Penspen Subsea Pipeline Damage Assessment and Repair… - subsea europe 2010.pdf · Anchor Damage...
Transcript of Penspen Subsea Pipeline Damage Assessment and Repair… - subsea europe 2010.pdf · Anchor Damage...
-
1
Subsea PipelinesAnchor Damage Assessment and Repair
A O i f M th d d Li it tiAn Overview of Methods and Limitations With A Case Study From the BP CATS
Pipeline
Roland Palmer-Jones
Penspen Ltd 2010
[email protected] Integrity, UK
SUBSEA EUROPE 2010 Paris
Outline
Challenges Safety pressure reductions Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options
Penspen Ltd 2010
Case Study
-
2
Pipeline Damage - Challenges
Ensure Safety M i t i O ti Maintain Operation
Prevent Failure Shutdown only if required
Select the Right Repair Contain pressure Support structure
Repair Quickly
Defect Identification, Measurement and Assessment
Emergency Repair System
Penspen Ltd 2010
Repair Permanentlyg y p y
Safety!
Industry Practice - Reduce Pressure Prevent Rupture 1.2
h
Prevent time dependent failure
Will Pipe Collapse? Bending Ovalisation Denting External pressure
Can Pressure be Reduced?
0.2
0.4
0.6
0.8
1
Failu
re S
tres
s/Yi
eld
Stre
ngth
leak
rupture
Penspen Ltd 2010
Can Pressure be Reduced? Hydrostatic head Phase change
Even Basic Pressure Reduction Decision Requires Defect + Risk Assessment
00 1 2 3 4 5 6 7 8
Normalised Defect Length
-
3
Outline
Challenges Safety pressure reductions
A t StAssessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options
Penspen Ltd 2010
Case Study
Defect Assessment - Stages
Incident Reported Preliminary assessment
ROV + Sonar Survey Secondary assessment
Detailed Diver/ROV Survey Main assessment
Penspen Ltd 2010
-
4
Preliminary Assessment - Questions
Incident ReportedShi i Ship reports snagging
ILI report indicates dent and gouge
Sonar/ROV survey indicates damage
Preliminary Assessment Questions Should the pipeline be shutdown?
Penspen Ltd 2010
Is a pressure reduction required? Is it safe for a vessel to approach? Will a repair be needed? What type of repair is likely?
Preliminary Assessment - Data Incident details
Location, Ship speed,Ship speed, Was anchor abandoned on Pipeline? Did anchor chain break? Leak?
Ship details Tonnage, Anchor size/weight, Anchor chain weight/breaking strain.
Pipeline details
Penspen Ltd 2010
Pipeline details Diameter, Wall thickness, Material, Coatings, Depth of burial, Operating pressure.
-
5
Preliminary Assessment - Approach
Calculate Damage Resistance Dent Depth vs Impact Energy
3
2 De-burial vs Ship kinetic energy Bending vs Ship kinetic energy
Calculate Available Energy for Damage Anchor + chain weight and velocity
Concrete crushing Local denting
Ed 2 100 m p
OD
Penspen Ltd 2010
Local denting Ship mass and velocity
Pipeline de-burial Global deformation/bending
Preliminary Assessment - Potential Conclusions
Significant damage not credible (Small ship + Large pipeline)pipeline) No immediate pressure reduction Proceed with ROV survey Review repair readiness
Significant damage possible (Large ship + Large pipeline) Reduce pressure Mobilise emergency repair system (grouted sleeve)
Penspen Ltd 2010
Mobilise emergency repair system (grouted sleeve) Proceed with ROV
Significant damage likely (Large ship + Small pipeline) Shutdown or significantly reduce pressure Mobilise emergency repair (mechanical connectors) Proceed with ROV
-
6
ROV + Sonar Survey
Initial survey to: Confirm location Provide general visual information
ROV Video survey
De-burial Displacement Coating state Evidence of denting Evidence of gouging
Currents
Penspen Ltd 2010
Cu e ts Sediment/silt Basic measurements CP stab identify bare metal
Sonar Displacement Seabed scars
Secondary Assessment- Questions
Should the pipeline be shutdown?shutdown?
Is a pressure reduction required? Is it safe for divers? Can the anchor be safely
removed? Can excavation / exposure be
carried out?
Penspen Ltd 2010
carried out? Can the coating be removed? Will a repair be needed? What type of repair is likely?
