Penang Transport Master Plan2016/05/05 · 4 Halcrow’s TMP Recommendations • Penang Transport...
Transcript of Penang Transport Master Plan2016/05/05 · 4 Halcrow’s TMP Recommendations • Penang Transport...
1
Penang Transport Master PlanPenang State Government’s
Response to NGOs’ Statement
5 May 2016
2
Content
1. Halcrow’s TMP recommendations.
2. Positive public response on PTMP.
3. Traffic growth main driver for ridership.
4. Multiple transit systems – common in all cities.
5. Tram (street level transit) not feasible.
6. Tram in heritage zone.
7. Monorails suitable as transit systems.
8. Highways still needed.
9. Financial model for PTMP.
3
Halcrow’s TMP Recommendations.
4
Halcrow’s TMP Recommendations
• Penang Transport Master Plan (PTMP) report which was done by Halcrow had been adopted as Penang State Government’s official document on 25 March 2013.
• Based on the Halcrow's recommendations, State Government had come out with several project as per the study, which included:
Ø 3 MAJOR HIGHWAYS & UNDERSEA TUNNEL constructed by Zenith BUCG Ø BICYCLE MASTER PLAN which now progressively done by MBPPØ PENANG ACCESSIBILITY ACTION GROUP (PAAG) to look into the accessibility
improvement plan
• The PTMP report by Halcrow was the foundation used during Request for Proposal (RFP) exercise – Project Delivery Partner (PDP).
• All the short-term, long-term including cost effective measures recommended by Halcrow were carried out by different parties in a holistic way.
5
Positive Public Response on PTMP.
6
• To-date the State Government has proactively conducted a TOTAL OF 18 OPEN DIALOGUES with all relevant stakeholders.
Ø Overall received POSITIVE SUPPORT.
• The State Government welcomes feedback and comments from all parties, including Non-Governmental Organisations (NGOs).
Positive Public Response on PTMP
• Why is the State Government committed to implement the PTMP?Ø Encourage use of public transportØ Mitigate traffic congestion
7
Traffic growth main driver for ridership.
8
Ridership Model
• Other drivers:Ø Department of Statistics’ population projectionØ Population growth from future developments
• TRAFFIC GROWTH is a main driver to the ridership model:Ø HIGHER THAN POPULATION GROWTHØ Traffic growth is driven by economic growth, tourist arrivals, etc.
Population (DOS)1.6%
Vehicle (JPJ) 7.1%
Traffic (LLM) 4.5%
Traffic (HPU)2.7%
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Vehicle (JPJ) - Registered Vehicles
State Government has appointed independent consultant for peer review of PTMP project feasibility and ridership.
9
Multiple transit systems – common in all cities.
10
Transit Systems Dependent on Demand etc.• Transit systems for each corridor are decided from various factors:
i. TARGET 40% PUBLIC TRANSPORT MODE SHAREii. TRAVEL DEMAND & DEVELOPMENTiii. ALIGNMENT CONSTRAINTS iv. SYSTEM CAPACITY, PERFORMANCE & SAFETY
• NOT ALL LINES WILL BE IMPLEMENTED AT ONCE
• The PTMP is used to as a GUIDE to ensure proper future planning.Ø Can be reviewed every 5 years
11
Appropriate Systems To Match Demand
Demand (PPHPD) – Mode
CorridorHalcrow TMP
Year 2030Improved TMP
Year 2055*
1. George Town - Bayan Lepas 2,200 - Tram 14,700 – LRT
2. George Town - Ayer Itam 1,300 - Tram 6,200 – Monorail
3. George Town - Tg Bungah 1,200 - Tram 5,800 – Monorail
4. Bayan Lepas extension to SRS no mention 7,500 – LRT
5. George Town - Butterworth no mention 6,000 – LRT
• Most appropriate system for the Komtar-Penang Airport corridor – LRT system. Why?Ø Airport passengers increase from 6.5 MIL TO 20 MIL PASSENGERSØ Bayan Lepas industrial zone will be expanded by 1,000 ACRES.
12
Comparison Between Systems
LRT Monorail Tram BRT BusTypical capacity (PPHPD) 18,500 7,000 4,500 2,500 500Speed (kph) 35 30 20 25 15Journey time (mins) 40 45 70 55 90
Headway (mins) 2 3 4 3 5No of car/train (or “veh”) 4 4 2 2 1
No of pax/car@ 4.8 pax/sq m
160 90 160 60 60
Construction costs/km (RM mil) @ 2015 prices
220 170 >40*(at-grade) 110
LRT has higher performance in terms of CAPACITY, SPEED and JOURNEY TIME.
*To have a dedicated tramway with high capacity, cost is estimated to be more than RM220mil per km – utility relocations, land acquisitions, time, etc.
