Performance Op Tim Ization
-
Upload
hebert-ccahuana -
Category
Documents
-
view
223 -
download
0
Transcript of Performance Op Tim Ization
-
7/29/2019 Performance Op Tim Ization
1/97
PerformanceOptimization:Fan, Pump, & Blower Systems
R E F E R E N C E G U I D E
Fourth Edition
-
7/29/2019 Performance Op Tim Ization
2/97
First Edition, 1992Second Edition, December 1998Third Edition, December 2000
Revised by:
Dan Dederer, P.Eng.,Enertech Solutions Inc.
Neither Ontario Power Generation, nor any person acting on its behalf,assumes any liabilities with respect to the use of, or for damages resultingfrom the use of, any information, equipment, product, method, or processdisclosed in this guide.
The sun represents sustained life
while the lightning bolt depicts energy.The integration
represents the perfect partnership of energy utilization and the
environment that encourages wise use and respect for all naturalresources.The roof represents the in-house aspect of energy
efficiency throughout Ontario Power Generation
Marcel Gauthier
Georgian Bay Region - Retail
Printed in Canada.Copyright 1992, 1998, 2000 Ontario Power Generation
Energy Savings are Good Business
-
7/29/2019 Performance Op Tim Ization
3/97
PerformanceOptimization:Fan, Pump & Blower Systems
R E F E R E N C E G U I D E
Third Edition
-
7/29/2019 Performance Op Tim Ization
4/97
i
TA B L E O F C O N T E N T S
INTRODUCTION ..............................................................................1
1.0 P ERFORMANCE OPTIMIZATION FUNDAMENTALS ...........................3
Fan,Pump,and Blower Systems ...................................................3System Defined......................................................................3
System Point of Operation.....................................................4System Flow and Pressure Relationship.................................4
Fan/Pump Performance Curve .............................................9
Energy-Saving Techniques.............................................................9General .................................................................................9
Reducing Motor Input Power ..............................................11
2.0 P ERFORMANCE OPTIMIZATIONTECHNIQUES AND MEASURES ..................................................15
Primary Measures For Energy Reduction ...................................15Speed Modulation ...............................................................15
Equipment Upgrade ............................................................16
High Efficiency Motors ........................................................16
Reduction of Impeller Diameter...........................................16
Variable Inlet Vanes ............................................................16
Booster Pony Applications .................................................16
Ancillary Measures for Energy Reduction ..................................17System Effect Factors ...........................................................17
Elimination of Cavitation ...................................................17
High Performance Lubricants.............................................17
Coatings..............................................................................17
Internal Running Clearances .............................................17
System Maintenance ...........................................................18
-
7/29/2019 Performance Op Tim Ization
5/97
Process Control ...................................................................18
3.0 ASSESSMENT METHODS .........................................................19
General .......................................................................................19
Prescreening Information...........................................................19Step 1: Review Process &
Instrumentation Diagram (P&ID).......................................21
Step 2 : Review Prescreening Information...........................22Step 3 : Prescreening Conclusions .......................................30
Load Data Gathering...................................................................30Design Data........................................................................31
Observations and Estimates by Operating Staff ...................31
Plant Operating Records .....................................................31
Temporary Metering............................................................32
Field Performance Testing ..................................................32
Development of Load Duty Cycle ..............................................34
Technical Options Review..........................................................35General...............................................................................35
System Loss Evaluation........................................................36
Equipment Internal Evaluation ..........................................37
Application Considerations.................................................38
Energy Assessment .....................................................................39
Economic Analysis ......................................................................40Total Savings.......................................................................40
Cost Estimates......................................................................40
Simple Payback and IRR .....................................................41
Feasibility Report........................................................................42
ii
TA B L E O F C O N T E N T S
-
7/29/2019 Performance Op Tim Ization
6/97
4.0 P ERFORMANCE EVALUATION OF CANDIDATES............................43
General .......................................................................................43
Applicable Safety Standards........................................................43
Applicable Performance Test Standards......................................44Pump Performance Test Standards.....................................44
Fan and Blower Performance Test Standards.....................44
Measurement Parameters and Test Instruments .........................45Measurement Parameters ...................................................45
Test Instruments..................................................................45
Calibration of Test Instruments...........................................45
General Test Procedures .............................................................46Location of Test Points ........................................................46
Control of Turbo Machine and System................................47
Performance Test Records...................................................48Rotational Speed Measurement ...........................................48
Motor Input Power Measurement ........................................49
Pump Test Procedures ................................................................51
Liquid Density.....................................................................51
Liquid Flow Rate Measurement ...........................................51
Pump Head Measurement...................................................53
Pump Test Calculation................................................................55Liquid Properties Calculation..............................................56
Liquid Flow Rate Calculation..............................................56
Pump Head Calculation .....................................................57
Pump Power Calculation ....................................................58
Fan and Blower Test Procedures.................................................59Gas Properties .....................................................................59
Gas Flow Rate Measurement ...............................................61
iii
TA B L E O F C O N T E N T S
-
7/29/2019 Performance Op Tim Ization
7/97
Fan and Blower Pressure Measurement..............................63
Fan and Blower Test Calculation.................................................65Gas Density Calculation (same as specific gravity).............65
Gas Flow Rate Calculation..................................................66
Fan and Blower Pressure Calculation ................................68
Fan Power Calculation .......................................................70
5.0 SAFETY...............................................................................71General .......................................................................................71
Plant Regulations........................................................................71
Safety Items Specific to Fan, Pump,and Blower Systems ...........72
APPENDICES ................................................................................75
iv
TA B L E O F C O N T E N T S
-
7/29/2019 Performance Op Tim Ization
8/97
CHAPTER1.0
1.1 Fixed Resistance System........................................................5
1.2 Fixed Resistance System with Constant Static Pressure........6
1.3 Variable Resistance System with Constant Pressure..............7
1.4 Variable Resistance System with Constant Flow....................8
1.5 Variable Resistance System withVarying Flow and Pressure ....................................................9
1.6 Performance Curve for 100 HP Motor.................................12
1.7 Effect of Speed Reduction ...................................................13
CHAPTER3.0
3.1 Process and Instrumentation Diagram ................................22
3.2 Data-Gathering Decision Tree..............................................33
3.3 Load Duty Cycle Chart ........................................................34
3.4 Typical Pump Load Duty Cycle............................................35
v
LI S T O F F I G U R E S
-
7/29/2019 Performance Op Tim Ization
9/97
CHAPTER4.0
4.1 Location of Test Points.........................................................46
4.2 Selection of Flow-Measuring Plane......................................47
4.3 Connecting a Wattmeter......................................................49
4.4 Liquid Flow Rate Measurement:Vessel and Timer ...............52
4.5 Liquid Flow Rate Measurement:Orifice Plate ......................524.6 Pressure Tap Geometry........................................................53
4.7 Gauge Reference to Datum .................................................54
4.8 Suction Head by Calculation ...............................................55
4.9 Pitot Static Tube...................................................................62
4.10 Double Reverse Tube.........................................................62
4.11 Inclined Manometer ..........................................................62
4.12 Static Pressure Readings ....................................................64
CHAPTER3.0
3.1 Prescreening Review...........................................................23
vi
LI S T O F F I G U R E S
LI S T O F TA B L E S
-
7/29/2019 Performance Op Tim Ization
10/97
It is estimated that as much as 20% to 50% of the electrical powerused to run industrial fan,pump, and blower systems can be savedby overcoming operating inefficiencies.
Opportunities to improve operating efficiency are overlooked forfour reasons:
low awareness about energy-efficient technologies the financial and operational benefits are not understood
initial costs taking precedence over life-cycle costs
energy-saving projects are considered less important than otherproduction-related expenditures.
This handbook:
characterizes various systems
provides a quick reference on performance optimizationtechniques
provides guidelines on how to pre-screen candidates andperform a feasibility study
Introduction 1
Introduction
-
7/29/2019 Performance Op Tim Ization
11/97
reviews field performance testing procedures
reviews general plant safety practices
2 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
12/97
-
7/29/2019 Performance Op Tim Ization
13/97
System Point of Operation
The system point of operation is the intersection between thesystem resistance curve and the turbo machine performance
curve. This point determines the flow rate. There are two ways tochange the point of operation:
change the characteristics of the turbo machine performancecurve,varying speed,changing inlet vane settings, etc;
alter the system curve by changing system losses or flow.
