Performance Op Tim Ization

download Performance Op Tim Ization

of 97

Transcript of Performance Op Tim Ization

  • 7/29/2019 Performance Op Tim Ization

    1/97

    PerformanceOptimization:Fan, Pump, & Blower Systems

    R E F E R E N C E G U I D E

    Fourth Edition

  • 7/29/2019 Performance Op Tim Ization

    2/97

    First Edition, 1992Second Edition, December 1998Third Edition, December 2000

    Revised by:

    Dan Dederer, P.Eng.,Enertech Solutions Inc.

    Neither Ontario Power Generation, nor any person acting on its behalf,assumes any liabilities with respect to the use of, or for damages resultingfrom the use of, any information, equipment, product, method, or processdisclosed in this guide.

    The sun represents sustained life

    while the lightning bolt depicts energy.The integration

    represents the perfect partnership of energy utilization and the

    environment that encourages wise use and respect for all naturalresources.The roof represents the in-house aspect of energy

    efficiency throughout Ontario Power Generation

    Marcel Gauthier

    Georgian Bay Region - Retail

    Printed in Canada.Copyright 1992, 1998, 2000 Ontario Power Generation

    Energy Savings are Good Business

  • 7/29/2019 Performance Op Tim Ization

    3/97

    PerformanceOptimization:Fan, Pump & Blower Systems

    R E F E R E N C E G U I D E

    Third Edition

  • 7/29/2019 Performance Op Tim Ization

    4/97

    i

    TA B L E O F C O N T E N T S

    INTRODUCTION ..............................................................................1

    1.0 P ERFORMANCE OPTIMIZATION FUNDAMENTALS ...........................3

    Fan,Pump,and Blower Systems ...................................................3System Defined......................................................................3

    System Point of Operation.....................................................4System Flow and Pressure Relationship.................................4

    Fan/Pump Performance Curve .............................................9

    Energy-Saving Techniques.............................................................9General .................................................................................9

    Reducing Motor Input Power ..............................................11

    2.0 P ERFORMANCE OPTIMIZATIONTECHNIQUES AND MEASURES ..................................................15

    Primary Measures For Energy Reduction ...................................15Speed Modulation ...............................................................15

    Equipment Upgrade ............................................................16

    High Efficiency Motors ........................................................16

    Reduction of Impeller Diameter...........................................16

    Variable Inlet Vanes ............................................................16

    Booster Pony Applications .................................................16

    Ancillary Measures for Energy Reduction ..................................17System Effect Factors ...........................................................17

    Elimination of Cavitation ...................................................17

    High Performance Lubricants.............................................17

    Coatings..............................................................................17

    Internal Running Clearances .............................................17

    System Maintenance ...........................................................18

  • 7/29/2019 Performance Op Tim Ization

    5/97

    Process Control ...................................................................18

    3.0 ASSESSMENT METHODS .........................................................19

    General .......................................................................................19

    Prescreening Information...........................................................19Step 1: Review Process &

    Instrumentation Diagram (P&ID).......................................21

    Step 2 : Review Prescreening Information...........................22Step 3 : Prescreening Conclusions .......................................30

    Load Data Gathering...................................................................30Design Data........................................................................31

    Observations and Estimates by Operating Staff ...................31

    Plant Operating Records .....................................................31

    Temporary Metering............................................................32

    Field Performance Testing ..................................................32

    Development of Load Duty Cycle ..............................................34

    Technical Options Review..........................................................35General...............................................................................35

    System Loss Evaluation........................................................36

    Equipment Internal Evaluation ..........................................37

    Application Considerations.................................................38

    Energy Assessment .....................................................................39

    Economic Analysis ......................................................................40Total Savings.......................................................................40

    Cost Estimates......................................................................40

    Simple Payback and IRR .....................................................41

    Feasibility Report........................................................................42

    ii

    TA B L E O F C O N T E N T S

  • 7/29/2019 Performance Op Tim Ization

    6/97

    4.0 P ERFORMANCE EVALUATION OF CANDIDATES............................43

    General .......................................................................................43

    Applicable Safety Standards........................................................43

    Applicable Performance Test Standards......................................44Pump Performance Test Standards.....................................44

    Fan and Blower Performance Test Standards.....................44

    Measurement Parameters and Test Instruments .........................45Measurement Parameters ...................................................45

    Test Instruments..................................................................45

    Calibration of Test Instruments...........................................45

    General Test Procedures .............................................................46Location of Test Points ........................................................46

    Control of Turbo Machine and System................................47

    Performance Test Records...................................................48Rotational Speed Measurement ...........................................48

    Motor Input Power Measurement ........................................49

    Pump Test Procedures ................................................................51

    Liquid Density.....................................................................51

    Liquid Flow Rate Measurement ...........................................51

    Pump Head Measurement...................................................53

    Pump Test Calculation................................................................55Liquid Properties Calculation..............................................56

    Liquid Flow Rate Calculation..............................................56

    Pump Head Calculation .....................................................57

    Pump Power Calculation ....................................................58

    Fan and Blower Test Procedures.................................................59Gas Properties .....................................................................59

    Gas Flow Rate Measurement ...............................................61

    iii

    TA B L E O F C O N T E N T S

  • 7/29/2019 Performance Op Tim Ization

    7/97

    Fan and Blower Pressure Measurement..............................63

    Fan and Blower Test Calculation.................................................65Gas Density Calculation (same as specific gravity).............65

    Gas Flow Rate Calculation..................................................66

    Fan and Blower Pressure Calculation ................................68

    Fan Power Calculation .......................................................70

    5.0 SAFETY...............................................................................71General .......................................................................................71

    Plant Regulations........................................................................71

    Safety Items Specific to Fan, Pump,and Blower Systems ...........72

    APPENDICES ................................................................................75

    iv

    TA B L E O F C O N T E N T S

  • 7/29/2019 Performance Op Tim Ization

    8/97

    CHAPTER1.0

    1.1 Fixed Resistance System........................................................5

    1.2 Fixed Resistance System with Constant Static Pressure........6

    1.3 Variable Resistance System with Constant Pressure..............7

    1.4 Variable Resistance System with Constant Flow....................8

    1.5 Variable Resistance System withVarying Flow and Pressure ....................................................9

    1.6 Performance Curve for 100 HP Motor.................................12

    1.7 Effect of Speed Reduction ...................................................13

    CHAPTER3.0

    3.1 Process and Instrumentation Diagram ................................22

    3.2 Data-Gathering Decision Tree..............................................33

    3.3 Load Duty Cycle Chart ........................................................34

    3.4 Typical Pump Load Duty Cycle............................................35

    v

    LI S T O F F I G U R E S

  • 7/29/2019 Performance Op Tim Ization

    9/97

    CHAPTER4.0

    4.1 Location of Test Points.........................................................46

    4.2 Selection of Flow-Measuring Plane......................................47

    4.3 Connecting a Wattmeter......................................................49

    4.4 Liquid Flow Rate Measurement:Vessel and Timer ...............52

    4.5 Liquid Flow Rate Measurement:Orifice Plate ......................524.6 Pressure Tap Geometry........................................................53

    4.7 Gauge Reference to Datum .................................................54

    4.8 Suction Head by Calculation ...............................................55

    4.9 Pitot Static Tube...................................................................62

    4.10 Double Reverse Tube.........................................................62

    4.11 Inclined Manometer ..........................................................62

    4.12 Static Pressure Readings ....................................................64

    CHAPTER3.0

    3.1 Prescreening Review...........................................................23

    vi

    LI S T O F F I G U R E S

    LI S T O F TA B L E S

  • 7/29/2019 Performance Op Tim Ization

    10/97

    It is estimated that as much as 20% to 50% of the electrical powerused to run industrial fan,pump, and blower systems can be savedby overcoming operating inefficiencies.

    Opportunities to improve operating efficiency are overlooked forfour reasons:

    low awareness about energy-efficient technologies the financial and operational benefits are not understood

    initial costs taking precedence over life-cycle costs

    energy-saving projects are considered less important than otherproduction-related expenditures.

    This handbook:

    characterizes various systems

    provides a quick reference on performance optimizationtechniques

    provides guidelines on how to pre-screen candidates andperform a feasibility study

    Introduction 1

    Introduction

  • 7/29/2019 Performance Op Tim Ization

    11/97

    reviews field performance testing procedures

    reviews general plant safety practices

    2 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    12/97

  • 7/29/2019 Performance Op Tim Ization

    13/97

    System Point of Operation

    The system point of operation is the intersection between thesystem resistance curve and the turbo machine performance

    curve. This point determines the flow rate. There are two ways tochange the point of operation:

    change the characteristics of the turbo machine performancecurve,varying speed,changing inlet vane settings, etc;

    alter the system curve by changing system losses or flow.

