Pert cpm

27
Slides Prepared by Slides Prepared by LEANDRO S. ESTADILLA LEANDRO S. ESTADILLA Pamantasan ng Lungsod ng Pamantasan ng Lungsod ng Maynila Maynila

description

 

Transcript of Pert cpm

Page 1: Pert cpm

Slides Prepared bySlides Prepared by

LEANDRO S. ESTADILLALEANDRO S. ESTADILLA

Pamantasan ng Lungsod ng MaynilaPamantasan ng Lungsod ng Maynila

Page 2: Pert cpm

Chapter 10Chapter 10Project Scheduling: PERT/CPMProject Scheduling: PERT/CPM

Project Scheduling with Known Activity TimesProject Scheduling with Known Activity Times Project Scheduling with Uncertain Activity Project Scheduling with Uncertain Activity

TimesTimes Considering Time-Cost Trade-OffsConsidering Time-Cost Trade-Offs

Page 3: Pert cpm

PERT/CPMPERT/CPM

PERTPERT• Program Evaluation and Review TechniqueProgram Evaluation and Review Technique

•Developed by U.S. Navy for Polaris missile Developed by U.S. Navy for Polaris missile projectproject

•Developed to handle uncertain activity timesDeveloped to handle uncertain activity times CPMCPM

•Critical Path MethodCritical Path Method

•Developed by Du Pont & Remington RandDeveloped by Du Pont & Remington Rand

•Developed for industrial projects for which Developed for industrial projects for which activity times generally were knownactivity times generally were known

Today’s project management software packages Today’s project management software packages have combined the best features of both have combined the best features of both approaches.approaches.

Page 4: Pert cpm

PERT/CPMPERT/CPM

PERT and CPM have been used to plan, schedule, PERT and CPM have been used to plan, schedule, and control a wide variety of projects:and control a wide variety of projects:

•R&D of new products and processesR&D of new products and processes

•Construction of buildings and highwaysConstruction of buildings and highways

•Maintenance of large and complex equipmentMaintenance of large and complex equipment

•Design and installation of new systemsDesign and installation of new systems

Page 5: Pert cpm

PERT/CPMPERT/CPM

PERT/CPM is used to plan the scheduling of PERT/CPM is used to plan the scheduling of individual individual activitiesactivities that make up a project. that make up a project.

Projects may have as many as several thousand Projects may have as many as several thousand activities.activities.

A complicating factor in carrying out the A complicating factor in carrying out the activities is that some activities depend on the activities is that some activities depend on the completion of other activities before they can be completion of other activities before they can be started.started.

Page 6: Pert cpm

PERT/CPMPERT/CPM

Project managers rely on PERT/CPM to help them Project managers rely on PERT/CPM to help them answer questions such as:answer questions such as:

•What is the What is the total timetotal time to complete the project? to complete the project?

•What are the What are the scheduled start and finish datesscheduled start and finish dates for each specific activity?for each specific activity?

•Which activities are Which activities are criticalcritical and must be and must be completed exactly as scheduled to keep the completed exactly as scheduled to keep the project on schedule?project on schedule?

•How long can How long can noncritical activitiesnoncritical activities be delayed be delayed before they cause an increase in the project before they cause an increase in the project completion time?completion time?

Page 7: Pert cpm

Project NetworkProject Network

A A project networkproject network can be constructed to model can be constructed to model the precedence of the activities. the precedence of the activities.

The The nodesnodes of the network represent the of the network represent the activities. activities.

The The arcsarcs of the network reflect the precedence of the network reflect the precedence relationships of the activities. relationships of the activities.

A A critical pathcritical path for the network is a path for the network is a path consisting of activities with zero slack.consisting of activities with zero slack.

Page 8: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Frank’s Fine Floats is in the business of Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his building elaborate parade floats. Frank and his crew have a new float to build and want to use crew have a new float to build and want to use PERT/CPM to help them manage the projectPERT/CPM to help them manage the project . .