Frequently, these two changes occur simultaneously.
For example: An increase in system resistance may beautomatically counteracted by an increase in speed,which keepsflow constant.
System Flow and Pressure Relationship
How flow and pressure are related in a system depends onwhether the system components are fixed resistance (e.g.,
ductwork) or variable resistance (e.g.,dampers, filter, etc.).
Fixed Resistance System
Pressure is proportional to Flow2
For example: A forced draft fan, fitted with variable inlet guidevanes, supplies air to a boiler. The ductwork system has nothrottling dampers.
4 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
14/97
Figure 1.1 shows the system, the fan curve, and a fixed
resistance system curve.
Fixed Resistance System with Constant Static Pressure
Pressure a FIow2 + Constant Static Pressure
For example: A pump supplying a water tower must overcomethe constant static pressure (head) corresponding to the
elevation of the tower, plus the fixed resistance in the pipesystem.
Performance Optimization Fundamentals 5
SystemResistance
CurveTurbo
MachinePerformance Curve
Inlet Stack
Boiler
Fan
Flow
Pressure
Figure 1.1
Fixed Resistance System
-
7/29/2019 Performance Op Tim Ization
15/97
Figure 1.2 shows the system, the pump curve, and a fixedresistance system curve with a constant static head.
Variable Resistance System with Constant Pressure
Pressure = Constant
For example: A blower on a multi-port fume collection systemis modulated by an inlet damper to maintain a constant
pressure in a header, regardless of the number of opencollection ports.
6 Fan, Pump, and Blower Systems
SystemResistance
Curve
ConstantStaticHead
InletPump
Flow
Press
ure
WaterTower
Figure 1.2:
Fixed Resistance System with Constant Static Pressure
-
7/29/2019 Performance Op Tim Ization
16/97
Figure 1.3 shows the system, the fan curve,and a constantpressure system resistance curve.
Variable Resistance System with Constant Flow
Flow = Constant
For example: To form insulation batts, a fan is used to drawinsulation fibers onto a moving conveyor. The fibers must
move at constant velocity to disperse uniformly, and the speedof the conveyor is varied to form different thicknesses of batts.The lower pressure drop through thinner batts is offset bypartially closing a damper at the fan inlet.
Performance Optimization Fundamentals 7
SystemResistance
Curve
Slide
Gates
Fan
Flow
Press
ure
Header
InletDamper
Collection Ports
Figure 1.3
Variable Resistance System with Constant Pressure
-
7/29/2019 Performance Op Tim Ization
17/97
Figure 1.4 shows the system, the fan curve, and a constant flow
system resistance curve.
Variable Resistance System with Varying Flow and Pressure
This system is usually defined as a series of discrete operatingpoints with no consistent relationship between flow andpressure.
For example:A mine ventilation fan is fitted with manual
control Variable Inlet Vanes (VIV), which are adjusted toprovide the correct air flow to various areas of the mine. Areasof the mine not in use are isolated by doors.
8 Fan, Pump, and Blower Systems
SystemResistance
Curve
FanFlow
Pr
essure
InletDamper
RawInsulation
Conveyor
Figure 1.4
Variable Resistance System with Constant Flow
-
7/29/2019 Performance Op Tim Ization
18/97
Figure 1.5 shows the system, the fan curve,and the operatingpoints defined by varying flow and pressure.
Fan/Pump Performance CurveEach fan or pump is characterized by a set of operating points(flow, pressure) called itsperformance curve. The manufacturersupplies this curve, from which the application engineer selectsthe best fan or pump to meet the system needs. Since systemsoften have a range of operating points, selecting the optimumfan/pump is critical.
ENERGY-SAVING TECHNIQUES
General
The objective of all turbo machinery performance optimizationtechniques is to provide the correct flow and pressure to meet theprocess requirements,using less electrical power.
Performance Optimization Fundamentals 9
Points of Operation
Fan
Doors
Mine Shafts
VIGV
Flow
Pressure
DesignPoint
ClosedMine
SupplyShaft
Figure 1.5
Variable Resistance System with Varying Flow and Pressure
-
7/29/2019 Performance Op Tim Ization
19/97
-
7/29/2019 Performance Op Tim Ization
20/97
The brake horsepower required by the fan, pump, or blower is afunction of the total efficiency of the turbo machine:
BHP = 1 x [AHP] or BHP = 1 x [WHP]hT hT
The input kW required to produce the BHP for the turbo machineis a function of the motor efficiencyhm and the efficiency of anyother components in the drive train,e.g.,V-belts, fluid drive,ASDho,etc.:
kW = 0.746 x 1 x 1 x BHP
hm ho
As shown above,all optimization techniques for fans,pumps, andblowers involve either an improvement in the efficiency of theturbo machine or drive train, and/or an improvement in systemrequirements (i.e., reduced flow and/or pressure).
Reducing Motor Input Power
Motor input power must be reduced to achieve energy savings.This is achieved by reducing the brake horsepower requirementsor varying the speed of the motor.
Maintaining Constant Motor Speed with Reduced Brake-Horsepower Requirements
For a constant speed motor, applying performance optimizationtechniques to the turbo machine will reduce input power tothe motor, since less brake horsepower (load) is applied to themotor shaft. Figure 1.6 shows a performance curve for atypical induction motor.
Performance Optimization Fundamentals 11
-
7/29/2019 Performance Op Tim Ization
21/97
Varying the Speed of the Motor and Turbo Machine
This approach includes all applications where the requiredpoints of operation can be achieved by varying the speed of
the motor. For a fixed resistance system, the theoreticalrelationship between speed and brake horsepower is:
BHP a RPM3
As brake-horsepower requirements decrease,motor inputpower reduces accordingly.
12 Fan, Pump, and Blower Systems
B - % Power Factor
C - Current (FLA=100%)
A - % Efficiency
D - kW Input
Shaft Output - BHP
90
80
70
60
0
0 25
94
92
90
88
86
A B
100
75
50
25
0
100
75
50
25
0
C D
50 75 100 125 150
Figure 1.6
Performance Curve for 100 HP Motor
-
7/29/2019 Performance Op Tim Ization
22/97
For example: Reducing system pressure losses by removingthe throttling valve and simultaneously slowing the machine,results in reduced brake horsepower, as shown in Figure 1.7.
Performance Optimization Fundamentals 13
Flow Capacity
Pressure
BrakeHorespower
Reduced Horsepower
System Resistance Curve
System Resistance Curve
Original Point of Operation
New Point of Operation
Figure 1.7
Effect of Speed Reduction
-
7/29/2019 Performance Op Tim Ization
23/97
-
7/29/2019 Performance Op Tim Ization
24/97
The performance optimization techniques addressed in thishandbook are divided into two categories:
1. Primary Measures for Energy Reduction moderate to high cost quantifiable energy savings
2. Ancillary Measures for Energy Reduction low to moderate cost fine-tuning measures may be done independently or in conjunction with primary
measures
PRIMARY MEASURES FOR ENERGY REDUCTION
Speed ModulationSpeed control of equipment is achieved in one of two ways:
by varying the speed of a motor coupled directly to the load,i.e.,ASDs,multi-speed motors,DC motors;
by coupling a fixed-speed driver to the load via a device thatpermits speed adjustment of the load, i.e., fluid drives, gear
systems and adjustable belt drives.
Techniques and Measures 15
C H A P T E R 2
Performance OptimizationTechniques and Measures
-
7/29/2019 Performance Op Tim Ization
25/97
Equipment Upgrade
Turbo machine upgrades may have applications in these areas:
higher efficiency turbo machinery may now be available; due to industrial process changes, turbo machine re-selection
may improve efficiency at the new points of operation;
worn impeller replacement.
High Efficiency Motors
The turbo machinery may operate more efficiently if the existingmotor is replaced with a high efficiency motor or one selectedcloser to its current operating conditions.