    Frequently, these two changes occur simultaneously.

    For example: An increase in system resistance may beautomatically counteracted by an increase in speed,which keepsflow constant.

    System Flow and Pressure Relationship

    How flow and pressure are related in a system depends onwhether the system components are fixed resistance (e.g.,

    ductwork) or variable resistance (e.g.,dampers, filter, etc.).

    Fixed Resistance System

    Pressure is proportional to Flow2

    For example: A forced draft fan, fitted with variable inlet guidevanes, supplies air to a boiler. The ductwork system has nothrottling dampers.

    4 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    14/97

    Figure 1.1 shows the system, the fan curve, and a fixed

    resistance system curve.

    Fixed Resistance System with Constant Static Pressure

    Pressure a FIow2 + Constant Static Pressure

    For example: A pump supplying a water tower must overcomethe constant static pressure (head) corresponding to the

    elevation of the tower, plus the fixed resistance in the pipesystem.

    Performance Optimization Fundamentals 5

    SystemResistance

    CurveTurbo

    MachinePerformance Curve

    Inlet Stack

    Boiler

    Fan

    Flow

    Pressure

    Figure 1.1

    Fixed Resistance System

  • 7/29/2019 Performance Op Tim Ization

    15/97

    Figure 1.2 shows the system, the pump curve, and a fixedresistance system curve with a constant static head.

    Variable Resistance System with Constant Pressure

    Pressure = Constant

    For example: A blower on a multi-port fume collection systemis modulated by an inlet damper to maintain a constant

    pressure in a header, regardless of the number of opencollection ports.

    6 Fan, Pump, and Blower Systems

    SystemResistance

    Curve

    ConstantStaticHead

    InletPump

    Flow

    Press

    ure

    WaterTower

    Figure 1.2:

    Fixed Resistance System with Constant Static Pressure

  • 7/29/2019 Performance Op Tim Ization

    16/97

    Figure 1.3 shows the system, the fan curve,and a constantpressure system resistance curve.

    Variable Resistance System with Constant Flow

    Flow = Constant

    For example: To form insulation batts, a fan is used to drawinsulation fibers onto a moving conveyor. The fibers must

    move at constant velocity to disperse uniformly, and the speedof the conveyor is varied to form different thicknesses of batts.The lower pressure drop through thinner batts is offset bypartially closing a damper at the fan inlet.

    Performance Optimization Fundamentals 7

    SystemResistance

    Curve

    Slide

    Gates

    Fan

    Flow

    Press

    ure

    Header

    InletDamper

    Collection Ports

    Figure 1.3

    Variable Resistance System with Constant Pressure

  • 7/29/2019 Performance Op Tim Ization

    17/97

    Figure 1.4 shows the system, the fan curve, and a constant flow

    system resistance curve.

    Variable Resistance System with Varying Flow and Pressure

    This system is usually defined as a series of discrete operatingpoints with no consistent relationship between flow andpressure.

    For example:A mine ventilation fan is fitted with manual

    control Variable Inlet Vanes (VIV), which are adjusted toprovide the correct air flow to various areas of the mine. Areasof the mine not in use are isolated by doors.

    8 Fan, Pump, and Blower Systems

    SystemResistance

    Curve

    FanFlow

    Pr

    essure

    InletDamper

    RawInsulation

    Conveyor

    Figure 1.4

    Variable Resistance System with Constant Flow

  • 7/29/2019 Performance Op Tim Ization

    18/97

    Figure 1.5 shows the system, the fan curve,and the operatingpoints defined by varying flow and pressure.

    Fan/Pump Performance CurveEach fan or pump is characterized by a set of operating points(flow, pressure) called itsperformance curve. The manufacturersupplies this curve, from which the application engineer selectsthe best fan or pump to meet the system needs. Since systemsoften have a range of operating points, selecting the optimumfan/pump is critical.

    ENERGY-SAVING TECHNIQUES

    General

    The objective of all turbo machinery performance optimizationtechniques is to provide the correct flow and pressure to meet theprocess requirements,using less electrical power.

    Performance Optimization Fundamentals 9

    Points of Operation

    Fan

    Doors

    Mine Shafts

    VIGV

    Flow

    Pressure

    DesignPoint

    ClosedMine

    SupplyShaft

    Figure 1.5

    Variable Resistance System with Varying Flow and Pressure

  • 7/29/2019 Performance Op Tim Ization

    19/97

  • 7/29/2019 Performance Op Tim Ization

    20/97

    The brake horsepower required by the fan, pump, or blower is afunction of the total efficiency of the turbo machine:

    BHP = 1 x [AHP] or BHP = 1 x [WHP]hT hT

    The input kW required to produce the BHP for the turbo machineis a function of the motor efficiencyhm and the efficiency of anyother components in the drive train,e.g.,V-belts, fluid drive,ASDho,etc.:

    kW = 0.746 x 1 x 1 x BHP

    hm ho

    As shown above,all optimization techniques for fans,pumps, andblowers involve either an improvement in the efficiency of theturbo machine or drive train, and/or an improvement in systemrequirements (i.e., reduced flow and/or pressure).

    Reducing Motor Input Power

    Motor input power must be reduced to achieve energy savings.This is achieved by reducing the brake horsepower requirementsor varying the speed of the motor.

    Maintaining Constant Motor Speed with Reduced Brake-Horsepower Requirements

    For a constant speed motor, applying performance optimizationtechniques to the turbo machine will reduce input power tothe motor, since less brake horsepower (load) is applied to themotor shaft. Figure 1.6 shows a performance curve for atypical induction motor.

    Performance Optimization Fundamentals 11

  • 7/29/2019 Performance Op Tim Ization

    21/97

    Varying the Speed of the Motor and Turbo Machine

    This approach includes all applications where the requiredpoints of operation can be achieved by varying the speed of

    the motor. For a fixed resistance system, the theoreticalrelationship between speed and brake horsepower is:

    BHP a RPM3

    As brake-horsepower requirements decrease,motor inputpower reduces accordingly.

    12 Fan, Pump, and Blower Systems

    B - % Power Factor

    C - Current (FLA=100%)

    A - % Efficiency

    D - kW Input

    Shaft Output - BHP

    90

    80

    70

    60

    0

    0 25

    94

    92

    90

    88

    86

    A B

    100

    75

    50

    25

    0

    100

    75

    50

    25

    0

    C D

    50 75 100 125 150

    Figure 1.6

    Performance Curve for 100 HP Motor

  • 7/29/2019 Performance Op Tim Ization

    22/97

    For example: Reducing system pressure losses by removingthe throttling valve and simultaneously slowing the machine,results in reduced brake horsepower, as shown in Figure 1.7.

    Performance Optimization Fundamentals 13

    Flow Capacity

    Pressure

    BrakeHorespower

    Reduced Horsepower

    System Resistance Curve

    System Resistance Curve

    Original Point of Operation

    New Point of Operation

    Figure 1.7

    Effect of Speed Reduction

  • 7/29/2019 Performance Op Tim Ization

    23/97

  • 7/29/2019 Performance Op Tim Ization

    24/97

    The performance optimization techniques addressed in thishandbook are divided into two categories:

    1. Primary Measures for Energy Reduction moderate to high cost quantifiable energy savings

    2. Ancillary Measures for Energy Reduction low to moderate cost fine-tuning measures may be done independently or in conjunction with primary

    measures

    PRIMARY MEASURES FOR ENERGY REDUCTION

    Speed ModulationSpeed control of equipment is achieved in one of two ways:

    by varying the speed of a motor coupled directly to the load,i.e.,ASDs,multi-speed motors,DC motors;

    by coupling a fixed-speed driver to the load via a device thatpermits speed adjustment of the load, i.e., fluid drives, gear

    systems and adjustable belt drives.

    Techniques and Measures 15

    C H A P T E R 2

    Performance OptimizationTechniques and Measures

  • 7/29/2019 Performance Op Tim Ization

    25/97

    Equipment Upgrade

    Turbo machine upgrades may have applications in these areas:

    higher efficiency turbo machinery may now be available; due to industrial process changes, turbo machine re-selection

    may improve efficiency at the new points of operation;

    worn impeller replacement.

    High Efficiency Motors

    The turbo machinery may operate more efficiently if the existingmotor is replaced with a high efficiency motor or one selectedcloser to its current operating conditions.

