Permit requirements for solar pV Plant in Kenya

10
Annexure-A: Permits Required Table-A.1 Permits required for grid connected FIT Solar plants <=40 MW # Name Issuing Agency Time Application Fees (Kshs.) Prerequisites 1 Approval for Expression of Interest and Detailed Feasibility Study The Ministry of Energy and Petroleum wants to determine how the proposed power plant can be integrated into the national power development plan and estimate suitability of proposed power plant location for interconnection including interconnection facilities and costs. Ministry of Energy and Petroleum Within 90 days None None 2 Environment Impact Assessment Ensuring sustainable development and the protection of the environment National Environment Management Authority 45 to 90 working days Application fee for EIA is 0.1 % of total project cost with a Minimum of Ksh 10,000 and no upper capping. Approval for Expression of Interest and Detailed Feasibility Study 3 Approval for Change of User Control of land use and development County Government 60 days KSh. 200 Environment Impact Assessment 4 Development Permit Safety of buildings, planning control. County Government 60-90 days KSh. 200 for the application form Approval for Change of User Environment Impact Assessment 5 Negotiate FIT based Power Purchasing Agreement Kenya Power Waiting time - 180 days , Negotiations - None Approval for Expression of Interest and Detailed Feasibility

description

This is a detailed table for the Permit requirements for setting up a solar pv plant in kenya

Transcript of Permit requirements for solar pV Plant in Kenya

Page 1: Permit requirements for solar pV Plant in Kenya

Annexure-A: Permits Required

Table-A.1 Permits required for grid connected FIT Solar plants <=40 MW

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

1

Approval for Expression of Interest and Detailed Feasibility

Study

The Ministry of Energy and Petroleum wants to determine how

the proposed power plant can be integrated into the national

power development plan and estimate suitability of proposed

power plant location for interconnection including

interconnection facilities and costs.

Ministry of

Energy and

Petroleum

Within 90 days None None

2

Environment Impact Assessment

Ensuring sustainable development and the protection of the

environment

National

Environment

Management

Authority

45 to 90 working

days

Application fee for EIA is

0.1 % of total project

cost with a Minimum of

Ksh 10,000 and no

upper capping.

Approval for Expression of

Interest and Detailed Feasibility

Study

3 Approval for Change of User

Control of land use and development County

Government 60 days KSh. 200

Environment Impact

Assessment

4 Development Permit

Safety of buildings, planning control. County

Government 60-90 days

KSh. 200 for the

application form

Approval for Change of User

Environment Impact

Assessment

5 Negotiate FIT based Power Purchasing Agreement Kenya Power

Waiting time - 180

days , Negotiations - None

Approval for Expression of

Interest and Detailed Feasibility

Page 2: Permit requirements for solar pV Plant in Kenya

Secure Energy Supply 90 days Study

Environment Impact

Assessment

Approval for Change of User

6

Special Use License: (Applies to power plants and sub

stations situated inside KFS land)

To grant access and use rights of KFS lands

Kenya Forest

Service 30 days None

Environment Impact

Assessment

7

Way Leave Authorization: (Applies to transmission and

distribution lines passing through KFS land)

To compensate Kenya Forest Service for the trees that have

to be felled for the transmission lines to gain access to the grid

or consumption areas

Kenya Forest

Service 30 days None

Environment Impact

Assessment

8

Approval of Power Purchasing Agreement (General: FiT

Based)

Evaluating the PPA with respect to fair consumer prices, fair

KW price paid by Kenya Power, and amount of energy

provided (firm)

Energy

Regulatory

Commission

30 days None

Approval for Expression of

Interest and Detailed Feasibility

Study

Environment Impact

Assessment

Approval for Change of User

Development Permit

Negotiate FIT based Power

Purchasing Agreement

Special Use License: (Applies to

power plants and sub stations

situated inside KFS land)

Way Leave Authorization:

(Applies to transmission and

distribution lines passing

Page 3: Permit requirements for solar pV Plant in Kenya

through KFS land)

9 Electricity Generation License: General - Non FiT Based

Compliance with the FiT Policy

Energy

Regulatory

Commission

90 days Ksh. 10,000 (application

fee),

Approval for Expression of

Interest and Detailed Feasibility

Study

Environment Impact

Assessment

Approval of Power Purchasing

Agreement (General: Non FiT

Based)

Table-A.2 Permits required for grid connected Non FIT Solar plants >40 MW

# Name Issuing

Agency

Time Application Fees (Kshs.) Prerequisites

1

Approval for Expression of Interest and Detailed Feasibility

Study

The Ministry of Energy and Petroleum wants to determine

how the proposed power plant can be integrated into the

national power development plan and estimate suitability of

proposed power plant location for interconnection including

interconnection facilities and costs.

