Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36...

23
Petrobras P-36 Incident Susana Leon Caceres Master’s Student in Safety Engineering Mary Kay O’Connor Process Safety Center Texas A&M University, College Station. January 14 th , 2016 Steering Committee Meeting

Transcript of Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36...

Page 1: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Petrobras P-36Incident

Susana Leon Caceres

Master’s Student in Safety Engineering

Mary Kay O’Connor Process Safety Center

Texas A&M University, College Station.

January 14th , 2016

Steering Committee Meeting

Page 2: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Susana Leon Caceres• I was born and raised in Bucaramanga, Colombia

• Bachelor’s degree in Chemical Engineering at “Universidad Industrial de Santander”

• Safety Engineer at Ecopetrol in Cartagena’s Refinery

• Master’s Student in Safety Engineering at Texas A&M University (First Year)

01/14/2016 STEERING COMMITTEE MEETING 2

Source: Google maps[1]

Page 3: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Outline

• Background

• Petrobras P-36 incident description

• Sequence of events

• Investigation-what went wrong?

• Causes and root causes

• Conclusions and recommendations

01/14/2016 STEERING COMMITTEE MEETING 3

Page 4: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Floating Production Unit (FPU) Background

01/14/2016 STEERING COMMITTEE MEETING 4

• Original name: “Spirit of Columbus”

• Designed and constructed in 1984-1994 in Italy

• Original intent: oil drilling and small production unit [3]

• Contracted by Petrobras in 1996, and renamed to P-36

• Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

• Major changes:

Designed to operate at 500 m water depth adapted to 1360 m [4,5]

Capacity 180,000 bpd of oil and 7.2 million m3/day of gas

Installed buoyancy boxes to accommodate extra weight of topsides

Average production on March 15: 84,000 bpd of oil and 1.3 millions m3/day gas [4,5]

• Installed at the Roncador Field in 2000

Fig 1. Location of Campos Basin’s Rocandor field [1,2]

Page 5: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Accident Description [6, 7]

01/14/2016 STEERING COMMITTEE MEETING 5

When – 15th March, 2001

Where – Roncador field in Campos Basin, 125 km from the coast of Brazil

2 explosions in one of the support legs, followed by flooding of the leg

The FPU sank (on March 20th)

Consequences

• 11 fatalities

• Financial losses nearing 1 billion dollars

• Around 316,000 gal of diesel and 80,000 gal of crude oil spilled

Fig 2. P-36 platformsinking [8]

Fig 3. P-36 spill on the sea [9]

Page 6: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Accident Description

01/14/2016 STEERING COMMITTEE MEETING 6

Aft

D

C

B

Fire pumps (seawater pumps): A: Portside aftB: Portside foreC: Starboard foreD: Starboard aft

Fig 4. General view of P-36 [6] Fig 5. Semi-submersible platform modelAdapted from [10]

Page 7: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Platform Layout “Aerial view” [6,12]

01/14/2016 STEERING COMMITTEE MEETING 7

Starbo

ard

Aft

Portsid

e

Bow/Fore

Fire pumps: A: Portside aftB: Portside foreC: Starboard foreD: Starboard aft

A

BC

D

Emergency Drain TankFig 6. Emergency Drain Tank , Top view.Source: The Accident of P-36 FPS [6].

Fig 7. Special drawings created,

Platform aerial view.Source: Accident

Investigation Petrobras P-36 Sinking

(DNV) [12].

Page 8: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Sequence of events (March 10th - 20th, 2001 )[4,6]

01/14/2016 STEERING COMMITTEE MEETING 8

Causes

Incident day Salvage operations

Fig 7. Adapted general timeline of the P-36 accident.Source: Petrobras and Brazilian navy reports [4,6].

Page 9: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Sequence of events (March 15th)[4,6]

01/14/2016 STEERING COMMITTEE MEETING 9

• First explosion (Mechanical explosion – pressure burst)― Due to pressure build-up in a drain tank

• Second explosion(Chemical explosion)― Due to ignition of released vapors

• Fire alarm system operations

Fig 8. Inclination six degreesSource: Acidente da P-36 –Explosao e Naufragio [11]

Page 10: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Investigation –what went wrong? [4,6,12]

01/14/2016 STEERING COMMITTEE MEETING 10

OPEN

CLOSE

Partially Close

HEADERVALVE

PRODUCTION HEADER

PORTEDT

STARBOARDEDT

BLIND FLANGE

ATMOSPHERICVENT

CAISSONVALVE

10 bar

Aft/Fore viewInitial conditions [4,6,12]

