KEGIATAN : The Support to the Development of Islamic of Higher Education ProjectPEKERJAAN : Construction of Nine (9) New Buildings and Supporting Infrastructures of UIN Raden Fatah PalembangLOKASI : UIN Raden Fatah Palembang
PREPARATION WORKS : 2.244 % : PT Patroon Arsindo KSO PT Griksa CiptaCENTRE ADMINISTRATION BUILDING : 10.895 % PMSC : PT Deta DeconINTEGRATED LIBRARY : 16.949 % - Team Leader : Mardiana DaoedINTEGRATED LABORATORY : 13.631 % RENCANA S/D MINGGU INI : Penyedia Jasa : PT Nindya Karya (Persero)FACULTY OF ISLAMIC ECONOMY AND BUSINESS : 14.693 % REALISASI S/D MINGGU INI : - PM : Satriyo Fajar DewantoroFACULTY OF SCIENCE AND TECHNOLOGY : 14.124 % DEVIASI : No. Loan : IND - 0164, February 16th 2012FACULTY OF TARBIYAH : 8.032 % Nilai Pekerjaan : Rp 289.618.674.000,00FACULTY OF PSYCHOLOGY : 7.878 % Waktu Pelaksanaan : 480 Hari Kalender (16 Oktober 2018 - 7 Februari 2020) SUPPORTING INFRASTRUCTURE : 11.556 % Waktu Pemeliharaan : 365 Hari Kalender (8 Februari 2020 - 6 Februari 2021)
100.000 %
Jangka Waktu Pelaksanaan : 480 hari kalenderLaporan Mingguan Ke : 47Waktu Pelaksanaan : 330 hari
Sisa Waktu Pelaksanaan : 150 hari
No1 Undangan Rapat Koordinasi
2
3
4
1 Perbaikan jalan kerja 11 1 Perbaikan jalan kerja 11
2 Pekerjaan pembesian (SW, kolom, Balok & plat) 12 2 Pekerjaan pembesian (SW, kolom, Balok & plat) 12
3 Pekerjaan bekisting (SW, kolom, Balok & plat) 13 3 Pekerjaan bekisting (SW, kolom, Balok & plat) 13
4 Pekerjaan pengecoran (SW, kolom, Balok & plat) 14 4 Pekerjaan pengecoran (SW, kolom, Balok & plat) 14
5 Pemasangan instalasi air bersih, air kotor & air bekas 15 5 Pemasangan instalasi air bersih, air kotor & air bekas 15
6 Pemasangan instalasi hydrant 16 6 16
7 Pengetesan kuat tekan beton 17 7 Pemasangan instalasi hydrant 17
8 18 8 Pengetesan kuat tekan beton 18
9 19 9 Pekerjaan Instalasi Listrik 19
10 20 Pekerjaan Pemasangan Keramik Lantai 10
1. 1.
2. 2.
3. 3.
Pekerja
Memo Penggunaan Scaffolding
- Percepatan pekerjaan dilaksanakan secara overlaping dengan
memaksimalkan kondisi site.
- Keterlambatan -2,629% akan tertutup setelah CCO disyahkan.
memaksimalkan kondisi site.
- Konsisten terhadap sekuens pekerjaan yang sedang berjalan
(metode kerja). (metode kerja).
Rencana Kerja
Gedung Library Scaffolding belum dibongkar, mengakibatkan
pekerjaan arsitek belum dilaksanakan.
Dilakukan pembongkaran scaffolding pada area yang sudah cukup
umur betonnya dan dilakukan penambahan tenaga kerja finishing.
Progress mengalami keterlambatan sebesar -2,629%.
Jumlah
AKTIVITAS PEKERJAAN MINGGU INI
Tower Crane (3 unit)
Target progress sampai dengan akhir bulan September adalah
68,73% dan minggu ke 47 realisasi progress tercapai 59,426%.
Pekerjaan arsitektur (Pasangan dinding, pintu & jendela)
Pekerjaan instalasi listrik
Pekerjaan pemasangan AC Cassette & Split Pekerjaan Pemasangan Keramik Lantai
Pekerjaan Cat Sealer
Pendatangan material pipa struktur rangka atap
Genset
Tenaga Kerja
Keahlian Material Digunakan Peralatan Digunakan
Pemasangan rangka struktur atap
Karyawan 58
Pekerjaan Fasade
Pekerjaan pemasangan AC Cassette & Split
Pipa PVC
NK
PMSC
RENCANA PEKERJAAN MINGGU DEPANPemasangan rangka struktur atap
Pekerjaan struktur tangga
Pendatangan material bata ringan
Pekerjaan arsitektur (Pasangan dinding, pintu &
PMSC NK
NK
PIU, PPK, NK
Pekerjaan Plafond
Pekerjaan Plafond
PMSC
Besi beton
Multiplek
Batu belah
PENYELESAIAN MASALAH
Beton
Floordeck
Mandor 5
502
Kabel (Elektrikal)
Sisa progress yang harus dicapai setiap minggunya oleh kontraktor
sampai akhir September adalah 3,101%, sehingga dilakukan
percepatan penyelesaian pekerjaan struktur pada gedung Library,
Psychology, Laboratory dan Febi.