Reduction of Impeller Diameter
Due to over-sizing, the turbo machine may operate against apartially-closed damper or valve. Resizing the impeller reduceshorsepower requirements. BHP is proportional to impeller
diameter.
BHP1 = Diameter1 5
BHP2 Diameter2
Variable Inlet Vanes
These are used to control flow on fans and blowers and aregenerally efficient in the range close to maximum flow conditions.
Booster Pony Applications
A booster fan,blower, or pump is used for systems that experienceinfrequent peaks or upset conditions. This allows main equipmentto operate at maximum efficiency under normal conditions.
16 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
26/97
ANCILLARY MEASURES FOR ENERGY REDUCTION
System Effect Factors
Equipment cannot perform at capacity if fans,pumps, and blowershave poor inlet and outlet conditions. Correction of system effectfactors (SEFs) can have a significant effect on performance andenergy savings.
Elimination of Cavitation
Flow, pressure,and efficiency are reduced in pumps operating
under cavitation. Performance can be restored to manufacturersspecifications through modifications. This usually involves inletalterations and may involve elevation of a supply tank.
High Performance Lubricants
The low temperature fluidity and high temperature stability ofhigh performance lubricants can increase energy efficiency byreducing frictional losses.
Coatings
Coating system components such as pump bowls, impellers,casings, and inner linings of pipe works reduces frictional lossesand increases efficiency.
Internal Running Clearances
The internal running clearances between rotating and non-rotatingelements strongly influences the turbo machine's ability to meetrated performance. Proper set-up reduces the amount of leakage(recirculation) from the discharge to the suction side of theimpeller.
Techniques and Measures 17
-
7/29/2019 Performance Op Tim Ization
27/97
System Maintenance
Fan, pump, and blower systems may undergo an actual loss ofefficiency due to dirt build-up on components such as filters, coils,
and impellers. Duct leaks may be a major problem with highpressure blower systems.
Process Control
The process served by fans,pumps, and blowers should utilize theflow in an efficient manner based on actual requirements.To achieve this:
shut turbo machinery off when it is not required
control flow to prevent usage of capacity not required for theprocess
eliminate recirculation modes if possible
close duct and pipe runs when they are not needed
18 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
28/97
GENERAL
Some industrial fan,pump, and blower systems operate efficiently,and regular maintenance will ensure continued performance ofthese systems.
The performance of most other turbo machines can be improved.
Determining the feasibility of performance optimization measuresinvolves:
l. Candidate Prescreening2. Load Data Gathering3. Development of a Load Duty Cycle4. Technical Option Review5. Energy Assessment
6. Economic Analysis7. Feasibility Report
PRESCREENING INFORMATION
Engineering and operating data are typically incomplete orunavailable. The information needed to establish candidatepotential and viability is usually obtained through observations anddiscussions with operating personnel.
Assessment Methods 19
C H A P T E R 3
Assessment Methods
-
7/29/2019 Performance Op Tim Ization
29/97
The following items should be noted when prescreeningcandidates:
VISUA L EXA MINAT ION
- visual overview of complete system
- condition of turbo machine and system (i.e., leakage, age)
- nameplate information of both motor and turbo machine
- inlet and outlet connections (i.e., elbows obstructingsmooth flow)
- type of elbows in system (i.e., long radius or short square)
- ductwork/piping changes (i.e., closure of runs)
- conditions of entry points to plenums or vessels (i.e., square-edged instead of bell-mouthed)
- maintenance condition of turbo machine and system
- gaskets protruding into fluid stream- damper and valve locations (i.e., percent closed)
- automatic or manual controls of dampers/valves
DISC USSIONS WIT H OPERATING PER SONNEL
- equipment installation date
- future expansion plans for process- turbo machine suitability for process (i.e.,
adequate capacity)
- equipment maintenance (i.e., last servicing by manufacturer)
- type of fluid handled (i.e., corrosive or erosive)
- system or process changes
20 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
30/97
- availability of process and instrumentation diagrams andperformance curves
- number of operating points
- required performance at each operating point
- estimated annual hours at each operating point
- control mechanism to achieve various operating points
- approximate range of valve or damper settings
- approximate range of speed control
- bypass, idling,or flow wastage when process cycle does not-require turbo machine
- turbo machine operation problems (i.e.,noise,vibration,duct pulsation)
Step 1: Review Process & Instrumentation Diagram (P&ID)
To enhance system knowledge, review a process andinstrumentation diagram (P&ID) of the system. Sketch by hand ifdrawings are unavailable. Figure 3.1 shows a P&ID for a typicalcentrifugal-induced draft (ID) and forced-draft (FD) fan application.
P&IDs graphically represent the system and process by:
- showing the position of the turbo machine to othercomponents
- differentiating between fixed and variable pressure losscomponents
- indicating the parameter controlled in the system (i.e.,pressure, flow, temperature)
- locating the system control point (i.e.,discharge ducting, inletplenum)
Assessment Methods 21
-
7/29/2019 Performance Op Tim Ization
31/97
Step 2 : Review Prescreening Information
Evaluate accuracy, importance, and relevance of informationobtained in the field. Use the following prescreening review todetermine if there are inefficient conditions that can be improved.
22 Fan, Pump, and Blower Systems
Cell 1
Cell 2
Cell 3
Cell 4
Gas
Furnace
Crude Oil
Hot Air
Flue Gases
Temperature
regulation
Heat
Exchanger
Oxygen percentage monitor
Multiple pipe
systemsHeated
crude oil
to first stage
separation
M1
I.D.
Fan
M2
F.D.
Fan
3-phase
600VTo Main
3-phase
600VTo Main
Cold Air
Flue gases
to atmosphere
1 and 2
AC motors
(250 hp)
Figure 3.1
Process and Instrumentation Diagram
-
7/29/2019 Performance Op Tim Ization
32/97
Table 3.1
Prescreening Review
Assessment Methods 23
Condition
Inefficient TurboMachine
Characteristic
Misapplication oflow efficiency
impeller
Inefficient drive
Age of equipment
Turbo machine
operating at poor
selection point
Comments
Radial blade impellers needed for material-handling
applications
Oversized motor
Motor not high efficiency design
Oversized V-belt drive package
Old adjustable speed-drive technology
Older equipment is generally less efficient
Turbo machine relocated for a different application
Elimination of some pipe/duct runs on multi-run
distribution system
Addition of auxiliary cleaning equipment
Throttled operation for oversized turbo machine
Straight Radial Blades
Approximately 65% / 70%
peak static efficiency
Airfoil Blades
Approximately 84% / 90%
peak static efficiency
Rota
tion
Rota
tion
Operation with original
equipment
Pressure
Actual
Operating Point
Flow
Original
Selection
Point
Operation with new
reselected equipment
Actual
Operating Point
Pressure
Flow
-
7/29/2019 Performance Op Tim Ization
33/97
Table 3.1
Prescreening Review (contd)
24 Fan, Pump, and Blower Systems
Condition
Poor Maintenance
Characteristic
Excessive systemresistance
Worn impeller or
bearings
Flow leakage
Internal turbo
machinedeficiencies
Comments
Dirty screens, nozzles, filters, coils Material build-up on impellers, turning vanes
Vibration/imbalance
Holes in flex connection
Deteriorated gaskets
Loose or distorted flanges
Corrosion or erosion in piping and ductwork
Worn pump seals Running clearance
Flow
Rota
tion
Build-upInlet Box
Improper set-up of fan
impeller allows air to
recirculate internally
Build-up on fan blades
reduces efficiency
Erosion of fan blades
reduces efficiency
-
7/29/2019 Performance Op Tim Ization
34/97
Table 3.1
Prescreening Review (contd)
Assessment Methods 25
Condition
System EffectFactors
Characteristic
Poor fan intakedesign
Comments
Elbow directly on inlet causes non-uniform flow profile
Rounded elbow is better than square elbow
Addition of turning vanes will streamline flow
Installation of splitter plate reduces entry turbulence on
fans located near walls
Length
of Duct
D
R
Turning
Vanes
Splitter
-
7/29/2019 Performance Op Tim Ization
35/97
Table 3.1
Prescreening Review (contd)
26 Fan, Pump, and Blower Systems
Condition
System EffectFactors (contd)
Characteristic
Poor fan intakedesign (contd)
Comments
Butterfly damper close to fan inlet creates turbulence and
decreases performance
Orientation of inlet elbows can cause air to pre-swirl in
the direction opposite to wheel rotation
Turning vanes can improve performance for this condition
Butterfly Inlet Damper
Turning
VanesImpeller
Rotation
Corrected Counterrotating SwirlCounterrotating Swirl
Impeller
Rotation
-
7/29/2019 Performance Op Tim Ization
36/97
Table 3.1
Prescreening Review (contd)
Assessment Methods 27
Condition
System EffectFactors (contd)
Characteristic
Poor fandischarge design
Obstructions at
fan inlets and
outlets
Comments
Elbow directly on fan discharge causes performance
deficiency
If fan cannot be re-oriented, careful turning-vane design is
required
Poor transition and flex connection installations disrupt
flow and cause turbulence
Elbow on Discharge Fan Re-oriented toUp-blast Position
Discharge Duct Work
Flex Connection
Axial Fan
Inlet Duct Work
-
7/29/2019 Performance Op Tim Ization
37/97
Table 3.1
Prescreening Review (contd)
28 Fan, Pump, and Blower Systems
Condition
System EffectFactors (contd)
Excessive Flow
and Pressure
Losses
Characteristic
Air pockets atpump inlet
Poor pump inlet
design
High pressure
losses across
system
components
Comments
Caused by lack of streamlined design
Increases exponentially with flow velocity
Pressure Loss = Co x (Velocity)2
An air pocket can form where
a symmetrical elbow appears
in a suction line
Eccentric tapered reducer
prevents air pockets (above)
when pipe size is reduced
Suction SuctionAir pocket
Vertical elbow permits
reasonably equal distribution
to impeller. Flow is still better
with straight section before
pump.