The table on the next slide shows the The table on the next slide shows the activities that comprise the project. Each activities that comprise the project. Each activity’s estimated completion time (in days) activity’s estimated completion time (in days) and immediate predecessors are listed as well.and immediate predecessors are listed as well.

Frank wants to know the total time to Frank wants to know the total time to complete the project, which activities are critical, complete the project, which activities are critical, and the earliest and latest start and finish dates and the earliest and latest start and finish dates for each activity.for each activity.

Page 9: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Immediate CompletionImmediate Completion

ActivityActivity DescriptionDescription PredecessorsPredecessors Time (days)Time (days)

A Initial Paperwork A Initial Paperwork --- --- 3 3

B Build Body B Build Body A A 3 3

C Build Frame C Build Frame A A 2 2

D Finish Body D Finish Body B B 3 3

E Finish Frame E Finish Frame C C 7 7

F Final Paperwork F Final Paperwork B,C B,C 3 3

G Mount Body to Frame D,EG Mount Body to Frame D,E 6 6

H Install Skirt on Frame CH Install Skirt on Frame C 2 2

Page 10: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Project NetworkProject Network

StartStart FinishFinish

BB33

DD33

AA33

CC22

GG66

FF33

HH22

EE77

Page 11: Pert cpm

Earliest Start and Finish TimesEarliest Start and Finish Times

Step 1:Step 1: Make a forward pass through the Make a forward pass through the network as follows: For each activity network as follows: For each activity i i beginning at the Start nodebeginning at the Start node, , compute:compute:

•Earliest Start TimeEarliest Start Time = the maximum of the = the maximum of the earliest finish times of all activities earliest finish times of all activities immediately preceding activity immediately preceding activity ii. (This is 0 . (This is 0 for an activity with no predecessors.)for an activity with no predecessors.)

•Earliest Finish TimeEarliest Finish Time = (Earliest Start Time) = (Earliest Start Time) + (Time to complete activity + (Time to complete activity i i ).).

The project completion time is the maximum The project completion time is the maximum of the Earliest Finish Times at the Finish node.of the Earliest Finish Times at the Finish node.

Page 12: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Earliest Start and Finish TimesEarliest Start and Finish Times

StartStart FinishFinish

3 63 6BB33

6 96 9DD33

0 30 3AA33

3 53 5CC22

12 12 1818

GG666 96 9FF

33

5 75 7HH22

5 125 12EE77

Page 13: Pert cpm

Latest Start and Finish TimesLatest Start and Finish Times

Step 2:Step 2: Make a backwards pass through the Make a backwards pass through the network as follows: Move sequentially network as follows: Move sequentially backwards from the Finish node to the Start backwards from the Finish node to the Start node. At a given node, node. At a given node, jj, consider all activities , consider all activities ending at nodeending at node j j. For each of these activities, . For each of these activities, ii, compute:, compute:

•Latest Finish TimeLatest Finish Time = the minimum of the = the minimum of the latest start times beginning at node latest start times beginning at node jj. (For . (For node node NN, this is the project completion time.), this is the project completion time.)

•Latest Start TimeLatest Start Time = (Latest Finish Time) - = (Latest Finish Time) - (Time to complete activity (Time to complete activity i i ).).

Page 14: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Latest Start and Finish TimesLatest Start and Finish Times

StartStart FinishFinish

3 63 6

6 96 9BB33

6 96 9

9 9 1212

DD33

0 30 3

0 30 3AA33

3 53 5

3 53 5CC22

12 12 181812 12 1818

GG666 96 9

15 15 1818

FF33

5 75 7

16 16 1818

HH22

5 125 12

5 125 12EE77

Page 15: Pert cpm

Determining the Critical PathDetermining the Critical Path

Step 3:Step 3: Calculate the slack time for each Calculate the slack time for each activity by: activity by:

SlackSlack = (Latest Start) - (Earliest = (Latest Start) - (Earliest Start), or Start), or

= (Latest Finish) - (Earliest = (Latest Finish) - (Earliest Finish).Finish).