-
7
Secondary Assessment
Global Stress analysis of snagging/displacement to
l t t diti
Tension
B di Bending
As-laid Pipeline
Displaced Pipeline
evaluate stress condition Span assessment Stability Identify likely local damage
type: Plain dent Dent on weld
CompressionBending Bending
Direction of Anchor Impact & Drag
Axial defect (fixed width, 20mm), axial compression, internal pressure (55 bar) DNV
-270 1.0mm Defect Depth2.0mm3.0mm
Penspen Ltd 2010
Dent on weld Dent plus gouge Gouge only
Calculate critical damage sizes Identifies measurements
required
-260
-250
-240
-230
-220
-2100 100 200 300 400 500 600 700 800 900 1000
Axial Defect Length 2c (mm)
'saf
e' a
llow
able
tota
l axi
al c
ompr
essi
on (M
Pa)
4.0mm5.0mm6.0mm7.0mm8.0mm
Diver Survey
Excavate Remove coating D t il d i l i ti Detailed visual inspection Geometric inspection Magnetic Particle
Inspection Ultrasonic inspection
Penspen Ltd 2010
Ultrasonic inspection
-
8
Final Assessment- Questions
Should the pipeline be shutdown? Is a pressure reduction required? Will a repair be needed? What type of repair?
Penspen Ltd 2010
Final Assessment
Assess local damage Burst pressure
Oil Pipeline Pressure history
800
1000
1200
1400
ure
(psi
)
Burst pressure Fatigue life Operational restrictions
Basis of assessment Industry guidance/experience FEA
0
200
400
600
22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr
Time
Pres
su
Penspen Ltd 2010
Include effects of displacement
Damage behaviour and failure mechanism Repair performance requirements
-
9
Outline
Challenges Safety pressure reductions Assessment Stages Assessment Stages
Typical Damage Inspection Options/LimitationsAssessment Methods/Limitations
R i O ti
Penspen Ltd 2010
Repair Options Case Study
Typical (Possible) Damage
Rupture Gouge Displacement Plain Dent Dent Plus Displacement
Penspen Ltd 2010
Dent on Weld Dent and Gouge Kinked Dent
-
10
Inspection Options and Limitations
Sonar Survey ROV
Vi l Visual Position CP
Diver Visual Calliper
Penspen Ltd 2010
Straight edge MPI UT Laser scanning
Assessment Options and Limitations
Gouge NG18 Displacement FEA or Beam
Theory (strain limits) ddt
dd
c
c
f
11
1
Theory (strain limits) Plain Dent Empirical limits, strain
assessment, EPRG fatigue model Dent Plus Displacement No
proven methods Dent on Weld EPRG fatigue
model
Mt1
2
501000
101
292.4
sA
U
KN
Penspen Ltd 2010
Dent and Gouge EPRG model Kinked Dent No Proven method
2
12
02
012
1 )ln(exp2
2.1028.115.1expcos2
KKC
RD
tRY
RDY
AdE vf
-
11
Offshore Pipeline Repair Options
Grinding Clamps / Sleeves Section
Replacement Connectors Hyperbaric welding Recovery to
Penspen Ltd 2010
Recovery to surface
Outline
Challenges Safety pressure reductions Assessment Stages Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations
Repair Options
Penspen Ltd 2010
Case Study
-
12
Grind repair
Area to be removed
Pipe
Cracking
Hardened layer
Penspen Ltd 2010
Clamps / Sleeves
Penspen Ltd 2010
-
13
Section Replacement
Penspen Ltd 2010
Outline
Challenges Safety pressure reductions Assessment Stages Assessment Stages Typical Damage Inspection Options/Limitations Assessment Methods/Limitations Repair Options
Penspen Ltd 2010
Case Study
-
14
Central Area Transmission System (CATS)
Penspen Ltd 2010
Details of the Incident
Late evening on 25th June 2007 a large crude tanker which had been anchored to the north of the CATS Pipeline for a period of time awaiting entry to Teessport Harbour, began to drag its anchor in deteriorating weather
At approx. 2330 the vessel reported that it had snagged its anchor on a pipeline to the south east of its original position
After around 10 minutes the vessel was able to free itself from the pipeline and move off to the south
Harbour Authority reported incident to CATS Terminal staff BP Emergency Response Plans instigated & investigation
Penspen Ltd 2010
commenced Incident has been fully investigated by Marine Accident
Investigation Branch & the report has recently been published (Report No. 3/2008 at www.maib.gov.uk)
-
15
Anchor Damage Case Study
25th June 2007 - A ship was in difficulty in bad weather.
O f it h hit th 36Anchor Weight circa
14t
One of its anchors hit the 36 pipeline and lifted it from under the seabed
Harbour Authority reported
Penspen Ltd 2010
Harbour Authority reported incident to CATS Terminal staff
BP Emergency Response Plans instigated & investigation commenced
Initial Assessment
No evidence of rupture No evidence of leak Potentially severe damage Small pressure reduction imposed Pressure controlled
Penspen Ltd 2010
Anchor weight and velocity approx. 15 mm dent (1,7%)
Gouging? Displacement? Bending?
-
16
ROV Survey
Initial reports showed concrete damage, bending,damage, bending, gouging, and denting
Penspen Ltd 2010
Secondary Assessment
Apparently severe damage Dent gouge calculations indicate
failure pressure below design for credible combinations.