Horizontal elbow distorts
and may reverse flow. With
double-suction pump, inlet
on small radius side may be
partly starved.
Poor ductwork offset with
square elbows
Improved ductwork with
turning vanes
-
7/29/2019 Performance Op Tim Ization
38/97
Table 3.1
Prescreening Review (contd)
Assessment Methods 29
Condition
Excessive Flowand Pressure
Losses (contd)
Oversized Turbo
Machine
Inefficient Control
of Turbo Machine
Characteristic
High pressurelosses across
system
components
(contd)
Excess flow
Flow wastage
Continuous
operation with
partially closed
dampers or valves
Throttled
operating point
Unnecessary
operation
Comments
System entry conditions from plenums and vessels should
provide smooth entry conditions for fluid
System constrictions may result from construction
methods used to bypass other plant equipment
System valves and dampers may be in a permanent,
partially closed position
Existing process may operate with less flow
Changes to process may reduce flow requirements
Process cycle may have periods with no need for turbo
machine operation
Turbo machine may be running while rest of process is shut down
Multi-port collection or distribution system may have ports
left open unnecessarily
Original performance margins were too great
Turbo machine relocated from different application
System resistance over-estimated
Removal of system component has reduced pressure drop
Original sizing done for infrequent upset condition
Turbo machine throttling used instead of speed control
Outlet fan dampers used instead of variable inlet vane control
No controls are used and turbo machine supplies excess capacity
Recirculation mode used when process does not require
turbo machine operation
Lack of control sequence may have turbo machine
running when not required
Vena Contracta increasesentry losses
Optimal off-set design with
rounded elbows and turning vanes
Addition of bell mouth creates
smooth entry with minimal losses
Vena Contracta
-
7/29/2019 Performance Op Tim Ization
39/97
Step 3 : Prescreening Conclusions
Figure 3.2 presents general conditions that may indicate wheresystems are operating inefficiently. With this information, you can
determine if a candidate(s) merits a more in-depth engineeringfeasibility study to determine viable technical solutions andquantify savings.
Further assessment should be carried out by an experiencedengineering specialist (i.e., consultant engineer, contractor,equipment manufacturer, or customer operating staff).
Appendix A provides guidelines engineering specialists may followwhen they prepare optimization feasibility studies.
LOAD DATA GATHERING
The engineering specialist will prepare feasibility study findingsand recommendations,based on:
evaluation of viable technical options that can be employed
accurate determination of energy savings
economic analysis
To effectively carry out this study:
locate all point(s) of operation (i.e., flow, pressure, and power);
determine the turbo machine load duty cycle;
evaluate data accuracy and reliability;
evaluate characteristic of data: seasonal, batch,product oroutput fluctuations.
Common sources of information are given in the followingsubsections. Figure 3.2 provides general guidelines on how togather data for development of the load duty cycle.
30 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
40/97
-
7/29/2019 Performance Op Tim Ization
41/97
Temporary Metering
performed when operating data is unavailable (or deemedunreliable)
typical power metering would be for a two-week period,with15-minute interval samples
interpretation of results should take into account seasonal orproduction variations
if possible, metering on other parameters should be donesimultaneously, i.e., temperature,rotational speed, damper
settings, pressure,pressure differential across variableresistance components,etc.
Field Performance Testing
testing must be done to verify point(s) of operation and systembehavior.
Chapter 4 of this handbook gives more guidelines on fieldperformance testing.
32 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
42/97
Assessment Methods 33
AreOperating Records
Complete?
No
Yes
Is theLoad Pattern
Seasonal?
Field MeasurementRequired
No
Yes
Can theDuty Cycle be
Developed by OtherMeans?
No
Yes
Gather GeneralInformation
Extended DataAccumulation Period
Generate Load Duty Cycle
Short DataAccumulation Period
AreOperating Records
Available?
- Horsepower of Motor- Hours of Operation- Suppliers' Performance Curve
InitiateData Gathering
No
Yes
Figure 3.2
Data Gathering Decision Tree
-
7/29/2019 Performance Op Tim Ization
43/97
DEVELOPMENT OF LOAD DUTY CYCLE
The load duty cycle is a frequency distribution of the time that aturbo machine operates at each point of operation. Two
components are needed for development:
turbo machine load Plot the points of operation on theturbo machine performance curve to identify system flow andpressure relationship.
duty cycle This is the number of hours the turbo machineoperates at each point of operation.
Tabulate all data in a load/duty/cycle chart. An example is shownin Figure 3.3.
Figure 3.3
Load Duty Cycle Chart
34 Fan, Pump, and Blower Systems
Point Time atof Flow Pressure Brake Speed Input Operating kWh/yr
Operation Hp (RPM) kW to Motor Point(hr/yr)
1
2
3
4
5
6
TOTALkWh/yr
-
7/29/2019 Performance Op Tim Ization
44/97
It may be useful to construct a histogram of load versus time toshow graphically the load duty cycle of the system. Select thehorizontal axis for an appropriate system parameter. See
Figure 3.4.
TECHNICAL OPTIONS REVIEW
General
Assess the practicality of implementing the various performanceoptimization techniques. The following items are needed for thisprocess:
manufacturer's performance curve; load duty-cycle charts, as completed for existing system,and for
system employing performance optimization techniques (seepage 34);
system P&ID (see page 21);
system loss evaluation (see page 36);
report on equipment internal inspection (see page 37).
Assessment Methods 35
Percent Flow
Perc
entTotalOperatingTime
20
10
0
0 10 20 30 40 50 60 70 80 90 100
B
Figure 3.4
Typical Pump Load Duty Cycle
-
7/29/2019 Performance Op Tim Ization
45/97
To determine the best performance optimization technique,
1. Review the process requirements. Determine if the processcan operate just as well with reduced flow or pressure.
2. Review system test results to identify peak pressure losses.Evaluate if these losses can be reduced by modifying thesystem.
3. Compare turbo machine field performance test results withmanufacturer's predicted performance. Check equipmentinternal inspection report to account for discrepancy between
actual and predicted performance. Assess the need forequipment repair/maintenance.
