Penspen Subsea Pipeline Damage Assessment and Repair… - subsea europe 2010.pdf · Anchor Damage...

download Penspen Subsea Pipeline Damage Assessment and Repair… - subsea europe 2010.pdf · Anchor Damage Assessment and Repair AO i fMthd dLiittiAn Overview of Methods and Limitations With

If you can't read please download the document

Transcript of Penspen Subsea Pipeline Damage Assessment and Repair… - subsea europe 2010.pdf · Anchor Damage...

  • 1

    Subsea PipelinesAnchor Damage Assessment and Repair

    A O i f M th d d Li it tiAn Overview of Methods and Limitations With A Case Study From the BP CATS

    Pipeline

    Roland Palmer-Jones

    Penspen Ltd 2010

    [email protected] Integrity, UK

    SUBSEA EUROPE 2010 Paris

    Outline

    Challenges Safety pressure reductions Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options

    Penspen Ltd 2010

    Case Study

  • 2

    Pipeline Damage - Challenges

    Ensure Safety M i t i O ti Maintain Operation

    Prevent Failure Shutdown only if required

    Select the Right Repair Contain pressure Support structure

    Repair Quickly

    Defect Identification, Measurement and Assessment

    Emergency Repair System

    Penspen Ltd 2010

    Repair Permanentlyg y p y

    Safety!

    Industry Practice - Reduce Pressure Prevent Rupture 1.2

    h

    Prevent time dependent failure

    Will Pipe Collapse? Bending Ovalisation Denting External pressure

    Can Pressure be Reduced?

    0.2

    0.4

    0.6

    0.8

    1

    Failu

    re S

    tres

    s/Yi

    eld

    Stre

    ngth

    leak

    rupture

    Penspen Ltd 2010

    Can Pressure be Reduced? Hydrostatic head Phase change

    Even Basic Pressure Reduction Decision Requires Defect + Risk Assessment

    00 1 2 3 4 5 6 7 8

    Normalised Defect Length

  • 3

    Outline

    Challenges Safety pressure reductions

    A t StAssessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options

    Penspen Ltd 2010

    Case Study

    Defect Assessment - Stages

    Incident Reported Preliminary assessment

    ROV + Sonar Survey Secondary assessment

    Detailed Diver/ROV Survey Main assessment

    Penspen Ltd 2010

  • 4

    Preliminary Assessment - Questions

    Incident ReportedShi i Ship reports snagging

    ILI report indicates dent and gouge

    Sonar/ROV survey indicates damage

    Preliminary Assessment Questions Should the pipeline be shutdown?

    Penspen Ltd 2010

    Is a pressure reduction required? Is it safe for a vessel to approach? Will a repair be needed? What type of repair is likely?

    Preliminary Assessment - Data Incident details

    Location, Ship speed,Ship speed, Was anchor abandoned on Pipeline? Did anchor chain break? Leak?

    Ship details Tonnage, Anchor size/weight, Anchor chain weight/breaking strain.

    Pipeline details

    Penspen Ltd 2010

    Pipeline details Diameter, Wall thickness, Material, Coatings, Depth of burial, Operating pressure.

  • 5

    Preliminary Assessment - Approach

    Calculate Damage Resistance Dent Depth vs Impact Energy

    3

    2 De-burial vs Ship kinetic energy Bending vs Ship kinetic energy

    Calculate Available Energy for Damage Anchor + chain weight and velocity

    Concrete crushing Local denting

    Ed 2 100 m p

    OD

    Penspen Ltd 2010

    Local denting Ship mass and velocity

    Pipeline de-burial Global deformation/bending

    Preliminary Assessment - Potential Conclusions

    Significant damage not credible (Small ship + Large pipeline)pipeline) No immediate pressure reduction Proceed with ROV survey Review repair readiness

    Significant damage possible (Large ship + Large pipeline) Reduce pressure Mobilise emergency repair system (grouted sleeve)