Page 16: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Activity Slack TimeActivity Slack Time

ActivityActivity ESES EFEF LSLS LFLF SlackSlack A 0 3 0 3 0 (crit.)A 0 3 0 3 0 (crit.) B 3 6 6 9 3B 3 6 6 9 3 C 3 5 3 5 0 (crit.)C 3 5 3 5 0 (crit.) D 6 9 9 12 3D 6 9 9 12 3 E 5 12 5 12 0 (crit.)E 5 12 5 12 0 (crit.) F 6 9 15 18 9F 6 9 15 18 9 G 12 18 12 18 0 (crit.)G 12 18 12 18 0 (crit.) H 5 7 16 18 11H 5 7 16 18 11

Page 17: Pert cpm

Determining the Critical PathDetermining the Critical Path

•A A critical pathcritical path is a path of activities, from the is a path of activities, from the Start node to the Finish node, with 0 slack Start node to the Finish node, with 0 slack times.times.

•Critical Path: A – C – E – GCritical Path: A – C – E – G

•The The project completion timeproject completion time equals the equals the maximum of the activities’ earliest finish maximum of the activities’ earliest finish times.times.

•Project Completion Time: 18 daysProject Completion Time: 18 days

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Page 18: Pert cpm

Example: Frank’s Fine FloatsExample: Frank’s Fine Floats

Critical PathCritical Path

StartStart FinishFinish

3 63 6

6 96 9BB33

6 96 9

9 9 1212

DD33

0 30 3

0 30 3AA33

3 53 5

3 53 5CC22

12 12 181812 12 1818

GG666 96 9

15 15 1818

FF33

5 75 7

16 16 1818

HH22

5 125 12

5 125 12EE77

Page 19: Pert cpm

In the In the three-time estimate approachthree-time estimate approach, the time to , the time to complete an activity is assumed to follow a Beta complete an activity is assumed to follow a Beta distribution. distribution.

An activity’s An activity’s mean completion timemean completion time is: is:

tt = ( = (aa + 4 + 4mm + + bb)/6)/6

An activity’s An activity’s completion time variancecompletion time variance is: is:

22 = (( = ((bb--aa)/6))/6)22

•aa = the = the optimisticoptimistic completion time estimate completion time estimate

•bb = the = the pessimisticpessimistic completion time completion time estimateestimate

•mm = the = the most likelymost likely completion time completion time estimateestimate

Uncertain Activity TimesUncertain Activity Times

Page 20: Pert cpm

Uncertain Activity TimesUncertain Activity Times

In the three-time estimate approach, the critical In the three-time estimate approach, the critical path is determined as if the mean times for the path is determined as if the mean times for the activities were fixed times. activities were fixed times.

The The overall project completion timeoverall project completion time is assumed is assumed to have a normal distribution with mean equal to to have a normal distribution with mean equal to the sum of the means along the critical path and the sum of the means along the critical path and variance equal to the sum of the variances along variance equal to the sum of the variances along the critical path.the critical path.

Page 21: Pert cpm

Example: ABC Associates Example: ABC Associates

Consider the following project:Consider the following project:

Immed. Optimistic Most Likely PessimisticImmed. Optimistic Most Likely Pessimistic

ActivityActivity Predec.Predec. Time (Hr.Time (Hr.) ) Time (Hr.)Time (Hr.) Time (Hr.)Time (Hr.) A A -- 4 -- 4 6 6 8 8 B B -- 1 -- 1 4.5 4.5

5 5 C C A A 3 3 3 3

3 3 D D A 4 5 A 4 5 6 6 E E A 0.5 1 A 0.5 1

1.51.5 F F B,C 3 4 5 B,C 3 4 5 G G B,C B,C 1 1.5 5 1 1.5 5 H H E,F E,F 5 6 7 5 6 7 I I E,F 2 5 8 E,F 2 5 8 J J D,H D,H 2.5 2.75 2.5 2.75

