Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control...

21
Permanently Installed Monitoring System for Accurate Wall-Thickness and Corrosion-Rate Measurement March 9, 2016 Sensor Networks, Inc. Steve Strachan V.P. – Sales North America

Transcript of Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control...

Page 1: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Permanently Installed Monitoring System for Accurate Wall-Thickness and Corrosion-Rate Measurement

March 9, 2016

Sensor Networks, Inc.Steve StrachanV.P. – Sales North America

Page 2: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Outline

• Motivation

• Permanently Installed Sensor System

• Power of Data through Continuous Monitoring & Trending

• Typical Applications

• Case Studies

NACE 2016

Page 3: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Corrosion Damage Accounts for the Cost of one Major Facility Annually

NACE 2016

Refining & Petrochemical $1.7 B

Pipeline , Oil/Gas Production $8 B

* NACE Cost of Corrosion Study

Page 4: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Data Monitoring Evolution

NACE 2016

1920s -

Manual

monitoring

1990s -

Wireless

2010s - Age

of Internet of

Things (IoT)

1980s -

Digital

Conversion

1960s -

Analog 4-

20mA loop

Page 5: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Data-to-Desk & The Internet of Things (IoT)

NACE 2016

Remote sensors leverage low-cost & ubiquitous communication infrastructure

Modbus / RS-485

Cellular

Satellite

WiFi

Etc.

24 x 7 asset-health monitoring

Data-to-desk-to-decision instantly

or in minutes

Mobile access by multiple parties

Page 6: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Why Installed Sensors Today?

Costs ($) associated with manual inspections• Pre-inspection activities:

o T & L – windshield timeo Excavationo Insulation preparationo Surface Preparationo Scaffolding o Rope access

• Access, permitting, approvals• Personnel cost – technicians, equipment, training, etc.• Cost per point is less for applications than manual data collection

Costs (intangibles) • Safety – ropes, ladders, radiation, non-invasive, etc.• Damages – environmental, reputation,• Time/productivity – short- & long-term decision making & planning• Data quality – precision & repeatability

NACE 2016

Page 7: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Data Quality Enhanced Using Installed Sensor Systems

NACE 2016

Operator variability

Transducer placement variability

Transducer coupling variability

Acoustic velocity uniformity

Measurement Precision

Temperature Compensation

Accurate Corrosion Rates

Data Accessibility

Precision Accuracy Resolution

-150

-100

-50

0

50

100

150

Flank

CrossingZero

Crossing

Page 8: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Measurement Precision

• Accurate and Precise UT thickness gauging requires a high precision measurement of the arrival time of the ultrasonic pulse

• Measurement principles:

– Depends on the precision of the TOF measurement, not the carrier frequency of the UT signal.

– Choose high slope portion of the waveform (zero crossing) rather than a peak.

– Waveform needs to be sampled at a sufficient speed (Nyquist +)

– Digitizer precision needs to be enhanced: 40MSPS -> 25nS steps -> 0.003” (0.07mm)

– Solution: 8X Upsample using low pass filter. 320MSPS -> 3nS steps -> 0.0004” (0.009mm)

– Interpolate between points yields even greater resolution ~6.1 picosecond resolution.

-150

-100

-50

0

50

100

150

Flank CrossingZero Crossing

Page 9: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Compensation for Temperature Change

𝐶1 = 𝐶0 1 + 𝑘 𝑇1 − 𝑇0 /100

𝑑1 Temperature corrected thickness

𝐶1 Temperature corrected velocity

𝐶0 Reference or calibration velocity

∆𝑡 Measured, round-trip time of flight

𝑇1 Measurement temperature

𝑇0 Reference or calibration temperature

𝑘 Correction factor in % per °F or °C

• Temperature change can be a significant factor in performing accurate thickness measurement.

• Material velocity AND wall thickness changes, but material velocity effect >10X linear expansion effect.

• Velocity in steel changes by approximately -1% per 100°F (55°F)

• ASTM E790 and API 570 make recommendations for when corrections should be made and how they should be applied.

• Permanently installed monitoring system requires a temperature measurement device such as a RTD or thermocouple to implement the correction

7

7.2

7.4

7.6

7.8

8

0 100 200 300 400 500

Thic

knes

s (m

m)

Temperature (deg C)

Actual vs Measured W.T., 6"SCH40 Pipe

WallThickness

Page 10: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

The Power of Data …

• Sufficient for inspection probably NOT for monitoring– 1/1/2013 inspection = 10.00mm

– 12/30/2013 inspection = 9.79mm

• Gross corrosion rate – cannot calculate, not enough information

9.60

9.65

9.70

9.75

9.80

9.85

9.90

9.95

10.00

10.05

10.10

1/1/2013 1/31/2013 3/2/2013 4/1/2013 5/2/2013 6/1/2013 7/1/2013 8/1/2013 8/31/2013 9/30/2013 10/31/2013 11/30/2013 12/30/2013

W.T

. (m

m)

Wall Thickness Data (1 msmt per year)

NACE 2016

Page 11: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

The Power of Data (ctd) …

• Various corrosion rates evident• Trends evident but still large uncertainty due to measurement precision• Summary – better!

9.60

9.65

9.70

9.75

9.80

9.85

9.90

9.95

10.00

10.05

10.10

1/1/2013 1/31/2013 3/2/2013 4/1/2013 5/2/2013 6/1/2013 7/1/2013 8/1/2013 8/31/2013 9/30/2013 10/31/2013 11/30/2013 12/30/2013

W.T

. (m

m)

Wall Thickness Data (1 msmt per month)

NACE 2016

Page 12: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

The Power of Data (ctd) …

• Various corrosion rates evident

• Regression can be used to obtain accurate corrosion rates over medium time scales.

