Jul-8

    1

    Apr-

    83

    Jan-8

    5

    Oct-

    86

    Jul-8

    8

    Apr-

    90

    Jan-9

    2

    Oct-

    93

    Jul-9

    5

    Apr-

    97

    Jan-9

    9

    Oct-

    00

    Jul-0

    2

    Apr-

    04

    Jan-0

    6

    Oct-

    07

    Jul-0

    9

    Apr-

    11

    Jan-1

    3

    ONI measures average surface sea temperatures and it is used by the US

    National Oceanic and Atmospheric Administration (NOAA) for their

    operational definition of El Nino and La Nina

    El-Nino

    La Nina

  • And of course hydro is not the same each day, week, month, season, or year

    6

    13

    2

    1

    0

    5.2

    12

    5.3

    11

    5.5

    08

    4.4

    10

    4.0

    09

    5.5

    05

    4.3

    04

    4.3

    03

    5.4

    07

    4.6

    06

    4

    3 2.9

    2002

    3.8

    6

    5

    Source: DOE Power Statistics (2002-13); PEMC; TLG analysis; NOAA

    Annual hydro generation in Luzon

    (2002-13)

    0

    5

    10

    15

    20

    25

    30

    0

    5

    10

    15

    20

    25

    30

    600

    400

    200

    0

    D N O S M F J A J J M A

    800

    Monthly hydro generation in Luzon and

    2011 precipitation (2006-2012)

    Hydro generation is

    low in Q2 when

    demand is at its

    peak

    Low inflows in severe El-

    Nino years reduce ability

    of hydro plants to

    generate

    TWh (bars) GWh (lines) mm (bars)

    2008

    2007

    2006

    2011 precipitation

    (RHS)

    2012

    2011

    2010

    2009

    Generation peaks

    when there is

    plentiful inflows

  • As a consequence of all these things timely, flexible, capacity is needed

    7

    0

    100

    200

    300

    400

    500

    600

    700

    2/3/14 2/2/14 2/1/14 1/31/14 1/30/14 1/29/14 1/28/14 1/27/14

    Sual G1

    Mariveles G2

    Pagbilao G1

    Typical weekly generation schedule (w/c January 27, 2014)

    MW

    Source: PEMC (ex-post schedules)

    COAL PLANTS

    And most flexibility in the market is currently provided by coal which is not ideal

  • New power stations running LNG would meet this need but building power

    stations in the Philippines is more complicated than many places in Asia

    There is no national Government owned electricity utility in the Philippines

    There are no Government backed long term PPAs on offer and no Government Guarantees

    The electricity legislation (EPIRA) prevents the Government from building or contracting for power stations

    (except in emergency situations)

    There are two electricity markets the WESM (Luzon and Visayas) and the IMEM (Mindanao)

    There is a degree of open access and retail competition meaning some loads are contestable

    There remains extensive regulation of electricity contracts between generators and retailers

    Not all of which is well designed or well implemented

    So an investor in power in Philippines has to manage commercial and regulatory risks

    through private sector investment and debt. Add to that the costs of building an LNG

    terminal as well

    8

    Is it even possible?

  • So how much LNG could be economic in the power sector?

    This is a question we answered recently as part of our work on the Gas Master Plan for the

    Philippines

    To answer the question, we modelled the electricity market using our electricity market simulation

    tool (QUAFU) to identify:

    What type of plant is is most economic to build in the future in the Philippines given the current plant mix,

    future load projections and costs of different type of new build options

    How would existing gas-fired plant operate after their existing gas contracts expire

    Are there any other ways LNG could enhance the system, without adding to system costs?