4. Assess the viability of each performance optimizationtechnique.
Since each installation has unique characteristics, good engineeringjudgement and experience is required to carry out a thoroughevaluation of each technical option.
System Loss Evaluation
To carry out a comprehensive performance evaluation, thefeasibility study must address:
original design parameters used for equipment rating
actual system requirements
duct/pipe geometry and associated system losses
Examples of duct/pipe arrangements that cause high system losses:
short radius elbows used in duct/pipe instead of long radiuselbows or turning vanes;
poor duct/pipe inlet conditions from vessels and plenums;
36 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
46/97
-
7/29/2019 Performance Op Tim Ization
47/97
steel bracing left inside ductwork
inappropriate damper linkage adjustments
Call a manufacturer's service representative or experienced turbomachinery engineer for an accurate evaluation of the internalcondition of the turbo machine.
Application Considerations
To check the suitability of each performance optimizationtechnique, consider the entire system including:
type of fluid stream
environmental consideration (i.e., indoor, outdoor, hazardousarea)
system limitations
physical constraints
Following are typical application considerations for turbo machineperformance optimization techniques:
Adjustable Speed Drives
- spectrum analysis on impeller may be required
- low-speed motor-cooling limitations
- reduced motor torque may not overcome high breakaway
torque at start-up- may require motor oversizing
- fans may be forced into unstable operating ranges
- pumps can experience extremely high temperature build-up,if pressure reduction is less than static head
38 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
48/97
Equipment Upgrade
- high efficiency impellers are generally not suitable for harshenvironments
Impeller Trimming
- provides permanent de-rating
- not suitable if full capacity occasionally needed
Variable Inlet Valves
- have non-linear control range when low flows required,maycause pulsations in pressure
ENERGY ASSESSMENT
Compare the electrical consumption of each of the selectedperformance optimization measures with the consumption of theexisting system. All desired points of operation will requireconsideration.
Electrical savings can occur in demand (kW) and energy (kWh).Demand savings depend on whether turbo machinery loadcoincides with the plant's monthly peak.
Annual energy savings are based on:
hours the process or turbo machine operates at each point ofoperation
average loading at times of monthly demand peaks demand and energy rates for the particular plant
Assessment Methods 39
-
7/29/2019 Performance Op Tim Ization
49/97
ECONOMIC ANALYSIS
Total Savings
Total savings of performance optimization may result from indirectbenefits as well as electrical savings.
Some examples are:
improved power factor
raw material savings
improved product quality
reduced labour costs
Classify non-energy savings into groups of hard and soft dollarsavings, based on how easily they can be quantified.
Cost Estimates
Assess the economics of the performance optimization technique
by establishing cost estimates:
Capital Equipment
- quotations from manufacturers
- suppliers catalogues
Engineering and Design
- estimate as a percentage of direct costs- quotations from consultants or contractors
Installation
- applying an hourly rate to estimated labour requirements
- quotations from contractors
40 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
50/97
- equipment rentals
- miscellaneous materials
Simple Payback and IRR
Compare the total cost of implementing a performanceoptimization technique against the total benefit. Two methodsusually used are: Simple payback and internal rate of return (IRR).
Simple payback is used to determine the time required for thesavings to repay the initial capital outlay.
Time (years) = Project costAverage annual cash savings
Internal rate of return takes into account the time value of money.It is an adjusted rate that discounts savings (inflows) and theexpense of the project (outflows) to zero. Determine a project'sacceptability on these grounds,by comparing the performanceoptimization project's IRR against the company's prescribed rate of
return.
If the IRR passes this test, the project will likely be undertaken.The IRR is calculated by finding the discount rate, R, that solves thefollowing equation:
(Cinflow) = (Coutflow)n
(1+R)n (1+R)n
where:Cinflow = cash inflowsCoutflow = cash outflowsR = rate of return that will solve the expressionn = signifies that the discounted inflows and
outflows must be added from time zerothrough time n.
Assessment Methods 41
n
t=0
-
7/29/2019 Performance Op Tim Ization
51/97
-
7/29/2019 Performance Op Tim Ization
52/97
GENERAL
This section provides an overview of information required toconduct field performance tests of fan, pump, and blower systems.The equations, and calculation procedures required to correct themeasured data back to the manufacturer's performance curves, arealso outlined.
APPLICABLE SAFETY STANDARDS
The fans,pumps, and blowers discussed in this handbook arerotating equipment driven by electric motors. When dealing withthis equipment, extreme caution must be exercised to avoidelectric shock or injury from rotating or moving mechanicalcomponents.
All applicable safety standards in effect at the equipment site mustbe observed. Also follow safety standards and practices outlined inChapter 5 of this handbook and:
AMCA Publication #410
Recommended Safety Practices for Air Moving Devices
Performance Evaluation of Candidates 43
C H A P T E R 4
Performance Evaluationof Candidates
-
7/29/2019 Performance Op Tim Ization
53/97
APPLICABLE PERFORMANCE TEST STANDARDS
The data included in the test manuals referenced below for fans,pumps, and blowers will be adequate to conduct the performance
tests in most cases. If unusual liquids or gases are being handled,or if a significant amount of duct work or piping is locatedbetween the pressure measuring points and the equipment, furtherinformation may be required. Additional information regarding thedensities and viscosities of various liquids or gases and the frictionlosses of pipes,ducts, fittings, and transitions may be required. Thisinformation is readily available in various engineering handbooks
and textbooks. Pump Performance Test Standards
Performance testing standards for pumps have been prepared andpublished by the Hydraulic Institute,Cleveland, Ohio,USA. Thetesting standard is part of a complete set of pump standardspublished as:
Hydraulic Institute Standards
Fan and Blower Performance Test Standards
The Air Movement and Control Association,Inc. (AMCA),ArlingtonHeight, Illinois,USA,has several publications for testing fans andblowers. The publication most applicable to the type of testperformed under this program is:
AMCA Publication 203
Field Performance Measurements of Fan Systems
This publication is one of four manuals that also cover the designof air systems, fan and system interaction, including fan laws andsystem effect factors (SEF), and troubleshooting of air-movingsystems.
44 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
54/97
MEASUREMENT PARAMETERS AND TEST INSTRUMENTS
Measurement Parameters
The parameters that must be determined for accurate evaluation offan, pump or blower performance are:
liquid or gas properties, i.e.,density and, for liquids,viscosity;
flow rate;
inlet and outlet pressure head;
rotational speed of equipment;
input power.
Test Instruments
The instruments required to measure each parameter are listed inthe appropriate test procedure sections.
Calibration of Test Instruments
Instruments used in field performance tests are often subjected torough handling and hostile environments.Consequently, it isessential to ensure that the instruments are in good condition andare capable of providing accurate and repeatable measurements.As a minimum, the following procedure should be adopted:
physical inspection and functionality test of instrument before,
during,and after each field test; scheduled calibration of instruments to a recognized national
standard;
calibration of instruments after repair, or if any doubt arisesregarding accuracy.
Note: An extra set of instruments can be useful to check accuracy
or replace malfunctioning instruments.
Performance Evaluation of Candidates 45
-
7/29/2019 Performance Op Tim Ization
55/97
GENERAL TEST PROCEDURES
Location of Test Points
To obtain reliable measurements of the inlet and dischargepressures of the equipment, the location of pressure test pointsin the pipes or ducts should normally be at least five to tenequivalent diameters downstream of the nearest elbow,transition, or other flow disturbance (Figure 4.1).
Figure 4.1
Location of Test Points
An appropriate pressure loss calculation for the duct or pipeand any fittings between the equipment flange and themeasuring point must be made and added to the measuredpressure.
The flow-measuring plane should also be five to ten equivalentdiameters downstream from the nearest flow disturbance oroutlet flange as illustrated in Figure 4.2.
46 Fan, Pump, and Blower Systems
, , , , , , , ,
, , , , , , , ,
, , , , , , , ,
, , , , , , , ,
y y y y y y y y
y y y y y y y y
y y y y y y y y
y y y y y y y y
do
di
L > 5 x do
L > 5 x di
-
7/29/2019 Performance Op Tim Ization
56/97
Inspect the duct/pipe to check that no branches or leaks occurbetween the measuring plane and the equipment to ensurethat the flow measured has passed through the equipment.