    Penspen Ltd 2010

    Mobilise emergency repair system (grouted sleeve) Proceed with ROV

    Significant damage likely (Large ship + Small pipeline) Shutdown or significantly reduce pressure Mobilise emergency repair (mechanical connectors) Proceed with ROV

  • 6

    ROV + Sonar Survey

    Initial survey to: Confirm location Provide general visual information

    ROV Video survey

    De-burial Displacement Coating state Evidence of denting Evidence of gouging

    Currents

    Penspen Ltd 2010

    Cu e ts Sediment/silt Basic measurements CP stab identify bare metal

    Sonar Displacement Seabed scars

    Secondary Assessment- Questions

    Should the pipeline be shutdown?shutdown?

    Is a pressure reduction required? Is it safe for divers? Can the anchor be safely

    removed? Can excavation / exposure be

    carried out?

    Penspen Ltd 2010

    carried out? Can the coating be removed? Will a repair be needed? What type of repair is likely?

  • 7

    Secondary Assessment

    Global Stress analysis of snagging/displacement to

    l t t diti

    Tension

    B di Bending

    As-laid Pipeline

    Displaced Pipeline

    evaluate stress condition Span assessment Stability Identify likely local damage

    type: Plain dent Dent on weld

    CompressionBending Bending

    Direction of Anchor Impact & Drag

    Axial defect (fixed width, 20mm), axial compression, internal pressure (55 bar) DNV

    -270 1.0mm Defect Depth2.0mm3.0mm

    Penspen Ltd 2010

    Dent on weld Dent plus gouge Gouge only

    Calculate critical damage sizes Identifies measurements

    required

    -260

    -250

    -240

    -230

    -220

    -2100 100 200 300 400 500 600 700 800 900 1000

    Axial Defect Length 2c (mm)

    'saf

    e' a

    llow

    able

    tota

    l axi

    al c

    ompr

    essi

    on (M

    Pa)

    4.0mm5.0mm6.0mm7.0mm8.0mm

    Diver Survey

    Excavate Remove coating D t il d i l i ti Detailed visual inspection Geometric inspection Magnetic Particle

    Inspection Ultrasonic inspection

    Penspen Ltd 2010

    Ultrasonic inspection

  • 8

    Final Assessment- Questions

    Should the pipeline be shutdown? Is a pressure reduction required? Will a repair be needed? What type of repair?

    Penspen Ltd 2010

    Final Assessment

    Assess local damage Burst pressure

    Oil Pipeline Pressure history

    800

    1000

    1200

    1400

    ure

    (psi

    )

    Burst pressure Fatigue life Operational restrictions

    Basis of assessment Industry guidance/experience FEA

    0

    200

    400

    600

    22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr

    Time

    Pres

    su

    Penspen Ltd 2010

    Include effects of displacement

    Damage behaviour and failure mechanism Repair performance requirements

  • 9

    Outline

    Challenges Safety pressure reductions Assessment Stages Assessment Stages

    Typical Damage Inspection Options/LimitationsAssessment Methods/Limitations

    R i O ti

    Penspen Ltd 2010

    Repair Options Case Study

    Typical (Possible) Damage

    Rupture Gouge Displacement Plain Dent Dent Plus Displacement

    Penspen Ltd 2010

    Dent on Weld Dent and Gouge Kinked Dent

  • 10

    Inspection Options and Limitations

    Sonar Survey ROV

    Vi l Visual Position CP

    Diver Visual Calliper

    Penspen Ltd 2010

    Straight edge MPI UT Laser scanning

    Assessment Options and Limitations

    Gouge NG18 Displacement FEA or Beam

    Theory (strain limits) ddt

    dd

    c

    c

    f

    11

    1

    Theory (strain limits) Plain Dent Empirical limits, strain

    assessment, EPRG fatigue model Dent Plus Displacement No

    proven methods Dent on Weld EPRG fatigue

    model

    Mt1

    2

    501000

    101

    292.4

    sA

    U

    KN

    Penspen Ltd 2010

    Dent and Gouge EPRG model Kinked Dent No Proven method

    2

    12

    02

    012

    1 )ln(exp2

    2.1028.115.1expcos2

    KKC

    RD

    tRY

    RDY

    AdE vf

  • 11

    Offshore Pipeline Repair Options

    Grinding Clamps / Sleeves Section

    Replacement Connectors Hyperbaric welding Recovery to

    Penspen Ltd 2010

    Recovery to surface

    Outline

    Challenges Safety pressure reductions Assessment Stages Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations

    Repair Options

    Penspen Ltd 2010

    Case Study

  • 12

    Grind repair

    Area to be removed

    Pipe

    Cracking

    Hardened layer

    Penspen Ltd 2010

    Clamps / Sleeves

    Penspen Ltd 2010

  • 13

    Section Replacement

    Penspen Ltd 2010

    Outline

    Challenges Safety pressure reductions Assessment Stages Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options

    Penspen Ltd 2010

    Case Study

  • 14

    Central Area Transmission System (CATS)

    Penspen Ltd 2010

    Details of the Incident

    Late evening on 25th June 2007 a large crude tanker which had been anchored to the north of the CATS Pipeline for a period of time awaiting entry to Teessport Harbour, began to drag its anchor in deteriorating weather

    At approx. 2330 the vessel reported that it had snagged its anchor on a pipeline to the south east of its original position

    After around 10 minutes the vessel was able to free itself from the pipeline and move off to the south

    Harbour Authority reported incident to CATS Terminal staff BP Emergency Response Plans instigated & investigation

    Penspen Ltd 2010

    commenced Incident has been fully investigated by Marine Accident

    Investigation Branch & the report has recently been published (Report No. 3/2008 at www.maib.gov.uk)

  • 15

    Anchor Damage Case Study

    25th June 2007 - A ship was in difficulty in bad weather.

    O f it h hit th 36Anchor Weight circa

    14t

    One of its anchors hit the 36 pipeline and lifted it from under the seabed

    Harbour Authority reported

    Penspen Ltd 2010

    Harbour Authority reported incident to CATS Terminal staff

    BP Emergency Response Plans instigated & investigation commenced

    Initial Assessment

    No evidence of rupture No evidence of leak Potentially severe damage Small pressure reduction imposed Pressure controlled

    Penspen Ltd 2010

    Anchor weight and velocity approx. 15 mm dent (1,7%)

    Gouging? Displacement? Bending?

  • 16

    ROV Survey

    Initial reports showed concrete damage, bending,damage, bending, gouging, and denting

    Penspen Ltd 2010

    Secondary Assessment

    Apparently severe damage Dent gouge calculations indicate

    failure pressure below design for credible combinations.

    P d ti i d

    Penspen Ltd 2010

    Pressure reduction requiredReview repair options

  • 17

    Investigation of Repair options

    BP Project Team established & dedicated to the repair.

    Do nothing or dress defect, assess and leave

    following repair options reviewed in parallel with inspection activities

    Penspen Ltd 2010

    Wet weld, metal build up Deploy existing BP clamp / identify alternatives across the globe Replace section with subsea connectors Replace section with hyperbaric welds Lift pipe and re-lay section with lay barge and tie-in Re-lay new section with lay barge and tie-in

    Detailed Inspection / Work Program

    1. Pipeline depressurisation (in controlled stages from 113 barg to 54 barg) to enable safe diver access

    2. Diverless excavation of pipeline and further ROV inspection2. Diverless excavation of pipeline and further ROV inspection 3. Final excavation of pipe spool (approx. 20m)4. Concrete & Coal Tar Coating removal (approx. 14m)5. Detailed Diver Inspection

    - Close visual inspection- Out of Straightness survey- Ovality Survey- Taut Wire

    Penspen Ltd 2010

    - Magnetic Particle Inspection (welds & defect areas)- Ultrasonic Inspection (welds & defect areas) automated and manual