Pekerjaan Girder Jembatan
Pekerjaan Cat Sealer
PERMASALAHAN / HAMBATAN
DOKUMENTASI PELAKSANAAN
Concrete Pump Long Boom
Concrete Bucket
Bar Bender, Bar Cutter
Compressor
Pekerjaan Plafond
Pekerjaan Girder Jembatan
Service Crane
Stationery Pump
Wiremesh
Bata ringan
Pemasangan rangka plafond
Pekerjaan Fasade
RESUME LAPORAN HARIAN MINGGU INI
Steel pipe
Excavator
Fabrikasi Rangka Struktur Atap
Pekerjaan Struktur Tangga
DATA UMUM
Memo Target Kualitas
DEDC
PMSC
KURVA S
PROGRESS PEKERJAANBOBOT PEKERJAAN
62.055%
59.426%
Perihal
-2.629%
EVALUASI WAKTU PELAKSANAAN
LAPORAN SURAT MENYURAT MINGGU INIDari Untuk
PMSC NK Surat Balasan Detail Warna Cat
Pekerjaan Cat Sealer
Palembang, 11 September 2019Konsultan PMSC
Mardiana DaoedIr.Team Leader
PENGGUNA JASA PROJECT MANAGEMENT AND SUPERVISION CONSULTANTRESUME LAPORAN
MINGGU KE - 4710 SEPTEMBER 2019-4 SEPTEMBER 2019 PERIODE
TOTAL BOBOT1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69
16-Oct 24-Oct 31-Oct 07-Nov 14-Nov 21-Nov 28-Nov 05-Dec 12-Dec 19-Dec 26-Dec 02-Jan 09-Jan 16-Jan 23-Jan 30-Jan 06-Feb 13-Feb 20-Feb 27-Feb 06-Mar 13-Mar 20-Mar 27-Mar 03-Apr 10-Apr 17-Apr 24-Apr 01-May 08-May 15-May 22-May 29-May 05-Jun 12-Jun 19-Jun 26-Jun 03-Jul 10-Jul 17-Jul 24-Jul 31-Jul 07-Aug 14-Aug 21-Aug 28-Aug 04-Sep 11-Sep 18-Sep 25-Sep 02-Oct 09-Oct 16-Oct 23-Oct 30-Oct 06-Nov 13-Nov 20-Nov 27-Nov 04-Dec 11-Dec 18-Dec 25-Dec 01-Jan 08-Jan 15-Jan 22-Jan 29-Jan 05-Feb(Rp.) (%) 23-Oct 30-Oct 06-Nov 13-Nov 20-Nov 27-Nov 04-Dec 11-Dec 18-Dec 25-Dec 01-Jan 08-Jan 15-Jan 22-Jan 29-Jan 05-Feb 12-Feb 19-Feb 26-Feb 05-Mar 12-Mar 19-Mar 26-Mar 02-Apr 09-Apr 16-Apr 23-Apr 30-Apr 07-May 14-May 21-May 28-May 04-Jun 11-Jun 18-Jun 25-Jun 02-Jul 09-Jul 16-Jul 23-Jul 30-Jul 06-Aug 13-Aug 20-Aug 27-Aug 03-Sep 10-Sep 17-Sep 24-Sep 01-Oct 08-Oct 15-Oct 22-Oct 29-Oct 05-Nov 12-Nov 19-Nov 26-Nov 03-Dec 10-Dec 17-Dec 24-Dec 31-Dec 07-Jan 14-Jan 21-Jan 28-Jan 04-Feb 07-Feb
PREPARATION WORKS 6,498,081,367.95 2.244%BUILDING ADMINISTRATIONSTRUCTURE WORKS BUILDING ADMINISTRATIONARCHITECTURE WORKS BUILDING ADMINISTRATIONMECHANICAL & ELECTRICAL BUILDING ADMINISTRATION 7,984,196,659.31 2.757%INTEGRATED LIBRARYSTRUCTURE WORKS INTEGRATED LIBRARYARCHITECTURE WORKS INTEGRATED LIBRARYMECHANICAL & ELECTRICAL INTEGRATED LIBRARY 17,006,604,691.37 5.872%INTEGRATED LABORATORYSTRUCTURE WORKS INTEGRATED LABORATORYARCHITECTURE WORKS INTEGRATED LABORATORYMECHANICAL & ELECTRICAL