Figure 4.2
Selection of Flow Measuring Plane
Control of Turbo Machine and System
The purpose of this test is to determine the performance of themachine during operation. If the system or process varies, themachine performance may modulate during the time the test isbeing conducted. This must be avoided.
The duty points at which a performance test is required mustbe selected by referencing the process and instrumentationdiagram and the duty cycle developed during the prescreeningand data-gathering process.
Performance Evaluation of Candidates 47
BadMeasuring
Plane
PreferredMeasuringPlane
, ,
, ,
y y
y y
, , , , , , , , , y y y y y y y y y
-
7/29/2019 Performance Op Tim Ization
57/97
A control lockout must be implemented in consultation withplant operating personnel to hold the machine at a constantpoint of operation during the test.
The determination of a single performance point may takefrom several minutes to several hours, depending on thegeometry of the system and the amount of test data to becollected.
Multiple readings of data such as power, speed,controlvalve/damper position, and temperature and pressure of fluidshould be taken to ensure these parameters are held constant
for long tests.
Performance Test Records
A field test data sheet should be prepared before the test toprovide a consistent and complete format for recording test data.
A custom form should be prepared for each machine to betested. Refer to theHydraulic Institute andAMCA 203handbooks for examples of typical data sheets.
Sketches of the test point locations, system duct, or pipingorientation and dimensions,and a copy of the P&ID are anecessary part of the performance test records.
Rotational Speed Measurement
Instruments most commonly used include an electronic contact ornon-contact tachometer, stroboscopic tachometer, or revolutioncounter with a chronometer. Following are some considerationsfor speed measurements:
Select good physical access to the shaft or some rotatingcomponent of the machine.
48 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
58/97
Select instruments that will provide accurate readings for the speedrange of interest. A demonstrable accuracy of 0.5% or better isacceptable.
At least two readings,one near the beginning of the test andone near the end, should be taken.
If the test duration is longer than 15 minutes,additionalreadings should be taken, approximately every 15 minutes.
If multiple readings show the speed to be constant, the timebetween readings can be extended.
Note: Rotational speed should not change during the course of thetest.
Motor Input Power Measurement
The primary reason for conducting the tests is to estimate howmuch the motor input power can be reduced, using theoptimization techniques available. Therefore, it is essential that a
comprehensive analysis of the motor input power be conducted.
Figure 4.3
Connecting a Wattmeter
Performance Evaluation of Candidates 49
Wattmeter
Motor
StarterMotor
CT-1 PT-1
CT-2
CT-3
PT-2
1
2
3
0
0
0
-
7/29/2019 Performance Op Tim Ization
59/97
Many of the machines to be tested under this program will bethree-phase, 320,460 or 575 volt. Portable power analyzers arereadily available measure the input power in this range, taking
into account voltage,amperage,and power factor. They canprovide a direct readout of kW. Refer to Figure 4.3.
Specialized measuring equipment,utilizing potential andcurrent transformers, would normally be required for systemsabove 600 volts. A qualified electrical engineer may have todesign an adequate power measuring system.
A qualified electrician should connect these analyzers to the
motor input power leads.
For systems fitted with ASDs, measure the power going into theASD, rather than the power going into the motor. To determinethe actual power being consumed by the equipment,efficiencycorrection factors for part load operation should be included inthe calculations.
The test data sheet should allow for the recording of volts, amps,power factor, and kilowatts, as a minimum.
At least two readings,one near the beginning of the test andone near the end, should be taken.
If the test duration is longer than 15 minutes,additionalreadings should be taken, approximately every 15 minutes.
If multiple readings show the power to be constant, the timebetween readings can be extended.
Note: The power consumed throughout the duration of the testshould be constant.
50 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
60/97
-
7/29/2019 Performance Op Tim Ization
61/97
-
7/29/2019 Performance Op Tim Ization
62/97
Pump Head Measurement
A broad range of instruments are available to suit any application.
Characteristics of the liquid, i.e., temperature, corrosiveness,etc., and the expected range of the measured head must beconsidered to avoid damage to the instrument by overloading,or by exposure to hot or corrosive fluids.
Figure 4.6
Pressure Tap Geometry
The range and precision of the instrument should be selectedso that the accuracy of the reading is better than 2%.
Pressure taps with the proper geometry should be used toensure accurate pressure readings. Refer to Figure 4.6 forexample.
Locate pressure taps in the suction and discharge lines in anarea where steady flow conditions exist.
Performance Evaluation of Candidates 53
Brass Plug
Nipple
Connects
HereNipple
Connects
HereApprox. Rad.
d
4
Approx. Rad.d
4
d to1"
8
1"
4d
Pipe Coupling
Weld
Minimum
2d
-
7/29/2019 Performance Op Tim Ization
63/97
-
7/29/2019 Performance Op Tim Ization
64/97
The geometry of the pipe between the gauge and the pumpflange must be known,so that friction loss can be calculatedand used to arrive at pump total head at the flanges.
If the pump is drawing from or discharging to a pit or tank thatis open to atmosphere, it may be more convenient to calculatethe head at the corresponding pump flange from the differencein elevation and the appropriate losses. Refer to Figure 4.8.
Pressure readings should be observed periodically throughoutthe test to ensure no significant fluctuation occurs.
Figure 4.8
Suction Head by Calculation
PUMP TEST CALCULATION
Measured pump performance will normally be compared with thepump performance curve issued by the manufacturer. Correctionsfor specific gravity, viscosity, and speed may be necessary if thefluid characteristics and/or pump speed tested differ from that
shown on the performance curve.
Performance Evaluation of Candidates 55
Static
Head
-
7/29/2019 Performance Op Tim Ization
65/97
-
7/29/2019 Performance Op Tim Ization
66/97
-
7/29/2019 Performance Op Tim Ization
67/97
-
7/29/2019 Performance Op Tim Ization
68/97
The pump input power should then be further corrected to therated speed and specific gravity shown on the performancecurve
BHPc = BHP x Nc 3 x SgcN Sg
where:BHPc = pump input power at rated speedBHP = pump input power at test speedNc = rated speedN = test speed
Sgc = rated specific gravitySg = test specific gravity
FAN AND BLOWER TEST PROCEDURES
Gas Properties
The gas density must be determined to accurately calculate other
performance parameters.Gas density is a function of absolutepressure, temperature,and molecular weight.
Absolute pressure is determined by adding the barometricpressure at the site and the static pressure at the measuringplane.
Barometric pressure can be determined with a portableaneroid barometer.
Static pressure at the measuring plane must be measured asdiscussed on page 64.
Gas temperature is determined with an instrument-qualitythermometer.
If the fan is handling ambient air, molecular weight can beassumed to be that of air with appropriate corrections made for
relative humidity. Relative humidity is determined by
Performance Evaluation of Candidates 59
-
7/29/2019 Performance Op Tim Ization
69/97
measuring wet bulb and dry bulb temperatures with a slingpsychrometer.
To determine the density of a gas other than air may require
the use of complex equipment by a qualified expert to obtainthe chemical composition of the gas. If the gas is a complexmixture of various constituents, as found in many industrialprocesses, the company chemist or an independent laboratoryshould be consulted to collect a gas sample for analysis in thelab. Particular care should be used if the gas is toxic,corrosive,or explosive.
Note: It is important to ascertain from the P&ID that the gas doesnot undergo any change in moisture content or molecular weight(i.e.,water sprays, cooling coils, burners,etc.) between the fan orblower and the plane at which wet and dry bulb temperatures orgas constituents and barometric pressure are measured. If nochanges occur, the gas wiIl approximate the perfect gas laws andthe ratio of absolute temperatures and absolute pressures can be
used to determine the density at all planes of interest. For thisreason, it is important to record the temperature and staticpressure at all planes of interest.