    Reduction of Impeller Diameter

    Due to over-sizing, the turbo machine may operate against apartially-closed damper or valve. Resizing the impeller reduceshorsepower requirements. BHP is proportional to impeller

    diameter.

    BHP1 = Diameter1 5

    BHP2 Diameter2

    Variable Inlet Vanes

    These are used to control flow on fans and blowers and aregenerally efficient in the range close to maximum flow conditions.

    Booster Pony Applications

    A booster fan,blower, or pump is used for systems that experienceinfrequent peaks or upset conditions. This allows main equipmentto operate at maximum efficiency under normal conditions.

    16 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    26/97

    ANCILLARY MEASURES FOR ENERGY REDUCTION

    System Effect Factors

    Equipment cannot perform at capacity if fans,pumps, and blowershave poor inlet and outlet conditions. Correction of system effectfactors (SEFs) can have a significant effect on performance andenergy savings.

    Elimination of Cavitation

    Flow, pressure,and efficiency are reduced in pumps operating

    under cavitation. Performance can be restored to manufacturersspecifications through modifications. This usually involves inletalterations and may involve elevation of a supply tank.

    High Performance Lubricants

    The low temperature fluidity and high temperature stability ofhigh performance lubricants can increase energy efficiency byreducing frictional losses.

    Coatings

    Coating system components such as pump bowls, impellers,casings, and inner linings of pipe works reduces frictional lossesand increases efficiency.

    Internal Running Clearances

    The internal running clearances between rotating and non-rotatingelements strongly influences the turbo machine's ability to meetrated performance. Proper set-up reduces the amount of leakage(recirculation) from the discharge to the suction side of theimpeller.

    Techniques and Measures 17

  • 7/29/2019 Performance Op Tim Ization

    27/97

    System Maintenance

    Fan, pump, and blower systems may undergo an actual loss ofefficiency due to dirt build-up on components such as filters, coils,

    and impellers. Duct leaks may be a major problem with highpressure blower systems.

    Process Control

    The process served by fans,pumps, and blowers should utilize theflow in an efficient manner based on actual requirements.To achieve this:

    shut turbo machinery off when it is not required

    control flow to prevent usage of capacity not required for theprocess

    eliminate recirculation modes if possible

    close duct and pipe runs when they are not needed

    18 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    28/97

    GENERAL

    Some industrial fan,pump, and blower systems operate efficiently,and regular maintenance will ensure continued performance ofthese systems.

    The performance of most other turbo machines can be improved.

    Determining the feasibility of performance optimization measuresinvolves:

    l. Candidate Prescreening2. Load Data Gathering3. Development of a Load Duty Cycle4. Technical Option Review5. Energy Assessment

    6. Economic Analysis7. Feasibility Report

    PRESCREENING INFORMATION

    Engineering and operating data are typically incomplete orunavailable. The information needed to establish candidatepotential and viability is usually obtained through observations anddiscussions with operating personnel.

    Assessment Methods 19

    C H A P T E R 3

    Assessment Methods

  • 7/29/2019 Performance Op Tim Ization

    29/97

    The following items should be noted when prescreeningcandidates:

    VISUA L EXA MINAT ION

    - visual overview of complete system

    - condition of turbo machine and system (i.e., leakage, age)

    - nameplate information of both motor and turbo machine

    - inlet and outlet connections (i.e., elbows obstructingsmooth flow)

    - type of elbows in system (i.e., long radius or short square)

    - ductwork/piping changes (i.e., closure of runs)

    - conditions of entry points to plenums or vessels (i.e., square-edged instead of bell-mouthed)

    - maintenance condition of turbo machine and system

    - gaskets protruding into fluid stream- damper and valve locations (i.e., percent closed)

    - automatic or manual controls of dampers/valves

    DISC USSIONS WIT H OPERATING PER SONNEL

    - equipment installation date

    - future expansion plans for process- turbo machine suitability for process (i.e.,

    adequate capacity)

    - equipment maintenance (i.e., last servicing by manufacturer)

    - type of fluid handled (i.e., corrosive or erosive)

    - system or process changes

    20 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    30/97

    - availability of process and instrumentation diagrams andperformance curves

    - number of operating points

    - required performance at each operating point

    - estimated annual hours at each operating point

    - control mechanism to achieve various operating points

    - approximate range of valve or damper settings

    - approximate range of speed control

    - bypass, idling,or flow wastage when process cycle does not-require turbo machine

    - turbo machine operation problems (i.e.,noise,vibration,duct pulsation)

    Step 1: Review Process & Instrumentation Diagram (P&ID)

    To enhance system knowledge, review a process andinstrumentation diagram (P&ID) of the system. Sketch by hand ifdrawings are unavailable. Figure 3.1 shows a P&ID for a typicalcentrifugal-induced draft (ID) and forced-draft (FD) fan application.

    P&IDs graphically represent the system and process by:

    - showing the position of the turbo machine to othercomponents

    - differentiating between fixed and variable pressure losscomponents

    - indicating the parameter controlled in the system (i.e.,pressure, flow, temperature)

    - locating the system control point (i.e.,discharge ducting, inletplenum)

    Assessment Methods 21

  • 7/29/2019 Performance Op Tim Ization

    31/97

    Step 2 : Review Prescreening Information

    Evaluate accuracy, importance, and relevance of informationobtained in the field. Use the following prescreening review todetermine if there are inefficient conditions that can be improved.

    22 Fan, Pump, and Blower Systems

    Cell 1

    Cell 2

    Cell 3

    Cell 4

    Gas

    Furnace

    Crude Oil

    Hot Air

    Flue Gases

    Temperature

    regulation

    Heat

    Exchanger

    Oxygen percentage monitor

    Multiple pipe

    systemsHeated

    crude oil

    to first stage

    separation

    M1

    I.D.

    Fan

    M2

    F.D.

    Fan

    3-phase

    600VTo Main

    3-phase

    600VTo Main

    Cold Air

    Flue gases

    to atmosphere

    1 and 2

    AC motors

    (250 hp)

    Figure 3.1

    Process and Instrumentation Diagram

  • 7/29/2019 Performance Op Tim Ization

    32/97

    Table 3.1

    Prescreening Review

    Assessment Methods 23

    Condition

    Inefficient TurboMachine

    Characteristic

    Misapplication oflow efficiency

    impeller

    Inefficient drive

    Age of equipment

    Turbo machine

    operating at poor

    selection point

    Comments

    Radial blade impellers needed for material-handling

    applications

    Oversized motor

    Motor not high efficiency design

    Oversized V-belt drive package

    Old adjustable speed-drive technology

    Older equipment is generally less efficient

    Turbo machine relocated for a different application

    Elimination of some pipe/duct runs on multi-run

    distribution system

    Addition of auxiliary cleaning equipment

    Throttled operation for oversized turbo machine

    Straight Radial Blades

    Approximately 65% / 70%

    peak static efficiency

    Airfoil Blades

    Approximately 84% / 90%

    peak static efficiency

    Rota

    tion

    Rota

    tion

    Operation with original

    equipment

    Pressure

    Actual

    Operating Point

    Flow

    Original

    Selection

    Point

    Operation with new

    reselected equipment

    Actual

    Operating Point

    Pressure

    Flow

  • 7/29/2019 Performance Op Tim Ization

    33/97

    Table 3.1

    Prescreening Review (contd)

    24 Fan, Pump, and Blower Systems

    Condition

    Poor Maintenance

    Characteristic

    Excessive systemresistance

    Worn impeller or

    bearings

    Flow leakage

    Internal turbo

    machinedeficiencies

    Comments

    Dirty screens, nozzles, filters, coils Material build-up on impellers, turning vanes

    Vibration/imbalance

    Holes in flex connection

    Deteriorated gaskets

    Loose or distorted flanges

    Corrosion or erosion in piping and ductwork

    Worn pump seals Running clearance

    Flow

    Rota

    tion

    Build-upInlet Box

    Improper set-up of fan

    impeller allows air to

    recirculate internally

    Build-up on fan blades

    reduces efficiency

    Erosion of fan blades

    reduces efficiency

  • 7/29/2019 Performance Op Tim Ization

    34/97

    Table 3.1

    Prescreening Review (contd)