9.60

9.65

9.70

9.75

9.80

9.85

9.90

9.95

10.00

10.05

10.10

1/1/2013 1/31/2013 3/2/2013 4/1/2013 5/2/2013 6/1/2013 7/1/2013 8/1/2013 8/31/2013 9/30/2013 10/31/2013 11/30/2013 12/30/2013

W.T

. (m

m)

Wall Thickness Data (1 msmt per week)

NACE 2016

Page 13: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

The Power of Data (ctd) …

• Various corrosion rates evident• Regression can be used to remove measurement noise and produce

very accurate corrosion rate data• GREAT!

9.6

9.65

9.7

9.75

9.8

9.85

9.9

9.95

10

10.05

10.1

1/1/2013 1/31/2013 3/2/2013 4/1/2013 5/2/2013 6/1/2013 7/1/2013 8/1/2013 8/31/2013 9/30/2013 10/31/2013 11/30/2013 12/30/2013

W.T

. (m

m)

Wall Thickness Data (1 msmt per day)

NACE 2016

Page 14: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Corrosion Rate Measurement

• An important by-product of wall thickness measurement and monitoring is the ability to measure corrosion rates.

• Corrosion rate measurements can be used for predictive maintenance as well as for process feedback.

• CR achieved through linear regression.

• Precision is achieved that exceeds the precision of the base measurement.

• Factors:– Standard deviation of the measurement system

– Measurement frequency

– Measurement interval

y = -0.0005x + 10.1039.95

10

10.05

10.1

10.15

0 50 100 150 200

Thic

knes

s (m

m)

Days

Linear Regression of Thickness Data

𝑠𝑚2 =

1

𝑛−2σ𝑖=1𝑛 𝑦𝑖−𝑌(𝑥𝑖)

2

σ𝑖=1𝑛 𝑥𝑖

2−1

𝑛σ𝑖=1𝑛 𝑥𝑖

2

95% 𝐶. 𝐼.≅ 𝑚 ± 2𝑠𝑚 𝑛 − 2 ≥ 6

Page 15: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Data-to-Desk & The Internet of Things (IoT)

NACE 2016

• Data available across the

organization – remote

viewing for critical decision

making

• Archiving & record

retention simplicity

• Alarms & Warnings

• Saving raw data: RF Signal

• Google Maps & GPS

___

Page 16: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Typical Applications

NACE 2016

• Replacement of ER probes/ Corrosion Coupons• Baseline of new infrastructure • Crude Unit Overhead w/ chemical Injection and/or Water

Washes• Injection/Mix-point Corrosion• High temperature (900F) real-time monitoring• Gas Spheres / containers• Sand erosion/corrosion in offshore production• Buried Pipelines• General Inspection

Page 17: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

UT Sensor Case Studies – Oil & Gas

NACE 2016

Process Control

• Corrosion RATE monitoring

• Chemical inhibitor injection mgmt.

• Different crude TAN rates require more/less chemical to reduce exposure to wall loss

• Temporary UT wireless sensors placed in misc. areas (1 reading per hour for 3 months)

• Reduction in chemical inhibitor spend varying based on crude slate (in this instance is estimated to be ~$20K/wk.)

Inspection

• Localized corrosion monitoring

• Gas spheres

• “underbelly” pitting/corrosion

• Inspection crews sent bi-weekly to inspect known areas on 4 spheres

• Cost $25K each time

• Manual UT gauges marked “low” spots, tethered UT sensors placed (3 readings per wk. using tablet)

• Saved >$150K in first 3 months of program

Re-Engineering

• TML reduction programs

• Cellular UT sensors in lieu of manual inspection (2 readings per month)

• <1 mil/yr. for +5 yrs.

• 27,000+ TML locations, cost >$3M to inspect 1/3 per year

• Were able to reduce from 27,000 TML points to 13,000 TMLs

• Saving ~$1.7M/yr in manual inspection cost

Page 18: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

UT Sensor Case Studies – Power Gen.

NACE 2016

Transmission

• Regulation driven

• Buried river & road crossings

• UT sensors placed on defined areas -tethered/manual collection

• Junction boxes placed 100’ from road tethered UT sensors installed (1 reading per qtr.)

• Savings in government fines

Storage

• Buried high pressure storage lines

• Installed tethered/manual UT sensors on new (replaced) segments of pipe where corrosion had previously been found (2-3 readings per yr. or as necessary via tablet)

• Savings from avoiding unplanned outages

Inspection

• Ongoing projects & evaluation …

• FAC programs

• Corrosion rate R&D

• MIC programs

• Installed sensors in lieu of manual inspections for known pitting between outages

• High-point vent

• Installed sensors in lieu of manual inspection to detect gas voids

• EHS – avoid radiation areas where possible

Page 19: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Summary & Q/A

NACE 2016

The world is changing … use technology to your advantage

Installed sensors can be used to optimize safety & asset integrity for inspection as well as monitoring for corrosion/erosion & cracking

The power of data … predictive uptime, real-time asset health monitoring, reduce unplanned outages

Applications for installed sensors exist everywhere, know your short- and long-term goals for any project/program

Page 20: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

Sensor Networks, IncSteve Strachan

V.P. Sales – North [email protected]

www.installedsensors.com

Page 21: Permanently Installed Monitoring System for Accurate Wall ... … · NACE 2016 Process Control •Corrosion RATE monitoring •Chemical inhibitor injection mgmt. •Different crude

NACE 2016