60 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
70/97
Gas Flow Rate Measurement
Air or gas flow rate is determined by performing a velocitypressure traverse in the duct using one of the following:
pitot tube and inclined manometer, electronic micromanometeror magnehelic gauge
vane anemometer
thermistor anemometer used as a probe and readout
The airflow measurement methods recognized by Air Movement
and Control Association (AMCA) require the use of a pitot statictube or a double reverse tube, and an inclined manometer,preferably with a variable slope ratio to provide sufficient accuracyat a range of air velocities. Figures 4.9 4.11 (p. 62) show variousdevices used to measure air or gas velocity pressure.
The velocity pressure traverse must be conducted in an area ofthe duct where the flow is stable and uniform. Refer to
AMCA 203 for guidelines to select and qualify a suitabletraverse plane location. Generally, the requirement is that morethan 75% of the velocity pressure readings should exceed 1/10of the maximum reading.
The number and distribution of traverse points required in aduct is a function of the duct geometry. Refer toAMCA 203 forguidelines on how to select traverse points. The number of
points required byAMCA 203 should be taken as a minimum.A traverse using fewer points is unacceptable.
Consider the following:
a pitot traverse normally requires two people, since it is usuallyimpossible to hold the pitot tube steady and record the velocitypressure reading at the same time.
Performance Evaluation of Candidates 61
-
7/29/2019 Performance Op Tim Ization
71/97
62 Fan, Pump, and Blower Systems
Air Flow
Static
PressureTotal
Pressure
Reverse
Tube
Stainless
Steel Tubing
preferred approx.
.375" OD
Air Flow
Impact Tube
10 in. wg1:1
Slope Ratio
0.5 in. wg20:1 Slope Ratio
1 in. wg10:1 Slope Ratio
2 in. wg5:1 Slope Ratio
Figure 4.9
Pitot Static Tube
Figure 4.10
Double Reverse Tube
Figure 4.11
Inclined Manometer
-
7/29/2019 Performance Op Tim Ization
72/97
The access holes drilled in the duct for the pitot tube should beplugged when not in use to prevent leakage or disruption offlow profiles in the duct.
A pitot traverse in a large duct may require special pitot tubes,longer than the standard maximum of 5 feet or access fromboth sides of the duct.
Measurements in high temperature, toxic, or combustible gasstreams also require special consideration. If possible, thetraverse should be conducted in a duct under negative staticpressure so that the gas will not leak out on the tester.
Note: Determining the f low through a fan or blower is generallythe most complex part of the performance measurements. Ifproper equipment and procedures are used,and the selection of atraverse plane is satisfactory, the flow rate can be determined towithin 2% to 10% accuracy. A review of the uncertainty analysis inAMCA 203will highlight the parameters that need to be mosttightly controlled to maintain the best accuracy.
Fan and Blower Pressure Measurement
A broad range of instruments are available.
Characteristics of the gas, i.e., temperature, corrosiveness,etc.,and the expected range of the measured pressure, must beconsidered to avoid damage to the instrument by overloadingor by exposure to hot or corrosive gases.
The range and precision of the instrument should be selectedso that the accuracy of the reading is better than 2%.
Pressures to be determined for fans and blowers include static andvelocity pressures, which,when added, equal total pressure.
Velocity pressure is determined from the calculated flow rate,the area of the duct,and the density of the gas stream.
Performance Evaluation of Candidates 63
-
7/29/2019 Performance Op Tim Ization
73/97
Record duct dimensions for all planes of interest.
Static pressure readings in the fan discharge duct and in the faninlet duct and static pressure readings at the velocity pressuretraverse plane will be required.
Static pressure can be measured from the static tap on the pitotstatic tube,as the tube is traversed in the duct. This willprovide several consistent readings. Refer to Figure 4.12.
The pitot tube should be oriented in the same way as forvelocity pressure readings or the pressure read from the statictap may not be accurate.
Static pressure taps can be made in the wall of the duct. RefertoAMCA 203 guidelines. Four pressure taps are required,equally spaced around the periphery of the duct. The readingsfrom the four taps should be averaged to provide the staticpressure at that plane.
Note: Fan suppliers normally specify pressures at the inlet and
discharge flanges of the equipment. Consequently, it is important
64 Fan, Pump, and Blower Systems
Ps3
Pv3
Ps5 Ps4
Fan Static Pressure
Ps = Ps2 - Ps1 - Pv1
where Ps2 = Ps5
where Ps1 = Ps4
where Pv1 = Pv3
Figure 4.12
Static Pressure Readings
-
7/29/2019 Performance Op Tim Ization
74/97
-
7/29/2019 Performance Op Tim Ization
75/97
-
7/29/2019 Performance Op Tim Ization
76/97
where:V3 = average velocity (ft/min)Pv3 = velocity pressure (in.wg)
d3 = density (lbm /ft3
)Knowing this velocity and the geometry of the ductwork, the flowrate can be calculated as follows:
Q3 = V3A3
where:Q3 = gas flow rate (cfm)
V3 = average velocity (ft/min)A3 = duct area at traverse plane (ft2)
The fan or blower flow rate is defined as being the volume flowrate at fan inlet density. Continuity of mass allows for thecalculations of volume flow rates at other planes in the system. Ifthe densities at the other planes are known, the following equationis used:
QX = Q3 x d3dx
where:Qx = flow rate at plane xQ3 = flow rate at traverse planed3 = density at traverse planedx = density at plane x
To compare the calculated fan or blower flow rate to theperformance curve supplied by the fan or blower manufacturer, itmay be necessary to correct for fan speed, using the followingequations:
Qc = Q x Nc
N
Performance Evaluation of Candidates 67
-
7/29/2019 Performance Op Tim Ization
77/97
-
7/29/2019 Performance Op Tim Ization
78/97
Performance curves supplied by the fan or blowermanufacturer will show the pressures based on the equipmentinlet and outlet flanges.
To compare the pressures measured during the test to theperformance curve, it is necessary to take into considerationany pressure losses and system effect factor (SEF) between thepressure measuring stations and the fan inlet and outlet flangesto determine the total pressure at the fan inlet and outletflanges.
Also calculate velocity pressure at the outlet flange.
Fan static pressure is given by
FSP = TPo - TP1 - VPo
where:FSP = fan static pressureTPo = total pressure at fan outletTP1 = total pressure at fan inlet
VPo = velocity pressure at fan outlet
Fan static pressure is normally shown on the manufacturer'sperformance curve. This is plotted against flow rate. To correctthe FSP from the test speed and density to that shown on theperformance curve, the following formula is used:
FSPc = FSP x Nc 2 x dc
N dwhere:
FSPc = corrected fan static pressureFSP = test fan static pressureNc = corrected speedN = test speeddc = corrected inlet density
d = test inlet density
Performance Evaluation of Candidates 69
-
7/29/2019 Performance Op Tim Ization
79/97
Fan Power Calculation
Input power to the motor must be calculated in the mannerapplicable to the instrument being used.
The performance curve supplied by the fan and blowermanufacturers normally shows the input power to the fan orblower. Therefore, the motor input power measured during thetest must be corrected for part-load efficiency to reflect thepercent of full-load power at which the motor is operating.
If the equipment is V-belt driven, further adjustment of the
measured power is required. It is necessary to estimate theV-belt drive losses as a function of motor horsepower.
To correct the measured power to the fan or blower for thespeed and density shown on the manufacturer's performancecurve, the following formula should be used:
BHPc = BHP x Nc 3 x dcN d
where:BHPc = corrected input horsepowerBHP = test input horsepower
= kWmeasured x Effmotor x Effdrive0.746
Nc = corrected speedN = test speed
dc = corrected inlet densityd = test inlet density
70 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
80/97
GENERAL
Rotating machinery is a particularly dangerous element of plantequipment due to the tremendous forces that they exert,bothmechanically and electrically. Always employ safety measureswhen carrying out performance tests and exercises. Extremecaution is to be exercised at all times. For the most part, this
means applying common sense to the situation. However, everyindustrial environment will have specific safety regulations thatmust be followed.
PLANT REGULATIONS
General safety items apply to most industrial settings. Always referto existing regulations in specific industrial plants.
Hard hat, safety glasses,and certified boots must be worn at alltimes.