  • 18

    Inspection Results

    1.5m vertical displacement

    4.5m horizontal displacement

    Damage over a 4m length in middle Damage over a 4m length in middle of spool

    2 Dents within a larger deformed area

    Penspen Ltd 2010

    2 Dents within a larger deformed area

    31mm and 25mm max. depth (3.4%D)

    2 Protrusions of max. 15mm

    Weld deformed

    No weld defects / cracking

    No gouging

    Final Defect Assessment Defects were assessed using

    the Pipeline Defect Assessment Manual (PDAM)

    Limitations: No method for combined No method for combined

    dent and external load. Limited test data for large

    diameter offshore pipelines. FEA of displacement. FEA of dented area EPRG dent fatigue Terminal Inlet Pressure (Previous 12 Months)

    123

    125

    Penspen Ltd 2010

    105

    107

    109

    111

    113

    115

    117

    119

    121

    Time

    Pres

    sure

    (bar

    )

  • 19

    Results of Defect Assessment

    Analysis Findings: No reduction in static strength of pipeline Fatigue life of pipeline reduced by dents on weld

    Repair Decision: Existing sleeve would not fit (too short and pipe bent) Structural, cement grouted sleeve repair selected to

    provide reinforcement of dented area

    Penspen Ltd 2010

    How long did it take?

    Incident occurred - 25 June Initial survey complete 30 June Pipeline shutdown 1 July Pipeline shutdown 1 July Pipe depressurised and safe to dive 18 July Detailed inspection complete 28 July Go ahead for sleeve fabrication 29 July Sleeve Fabrication / Fit-Up Trials complete - 17 August Diving Support Vessel on location - 18 August Pipeline recommissioning commenced - 24 August

    Penspen Ltd 2010

    p g g Delivery of on-spec gas - 1 Sept Rock dump complete 2 Oct

  • 20

    Cross-industry support to release vessels during peak summerperiod both from operators and contractors

    Fantastic support & dedication from key contractors with whomBP already had long term relationships Technip Acergy RBG

    Critical Success Factors

    BP already had long term relationships Technip, Acergy, RBG,JP Kenny, Penspen/APA, Jee, Foundocean, Subsea 7 andothers

    Rapid mobilization of dedicated project team from BP &contractors

    Existing relations with BP global experts simplified assuranceprocesses

    Clear accountabilities within Project Team Pipeline Integrity,Subsea Activities Terminal Ops Sleeve Fabrication JV and

    Penspen Ltd 2010

    Subsea Activities, Terminal Ops, Sleeve Fabrication, JV andReputation Management

    Strong engagement with regulators from Day 1

    HIGH QUALITY, PERMANENT PIPELINE REPAIR SAFELY IMPLEMENTED IN LESS THAN 3

    MONTHS

    Summary There are stages to damage assessment Uncertainties at each stage Data changes Need to use all available data Specialist skills/experience needed Contingency plans/repairs may not be appropriate Proven methods for assessment may not be available Caution is needed

    Penspen Ltd 2010

  • 21

    Repair Management

    Pipeline operator Vessel operator Diving contractor ROV operator ROV operator NDT contractor Defect specialists Welding Re-commissioning Subsea designer Verification agency/consultant Equipment suppliers

    Pipe handling

    Penspen Ltd 2010

    Pipe handling Concrete removal Pipe cutting Clamp or connectors Welding habitat Isolation tools De-watering pigs

    Regulator

    REPAIR: Caution.

    Some wise words on repair*: Do no harm!

    A bad repair can makeA bad repair can make matters worse.

    Repairs need careful engineering, at least as much as a new construction.

    Do not act in haste. A repair is often not a good time to try

    something new.

    Penspen Ltd 2010

    g There is less experience with a new procedure,

    compared to tried and tested designs. Surprises may occur with uncertainty and incompletely planned engineering

    *A C Palmer, R King, Subsea Pipeline Engineering, Penwell. 2004.