13
Multiple Systems in Major Cities
• Established cities are known to run MULTIPLE TRANSIT SYSTEMS functioning as a single integrated network:
LONDON PARIS AMSTERDAM• Underground metro• Light rail• Tram• Commuter rail• High-speed train
• Underground metro• Commuter rail• Tram• High-speed train
• Underground metro• Light rail• Tram
High Speed 1
Different transit systems in London
Underground metro Light rail
14
Trams (street level transit) not feasible.
15
• To achieve State Government’s objective – 40% public transport mode share:
Ø Proposed systems needs HIGH CAPACITY, hence the need for DEDICATED CORRIDOR
No Planned Corridor For Rail Transit
• New transit lines need to be PARACHUTED ON THE ROAD SPACE TO MINIMISE LAND ACQUISITION AND SOCIAL IMPACT
16
Adverse Impacts With Trams
• If the State Government were to maintain the number of traffic lanes:
Ø Will have to ACQUIRE ADJACENT LAND AND BUILDINGS (costly exercise)Ø Massive social consequences and PUBLIC OUTCRY
• If the State Government were to build trams:Ø Will have to SACRIFICE TRAFFIC LANES to accommodate dedicated
corridorØ Severe TRAFFIC IMPACT to already congested road system
17
Major Inconvenience With Trams
• During construction, there will be long periods of disruption to the local communities:
Ø TOTAL ROAD CLOSURES (> 2 years) to allow for utilities relocations Ø Extend construction period FROM 6 TO 8 YEARS
Tram works roadworks at Princes Street, Edinburgh, Scotland, UK
18
Total Road Closures With Trams
19
Businesses Will Suffer During Utilities Relocation
20
Utilities relocated under Road Lanefor future maintenance/replacement Utilities under Tram Lane to be relocated
3.35m Tram Lane 1 Lane 1
3.5m 3.35mTram Lane 2
6.7m TRAM LANES
2.5mWalkway
2.2m
Excavation
Massive Utilities Relocation
• Relocation of underground utilities is required. • NO OPPORTUNITY for future utility maintenance under tramway.
21
BEFORE AFTER
JLN PERUSAHAAN JELUTONG
LEBUHRAYA TUN DR LIM CHONG EU
TR
AM
TR
AM
SIGNALISED T-JUNCTION
Traffic Conflicts Inevitable – During Operation
22
BEFORE AFTER
JLN MAGAZINELEBUHRAYA TUN DR LIM CHONG EU
TRAM
TRAM
Motorists Will Bear The Brunt – During Operation
23
0
3
6
9
12
15
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2013 2014 2015
CountPerson
Moving average 3 years
Tram-Pedestrian Accidents – During Operation
SOURCE: http://transportsafety.vic.gov.au
24
0
50
100
150
200
250
300
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2013 2014 2015
CountRoad vehicle
Moving average 3 years
Tram-Road Vehicle Accidents – During Operation
SOURCE: http://transportsafety.vic.gov.au
25
Street Level Transit System Is Not Cheaper• SYDNEY CBD AND SOUTH EAST 12km LRV PROJECT (street level),
reported a budget overrun of AUD$600mil to AUD$2.2bil for AUD$183mil per km
• Proposed 21km Bayan Lepas LRT with a similar capacity of 18,000 passengers per hour per direction is estimated to cost about RM220mil per km
Transit System Length Cost
(per km)Total Cost Grade Level
Sydney LRV Project
12km AUD$183mil AUD$2bil Street Level
Bayan Lepas LRT
30km RM220mil RM7bil Elevated
AUD$1 = RM3
26
Komtar-Penang Airport Corridor.
27
• Bayan Lepas LRT is the first TMP to be implemented:Ø Studies show it is ECONOMICALLY VIABLE (EIRR > 10%)
1ST TMP Project – Bayan Lepas LRT
• It is an LRT system: Ø ELEVATED Ø The MAIN N-S BACKBONE connecting Komtar to the airportØ CONNECTS TO SEBERANG PERAI in future
• As lines are implemented at different times, INVARIABLY THERE WILL BE DIFFERENT SYSTEMS (system technology changes rapidly with time)
• More important is the SEAMLESS TRANSFER of transit passengers:Ø PHYSICAL INTEGRATION @ interchanges at Sia Boey and The LightØ SINGLE TICKETING SYSTEM
28
Komtar-Penang Airport Corridor – Transit System Has To Be Elevated
• For the Komtar-Penang Airport dedicated corridor, OVER 91% OF TOTAL ALIGNMENT HAS TO BE ELEVATED (19km out of 21km). Why?