Visitors must stay in designated areas.
Safety meetingsare to be conducted before workcommences to discuss hazardous aspects of the work.
Safety 71
C H A P T E R 5
Safety
-
7/29/2019 Performance Op Tim Ization
81/97
-
7/29/2019 Performance Op Tim Ization
82/97
-
7/29/2019 Performance Op Tim Ization
83/97
couplings,and bearings, even when these parts are enclosed bysuitable guards.
During testing, the rotating speeds must never exceed the
manufacturer's rating or catastrophic failure may result.
When testing at various points of operation,care should betaken to ensure that the equipment is not operated in anunstable region of the equipment's performance curve. Severevibration and catastrophic equipment failure may result if:
- a fan is operated in a stall condition
- a pump is operated in a manner that causes cavitation
It must always be recognized that the components of fans,pumps, and blowers are highly stressed. Operation and testingshould be done only by knowledgeable and experiencedpersonnel. If there is any doubt as to safety aspects of thework,refer either to a qualified plant engineer or to themanufacturer of the particular equipment involved.
74 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
84/97
A - ENGINEERING SPECIALIST PROPOSAL GUIDELINES
The Performance Optimization Feasibility Study proposal shouldinclude the following outline:
(1) Cover Sheet
Study title
Submitted to (customer name,contact, and location)
Date submitted
Submitted by (engineering specialist and company)
(2) Executive Summary
(3) Application/Process Description
Equipment type and size (fan, pump,or blower system)
Process information (batch, continuous,other)
Fluid or material moved (air, water, gas, sewage,etc.)
(4) Current Situation
Current operating conditions
Appendices 75
C H A P T E R 6
Appendices
-
7/29/2019 Performance Op Tim Ization
85/97
Equipment condition (new, refurbished,etc.)
Estimated service life remaining
Present control scheme Future expansion plan if known
(5) Potential for Energy Savings
Classify options or measures to be examined into thefollowing general categories:
a) ASD (electronic, mechanical, other)
b) Equipment modification (sizing, new designs,etc.)
c) Process modification (process change,ponyequipment,etc.)
d) Other (specify)
Estimated annual savings (on-peak and off-peak kW and
kWh)(6) Customer Benefits
(7) Scope of Work
Objectives of the study
Project initiatives and methodology
Project schedule(8) Study Team
Proposed staff
Sub-contractors
Resums for key personnel
Type of liability insurance, if any
76 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
86/97
-
7/29/2019 Performance Op Tim Ization
87/97
-
7/29/2019 Performance Op Tim Ization
88/97
Estimated service life remaining
Future expansion plan
(6) Feasibility Study Methodologya) Load-Data Gathering
Discuss load-data gathering sources
Test methodology and instrumentations used
Field data summary
Internal inspection of equipment Load-data sensitivity analysis
b) Development of Load-Duty Cycle
System curve
Number of operating hours at each operating point
Develop lead/duty/cycle chart and/or histogramc) Technical Options Review
Equipment performance curve
List at least three alternatives to optimize the system
Assess viability of each technical option
Identify ancillary measures to fine-tune system Analysis of Equipment condition
d) Energy Assessment and Economic Analysis
Develop load/duty/cycle chart for each technical option
Calculate demand and energy savings for each option(on-peak and off-peak)
Appendices 79
-
7/29/2019 Performance Op Tim Ization
89/97
-
7/29/2019 Performance Op Tim Ization
90/97
C - GLOSSARY OF TERMS
Adjustable Speed Drive: A mechanical, hydraulic,or electricsystem used to match motor speed to changes in process load
requirements.
Blower: A fan with discharge pressure from 2 psig (55.4 Wg) to36 psig (914.6 Wg).
Design Point: A point of operation generally based on a duty thatis slightly higher than the highest duty ever expected for theapplication.This point represents a specific set of criteria used to
select the fan,pump,or blower.Duty: For a fan, the inlet volume flow at a rated fan pressure; for apump, the inlet volume at a rated head.
Fan: A device that causes flow of gaseous fluid by creating apressure difference on the medium to be transported.
Field Performance Tests: Field determination of turbo machine
flow, pressure and power to identify actual points of operation.Head, Dynamic or Total: In flowing fluid, the sum of the staticand velocity pressures at the point of measurement.
Head, Static: The static pressure of a fluid expressed in terms ofthe height of a column of fluid that it would support.
Horsepower (Hp): The measure of work equivalent to lifting
550 lbs one foot in one second,or 745.7 watts.Load Duty Cycle: The relationship between the operating timeand rest time,or repeatable operation at different loads.
Load: The burden on a motor by the driven machine,sometimessynonymous with 'required power.'
Motor: A device that takes electrical energy and converts it into
mechanical energy to turn a shaft.
Appendices 81
-
7/29/2019 Performance Op Tim Ization
91/97
Net Positive Suction Head (NPSH): The amount of pressure inexcess of the fluid vapor pressure required to prevent theformation of vapor pockets.
Performance Curve: A plot of the fan,pump, or blowerperformance characteristics from zero delivery to free flow.
Point of Operation: Where the system curve intersects thepressure and flow curve on the turbo machine's actualperformance curve.
Pressure, Static: The pressure with respect to a surface at rest in
relation to the surrounding fluid.Pressure, Total: The sum of the static pressure and the velocitypressure at the point of measurement.
Pressure, Velocity: The pressure at a point in a fluid existing byvirtue of its density and its rate of motion.
Process and Instrumentation Diagram (P&ID): A schematic
of a process that graphically represents the relationship of allprocess equipment to interconnecting piping,duct-work,and theassociated control sensors, actuators, and controllers; usuallyaccompanied by a sequence of operation.
Process Control: How turbo machine performance is altered tosatisfy system requirements.
Speed Modulation: A control process whereby the speed of a
rotating machine is varied between preset speeds to maintain acontrol setpoint.
Static Efficiency of a Fan: The total efficiency multiplied by theratio of fan static pressure to fan total pressure.
Static Suction Head: The total system head on the suction sideof a pump with zero flow (can be positive or negative).
82 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
92/97
Suction Lift: The head in reference to the system datum that isimposed on the suction of a pump and, for open systems, is theelevation of the pump above the transported fluid exposed to
atmosphere.System: The combination of turbo machine and the connectedhardware through which flow occurs.
System Effect Factor: A factor related to the velocity of thetransported medium that corrects for pressure losses due tosystem inlet and outlet conditions that deviate from standard testconditions.
System Losses: Pressure drop across system hardwarecomponents.
System Resistance: Resistance to flow resulting from thepressure drop and frictional losses of all system hardware.
Throttling: An irreversible adiabatic process that involveslowering the pressure of a fluid without work to control flow rate.
Turbo Machinery: Equipment that uses rotating elements toimpart work on a transported medium, or that uses the energy in aflowing medium to impart work on an external load.
Variable Inlet Vanes (VIVs): An inlet device that changes thedynamic characteristics of the machine as if it were a differentmachine at each of the vane positions.
Appendices 83
-
7/29/2019 Performance Op Tim Ization
93/97
-
7/29/2019 Performance Op Tim Ization
94/97
-
7/29/2019 Performance Op Tim Ization
95/97
ACKNOWLEDGEMENT
Portions of this publication have been reprinted with thepermission of the Air Movement and Control Association, Inc. and
the Hydraulic Institute. More information on standards for thedesign, testing, and application of fan,pump,and blower systems isavailable from the above-mentioned associations.
Fans/Blowers: Air Movement and Control Association, Inc.30 West University DriveArlington Heights, Illinois, 60004-1893Tel: (708) 394-0150
Fax:(708) 253-0088
Pumps: Hydraulic Institute30200 Detroit RoadCleveland, Ohio,44145Tel: (216) 899-0010Fax:(216) 892-1404
Neither of the said associations assume any liability with respect tothe use or misuse of the information, data,designs,concepts,calculations, or source listing,contained in the handbook.
86 Fan, Pump, and Blower Systems
-
7/29/2019 Performance Op Tim Ization
96/97
-
7/29/2019 Performance Op Tim Ization
97/97