    9

  • We showed that there was a case for LNG in the least-cost capacity expansion

    plan for the WESM and that this ran mid-merit

    10

    Least-cost capacity expansion plan for Luzon

    under expected assumptions

    0

    200

    400

    600

    800

    1,000

    1,200

    29 27 25 23 21 19 17 15 2013

    Net MW

    Economic least-cost entry

    Natural Gas

    Biofuel

    Wind

    Geothermal

    Hydro

    Oil

    Coal

    Note: EWC plant assumed to not be committed

    Source: DOE (committed plants as of Aug 2013); TLG analysis

    Near-term need for more cost

    effective mid-merit / peaking capacity

    Conservatively, an LNG-fired CCGT

    of about 600-800 MW and a LNG

    import terminal appear to be the

    least-cost option

    They are able to recover reasonable

    returns on their invested capital

    (including for terminal)

    The amount of LNG-fired capacity

    required is relatively robust to near-

    term committed capacity

    However, at expected coal and LNG

    prices, coal generation will continue

    to be least-cost option for most of

    future capacity requirement

    Uncertainty over

    how further supplies

    from Malampaya

    could be used?

  • In the longer term, existing plants would run mid-merit rather than as baseload

    plant if take-or-pay constraints are eased

    As we noted earlier, the Philippines already has 2700MW of gas-fired capacity which runs

    baseload, out of merit

    Between 2022 and 2024, the gas contracts forcing this plant to run baseload expire

    When that happens, the existing plant will be able to operate economically in a mid-merit role

    This means that no further gas-fired capacity is needed in the WESM

    11

    There is a current window of opportunity for some additional mid-merit plant, but LNG

    fired power does not require investments in large amounts of plant

  • In addition to building new power stations, there is also an opportunity to import

    LNG to back up the existing domestic gas

    12

    Start date Duration

    Estimated additional system cost (mPhP)

    Scheduled Malampaya maintenance outage

    22 Nov 2006 25 days 2,500

    27 Jun 2008 4 days 1,000

    10 Feb 2010 30 days 1,300

    20 Oct 2011 7 days 900

    13 Jul 2012 8 days 600

    11 Nov 2013 30 days 4,000

    Subtotal: 10,300

    Unscheduled Malampaya supply outages

    Average curtailment of 1,700MW over about 287

    hours since 2006 740

    Total: 11,040

    Imported LNG is more cost

    effective than liquids, meaning

    that having the option to back-

    up Malampaya with LNG is a

    valuable option

    If LNG is used to replace liquid

    fuels when Malampaya is on

    outage, an opportunity to save

    in the order of USD20-25

    million per annum exists

    Reduced availability also

    means more expensive

    generation is needed to

    replace lost capacity

    Note: * Used in scheduled maintenance outages

    Source: DOE; TLG analysis

    This is a conservative value if one took into account the impact on the market price

    as well it may be higher

  • And in the longer term, there are additional markets for gas

    13

    LNG would result in considerable

    savings over LPG and diesel as a

    heating fuel

    And also as a transport fuel 05

    10

    15

    20

    25

    30

    35

    US

    D/m

    mb

    tu

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    35.0

    US

    D/m

    mb

    tu

  • Our base case scenario has growing demand from power, industry and

    transport

    In the short term, we believe it is more economic to

    move LNG by truck to industry than by pipeline

    There are a number of diesel fired power stations

    in Visayas and Mindanao that could be converted

    to run on LNG most of these are proximate to the

    coast and could be serviced by small barges on a

    milk run from the main Luzon terminal

    Development of gas pipelines in the Philippines is

    problematic due to access to land over time if

    this is solved and after a base industrial demand

    has grown, then additional pipelines into Manila

    make sense

    14

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    3.5

    4.0

    4.5

    2017 2020 2025 2030

    mtpa

    Power

    Industry

    Transport

    Forecast LNG consumption

  • So, there IS commercial potential for LNG in the Philippines, but not a huge

    amount

    Most of the potential LNG demand comes from the power sector:

    To back up existing power stations now; or fuel existing power stations after 2024

    Fuel for new power stations from 2017 onwards

    Backing up existing power stations is worth about USD 20-25 million per annum until 2024

    There is an economic case for about 600-800 MW of new power stations, running mid-merit

    Highly variable gas demand due to variations in annual rainfall (hydro), outages, and weather (El Nino)

    meaning quantities of LNG required are significantly less than 1mtpa in the near term

    No economic case for new baseload gas fired power stations coal is always a cheaper option for

    baseload, even after factoring in possible carbon credits

    Small but potentially growing demand for gas in industry and transport

    15

  • Unfortunately our findings do not sit well with recent policy developed

    independently of this work

    The Energy Secretary developed a Fuel Mix policy at the same time we were running this project,

    which states that 30% of the electricity in the Philippines will come from gas.