Ø To avoid re-signalising / overhaul road junctionsØ To avoid traffic impact to connecting/ adjacent roadsØ To avoid lane closures and removal of parking spaceØ To avoid encroachment into buildings and land acquisitions
ELEVATED RAIL TRANSIT = ELEVATED LRT
29
RENESASBOSCH
2 lanes service road withSide Parking
11.1 m
One Lane Service Road with Side Parking
7.1 m
FenceFenceFenceFence
Traffic lane11.3 m
Traffic lane10.9 m
Divider2.6 m
Divider6.4 m
Divider2.4 m
ALONG FIZ STRETCH = 2KM
SideParking
SideParking
FenceFence
RENESASBOSCH
SideParking
2 lanes service road withSide Parking
11.1 m
Tram Stop3.0 m
Tram Lane3.65 m
Tram Lane3.65 m
Separator0.6m
Separator0.6m
Traffic lane7.6 m
Traffic lane7.6 m
5.7 m 1.5 mWalkway
3.0 mSpace
forLink Bridge
5.0 mOne Lane
Service Road
Fence
Pedestrian Link Bridge
Reduction of traffic lanes from dual three to dual two
FIZ SOUTHSTATION
Side Parking Removed
Note: No drop-off / lay-by areas
Komtar-Penang Airport Corridor - Lane Closures and Removal Of Parking Space (Tram)
FIZ SOUTH STATIONØ Lane reductionØ Side parking removed
30
Komtar-Penang Airport Corridor - Encroachment, Blocked Access And Land Acquisition (Tram)
Tram Lane3.65 m
Tram Lane3.65 m
Traffic Lane5.0 m
Divider/ Walkway8.33m
1 Traffic Lane+ 1 access lane to
school
Shoulder3.00m
Compound8.00m
SCHOOL
SCHOOL
SINGLE STOREY HOUSES COMPOUND
SINGLE STOREY HOUSES COMPOUND
JLN SULTAN AZLAN SHAH (ELEVATED)
JLN SULTAN AZLAN SHAH (ELEVATED)
- Tram lane encroaches into school compound (internal car park affected)
- Access to / from school affected / blocked by tram lanes
- Land acquisition (school compound)
3.6m
Lo
t B
ou
nd
ary
Buf
fer
Zon
e 0.
6m
Reinstatement of
Walkway1.5m
RO
W
Kwang Hwa SchoolØ EncroachmentØ Land
acquisitionØ Lane reductionØ Blocked
access
31
Elevated Rail Transit@ Lebuhraya Tun Dr Lim Chong Eu
KOMTAR
MACALLUM
BANDAR SRI PINANG
SKYCAB
EAST JELUTONG
THE LIGHT
JLN MAGAZINE
JLN C
.Y. C
HOY
LEBUH SG PINANG
JLN AHMAD NOR
LEB
UH
RAY
A TU
N D
R L
IM C
HO
NG
EU
TINGKAT SG GELUGOR 5
SUNGAI PINANG
IRR
JLN PERUSAHAAN JELUTONG
OUTER BYPASS
7.2km
Legend
Elevated Section
CH 0km
SKYCAB
GB LRT
1
2
3
4
5
6
7
8910
11
12
REASONS FOR ADOPTING ELEVATED RAIL TRANSIT :
• Loc 1 Crossing Lim CE expressway
• Loc 2-5 Crossing major T-junctions
• Loc 6 IJM Reclamation Area – Future Junctions
• Loc 7 Crossing Lim CE expressway
• Loc 8 Crossing Jalan Akuarium
• Loc 9-10 Crossing RECSAM’s access road
• Loc 11 Crossing Outer Bypass
• Loc 12Crossing Hindu Temple’s access
• Loc 13Crossing T-junction
13
GAT LEBUH MACALLUM
GAT LEBUH CECIL
JLN
AK
UA
RIU
M
32
GELUGOR
JLN ISMAIL NAGORE
JLN SG GELUGOR 2
JLN SUNGAI DUA
LORONG SG DUA
LORONG SG DUA 1PERSIARAN BATU UBAN
JLN PANTAI JEREJAK 1JLN AZIZ IBRAHIM
LIN
TAN
G
NIP
AHLEBUH NIPAH 1
JLN KAMPUNG
RELAU
JALAN MAHSURI
USM
BATU UBAN
PESTA
SUNGAI NIBONG
BUKIT JAMBUL
SPICEJL
N S
ULT
AN
AZ
LA
N S
HA
H PENANG 1ST BRIDGE
ELEV
ATE
D H
IGH
WA
Y
Elevated Rail Transit@ Jalan Sultan Azlan Shah
JLN SUNGAI DUA
JLN SUNGAI 2
JLN TUN DR AWANG
LegendElevated Section
REASONS FOR ADOPTING ELEVATED RAIL TRANSIT :
• Loc 14 Crossing Jalan Sultan Azlan Shah
• Loc 15Crossing Jln Sg Dua
• Loc 16 Crossing Lebuh Nipah 1
• Loc 17 Crossing Kwang Hwa School’s Access