    Assessment Methods 25

    Condition

    System EffectFactors

    Characteristic

    Poor fan intakedesign

    Comments

    Elbow directly on inlet causes non-uniform flow profile

    Rounded elbow is better than square elbow

    Addition of turning vanes will streamline flow

    Installation of splitter plate reduces entry turbulence on

    fans located near walls

    Length

    of Duct

    D

    R

    Turning

    Vanes

    Splitter

  • 7/29/2019 Performance Op Tim Ization

    35/97

    Table 3.1

    Prescreening Review (contd)

    26 Fan, Pump, and Blower Systems

    Condition

    System EffectFactors (contd)

    Characteristic

    Poor fan intakedesign (contd)

    Comments

    Butterfly damper close to fan inlet creates turbulence and

    decreases performance

    Orientation of inlet elbows can cause air to pre-swirl in

    the direction opposite to wheel rotation

    Turning vanes can improve performance for this condition

    Butterfly Inlet Damper

    Turning

    VanesImpeller

    Rotation

    Corrected Counterrotating SwirlCounterrotating Swirl

    Impeller

    Rotation

  • 7/29/2019 Performance Op Tim Ization

    36/97

    Table 3.1

    Prescreening Review (contd)

    Assessment Methods 27

    Condition

    System EffectFactors (contd)

    Characteristic

    Poor fandischarge design

    Obstructions at

    fan inlets and

    outlets

    Comments

    Elbow directly on fan discharge causes performance

    deficiency

    If fan cannot be re-oriented, careful turning-vane design is

    required

    Poor transition and flex connection installations disrupt

    flow and cause turbulence

    Elbow on Discharge Fan Re-oriented toUp-blast Position

    Discharge Duct Work

    Flex Connection

    Axial Fan

    Inlet Duct Work

  • 7/29/2019 Performance Op Tim Ization

    37/97

    Table 3.1

    Prescreening Review (contd)

    28 Fan, Pump, and Blower Systems

    Condition

    System EffectFactors (contd)

    Excessive Flow

    and Pressure

    Losses

    Characteristic

    Air pockets atpump inlet

    Poor pump inlet

    design

    High pressure

    losses across

    system

    components

    Comments

    Caused by lack of streamlined design

    Increases exponentially with flow velocity

    Pressure Loss = Co x (Velocity)2

    An air pocket can form where

    a symmetrical elbow appears

    in a suction line

    Eccentric tapered reducer

    prevents air pockets (above)

    when pipe size is reduced

    Suction SuctionAir pocket

    Vertical elbow permits

    reasonably equal distribution

    to impeller. Flow is still better

    with straight section before

    pump.

    Horizontal elbow distorts

    and may reverse flow. With

    double-suction pump, inlet

    on small radius side may be

    partly starved.

    Poor ductwork offset with

    square elbows

    Improved ductwork with

    turning vanes

  • 7/29/2019 Performance Op Tim Ization

    38/97

    Table 3.1

    Prescreening Review (contd)

    Assessment Methods 29

    Condition

    Excessive Flowand Pressure

    Losses (contd)

    Oversized Turbo

    Machine

    Inefficient Control

    of Turbo Machine

    Characteristic

    High pressurelosses across

    system

    components

    (contd)

    Excess flow

    Flow wastage

    Continuous

    operation with

    partially closed

    dampers or valves

    Throttled

    operating point

    Unnecessary

    operation

    Comments

    System entry conditions from plenums and vessels should

    provide smooth entry conditions for fluid

    System constrictions may result from construction

    methods used to bypass other plant equipment

    System valves and dampers may be in a permanent,

    partially closed position

    Existing process may operate with less flow

    Changes to process may reduce flow requirements

    Process cycle may have periods with no need for turbo

    machine operation

    Turbo machine may be running while rest of process is shut down

    Multi-port collection or distribution system may have ports

    left open unnecessarily

    Original performance margins were too great

    Turbo machine relocated from different application

    System resistance over-estimated

    Removal of system component has reduced pressure drop

    Original sizing done for infrequent upset condition

    Turbo machine throttling used instead of speed control

    Outlet fan dampers used instead of variable inlet vane control

    No controls are used and turbo machine supplies excess capacity

    Recirculation mode used when process does not require

    turbo machine operation

    Lack of control sequence may have turbo machine

    running when not required

    Vena Contracta increasesentry losses

    Optimal off-set design with

    rounded elbows and turning vanes

    Addition of bell mouth creates

    smooth entry with minimal losses

    Vena Contracta

  • 7/29/2019 Performance Op Tim Ization

    39/97

    Step 3 : Prescreening Conclusions

    Figure 3.2 presents general conditions that may indicate wheresystems are operating inefficiently. With this information, you can

    determine if a candidate(s) merits a more in-depth engineeringfeasibility study to determine viable technical solutions andquantify savings.

    Further assessment should be carried out by an experiencedengineering specialist (i.e., consultant engineer, contractor,equipment manufacturer, or customer operating staff).

    Appendix A provides guidelines engineering specialists may followwhen they prepare optimization feasibility studies.

    LOAD DATA GATHERING

    The engineering specialist will prepare feasibility study findingsand recommendations,based on:

    evaluation of viable technical options that can be employed

    accurate determination of energy savings

    economic analysis

    To effectively carry out this study:

    locate all point(s) of operation (i.e., flow, pressure, and power);

    determine the turbo machine load duty cycle;

    evaluate data accuracy and reliability;

    evaluate characteristic of data: seasonal, batch,product oroutput fluctuations.

    Common sources of information are given in the followingsubsections. Figure 3.2 provides general guidelines on how togather data for development of the load duty cycle.

    30 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    40/97

  • 7/29/2019 Performance Op Tim Ization

    41/97

    Temporary Metering

    performed when operating data is unavailable (or deemedunreliable)

    typical power metering would be for a two-week period,with15-minute interval samples

    interpretation of results should take into account seasonal orproduction variations

    if possible, metering on other parameters should be donesimultaneously, i.e., temperature,rotational speed, damper

    settings, pressure,pressure differential across variableresistance components,etc.

    Field Performance Testing

    testing must be done to verify point(s) of operation and systembehavior.

    Chapter 4 of this handbook gives more guidelines on fieldperformance testing.

    32 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    42/97

    Assessment Methods 33

    AreOperating Records

    Complete?

    No

    Yes

    Is theLoad Pattern

    Seasonal?

    Field MeasurementRequired

    No

    Yes

    Can theDuty Cycle be

    Developed by OtherMeans?

    No

    Yes

    Gather GeneralInformation

    Extended DataAccumulation Period

    Generate Load Duty Cycle

    Short DataAccumulation Period

    AreOperating Records

    Available?

    - Horsepower of Motor- Hours of Operation- Suppliers' Performance Curve

    InitiateData Gathering

    No

    Yes

    Figure 3.2

    Data Gathering Decision Tree

  • 7/29/2019 Performance Op Tim Ization

    43/97

    DEVELOPMENT OF LOAD DUTY CYCLE

    The load duty cycle is a frequency distribution of the time that aturbo machine operates at each point of operation. Two

    components are needed for development:

    turbo machine load Plot the points of operation on theturbo machine performance curve to identify system flow andpressure relationship.

    duty cycle This is the number of hours the turbo machineoperates at each point of operation.

    Tabulate all data in a load/duty/cycle chart. An example is shownin Figure 3.3.

    Figure 3.3

    Load Duty Cycle Chart

    34 Fan, Pump, and Blower Systems

    Point Time atof Flow Pressure Brake Speed Input Operating kWh/yr

    Operation Hp (RPM) kW to Motor Point(hr/yr)

    1

    2

    3

    4

    5

    6

    TOTALkWh/yr

  • 7/29/2019 Performance Op Tim Ization

    44/97

    It may be useful to construct a histogram of load versus time toshow graphically the load duty cycle of the system. Select thehorizontal axis for an appropriate system parameter. See

    Figure 3.4.

    TECHNICAL OPTIONS REVIEW

    General

    Assess the practicality of implementing the various performanceoptimization techniques. The following items are needed for thisprocess:

    manufacturer's performance curve; load duty-cycle charts, as completed for existing system,and for

    system employing performance optimization techniques (seepage 34);

    system P&ID (see page 21);

    system loss evaluation (see page 36);

    report on equipment internal inspection (see page 37).

    Assessment Methods 35

    Percent Flow

    Perc

    entTotalOperatingTime

    20

    10

    0

    0 10 20 30 40 50 60 70 80 90 100

    B

    Figure 3.4

    Typical Pump Load Duty Cycle

  • 7/29/2019 Performance Op Tim Ization

    45/97

    To determine the best performance optimization technique,

    1. Review the process requirements. Determine if the processcan operate just as well with reduced flow or pressure.

    2. Review system test results to identify peak pressure losses.Evaluate if these losses can be reduced by modifying thesystem.