4.5 4.5 K K G,I 3 5 7 G,I 3 5 7

Page 22: Pert cpm

Example: ABC AssociatesExample: ABC Associates

Project NetworkProject Network

E

Start

A

H

D

F

J

I

K

Finish

B

C

G

E

Start

A

H

D

F

J

I

K

Finish

B

C

G

6666

4444

3333

5555

5555

2222

4444

11116666

3333

5555

Page 23: Pert cpm

Example: ABC AssociatesExample: ABC Associates

Activity Expected Times and VariancesActivity Expected Times and Variances

tt = ( = (aa + 4 + 4mm + + bb)/6 )/6 22 = (( = ((bb--aa)/6))/6)22

ActivityActivity Expected TimeExpected Time VarianceVariance A A 6 6 4/9 4/9

B B 4 4 4/9 4/9 C C 3 3 0 0 D D 5 5 1/9 1/9 E E 1 1 1/36 1/36 F F 4 4 1/9 1/9 G G 2 2 4/9 4/9 H H 6 6 1/9 1/9 I I 5 5 1 1 J J 3 3 1/9 1/9 K K 5 5 4/9 4/9

Page 24: Pert cpm

Example: ABC AssociatesExample: ABC Associates

Earliest/Latest Times and SlackEarliest/Latest Times and Slack

ActivityActivity ESES EF EF LSLS LFLF SlackSlack A A 0 6 0 6 0 * 0 6 0 6 0 *

B B 0 4 5 9 5 0 4 5 9 5 C 6 9 6 9 0 *C 6 9 6 9 0 * D D 6 11 15 20 9 6 11 15 20 9 E E 6 7 12 13 6 6 7 12 13 6 F F 9 13 9 13 0 * 9 13 9 13 0 * G 9 11 16 18 7G 9 11 16 18 7 H H 13 19 14 20 1 13 19 14 20 1 I I 13 18 13 18 0 * 13 18 13 18 0 * J J 19 22 20 23 1 19 22 20 23 1 K K 18 23 18 23 0 * 18 23 18 23 0 *

Page 25: Pert cpm

Determining the Critical PathDetermining the Critical Path

•A A critical pathcritical path is a path of activities, from the is a path of activities, from the Start node to the Finish node, with 0 slack Start node to the Finish node, with 0 slack times.times.

•Critical Path: A – C – F – I – KCritical Path: A – C – F – I – K

•The The project completion timeproject completion time equals the equals the maximum of the activities’ earliest finish maximum of the activities’ earliest finish times.times.

•Project Completion Time: 23 hoursProject Completion Time: 23 hours

Example: ABC AssociatesExample: ABC Associates

Page 26: Pert cpm

Example: ABC AssociatesExample: ABC Associates

Critical Path (A-C-F-I-K)Critical Path (A-C-F-I-K)

E

Start

A

H

D

F

J

I

K

Finish

B

C

G

E

Start

A

H

D

F

J

I

K

Finish

B

C

G

6666

4444

3333

5555

5555

2222

4444

11116666

3333

5555

0 60 60 60 6

9 139 139 139 13

13 1813 1813 1813 18

9 119 1116 1816 18

13 1913 1914 2014 20

19 2219 2220 2320 23

18 2318 2318 2318 23

6 76 712 1312 13

6 96 96 96 9

0 40 45 95 9

6 116 1115 2015 20

Page 27: Pert cpm

Example: ABC AssociatesExample: ABC Associates

Probability the project will be completed within 24 Probability the project will be completed within 24 hrshrs

22 = = 22AA + + 22

CC + + 22FF + + 22

HH + + 22KK

= 4/9 + 0 + 1/9 + 1 + 4/9 = 4/9 + 0 + 1/9 + 1 + 4/9

= 2= 2

= 1.414= 1.414

zz = (24 - 23)/ = (24 - 23)/(24-23)/1.414 (24-23)/1.414 = .71= .71

From the Standard Normal Distribution From the Standard Normal Distribution table: table:

P(z P(z << .71) = .5 + .2612 = .7612 .71) = .5 + .2612 = .7612