Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro...

19
Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd

Transcript of Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro...

Page 1: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Rod Edwards

Technical DirectorPerpetual Energy Ltd

and

Treasurer, Bro Dyfi Community Renewables Ltd

Page 2: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Windfarm DevelopmentWindfarm DevelopmentCommunity Involvement and Community Involvement and

BenefitsBenefits

Community Benefits

Community Participation/ownership

Community Consultation

Page 3: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Community BenefitsCommunity Benefits

WHY ?• Windfarms make little long term

contribution to the local economy

• There may be impacts and disturbance to

the local community – particularly during

construction

Page 4: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Community BenefitsCommunity Benefits

• An annual payment to a local community

body is seen as a way of contributing to

the local economy, and as compensation

for any disruption

• NOT a material consideration in Planning

• Sometimes viewed negatively as “Planning

Gain”

• Local Business Rates (~£2000/MW) cannot

be viewed as a community benefit – but

there is a proposal to change this

Page 5: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• Typically, the operator would make an annual cash contribution (typically around £2000/MW) to the local Parish or Community Council (s)

• These bodies are not always well equipped to manage and disburse large sums of money – “only so many times you can paint the Village Hall”

• In some cases, the benefit had to be used in the main for a specific purpose – e.g education grants, energy efficiency measures

Community BenefitsCommunity BenefitsDevelopment of DeliveryDevelopment of Delivery

Page 6: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• This ad hoc arrangement left developers feeling exposed – benefits were not legitimised in the planning system, yet were expected.

• Industry guidance in 1994 set out best practice for community consultation, but offered no advice on community benefit

• Developers are not equipped to distribute and manage the benefits – this should be left to a local body

Community BenefitsCommunity BenefitsDevelopment of DeliveryDevelopment of Delivery

Page 7: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• As the volume of developments increased, local and regional bodies (particularly Energy Agencies) saw the need for a coherent approach

• Protocols for community involvement were established – Regen SW and Highland Council good examples

• In some cases Trusts have been established (eg Windfall in mid Wales) to specifically manage windfarm community benefits

Community BenefitsCommunity BenefitsDevelopment of DeliveryDevelopment of Delivery

Page 8: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• Developers became more innovative in proposing community benefits – funding projects that would facilitate longer term economic activity

• Planning policy (particularly TAN8 in Wales) gave some legitimacy to community benefits

Community BenefitsCommunity BenefitsDevelopment of DeliveryDevelopment of Delivery

Page 9: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• Establishment/consolidation of local bodies for delivery – particularly in areas of concentrated development

• Developers need to be more proactive in establishing community priorities

• For larger developments, a community liaison officer during development, construction and early operation should be considered

• Community liaison groups should be established

Community BenefitsCommunity BenefitsFuture DirectionsFuture Directions

Page 10: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Community BenefitsCommunity BenefitsFuture DirectionsFuture Directions

• Benefits should also be directed at local economic growth – particularly working through established community regeneration programmes

• Working through local regeneration bodies can help to target economic benefits

• Local Authorities (in general) need to be better informed and more open to discussion of community benefits issues

• Lobby Government to allow business rate revenue to accrue to local authority

Page 11: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Community BenefitsCommunity BenefitsCheap Electricity !!Cheap Electricity !!

• “Cheaper Electricity” is often the most expressed wish of local communities

• Under the present legislation, this is nearly impossible:• Suppliers have to offer same tariff throughout their

operating area• Very difficult to arrange where the owner/operator did

not have a supply licence• Consumers have right to terminate contract at 1

month notice

• Government could consider changing regulations to facilitate this

Page 12: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Need to define “Community”...

Community of Interest

Community of Place

Community Participation and Community Participation and OwnershipOwnership

Page 13: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• Most community projects are a mixture of both – local and distant investors involved

• Very few community led projects..• ... perhaps because they are very difficult to

implement – communities normally suffer from difficulties in:

• Access to expertise

• Access to information

• Access to finance

Community Participation and Community Participation and OwnershipOwnership

Page 14: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• FSA rules and Companies Act make raising share capital difficult (and expensive)

• Investment Clubs can provide a way round this

• Finance is not the only contribution – time and services are contributed – strengthening community cohesion

• Established groups will offer advise – but remember they are usually volunteers

• A high level of commitment from a group of individuals is required

Community Participation and Community Participation and OwnershipOwnership

Page 15: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• Long term commitment is needed – not just during development.

• Community projects can have as much difficulty over planning as commercial developers.

• ...but despite all this, community operation of wind turbines is rewarding – if not financially !!

Community Participation and Community Participation and OwnershipOwnership

Page 16: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• Community ownership of one or more turbines in a larger development is an option

• Developer is not well placed (or is unwilling) to solicit community involvement

• A specialist organisation such as Energy4All will undertake this

• This involves promoting the scheme in the local area (and wider), arranging the share offer and establishing the business model

Community Participation and Community Participation and OwnershipOwnership

Page 17: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

• The community group usually takes ownership of the turbine after commissioning

• The turbine(s) is owned by the community business, but the windfarm operator will be responsible for O&M, and selling of the output

• Distribution of income is responsibility of the community business

• Business is usually a co-operative, or IPS and some profit may be used for community projects

Community Participation and Community Participation and OwnershipOwnership

Page 18: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

ConclusionsCommunity led projects can be successful, but more support is needed in access to finance, expertise and knowledge

Community involvement in larger developments is possible, but greater developer participation, and support to facilitating organisations is required

Community Participation and Community Participation and OwnershipOwnership

Page 19: Perpetual Energy Feb 2009 Rod Edwards Technical Director Perpetual Energy Ltd and Treasurer, Bro Dyfi Community Renewables Ltd.

Perpetual Energy Feb 2009

Thank You