    It appears to roughly take the fuel mix in 2008 (the year the RE law was passed) and expands it

    out into the future

    However, appears to be a political desire with no economics nor analytics underpinning in.

    Nor any active policy either (no mandatory actions required)

    16

    The recommendations of the Gas Master Plan are out of line with the new Fuel Mix

    policy which is causing confusion in the DOE

  • So what will actually happen?

    The Natural Gas Master Plan proposed a specific transaction structure to bring in a privately

    owned FSRU to deliver back up LNG and supply for the economic amount of new power stations

    It required only a small amount of Government assistance to get the process started but so far,

    there are no indications that the DOE will act on any of the recommendations

    DOE is understaffed and much focus is currently on the emergency power for next year

    A number of internal movements within DOE mean that staff who were in charge of this project have now

    moved elsewhere

    However, all is not lost.

    There are a number of initiatives from the private sector that may deliver very similar outcomes

    17

  • A year ago a number of private sector proponents were active in this space.

    At the start of our Master Plan study, we interviewed all the active proponents looking to build

    LNG terminals in Philippines

    Most were looking at land-based terminals

    Most were looking at base load options for gas power plants and off-take

    Few really understood the market

    Our study recommended an FSRU instead of a land-based terminal

    The amount of gas required is small, meaning expensive land-based terminals are unnecessary

    Flexibility is important timing may change faster options are more appropriate

    Building on land is problematic in Philippines land acquisition and approvals delay projects so a floating

    solution has advantages

    18

  • however now the credible suspects have been narrowed down

    EWC is under construction at Pagbilao

    Land-based terminal using marine-based technology to keep costs down

    Significant progress has been made on the terminal and turbines have arrived on site for the power station

    Construction started before the project was fully funded, making it hard to predict how it would outturn

    Shell has been undertaking a FEED study for LNG import at Batangas

    Their JV SPEX is currently the sole supplier of gas to the Philippines, with a depleting field, giving Shell a

    clear economic incentive to find a way to continue supplying gas to the Philippines market

    First Gen has also been looking at LNG options

    First Gen owns two of the three gas-fired power stations currently operating and is building two more a

    peaking plant and another mid-merit plant

    Those plants will initially share gas from the existing gas supply, but this is only a short term solution so

    First Gen have a clear economic driver to find alternative supplies

    Meralco was previously looking at a terminal but now appears to be just looking at a gas-fired

    power station

    As the largest distribution utility in the Philippines, it makes a very credible and credit-worthy counter party

    for any importer of LNG

    19

  • Any of the options could supply the economic need for LNG-fired capacity in

    the power sector

    EWCs project is around 600MW and currently has no power contracts - meaning that it would

    operate as required in the WESM exactly as our model predicted

    First Gens projects take existing inflexible gas and remove the take-or-pay to allow much more

    flexible and economic burn of the existing Malampaya gas but all these power stations will

    need fuel in the future after Malampaya

    Meralco has long argued that flexible, mid-merit power is what is needed in the Philippines

    electricity market

    20

    All these projects are consistent with the economic requirement of the power sector

    and all are private-sector driven

  • But barriers to entry still remain

    There are no environmental incentives for gas-based generation in the Philippines

    Regulation of power supply contracts continues to undermine efficient outcomes

    Contract regulation is currently based on a cost-plus basis that does not take account of market prices

    nor what alternative contracts might be available.

    There are no incentives for distribution utilities to procure an overall least cost portfolio

    As such, it makes it harder to highlight how mid-merit and peaking generation options fit into the mix

    compared to cheaper baseload coal.

