PROJECT: Aerial Pipeline Dismantlement LOCATION: Wax Lake Outlet, Atchafalaya Bay, Louisiana WORK SCOPE: Lower super structure; removal of 22” diameter pipeline at 73’ above sea level, removal of inverted internally braced “Y” towers. Aerial Pipeline Abandonment Reaches New Heights “We were especially successful at reducing risks associated with working at heights, by developing an alternative solution to putting people in the air.” JEROME SHAW VP Construction MARINE CONSTRUCTION Project Highlight CHET MORRISON CONTRACTORS 985.868.1950 | CHETMORRISON.COM Erected in the 1970’s, this was the first aerial of its kind to be removed in the US Restrictive access preventing heavy equipment transportation over the levees High velocity currents Both shallow and deep (100’) water depth contours Instable weather conditions Unsprung energy storage Workers at height restrictions (Installation methods were 40 years old) Environmental concerns Close proximity to other buried and aerial pipelines Boat traffic during day and night CHALLENGES OVERCOME Chet Morrison Contractors was contracted to develop a solution that met stringent regulatory and safety requirements. A major key to the safe and successful completion of this ground breaking project was the meticulous planning of the work and the proactive client/contractor partnership.

Transcript of PH Aerial Pipeline - MorrisonPROJECT: Aerial Pipeline Dismantlement LOCATION: Wax Lake Outlet,...

Page 1: PH Aerial Pipeline - MorrisonPROJECT: Aerial Pipeline Dismantlement LOCATION: Wax Lake Outlet, Atchafalaya Bay, Louisiana WORK SCOPE: Lower super structure; removal of 22” diameter

PROJECT: Aerial Pipeline Dismantlement

LOCATION: Wax Lake Outlet, Atchafalaya Bay, Louisiana

WORK SCOPE: Lower super structure; removal of 22” diameter pipeline

at 73’ above sea level, removal of inverted internally braced “Y” towers.

Aerial Pipeline Abandonment Reaches New Heights

“We were especially successful at reducing risks associated with working at heights, by developing an alternative solution to putting people in the air.”

JEROME SHAWVP Construction

M A R I N E C O N S T R U C T I O N P r o j e c t H i g h l i g h t

C H E T M O R R I S O N C O N T R A C T O R S

985.868.1950 | CHETMORRISON.COM

Erected in the 1970’s, this was the first aerial of its kind to be removed in the US

Restrictive access preventing heavy equipment transportation over the levees

High velocity currents

Both shallow and deep (100’) water depth contours

Instable weather conditions

Unsprung energy storage

Workers at height restrictions (Installation methods were 40 years old)

Environmental concerns

Close proximity to other buried and aerial pipelines

Boat traffic during day and night

CHALLENGES OVERCOME

Chet Morrison Contractors was

contracted to develop a solution that

met stringent regulatory and safety

requirements. A major key to the safe

and successful completion of this ground

breaking project was the meticulous

planning of the work and the proactive

client/contractor partnership.