    3. Compare turbo machine field performance test results withmanufacturer's predicted performance. Check equipmentinternal inspection report to account for discrepancy between

    actual and predicted performance. Assess the need forequipment repair/maintenance.

    4. Assess the viability of each performance optimizationtechnique.

    Since each installation has unique characteristics, good engineeringjudgement and experience is required to carry out a thoroughevaluation of each technical option.

    System Loss Evaluation

    To carry out a comprehensive performance evaluation, thefeasibility study must address:

    original design parameters used for equipment rating

    actual system requirements

    duct/pipe geometry and associated system losses

    Examples of duct/pipe arrangements that cause high system losses:

    short radius elbows used in duct/pipe instead of long radiuselbows or turning vanes;

    poor duct/pipe inlet conditions from vessels and plenums;

    36 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    46/97

  • 7/29/2019 Performance Op Tim Ization

    47/97

    steel bracing left inside ductwork

    inappropriate damper linkage adjustments

    Call a manufacturer's service representative or experienced turbomachinery engineer for an accurate evaluation of the internalcondition of the turbo machine.

    Application Considerations

    To check the suitability of each performance optimizationtechnique, consider the entire system including:

    type of fluid stream

    environmental consideration (i.e., indoor, outdoor, hazardousarea)

    system limitations

    physical constraints

    Following are typical application considerations for turbo machineperformance optimization techniques:

    Adjustable Speed Drives

    - spectrum analysis on impeller may be required

    - low-speed motor-cooling limitations

    - reduced motor torque may not overcome high breakaway

    torque at start-up- may require motor oversizing

    - fans may be forced into unstable operating ranges

    - pumps can experience extremely high temperature build-up,if pressure reduction is less than static head

    38 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    48/97

    Equipment Upgrade

    - high efficiency impellers are generally not suitable for harshenvironments

    Impeller Trimming

    - provides permanent de-rating

    - not suitable if full capacity occasionally needed

    Variable Inlet Valves

    - have non-linear control range when low flows required,maycause pulsations in pressure

    ENERGY ASSESSMENT

    Compare the electrical consumption of each of the selectedperformance optimization measures with the consumption of theexisting system. All desired points of operation will requireconsideration.

    Electrical savings can occur in demand (kW) and energy (kWh).Demand savings depend on whether turbo machinery loadcoincides with the plant's monthly peak.

    Annual energy savings are based on:

    hours the process or turbo machine operates at each point ofoperation

    average loading at times of monthly demand peaks demand and energy rates for the particular plant

    Assessment Methods 39

  • 7/29/2019 Performance Op Tim Ization

    49/97

    ECONOMIC ANALYSIS

    Total Savings

    Total savings of performance optimization may result from indirectbenefits as well as electrical savings.

    Some examples are:

    improved power factor

    raw material savings

    improved product quality

    reduced labour costs

    Classify non-energy savings into groups of hard and soft dollarsavings, based on how easily they can be quantified.

    Cost Estimates

    Assess the economics of the performance optimization technique

    by establishing cost estimates:

    Capital Equipment

    - quotations from manufacturers

    - suppliers catalogues

    Engineering and Design

    - estimate as a percentage of direct costs- quotations from consultants or contractors

    Installation

    - applying an hourly rate to estimated labour requirements

    - quotations from contractors

    40 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    50/97

    - equipment rentals

    - miscellaneous materials

    Simple Payback and IRR

    Compare the total cost of implementing a performanceoptimization technique against the total benefit. Two methodsusually used are: Simple payback and internal rate of return (IRR).

    Simple payback is used to determine the time required for thesavings to repay the initial capital outlay.

    Time (years) = Project costAverage annual cash savings

    Internal rate of return takes into account the time value of money.It is an adjusted rate that discounts savings (inflows) and theexpense of the project (outflows) to zero. Determine a project'sacceptability on these grounds,by comparing the performanceoptimization project's IRR against the company's prescribed rate of

    return.

    If the IRR passes this test, the project will likely be undertaken.The IRR is calculated by finding the discount rate, R, that solves thefollowing equation:

    (Cinflow) = (Coutflow)n

    (1+R)n (1+R)n

    where:Cinflow = cash inflowsCoutflow = cash outflowsR = rate of return that will solve the expressionn = signifies that the discounted inflows and

    outflows must be added from time zerothrough time n.

    Assessment Methods 41

    n

    t=0

  • 7/29/2019 Performance Op Tim Ization

    51/97

  • 7/29/2019 Performance Op Tim Ization

    52/97

    GENERAL

    This section provides an overview of information required toconduct field performance tests of fan, pump, and blower systems.The equations, and calculation procedures required to correct themeasured data back to the manufacturer's performance curves, arealso outlined.

    APPLICABLE SAFETY STANDARDS

    The fans,pumps, and blowers discussed in this handbook arerotating equipment driven by electric motors. When dealing withthis equipment, extreme caution must be exercised to avoidelectric shock or injury from rotating or moving mechanicalcomponents.

    All applicable safety standards in effect at the equipment site mustbe observed. Also follow safety standards and practices outlined inChapter 5 of this handbook and:

    AMCA Publication #410

    Recommended Safety Practices for Air Moving Devices

    Performance Evaluation of Candidates 43

    C H A P T E R 4

    Performance Evaluationof Candidates

  • 7/29/2019 Performance Op Tim Ization

    53/97

    APPLICABLE PERFORMANCE TEST STANDARDS

    The data included in the test manuals referenced below for fans,pumps, and blowers will be adequate to conduct the performance

    tests in most cases. If unusual liquids or gases are being handled,or if a significant amount of duct work or piping is locatedbetween the pressure measuring points and the equipment, furtherinformation may be required. Additional information regarding thedensities and viscosities of various liquids or gases and the frictionlosses of pipes,ducts, fittings, and transitions may be required. Thisinformation is readily available in various engineering handbooks

    and textbooks. Pump Performance Test Standards

    Performance testing standards for pumps have been prepared andpublished by the Hydraulic Institute,Cleveland, Ohio,USA. Thetesting standard is part of a complete set of pump standardspublished as:

    Hydraulic Institute Standards

    Fan and Blower Performance Test Standards

    The Air Movement and Control Association,Inc. (AMCA),ArlingtonHeight, Illinois,USA,has several publications for testing fans andblowers. The publication most applicable to the type of testperformed under this program is:

    AMCA Publication 203

    Field Performance Measurements of Fan Systems

    This publication is one of four manuals that also cover the designof air systems, fan and system interaction, including fan laws andsystem effect factors (SEF), and troubleshooting of air-movingsystems.

    44 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    54/97

    MEASUREMENT PARAMETERS AND TEST INSTRUMENTS

    Measurement Parameters

    The parameters that must be determined for accurate evaluation offan, pump or blower performance are:

    liquid or gas properties, i.e.,density and, for liquids,viscosity;

    flow rate;

    inlet and outlet pressure head;

    rotational speed of equipment;

    input power.

    Test Instruments

    The instruments required to measure each parameter are listed inthe appropriate test procedure sections.

    Calibration of Test Instruments

    Instruments used in field performance tests are often subjected torough handling and hostile environments.Consequently, it isessential to ensure that the instruments are in good condition andare capable of providing accurate and repeatable measurements.As a minimum, the following procedure should be adopted:

    physical inspection and functionality test of instrument before,

    during,and after each field test; scheduled calibration of instruments to a recognized national

    standard;

    calibration of instruments after repair, or if any doubt arisesregarding accuracy.

    Note: An extra set of instruments can be useful to check accuracy

    or replace malfunctioning instruments.

    Performance Evaluation of Candidates 45

  • 7/29/2019 Performance Op Tim Ization

    55/97

    GENERAL TEST PROCEDURES

    Location of Test Points

    To obtain reliable measurements of the inlet and dischargepressures of the equipment, the location of pressure test pointsin the pipes or ducts should normally be at least five to tenequivalent diameters downstream of the nearest elbow,transition, or other flow disturbance (Figure 4.1).

    Figure 4.1

    Location of Test Points

    An appropriate pressure loss calculation for the duct or pipeand any fittings between the equipment flange and themeasuring point must be made and added to the measuredpressure.

    The flow-measuring plane should also be five to ten equivalentdiameters downstream from the nearest flow disturbance oroutlet flange as illustrated in Figure 4.2.