• Both tanks contained 50% of water• The pump of the Starboard-aft Emergency Drain Tank was removed for maintenance• 3 valves were closed and properly isolated with blind flanges• 1 valve was manually closed but no blind flange was installed(allowing liquid to enter)

Fig 9. Flow chart Emergency Drain tank system on the aft site (initial conditions on March 14th).Source: Adapted from [4,7,11,12]

BLIND FLANGE

Page 11: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Investigation –what went wrong? [4,6,12]

01/14/2016 STEERING COMMITTEE MEETING 11

HEADERVALVE

PRODUCTION HEADER

PORTEMERGENCYDRAIN TANK

ATMOSPHERICVENT

CAISSONVALVE

10 bar

Aft/Fore viewEmptying portside TDE [4,6]

• Port pump aligned towards the production header

• Outflow line valves (starboard) opened

• Delay to start up the drain pump of the port aft TDE

• Reverse flow during 54 min The

pressure started

increasing

STARBOARD EMERGENCYDRAIN TANK

Valve leaks

Fig 10. Flow chart Emergency Drain tank system on the aft site (unsuccessful activation of the port tank pump).Source: Adapted from [4,7,11,12]

OPEN

CLOSE

Partially Close

BLIND FLANGE

BLIND FLANGE

VA

PO

RO

ILW

ATE

R

Page 12: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Investigation –what went wrong? [6,11]

01/14/2016 STEERING COMMITTEE MEETING 12

HEADERVALVE

PRODUCTION HEADER

ATMOSPHERICVENT

CAISSON VALVE

10 bar

Aft/Fore view

Internal pressure reaches 10 bar

P (

bar

)

Min

ute

s

STARBOARD EMERGENCYDRAIN TANK

Water started

pumping out

19 barCapacity

Valve leaks

Fig 11. Flow chart Emergency Drain tank system on the aft site (Port tank pump start up).Source: Adapted from [4,7,11,12]

PORT EMERGENCYDRAIN TANK

OPEN

CLOSE

Partially Close

BLIND FLANGE

BLIND FLANGE

Page 13: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Investigation –what went wrong ? [6,11]

01/14/2016 STEERING COMMITTEE MEETING 13

Tank’s wall Rupture (Leakage) Tank’s wall Rupture (Gas Dispersion) Flooding in 4th Level (Oil and Water)

Fig 12. Adapted From Acidente da P-36 –Explosao e Naufragio.Source: Acidente da P-36 –Explosao e Naufragio (Petrobras – 15.03.2001)

.

3RD LEVEL 3RD LEVEL 3RD LEVEL

4th LEVEL 4th LEVEL 4th LEVEL

Page 14: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Investigation –what went wrong ? [6,12]

01/14/2016 STEERING COMMITTEE MEETING 14

• The fire alarm system was activated and the starboard pump was automatically started .

•Water reached the ventilation duct rupture, and filled the pump room (pontoon).

• Manholes connecting the pontoon with the stability box and ballast tanks were opened for inspection. Fig 13. Starboard aft column.

Source: Accident Investigation Petrobras P-36 Sinking (DNV) [12].

Page 15: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Cause and effect – (Fishbone) [4,6,7]

01/14/2016 STEERING COMMITTEE MEETING 15

Page 16: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Causes [4,6]

01/14/2016 STEERING COMMITTEE MEETING 16

Explosion

• Absence of a blind flange in the intake valve on the starboard aft tank

• The port pump was aligned towards production header, instead of caisson production.

Unit Sinking

• Failure of the ventilation system- watertight dampers actuators

• Manholes opened on the ballast tank and stability box

• Lack of training in emergency stability control

• Design of the sea-chest valve (fail mode)

Page 17: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Conclusions

01/14/2016 STEERING COMMITTEE MEETING 17

• Investigation results indicate that the most likely scenario was

overpressure in the starboard aft emergency drain tank, which caused

a mechanical explosion and lead to the rupture of the tank. This initial

event allowed the release of flammable hydrocarbon gas, which

eventually originated a second explosion.

• It was concluded that the main cause of these events was failure to

provide effective isolation in the intake valve at the starboard aft tank

during maintenance (i.e., absence of blind flange), which allowed

unexpected reverse oil and gas flow into the starboard aft tank.

Page 18: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Conclusions

01/14/2016 STEERING COMMITTEE MEETING 18

• Although there were many factors that contributed to the flooding

process of the unit. However, this process was accelerated because of

the fail mode / fail state of the sea-chest valves and because several

buoyancy boxes were open at the same time for inspection and thus

when water entered they flooded.