INTEGRATED LABORATORY 10,893,009,687.76 3.761%FACULTY OF ISLAMIC ECONOMY AND BUSINESSSTRUCTURE WORKS FACULTY OF ISLAMIC ECONOMY AND BUSINESSARCHITECTURE WORKS FACULTY OF ISLAMIC ECONOMY AND BUSINESSMECHANICAL & ELECTRICAL FACULTY OF ISLAMIC ECONOMY AND BUSINESS10,060,044,579.76 3.474%FACULTY OF SCIENCE AND TECHNOLOGYSTRUCTURE WORKS FACULTY OF SCIENCE AND TECHNOLOGYARCHITECTURE WORKS FACULTY OF SCIENCE AND TECHNOLOGYMECHANICAL & ELECTRICAL FACULTY OF SCIENCE AND TECHNOLOGY 9,357,080,268.25 3.231%FACULTY OF TARBIYAHSTRUCTURE WORKS FACULTY OF TARBIYAHARCHITECTURE WORKS FACULTY OF TARBIYAHMECHANICAL & ELECTRICAL FACULTY OF TARBIYAH 5,836,405,170.73 2.015%FACULTY OF PSYCHOLOGYSTRUCTURE WORKS FACULTY OF PSYCHOLOGYARCHITECTURE WORKS FACULTY OF PSYCHOLOGYMECHANICAL & ELECTRICAL FACULTY OF PSYCHOLOGY 5,635,236,644.78 1.946%EXTERNAL WORKS
Total 289,618,674,166.51 100.00%Rencana Mingguan 0.033% 0.033% 0.362% 1.160% 1.307% 1.307% 2.380% 2.380% 1.912% 1.949% 0.933% 0.946% 0.905% 0.905% 0.992% 1.024% 1.010% 1.010% 0.953% 1.101% 1.246% 1.175% 1.077% 1.147% 1.090% 1.172% 1.170% 1.128% 1.079% 1.197% 1.204% 1.266% 0.000% 0.000% 1.826% 1.935% 1.762% 1.832% 1.958% 1.901% 1.860% 1.914% 1.891% 1.917% 2.240% 2.240% 2.225% 2.242% 2.198% 2.238% 2.206% 2.235% 2.218% 2.142% 2.001% 1.923% 1.882% 1.775% 1.667% 1.547% 1.547% 1.475% 1.385% 1.325% 1.261% 1.223% 1.202% 1.126% 1.126%Kum. Renc Mingguan 0.000% 0.033% 0.067% 0.429% 1.589% 2.897% 4.204% 6.584% 8.965% 10.876% 12.825% 13.758% 14.704% 15.609% 16.515% 17.507% 18.530% 19.540% 20.550% 21.503% 22.604% 23.849% 25.025% 26.101% 27.249% 28.338% 29.510% 30.680% 31.808% 32.887% 34.084% 35.288% 36.554% 36.554% 36.554% 38.380% 40.315% 42.077% 43.909% 45.867% 47.769% 49.629% 51.543% 53.433% 55.350% 57.590% 59.830% 62.055% 64.296% 66.494% 68.732% 70.938% 73.173% 75.391% 77.533% 79.534% 81.457% 83.340% 85.114% 86.782% 88.329% 89.876% 91.351% 92.736% 94.061% 95.322% 96.545% 97.747% 98.873% 100.000%
URAIAN PEKERJAAN
TAHUN 2018 TAHUN 2019 TAHUN 2020
62.055%
Tampak Gedung SAINTEK Tampak Gedung SAINTEK Tampak Gedung TARBIYAH Tampak Gedung LIBRARY
Tampak Gedung ADM Tampak Gedung LABORATORY Tampak Gedung FEBI Tampak Gedung PSYCHOLOGY
Aktifitas Pemasangan Partisi Glass Aktifitas Pemasangan Keramik Lantai Aktifitas Pemasangan Jendela
Pekerjaan Atap Metal RoofAktifitas Pasangan Dinding Pit Lift
Aktifitas Pekerjaan Fasade
Rapat Kordinasi Mingguan
59.426%
2.225%
1.448%