P d ti i d
Penspen Ltd 2010
Pressure reduction requiredReview repair options
-
17
Investigation of Repair options
BP Project Team established & dedicated to the repair.
Do nothing or dress defect, assess and leave
following repair options reviewed in parallel with inspection activities
Penspen Ltd 2010
Wet weld, metal build up Deploy existing BP clamp / identify alternatives across the globe Replace section with subsea connectors Replace section with hyperbaric welds Lift pipe and re-lay section with lay barge and tie-in Re-lay new section with lay barge and tie-in
Detailed Inspection / Work Program
1. Pipeline depressurisation (in controlled stages from 113 barg to 54 barg) to enable safe diver access
2. Diverless excavation of pipeline and further ROV inspection2. Diverless excavation of pipeline and further ROV inspection 3. Final excavation of pipe spool (approx. 20m)4. Concrete & Coal Tar Coating removal (approx. 14m)5. Detailed Diver Inspection
- Close visual inspection- Out of Straightness survey- Ovality Survey- Taut Wire
Penspen Ltd 2010
- Magnetic Particle Inspection (welds & defect areas)- Ultrasonic Inspection (welds & defect areas) automated and manual
-
18
Inspection Results
1.5m vertical displacement
4.5m horizontal displacement
Damage over a 4m length in middle Damage over a 4m length in middle of spool
2 Dents within a larger deformed area
Penspen Ltd 2010
2 Dents within a larger deformed area
31mm and 25mm max. depth (3.4%D)
2 Protrusions of max. 15mm
Weld deformed
No weld defects / cracking
No gouging
Final Defect Assessment Defects were assessed using
the Pipeline Defect Assessment Manual (PDAM)
Limitations: No method for combined No method for combined
dent and external load. Limited test data for large
diameter offshore pipelines. FEA of displacement. FEA of dented area EPRG dent fatigue Terminal Inlet Pressure (Previous 12 Months)
123
125
Penspen Ltd 2010
105
107
109
111
113
115
117
119
121
Time
Pres
sure
(bar
)
-
19
Results of Defect Assessment
Analysis Findings: No reduction in static strength of pipeline Fatigue life of pipeline reduced by dents on weld
Repair Decision: Existing sleeve would not fit (too short and pipe bent) Structural, cement grouted sleeve repair selected to
provide reinforcement of dented area
Penspen Ltd 2010
How long did it take?
Incident occurred - 25 June Initial survey complete 30 June Pipeline shutdown 1 July Pipeline shutdown 1 July Pipe depressurised and safe to dive 18 July Detailed inspection complete 28 July Go ahead for sleeve fabrication 29 July Sleeve Fabrication / Fit-Up Trials complete - 17 August Diving Support Vessel on location - 18 August Pipeline recommissioning commenced - 24 August
Penspen Ltd 2010
p g g Delivery of on-spec gas - 1 Sept Rock dump complete 2 Oct
-
20
Cross-industry support to release vessels during peak summerperiod both from operators and contractors
Fantastic support & dedication from key contractors with whomBP already had long term relationships Technip Acergy RBG
Critical Success Factors
BP already had long term relationships Technip, Acergy, RBG,JP Kenny, Penspen/APA, Jee, Foundocean, Subsea 7 andothers
Rapid mobilization of dedicated project team from BP &contractors
Existing relations with BP global experts simplified assuranceprocesses
Clear accountabilities within Project Team Pipeline Integrity,Subsea Activities Terminal Ops Sleeve Fabrication JV and
Penspen Ltd 2010
Subsea Activities, Terminal Ops, Sleeve Fabrication, JV andReputation Management
Strong engagement with regulators from Day 1
HIGH QUALITY, PERMANENT PIPELINE REPAIR SAFELY IMPLEMENTED IN LESS THAN 3
MONTHS
Summary There are stages to damage assessment Uncertainties at each stage Data changes Need to use all available data Specialist skills/experience needed Contingency plans/repairs may not be appropriate Proven methods for assessment may not be available Caution is needed
Penspen Ltd 2010
-
21
Repair Management
Pipeline operator Vessel operator Diving contractor ROV operator ROV operator NDT contractor Defect specialists Welding Re-commissioning Subsea designer Verification agency/consultant Equipment suppliers
Pipe handling
Penspen Ltd 2010
Pipe handling Concrete removal Pipe cutting Clamp or connectors Welding habitat Isolation tools De-watering pigs
Regulator
REPAIR: Caution.
Some wise words on repair*: Do no harm!
A bad repair can makeA bad repair can make matters worse.
Repairs need careful engineering, at least as much as a new construction.
Do not act in haste. A repair is often not a good time to try
something new.
Penspen Ltd 2010
g There is less experience with a new procedure,
compared to tried and tested designs. Surprises may occur with uncertainty and incompletely planned engineering
*A C Palmer, R King, Subsea Pipeline Engineering, Penwell. 2004.