• Loc 18To cater for future underpass
• Loc 19Crossing Jalan Tun Dr Awang
• Loc 20Crossing Jln Mahsuri
14
At-Grade Section
15
16
17
1819
20
1.8km
33
FIZ NORTH
FIZ SOUTH
SG TIRAM
PENANG AIRPORT
PERMATANG DAMAR LAUT
HILIR SG KLUANG 4
JLN T
OKONG ULAR
JLN MAYANG PASIR
JLN SG TIRAM
1JLN SG TIRAM
3
PENANG 2ND BRIDGEAIRPORT
EXPANSION PLAN
Elevated Rail Transit@ FIZ to Permatang Damar Laut
JALA
N M
AYA
NG
PA
SIR
JLN
PE
RM
ATA
NG
DA
MA
R L
AU
T
JALAN TENGAH
LegendElevated Section
CH 20.9km
21 22
23
24
25
At-Grade Section
REASONS FOR ADOPTING ELEVATED RAIL TRANSIT :
• Loc 21 Crossing Jalan Tengah
Ø Hospital & School access
• Loc 22Crossing Jalan Sultan Azlan Shah
• Loc 23Crossing JKR Elevated U-turn
• Loc 24Crossing Airport Roundabout
• Loc 25Crossing Kampung Area & Jln Permatang Damar Laut
11.9km
Element Length (km)
Elevated 19.1 (91%)
At-Grade 1.8 (9%)
Total 20.9
34
Tram in Heritage Zone.
35
Heritage Preservation in George Town
• Heritage Tram (street level) is in line with George Town as a HERITAGE CITY.Ø MOBILITY WITHIN HERITAGE ZONE Ø TOURIST ATTRACTION
• NO ELEVATED STRUCTURES within the World Heritage Site.
36
Monorails suitable as transit systems.
37
Monorails are SAFE & Suitable• There are 2 TYPES OF MONORAILS – transit and theme parks. • Major cities with transit monorails – CHINA, JAPAN, SOUTH KOREA, CHINA,
INDIA, BRAZIL AND UNITED STATES.
Sao Paulo Monorail Las Vegas Monorail
Emergency walkway
Emergency walkway
38
LOCATION COUNTRY NAME YEAR OPENED LENGTH
Chongqing China Chongqing Monorail (Lines 2 & 3)
2005 86.8 km
Mumbai India Mumbai Monorail 2014 19.54 km
Kitakyushu Japan Kitakyushu Monorail 1985 8.8 km Naha, Okinawa Japan Okinawa Monorail 2003 12.8 km Osaka Prefecture Japan Osaka Monorail 1990 28 kmTokyo Japan Tokyo Monorail 1964 17.8 km Western Tokyo Japan Tama Toshi Monorail Line 1998 16 km Kuala Lumpur Malaysia Kuala Lumpur Monorail 2003 8.6 km
Daegu S. KoreaDaegu Metro
(Line 3) 2015 23.9 km
Las Vegas Strip US Las Vegas Monorail 2004 6.3 km
São Paulo Brazil São Paulo Metro (Line 15)
2014 2.9 km
Operational Transit Monorails In Other Countries
39
Highways still needed.
40
• Eg. Full electronic tolling – took >25 years to implement in Klang Valley.
Highways Still Needed
• Lessons from Singapore – Despite achieving 60% public transport mode share, the island republic is still building new highways.
As of 2014, there were 163 km of expressways in Singapore, with new highways in the pipeline.
• 40% public transport mode shift CANNOT HAPPEN OVERNIGHT – NEEDS TO BE ENCOURAGED PROGRESSIVELY.
• HIGHWAYS STILL NEEDED to cater for the GROWTH OF REMAINING 60% PRIVATE VEHICLES.
41
Financial model for PTMP.
42
Sale of Reclaimed Land To Finance The PTMP
• Reclaimed land and PTMP components BELONG SOLELY TO THE STATE GOVERNMENT
• Proceeds from the SALE OF RECLAIMED LAND VIA PUBLIC AUCTION will be used to fund the PTMP components that are to be implemented.
• Implementation of each PTMP component (whether rail or road) depends on:• ECONOMIC VIABILITY • FUND AVAILABILITY
• Each PTMP component to be implemented will be tendered out via OPEN TENDER.
• The State Government is studying options for SUSTAINABLE RAIL OPERATIONS
43
THANK YOU