    Government policy and intervention in the electricity market is undermining private sector

    incentives

    Interference in the market to lower market prices after the fact has caused some generators to lose

    money

    Lowering the cap on the market price and adding a new secondary price cap at a level lower than a

    peaking plant needs to recover its costs has serious implications for new investment

    There remains no clarity of rules on NG use and infrastructure

    21

  • Lack of regulatory incentives for retailers to contract are possible one of the

    biggest barriers to entry of new flexible plant

    Retailers are the companies who buy from the wholesale market and sell to end use customers

    In the Philippines these are distribution utilities and co-operatives servicing franchise consumers

    (as well as a small number of retailers servicing the contestable market)

    The purchases of these retailers are regulated by the ERC, but this regulation is unlike that found

    in most markets

    The regulation is focussed solely on individual contracts

    It does no analysis of whether the contract is actually NEEDED, only the cost of the contract

    It does not take account overall purchases by the retailer

    It does not take into account alternatives available

    And nobody regulates what is not contracted (that is, purchases from the spot market)

    Once approved, all the costs of these contracts are passed directly through to the consumer,

    even if they later change, even if the contract is not needed

    22

    The impact means that retailers focus on what is easy to get approved, not on what is

    actually needed. They have no incentives to contract efficiently

  • In any market, or to meet any load shape of electricity demand, there is a mix

    of plants that is cheapest

    23

    Oil Gas Coal Oil Gas Coal

    0

    50

    100

    150

    200

    250

    300

    Fixed costs - $/kW per year Variable costs - $/MWh

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    Capital

    Fixed O&M

    Fuel

    Variable O&M

    ITS BECAUSE

    YOU WANT TO RUN IT A LOT

    IF YOU SPEND ALL THIS

    MONEY TO BUILD IT

    No single technology is inherently better than the other it is the way they are mixed

    that makes the optimal solution

  • In a market like the Philippines, we would expect retailers to purchase a mix of

    peak, baseload and mid-merit capacity to meet their needs

    24

    Peaking plant such as diesel or hydro

    Mid-merit (flexible) plant such as CCGT or recips

    Baseload (always on) plant such as coal, geothermal

    This is important because it is the incentives on retailers to contract that drives the

    contract underpinning new entry into a merchant market

    LO

    AD

    Hours in the year

  • If you look at the data, retailers in the Philippines are not contracting according to

    an optimal mix

    25

    Average power cost vs. load factor for Luzon grid ECs (2012)

    The evidence is consistent with our hypothesis, that the structure of regulation does not

    incentivise contracting for anything other than baseload plant

  • In addition, normal merchant markets put risks on retailers to encourage them

    to contract (and to contract efficiently)

    Since WESM purchases are not subject to regulation, all WESM costs are passed through to

    consumers

    In other markets, customers have fixed tariffs, and if spot prices are high, it is RETAILERS, not

    the customers, who bear this risk

    In Philippines this is backwards.

    Since customers bear the risk, the regulator and the DOE worry about high WESM prices and

    have capped the price

    26

    This band-aid solution merely tackles the symptom, not the disease and in the long

    term will make the problem worse

  • The market cap price much lower than other markets

    27

    Comparison of the Market Price Caps

    0

    100

    200

    300

    400

    500

    600

    Singapore

    NEMS

    159

    US

    ERCOT

    226

    32

    Australian

    NEM

    WESM

    (2013)

    538

    62

    PhP/kWh

    Due to increase

    in 2015

    With a higher price cap:

    More attention would be paid to effective

    contracting

    strategies especially contracts to cover

    disruptions

    outages and peak demand

    Flexible and responsive capacity (such as that

    provided by LNG) would become

    more commercially attractive, leading to

    earlier

    replacement of older, expensive, and less

    responsive

    capacity

    However risk to retailers would increase, as

    they would be more exposed to uncovered

    (spot) price risk

    And changes to the regulatory environment

    are required to support this outcome

    WESM

    (2014)

    The market woes and regulatory short-comings may yet hinder efficient development of

    LNG in the Philippines

  • In summary

    There is an economic case for LNG to enter the Philippines

    The market is driven by the private sector and the private sector is responding to the needs

    Government policy is lagging private sector needs and recent decisions are actively deterring

    new investment

    And regulation continues to undermine the incentives for efficient contracting which would assist

    in underpinning new entry

    28

    We continue to watch, wait and push for improvements

  • Sarah Fairhurst

    [email protected]

    The Lantau Group

    4602-4606 Tower 1, Metroplaza

    223 Hing Fong Road

    Kwai Fong, Hong Kong