Page 19: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Recommendations [4,6,14]

01/14/2016 STEERING COMMITTEE MEETING 19

Petrobras Inquiry Commission

• Improve offshore operations and enhance safety on board offshore units.

• Do not install pressure vessels and atmospheric tanks connected to the production

process facilities (i.e. hydrocarbons) inside columns or pontoons: Re-assess the risk and

review the design of the units that operate with these design issues.

Brazilian Governmental Petroleum Agency (ANP) & Brazilian Port Administration

(DPC)

• Review the criteria for a number of simultaneous work permits in offshore activities.

• Review the content of the current contingency plans.

Key Recommendation: Creation of the Operational Excellence Program – PEO

Engineering design/ Safety/ Ballast and Stability/ Maintenance/ Operation/ Human Resources

Page 20: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Recommendation

01/14/2016 STEERING COMMITTEE MEETING 20

Budget cutting – needs Risk Based review

Understand impacts of cuts in budgets in important areas such as

SAFETY and QUALITY

Page 21: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

References

01/14/2016 STEERING COMMITTEE MEETING 21

1. Google Map 2016 [cite 2016 01/11]; Available from: https://www.google.it/maps/place/Colombia/@4.18406,-77.4395073,6z/data=!3m1!4b1!4m2!3m1!1s0x8e15a43aae1594a3:0x9a0d9a04eff2a340

2. Noticias Internacionais – International Oil and Gas News 2014 [cite 2016 01/11]; Available from:http://blogonip.blogspot.com/2014_07_16_archive.html

3. Mogensen, V., Worker Safety under Siege: Labor, Capital, and the Politics of Workplace Safety in a Deregulated World. ILR Review, 2008.61(2): p. 82.

4. (ANP), B.G.P.A.-. and B.P.A.-. (DPC), CASUALTY OF PLATFORM "P-36". 2001: p. 29.5. Henriques, C. and M. Fachetti. Roncador Field: Transport of P-36 and Installation of the Mooring System. in Offshore Technology Conference.

2000. Offshore Technology Conference.6. Barusco, P. The accident of P-36 FPS. in Offshore Technology Conference. 2002. Offshore Technology Conference.7. Whelan, S., Petrobras P-36 Accident. Proto-Type, 2013. 1.8. Mail Online 2010 [cite 2016 01/11]; Available from: http://www.dailymail.co.uk/home/moslive/article-1328470/Britains-latest-offshore-

investment-The-Brazilian-oil-boom.html9. Gulf Oil Disaster with enormous oil plume as much as 300 feet thick in place-from Deepwater Horizon crude oil drilling accident 2010 [cite

2016 01/11]; Available from: https://cricketdiane.wordpress.com/tag/oil-spill-in-gulf-of-mexico/10. Keel 2016 [cite 2016 01/11]; Available from: http://keelsolution.com/project/semi-submersible/#11. Acidente da P-36 –Explosao e Naufragio (Petrobras – 15.03.2001). 2015 [cite 2016 01/11]; Available from <

https://www.youtube.com/watch?v=Oz10Rsw_bJc>12. Pitblado, R., Accident Investigation Petrobras P-36 Sinking 2001.13. Videiro, P.M., et al. The Accident of the P-36 Platform: The Rupture of the Emergency Drainage Tank. in ASME 2002 21st International

Conference on Offshore Mechanics and Arctic Engineering. 2002. American Society of Mechanical Engineers.14. da Costa Fraga, C.T. and C.F. Mastrangelo, Petrobras Operational Excellence Programme. paper, 2002. 28605: p. 24-27.15. Berends, W.R., $PRICE AND PROFIT %, The Essential Guide to Product and Service Pricing and Profit Forecasting. 2004. p. 6116. Hancock, C., M. Jarvis, and N. Vineall, PETROLEO BRASILEIRO SA (“PETROBRAS”) Appellant - and - PETROMEC INC Respondent. 2012.

Page 22: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Acknowledgement • Dr. Sam Mannan

• Dr. Clementina Ramirez

• Dr. Robin Pitblado

• Mr. Jim Pettigrew

• Ms. Valerie Green

• Wen Zhu

10/26/2015 STEERING COMMITTEE MEETING 22

• Logan Hatanaka

• Zohra Halim

• Tatiana Flechas

• All members of SC

• All members of MKOPSC

Page 23: Petrobras P-36 Incident 14/… · •Contracted by Petrobras in 1996, and renamed to P-36 •Adapted into a large oil production platform (FPU) by Canadian Shipyard Davie Industry[3]

Thank you!

Questions?

January 14th, 2016

Steering Committee Meeting