    46 Fan, Pump, and Blower Systems

    , , , , , , , ,

    , , , , , , , ,

    , , , , , , , ,

    , , , , , , , ,

    y y y y y y y y

    y y y y y y y y

    y y y y y y y y

    y y y y y y y y

    do

    di

    L > 5 x do

    L > 5 x di

  • 7/29/2019 Performance Op Tim Ization

    56/97

    Inspect the duct/pipe to check that no branches or leaks occurbetween the measuring plane and the equipment to ensurethat the flow measured has passed through the equipment.

    Figure 4.2

    Selection of Flow Measuring Plane

    Control of Turbo Machine and System

    The purpose of this test is to determine the performance of themachine during operation. If the system or process varies, themachine performance may modulate during the time the test isbeing conducted. This must be avoided.

    The duty points at which a performance test is required mustbe selected by referencing the process and instrumentationdiagram and the duty cycle developed during the prescreeningand data-gathering process.

    Performance Evaluation of Candidates 47

    BadMeasuring

    Plane

    PreferredMeasuringPlane

    , ,

    , ,

    y y

    y y

    , , , , , , , , , y y y y y y y y y

  • 7/29/2019 Performance Op Tim Ization

    57/97

    A control lockout must be implemented in consultation withplant operating personnel to hold the machine at a constantpoint of operation during the test.

    The determination of a single performance point may takefrom several minutes to several hours, depending on thegeometry of the system and the amount of test data to becollected.

    Multiple readings of data such as power, speed,controlvalve/damper position, and temperature and pressure of fluidshould be taken to ensure these parameters are held constant

    for long tests.

    Performance Test Records

    A field test data sheet should be prepared before the test toprovide a consistent and complete format for recording test data.

    A custom form should be prepared for each machine to betested. Refer to theHydraulic Institute andAMCA 203handbooks for examples of typical data sheets.

    Sketches of the test point locations, system duct, or pipingorientation and dimensions,and a copy of the P&ID are anecessary part of the performance test records.

    Rotational Speed Measurement

    Instruments most commonly used include an electronic contact ornon-contact tachometer, stroboscopic tachometer, or revolutioncounter with a chronometer. Following are some considerationsfor speed measurements:

    Select good physical access to the shaft or some rotatingcomponent of the machine.

    48 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    58/97

    Select instruments that will provide accurate readings for the speedrange of interest. A demonstrable accuracy of 0.5% or better isacceptable.

    At least two readings,one near the beginning of the test andone near the end, should be taken.

    If the test duration is longer than 15 minutes,additionalreadings should be taken, approximately every 15 minutes.

    If multiple readings show the speed to be constant, the timebetween readings can be extended.

    Note: Rotational speed should not change during the course of thetest.

    Motor Input Power Measurement

    The primary reason for conducting the tests is to estimate howmuch the motor input power can be reduced, using theoptimization techniques available. Therefore, it is essential that a

    comprehensive analysis of the motor input power be conducted.

    Figure 4.3

    Connecting a Wattmeter

    Performance Evaluation of Candidates 49

    Wattmeter

    Motor

    StarterMotor

    CT-1 PT-1

    CT-2

    CT-3

    PT-2

    1

    2

    3

    0

    0

    0

  • 7/29/2019 Performance Op Tim Ization

    59/97

    Many of the machines to be tested under this program will bethree-phase, 320,460 or 575 volt. Portable power analyzers arereadily available measure the input power in this range, taking

    into account voltage,amperage,and power factor. They canprovide a direct readout of kW. Refer to Figure 4.3.

    Specialized measuring equipment,utilizing potential andcurrent transformers, would normally be required for systemsabove 600 volts. A qualified electrical engineer may have todesign an adequate power measuring system.

    A qualified electrician should connect these analyzers to the

    motor input power leads.

    For systems fitted with ASDs, measure the power going into theASD, rather than the power going into the motor. To determinethe actual power being consumed by the equipment,efficiencycorrection factors for part load operation should be included inthe calculations.

    The test data sheet should allow for the recording of volts, amps,power factor, and kilowatts, as a minimum.

    At least two readings,one near the beginning of the test andone near the end, should be taken.

    If the test duration is longer than 15 minutes,additionalreadings should be taken, approximately every 15 minutes.

    If multiple readings show the power to be constant, the timebetween readings can be extended.

    Note: The power consumed throughout the duration of the testshould be constant.

    50 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    60/97

  • 7/29/2019 Performance Op Tim Ization

    61/97

  • 7/29/2019 Performance Op Tim Ization

    62/97

    Pump Head Measurement

    A broad range of instruments are available to suit any application.

    Characteristics of the liquid, i.e., temperature, corrosiveness,etc., and the expected range of the measured head must beconsidered to avoid damage to the instrument by overloading,or by exposure to hot or corrosive fluids.

    Figure 4.6

    Pressure Tap Geometry

    The range and precision of the instrument should be selectedso that the accuracy of the reading is better than 2%.

    Pressure taps with the proper geometry should be used toensure accurate pressure readings. Refer to Figure 4.6 forexample.

    Locate pressure taps in the suction and discharge lines in anarea where steady flow conditions exist.

    Performance Evaluation of Candidates 53

    Brass Plug

    Nipple

    Connects

    HereNipple

    Connects

    HereApprox. Rad.

    d

    4

    Approx. Rad.d

    4

    d to1"

    8

    1"

    4d

    Pipe Coupling

    Weld

    Minimum

    2d

  • 7/29/2019 Performance Op Tim Ization

    63/97

  • 7/29/2019 Performance Op Tim Ization

    64/97

    The geometry of the pipe between the gauge and the pumpflange must be known,so that friction loss can be calculatedand used to arrive at pump total head at the flanges.

    If the pump is drawing from or discharging to a pit or tank thatis open to atmosphere, it may be more convenient to calculatethe head at the corresponding pump flange from the differencein elevation and the appropriate losses. Refer to Figure 4.8.

    Pressure readings should be observed periodically throughoutthe test to ensure no significant fluctuation occurs.

    Figure 4.8

    Suction Head by Calculation

    PUMP TEST CALCULATION

    Measured pump performance will normally be compared with thepump performance curve issued by the manufacturer. Correctionsfor specific gravity, viscosity, and speed may be necessary if thefluid characteristics and/or pump speed tested differ from that

    shown on the performance curve.

    Performance Evaluation of Candidates 55

    Static

    Head

  • 7/29/2019 Performance Op Tim Ization

    65/97

  • 7/29/2019 Performance Op Tim Ization

    66/97

  • 7/29/2019 Performance Op Tim Ization

    67/97

  • 7/29/2019 Performance Op Tim Ization

    68/97

    The pump input power should then be further corrected to therated speed and specific gravity shown on the performancecurve

    BHPc = BHP x Nc 3 x SgcN Sg

    where:BHPc = pump input power at rated speedBHP = pump input power at test speedNc = rated speedN = test speed

    Sgc = rated specific gravitySg = test specific gravity

    FAN AND BLOWER TEST PROCEDURES

    Gas Properties

    The gas density must be determined to accurately calculate other

    performance parameters.Gas density is a function of absolutepressure, temperature,and molecular weight.

    Absolute pressure is determined by adding the barometricpressure at the site and the static pressure at the measuringplane.

    Barometric pressure can be determined with a portableaneroid barometer.

    Static pressure at the measuring plane must be measured asdiscussed on page 64.

    Gas temperature is determined with an instrument-qualitythermometer.

    If the fan is handling ambient air, molecular weight can beassumed to be that of air with appropriate corrections made for

    relative humidity. Relative humidity is determined by

    Performance Evaluation of Candidates 59

  • 7/29/2019 Performance Op Tim Ization

    69/97

    measuring wet bulb and dry bulb temperatures with a slingpsychrometer.

    To determine the density of a gas other than air may require

    the use of complex equipment by a qualified expert to obtainthe chemical composition of the gas. If the gas is a complexmixture of various constituents, as found in many industrialprocesses, the company chemist or an independent laboratoryshould be consulted to collect a gas sample for analysis in thelab. Particular care should be used if the gas is toxic,corrosive,or explosive.

    Note: It is important to ascertain from the P&ID that the gas doesnot undergo any change in moisture content or molecular weight(i.e.,water sprays, cooling coils, burners,etc.) between the fan orblower and the plane at which wet and dry bulb temperatures orgas constituents and barometric pressure are measured. If nochanges occur, the gas wiIl approximate the perfect gas laws andthe ratio of absolute temperatures and absolute pressures can be

    used to determine the density at all planes of interest. For thisreason, it is important to record the temperature and staticpressure at all planes of interest.