Ministry of

Energy and

Petroleum

Within 90 days None None

2

Environment Impact Assessment

Ensuring sustainable development and the protection of the

environment

National

Environment

Management

Authority

45 to 90 working

days

Application fee for EIA is 0.1 % of

total project cost with a Minimum of

Ksh 10,000 and no upper capping.

Approval for Expression of Interest

and Detailed Feasibility Study

Page 4: Permit requirements for solar pV Plant in Kenya

# Name Issuing

Agency

Time Application Fees (Kshs.) Prerequisites

3 Approval for Change of User

Control of land use and development County

Government 60 days KSh. 200 Environment Impact Assessment

4 Development Permit

Safety of buildings, planning control. County

Government 60-90 days KSh. 200 for the application form

Approval for Change of User

Environment Impact Assessment

5

Special Use License: (Applies to power plants and sub

stations situated inside KFS land)

To grant access and use rights of KFS lands

Kenya

Forest

Service

30 days None Environment Impact Assessment

6

Way Leave Authorization: (Applies to transmission and

distribution lines passing through KFS land)

To compensate Kenya Forest Service for the trees that have

to be felled for the transmission lines to gain access to the

grid or consumption areas

Kenya

Forest

Service

30 days None Environment Impact Assessment

7 Negotiate Capacity based Power Purchasing Agreement

Secure Energy Supply Kenya

Power

Waiting time - 180

days , Negotiations -

90 days

None

Approval for Expression of Interest

and Detailed Feasibility Study

Environment Impact Assessment

8

Approval of Power Purchasing Agreement (General: Non FiT

Based)

Evaluating the PPA with respect to fair consumer prices, fair

KW price paid by Kenya Power, and amount of energy

Energy

Regulatory

Commission

30 days None

Approval for Expression of Interest

and Detailed Feasibility Study

Environment Impact Assessment

Approval for Change of User

Page 5: Permit requirements for solar pV Plant in Kenya

# Name Issuing

Agency

Time Application Fees (Kshs.) Prerequisites

provided (firm) Development Permit

Negotiate Capacity based Power

Purchasing Agreement

Special Use License: (Applies to

power plants and sub stations situated

inside KFS land)

Way Leave Authorization: (Applies to

transmission and distribution lines

passing through KFS land)

9 Electricity Generation License: General - Non FiT Based

Compliance with the FiT Policy

Energy

Regulatory

Commission

90 days Ksh. 10,000 (application fee),

Approval for Expression of Interest

and Detailed Feasibility Study

Environment Impact Assessment

Approval of Power Purchasing

Agreement (General: Non FiT Based)

Table A.3 Permits required for off grid FIT Solar plants 0.5 to 10 MW

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

1

Approval for Expression of Interest and

Detailed Feasibility Study

The Ministry of Energy and Petroleum wants to

determine how the proposed power plant can

be integrated into the national power

development plan and estimate suitability of

Ministry of Energy and

Petroleum Within 90 days None None

Page 6: Permit requirements for solar pV Plant in Kenya

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

proposed power plant location for

interconnection including interconnection

facilities and costs.

2

Environment Impact Assessment

Ensuring sustainable development and the

protection of the environment

National Environment

Management Authority 45 to 90 working days

Application fee for EIA is 0.1

% of total project cost with a

Minimum of Ksh 10,000 and

no upper capping.