    60 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    70/97

    Gas Flow Rate Measurement

    Air or gas flow rate is determined by performing a velocitypressure traverse in the duct using one of the following:

    pitot tube and inclined manometer, electronic micromanometeror magnehelic gauge

    vane anemometer

    thermistor anemometer used as a probe and readout

    The airflow measurement methods recognized by Air Movement

    and Control Association (AMCA) require the use of a pitot statictube or a double reverse tube, and an inclined manometer,preferably with a variable slope ratio to provide sufficient accuracyat a range of air velocities. Figures 4.9 4.11 (p. 62) show variousdevices used to measure air or gas velocity pressure.

    The velocity pressure traverse must be conducted in an area ofthe duct where the flow is stable and uniform. Refer to

    AMCA 203 for guidelines to select and qualify a suitabletraverse plane location. Generally, the requirement is that morethan 75% of the velocity pressure readings should exceed 1/10of the maximum reading.

    The number and distribution of traverse points required in aduct is a function of the duct geometry. Refer toAMCA 203 forguidelines on how to select traverse points. The number of

    points required byAMCA 203 should be taken as a minimum.A traverse using fewer points is unacceptable.

    Consider the following:

    a pitot traverse normally requires two people, since it is usuallyimpossible to hold the pitot tube steady and record the velocitypressure reading at the same time.

    Performance Evaluation of Candidates 61

  • 7/29/2019 Performance Op Tim Ization

    71/97

    62 Fan, Pump, and Blower Systems

    Air Flow

    Static

    PressureTotal

    Pressure

    Reverse

    Tube

    Stainless

    Steel Tubing

    preferred approx.

    .375" OD

    Air Flow

    Impact Tube

    10 in. wg1:1

    Slope Ratio

    0.5 in. wg20:1 Slope Ratio

    1 in. wg10:1 Slope Ratio

    2 in. wg5:1 Slope Ratio

    Figure 4.9

    Pitot Static Tube

    Figure 4.10

    Double Reverse Tube

    Figure 4.11

    Inclined Manometer

  • 7/29/2019 Performance Op Tim Ization

    72/97

    The access holes drilled in the duct for the pitot tube should beplugged when not in use to prevent leakage or disruption offlow profiles in the duct.

    A pitot traverse in a large duct may require special pitot tubes,longer than the standard maximum of 5 feet or access fromboth sides of the duct.

    Measurements in high temperature, toxic, or combustible gasstreams also require special consideration. If possible, thetraverse should be conducted in a duct under negative staticpressure so that the gas will not leak out on the tester.

    Note: Determining the f low through a fan or blower is generallythe most complex part of the performance measurements. Ifproper equipment and procedures are used,and the selection of atraverse plane is satisfactory, the flow rate can be determined towithin 2% to 10% accuracy. A review of the uncertainty analysis inAMCA 203will highlight the parameters that need to be mosttightly controlled to maintain the best accuracy.

    Fan and Blower Pressure Measurement

    A broad range of instruments are available.

    Characteristics of the gas, i.e., temperature, corrosiveness,etc.,and the expected range of the measured pressure, must beconsidered to avoid damage to the instrument by overloadingor by exposure to hot or corrosive gases.

    The range and precision of the instrument should be selectedso that the accuracy of the reading is better than 2%.

    Pressures to be determined for fans and blowers include static andvelocity pressures, which,when added, equal total pressure.

    Velocity pressure is determined from the calculated flow rate,the area of the duct,and the density of the gas stream.

    Performance Evaluation of Candidates 63

  • 7/29/2019 Performance Op Tim Ization

    73/97

    Record duct dimensions for all planes of interest.

    Static pressure readings in the fan discharge duct and in the faninlet duct and static pressure readings at the velocity pressuretraverse plane will be required.

    Static pressure can be measured from the static tap on the pitotstatic tube,as the tube is traversed in the duct. This willprovide several consistent readings. Refer to Figure 4.12.

    The pitot tube should be oriented in the same way as forvelocity pressure readings or the pressure read from the statictap may not be accurate.

    Static pressure taps can be made in the wall of the duct. RefertoAMCA 203 guidelines. Four pressure taps are required,equally spaced around the periphery of the duct. The readingsfrom the four taps should be averaged to provide the staticpressure at that plane.

    Note: Fan suppliers normally specify pressures at the inlet and

    discharge flanges of the equipment. Consequently, it is important

    64 Fan, Pump, and Blower Systems

    Ps3

    Pv3

    Ps5 Ps4

    Fan Static Pressure

    Ps = Ps2 - Ps1 - Pv1

    where Ps2 = Ps5

    where Ps1 = Ps4

    where Pv1 = Pv3

    Figure 4.12

    Static Pressure Readings

  • 7/29/2019 Performance Op Tim Ization

    74/97

  • 7/29/2019 Performance Op Tim Ization

    75/97

  • 7/29/2019 Performance Op Tim Ization

    76/97

    where:V3 = average velocity (ft/min)Pv3 = velocity pressure (in.wg)

    d3 = density (lbm /ft3

    )Knowing this velocity and the geometry of the ductwork, the flowrate can be calculated as follows:

    Q3 = V3A3

    where:Q3 = gas flow rate (cfm)

    V3 = average velocity (ft/min)A3 = duct area at traverse plane (ft2)

    The fan or blower flow rate is defined as being the volume flowrate at fan inlet density. Continuity of mass allows for thecalculations of volume flow rates at other planes in the system. Ifthe densities at the other planes are known, the following equationis used:

    QX = Q3 x d3dx

    where:Qx = flow rate at plane xQ3 = flow rate at traverse planed3 = density at traverse planedx = density at plane x

    To compare the calculated fan or blower flow rate to theperformance curve supplied by the fan or blower manufacturer, itmay be necessary to correct for fan speed, using the followingequations:

    Qc = Q x Nc

    N

    Performance Evaluation of Candidates 67

  • 7/29/2019 Performance Op Tim Ization

    77/97

  • 7/29/2019 Performance Op Tim Ization

    78/97

    Performance curves supplied by the fan or blowermanufacturer will show the pressures based on the equipmentinlet and outlet flanges.

    To compare the pressures measured during the test to theperformance curve, it is necessary to take into considerationany pressure losses and system effect factor (SEF) between thepressure measuring stations and the fan inlet and outlet flangesto determine the total pressure at the fan inlet and outletflanges.

    Also calculate velocity pressure at the outlet flange.

    Fan static pressure is given by

    FSP = TPo - TP1 - VPo

    where:FSP = fan static pressureTPo = total pressure at fan outletTP1 = total pressure at fan inlet

    VPo = velocity pressure at fan outlet

    Fan static pressure is normally shown on the manufacturer'sperformance curve. This is plotted against flow rate. To correctthe FSP from the test speed and density to that shown on theperformance curve, the following formula is used:

    FSPc = FSP x Nc 2 x dc

    N dwhere:

    FSPc = corrected fan static pressureFSP = test fan static pressureNc = corrected speedN = test speeddc = corrected inlet density

    d = test inlet density

    Performance Evaluation of Candidates 69

  • 7/29/2019 Performance Op Tim Ization

    79/97

    Fan Power Calculation

    Input power to the motor must be calculated in the mannerapplicable to the instrument being used.

    The performance curve supplied by the fan and blowermanufacturers normally shows the input power to the fan orblower. Therefore, the motor input power measured during thetest must be corrected for part-load efficiency to reflect thepercent of full-load power at which the motor is operating.

    If the equipment is V-belt driven, further adjustment of the

    measured power is required. It is necessary to estimate theV-belt drive losses as a function of motor horsepower.

    To correct the measured power to the fan or blower for thespeed and density shown on the manufacturer's performancecurve, the following formula should be used:

    BHPc = BHP x Nc 3 x dcN d

    where:BHPc = corrected input horsepowerBHP = test input horsepower

    = kWmeasured x Effmotor x Effdrive0.746

    Nc = corrected speedN = test speed

    dc = corrected inlet densityd = test inlet density

    70 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    80/97

    GENERAL

    Rotating machinery is a particularly dangerous element of plantequipment due to the tremendous forces that they exert,bothmechanically and electrically. Always employ safety measureswhen carrying out performance tests and exercises. Extremecaution is to be exercised at all times. For the most part, this

    means applying common sense to the situation. However, everyindustrial environment will have specific safety regulations thatmust be followed.

    PLANT REGULATIONS

    General safety items apply to most industrial settings. Always referto existing regulations in specific industrial plants.