Approval for Expression of

Interest and Detailed

Feasibility Study

3 Approval for Change of User

Control of land use and development County Government 60 days KSh. 200 Environment Impact

Assessment

4 Development Permit

Safety of buildings, planning control. County Government 60-90 days KSh. 200 for the application

form

Approval for Change of

User

Environment Impact

Assessment

5

Special Use License: (Applies to power plants

and sub stations situated inside KFS land)

To grant access and use rights of KFS lands Kenya Forest Service 30 days None

Environment Impact

Assessment

6

Way Leave Authorization: (Applies to

transmission and distribution lines passing

through KFS land)

To compensate Kenya Forest Service for the

trees that have to be felled for the transmission

lines to gain access to the grid or consumption

Kenya Forest Service 30 days None Environment Impact

Assessment

Page 7: Permit requirements for solar pV Plant in Kenya

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

areas

7

Negotiate FIT based Power Purchasing

Agreement

Secure Energy Supply Kenya Power

Waiting time - 180 days ,

Negotiations - 90 days None

Approval for Expression of

Interest and Detailed

Feasibility Study

Environment Impact

Assessment

Approval for Change of

User

8

Approval of Power Purchasing Agreement

(General: FiT Based)

Evaluating the PPA with respect to fair

consumer prices, fair KW price paid by Kenya

Power, and amount of energy provided (firm)

Energy Regulatory

Commission 30 days None

Approval for Expression of

Interest and Detailed

Feasibility Study

Environment Impact

Assessment

Approval for Change of

User

Development Permit

Negotiate FIT based

Power Purchasing

Agreement

Special Use License:

(Applies to power plants

and sub stations situated

inside KFS land)

Way Leave Authorization:

(Applies to transmission

and distribution lines

passing through KFS

Page 8: Permit requirements for solar pV Plant in Kenya

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

land)

9

Electricity Generation License: FiT Based -

General

Compliance with the FiT Policy

Energy Regulatory

Commission 90 days Ksh. 10,000 (application fee),

Approval for Expression of

Interest and Detailed

Feasibility Study

Environment Impact

Assessment

Approval of Power

Purchasing Agreement

(General: FiT Based)

10

Electricity Generation, Distribution and/or

Supply License

Compliance with Energy Act and Electricity

Licensing Regulations 2010

Energy Regulatory

Commission 90 days Kshs. 10,000

Approval for Expression of

Interest and Detailed

Feasibility Study

Approval of Power

Purchasing Agreement

Electricity Generation

License

Table A.4 Permits required for off grid Non FIT Solar plants all capacities

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

1

Approval for Expression of Interest and Detailed Feasibility

Study

The Ministry of Energy and Petroleum wants to determine how

the proposed power plant can be integrated into the national

Ministry of

Energy and

Petroleum

Within 90 days None None

Page 9: Permit requirements for solar pV Plant in Kenya

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

power development plan and estimate suitability of proposed

power plant location for interconnection including

interconnection facilities and costs.

2

Environment Impact Assessment

Ensuring sustainable development and the protection of the

environment

National

Environment

Management

Authority

45 to 90 working

days

Application fee for EIA is 0.1 %

of total project cost with a

Minimum of Ksh 10,000 and no

upper capping.

Approval for Expression of

Interest and Detailed

Feasibility Study

3

Approval for Change of User

Control of land use and development

County

Government 60 days KSh. 200 Environment Impact

Assessment

4

Development Permit

Safety of buildings, planning control.

County

Government 60-90 days KSh. 200 for the application form

Approval for Change of User

Environment Impact

Assessment

5

Special Use License: (Applies to power plants and sub stations

situated inside KFS land)

To grant access and use rights of KFS lands

Kenya Forest

Service 30 days None Environment Impact

Assessment

6

Way Leave Authorization: (Applies to transmission and

distribution lines passing through KFS land)

To compensate Kenya Forest Service for the trees that have to

Kenya Forest

Service 30 days None Environment Impact

Assessment

Page 10: Permit requirements for solar pV Plant in Kenya

# Name Issuing Agency Time Application Fees (Kshs.) Prerequisites

be felled for the transmission lines to gain access to the grid or

consumption areas

7

Electricity Generation License: General - Non FiT Based

Compliance with the FiT Policy

Energy

Regulatory

Commission

90 days Ksh. 10,000 (application fee),

Approval for Expression of

Interest and Detailed

Feasibility Study

Environment Impact

Assessment

Approval of Power Purchasing

Agreement (General: Non FiT

Based)

8

Electricity Generation, Distribution and/or Supply License

Compliance with Energy Act and Electricity Licensing

Regulations 2010

Energy

Regulatory

Commission

90 days Kshs. 10,000

Approval for Expression of

Interest and Detailed

Feasibility Study

Approval of Power Purchasing

Agreement

Electricity Generation License