    Hard hat, safety glasses,and certified boots must be worn at alltimes.

    Visitors must stay in designated areas.

    Safety meetingsare to be conducted before workcommences to discuss hazardous aspects of the work.

    Safety 71

    C H A P T E R 5

    Safety

  • 7/29/2019 Performance Op Tim Ization

    81/97

  • 7/29/2019 Performance Op Tim Ization

    82/97

  • 7/29/2019 Performance Op Tim Ization

    83/97

    couplings,and bearings, even when these parts are enclosed bysuitable guards.

    During testing, the rotating speeds must never exceed the

    manufacturer's rating or catastrophic failure may result.

    When testing at various points of operation,care should betaken to ensure that the equipment is not operated in anunstable region of the equipment's performance curve. Severevibration and catastrophic equipment failure may result if:

    - a fan is operated in a stall condition

    - a pump is operated in a manner that causes cavitation

    It must always be recognized that the components of fans,pumps, and blowers are highly stressed. Operation and testingshould be done only by knowledgeable and experiencedpersonnel. If there is any doubt as to safety aspects of thework,refer either to a qualified plant engineer or to themanufacturer of the particular equipment involved.

    74 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    84/97

    A - ENGINEERING SPECIALIST PROPOSAL GUIDELINES

    The Performance Optimization Feasibility Study proposal shouldinclude the following outline:

    (1) Cover Sheet

    Study title

    Submitted to (customer name,contact, and location)

    Date submitted

    Submitted by (engineering specialist and company)

    (2) Executive Summary

    (3) Application/Process Description

    Equipment type and size (fan, pump,or blower system)

    Process information (batch, continuous,other)

    Fluid or material moved (air, water, gas, sewage,etc.)

    (4) Current Situation

    Current operating conditions

    Appendices 75

    C H A P T E R 6

    Appendices

  • 7/29/2019 Performance Op Tim Ization

    85/97

    Equipment condition (new, refurbished,etc.)

    Estimated service life remaining

    Present control scheme Future expansion plan if known

    (5) Potential for Energy Savings

    Classify options or measures to be examined into thefollowing general categories:

    a) ASD (electronic, mechanical, other)

    b) Equipment modification (sizing, new designs,etc.)

    c) Process modification (process change,ponyequipment,etc.)

    d) Other (specify)

    Estimated annual savings (on-peak and off-peak kW and

    kWh)(6) Customer Benefits

    (7) Scope of Work

    Objectives of the study

    Project initiatives and methodology

    Project schedule(8) Study Team

    Proposed staff

    Sub-contractors

    Resums for key personnel

    Type of liability insurance, if any

    76 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    86/97

  • 7/29/2019 Performance Op Tim Ization

    87/97

  • 7/29/2019 Performance Op Tim Ization

    88/97

    Estimated service life remaining

    Future expansion plan

    (6) Feasibility Study Methodologya) Load-Data Gathering

    Discuss load-data gathering sources

    Test methodology and instrumentations used

    Field data summary

    Internal inspection of equipment Load-data sensitivity analysis

    b) Development of Load-Duty Cycle

    System curve

    Number of operating hours at each operating point

    Develop lead/duty/cycle chart and/or histogramc) Technical Options Review

    Equipment performance curve

    List at least three alternatives to optimize the system

    Assess viability of each technical option

    Identify ancillary measures to fine-tune system Analysis of Equipment condition

    d) Energy Assessment and Economic Analysis

    Develop load/duty/cycle chart for each technical option

    Calculate demand and energy savings for each option(on-peak and off-peak)

    Appendices 79

  • 7/29/2019 Performance Op Tim Ization

    89/97

  • 7/29/2019 Performance Op Tim Ization

    90/97

    C - GLOSSARY OF TERMS

    Adjustable Speed Drive: A mechanical, hydraulic,or electricsystem used to match motor speed to changes in process load

    requirements.

    Blower: A fan with discharge pressure from 2 psig (55.4 Wg) to36 psig (914.6 Wg).

    Design Point: A point of operation generally based on a duty thatis slightly higher than the highest duty ever expected for theapplication.This point represents a specific set of criteria used to

    select the fan,pump,or blower.Duty: For a fan, the inlet volume flow at a rated fan pressure; for apump, the inlet volume at a rated head.

    Fan: A device that causes flow of gaseous fluid by creating apressure difference on the medium to be transported.

    Field Performance Tests: Field determination of turbo machine

    flow, pressure and power to identify actual points of operation.Head, Dynamic or Total: In flowing fluid, the sum of the staticand velocity pressures at the point of measurement.

    Head, Static: The static pressure of a fluid expressed in terms ofthe height of a column of fluid that it would support.

    Horsepower (Hp): The measure of work equivalent to lifting

    550 lbs one foot in one second,or 745.7 watts.Load Duty Cycle: The relationship between the operating timeand rest time,or repeatable operation at different loads.

    Load: The burden on a motor by the driven machine,sometimessynonymous with 'required power.'

    Motor: A device that takes electrical energy and converts it into

    mechanical energy to turn a shaft.

    Appendices 81

  • 7/29/2019 Performance Op Tim Ization

    91/97

    Net Positive Suction Head (NPSH): The amount of pressure inexcess of the fluid vapor pressure required to prevent theformation of vapor pockets.

    Performance Curve: A plot of the fan,pump, or blowerperformance characteristics from zero delivery to free flow.

    Point of Operation: Where the system curve intersects thepressure and flow curve on the turbo machine's actualperformance curve.

    Pressure, Static: The pressure with respect to a surface at rest in

    relation to the surrounding fluid.Pressure, Total: The sum of the static pressure and the velocitypressure at the point of measurement.

    Pressure, Velocity: The pressure at a point in a fluid existing byvirtue of its density and its rate of motion.

    Process and Instrumentation Diagram (P&ID): A schematic

    of a process that graphically represents the relationship of allprocess equipment to interconnecting piping,duct-work,and theassociated control sensors, actuators, and controllers; usuallyaccompanied by a sequence of operation.

    Process Control: How turbo machine performance is altered tosatisfy system requirements.

    Speed Modulation: A control process whereby the speed of a

    rotating machine is varied between preset speeds to maintain acontrol setpoint.

    Static Efficiency of a Fan: The total efficiency multiplied by theratio of fan static pressure to fan total pressure.

    Static Suction Head: The total system head on the suction sideof a pump with zero flow (can be positive or negative).

    82 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    92/97

    Suction Lift: The head in reference to the system datum that isimposed on the suction of a pump and, for open systems, is theelevation of the pump above the transported fluid exposed to

    atmosphere.System: The combination of turbo machine and the connectedhardware through which flow occurs.

    System Effect Factor: A factor related to the velocity of thetransported medium that corrects for pressure losses due tosystem inlet and outlet conditions that deviate from standard testconditions.

    System Losses: Pressure drop across system hardwarecomponents.

    System Resistance: Resistance to flow resulting from thepressure drop and frictional losses of all system hardware.

    Throttling: An irreversible adiabatic process that involveslowering the pressure of a fluid without work to control flow rate.

    Turbo Machinery: Equipment that uses rotating elements toimpart work on a transported medium, or that uses the energy in aflowing medium to impart work on an external load.

    Variable Inlet Vanes (VIVs): An inlet device that changes thedynamic characteristics of the machine as if it were a differentmachine at each of the vane positions.

    Appendices 83

  • 7/29/2019 Performance Op Tim Ization

    93/97

  • 7/29/2019 Performance Op Tim Ization

    94/97

  • 7/29/2019 Performance Op Tim Ization

    95/97

    ACKNOWLEDGEMENT

    Portions of this publication have been reprinted with thepermission of the Air Movement and Control Association, Inc. and

    the Hydraulic Institute. More information on standards for thedesign, testing, and application of fan,pump,and blower systems isavailable from the above-mentioned associations.

    Fans/Blowers: Air Movement and Control Association, Inc.30 West University DriveArlington Heights, Illinois, 60004-1893Tel: (708) 394-0150

    Fax:(708) 253-0088

    Pumps: Hydraulic Institute30200 Detroit RoadCleveland, Ohio,44145Tel: (216) 899-0010Fax:(216) 892-1404

    Neither of the said associations assume any liability with respect tothe use or misuse of the information, data,designs,concepts,calculations, or source listing,contained in the handbook.

    86 Fan, Pump, and Blower Systems

  • 7/29/2019 Performance Op Tim Ization

    96/97

  • 7/29/2019 Performance Op Tim Ization

    97/97