PED 2 Report Group 8

download PED 2 Report Group 8

of 10

Transcript of PED 2 Report Group 8

  • 8/19/2019 PED 2 Report Group 8

    1/21

     

    PROCESS EQUIPMENT

    DESIGN –

     II

    ASSIGNMENT-I

    SUBMITTED TO:

    PROF. JAYANTA CHAKRABORTY

    SUBMITTED BY:GROUP 8

    RAHUL KUMAR 13CH10034

    RAHUL YADAV 13CH10035

    RAJA BARNWAL 13CH10036

    RAKESH CHHIPA 13CH10037

  • 8/19/2019 PED 2 Report Group 8

    2/21

     

    TABLE OF

    CONTENTS

    CONTENT PAGE

    PROBLEM STATEMENT 03

    BASIC THEORY 04

    PROCESS DEISGN 05

    MECHANICAL DESIGN 14

    REFERENCES 21

  • 8/19/2019 PED 2 Report Group 8

    3/21

     

    PROBLEM STATEMENT

    A sieve plate column is to be designed to separate 8000 kg/hr of feedhaving 40 mole % Methanol (A) & 55 mole % Water (B) into an

    overhead product containing 96 mole % A and a bottom product

    containing mole 98 mole % B. The feed enters as an equilibrium

    mixture of 30% liquid & 70% vapor. A reflux equal to 1.5 times the

    minimum is to be used. Also an external reboiler is necessary to

    remove the bottom product from the reboiler. The condensate

    C & the

    reflux enters the column at this temperature. Assume the Murphree

    P ffiiy 70%. Gi αAB=3.91 

    (a) Complete the process design calculation.

    (b) Mechanical design of the column.

    (c) Enclose a drawing showing the details of the column.

  • 8/19/2019 PED 2 Report Group 8

    4/21

     

    BASIC THEORY

    Optimization stems from the need for improvement. Typical problems in

    chemical engineering arise in process design, process control, model

    development, process identification, and real-time optimization.

    Distillation, being the most common industrial process for separation of

    chemical components, is the focal unit of petroleum refining. While distillation

    can be economically and easily scaled to different production levels, it is highly

    energy intensive, consuming up to 80-90% of the total energy of a typical

    petrochemical process. This makes the need for optimization essential to

    maximize profitability of the entire process.

    The performance of a distillation column is determined by many factors, such

    as distillation feeds, internal liquid and fluid flow conditions, state of trays and

    even ambient conditions which change over time, which makes the response

    of real-time optimization to these changes a key contributor to successful

    operation. In this particular process, detailed analysis of the operation and

    design of the distillation column is performed involving the optimisation of

    reflux ratio subject to various practical constraints and also the different

    problems and cost analysis regarding the setting up of a distillation column inreal time.

    In this design problem our task is to first find optimum value of reflux ratio at

    which the total cost (operating + fixed cost) for setting up the distillation

    facility for required separation of methanol is minimum. There are two

    opposite factors contributing to the total cost. As the reflux ratio is increased

    the number of trays required for a given degree of separation reduces which in

    turn reduces the column height. However because of higher liquid and vapour

    flow rates there is a increase in column diameter. Also the operating cost

    increases because of higher heat duty of both the re-boiler and the condenser.

    The optimum value of reflux ratio is determined by determining the minima in

    a plot of Total cost Vs reflux ratio. The total cost calculated in our case is

    actually annualised total cost which is calculated by dividing the total cost by

    im “if” f qim f kig  into account the interest

    rates on various cost items.

  • 8/19/2019 PED 2 Report Group 8

    5/21

     

    PROCESS DESIGN

    In this problem, we need to separate methanol from a mixture of water and

    methanol by using a bubble cap distillation column.

    Given Data

    Mol. Wt. (Methanol)(MWm) 32.04 gm/mol

    Operating Pr. 14.7 Psig

    Temperature (T) 148.5 F

    Liquid Density (rhoL) 47.1645 lb/ft3

    Vapour Density (rhoV) 0.08 lb/ft3

    Liq. Surface Tension(sigma) 19.3 dyne/cm

    Liquid Rate(L) 14875 lb/hr

    Vapour Rate(V) 25581 lb/hr

    Liquid rate (expressed in gpm) = 39.32 gpm

    Vapour rate (expressed in cfs) = V*1/rhoV*3600

    = (25581*1)/(.08*3600)

    = 88.82292 cfs

  • 8/19/2019 PED 2 Report Group 8

    6/21

     

    Cost optimization

    F = 8000/(0.45*32+0.55*18) = 329.2181 kmol/hr

    D = =(0.45-0.02)/(0.96-0.02)*F = 150.5998 kmol/hr

    B = F-D = 178.6183 kmol/hr

    Roptimum = Rmin *  (R/Rmin)optimum

    Refer to Excel sheet for detailed calculations. The optimization has been done

    in MATLAB. The following is the result)

    Roptimum = 1.3984

    Theoretical number of trays have been derived from McCabe Thiele method.For calculation of column diameter, qc, qr, and cost of column, condenser,

    reboiler, reboiler, cooling water and total annual cost, refer attached excel

    sheet. Also refer [4]

    Theoretical number of trays = 20

    McCabe Thiele (Equilibrium curve and Equilibrium line)

  • 8/19/2019 PED 2 Report Group 8

    7/21

     

    232000

    233000

    234000

    235000

    236000

    237000

    238000

    239000

    1 1.02 1.04 1.06 1.08 1.1 1.12

       T   o   t   a    l   A   n   n   u   a    l   C   o   s   t

    R/Rmin

    Cost Optimization

    R/Rmin |optimum = 1.0393

  • 8/19/2019 PED 2 Report Group 8

    8/21

     

    Calculation of tower diameter:

    F(lv) = (L /V)*sqrt(rhoV/rhoL)

    = 0.023948418

    Assume tray spacing = 24 inch

    Cab= 0.4 [1](Figure 14.4)

    Cab(corrected) = 0.4*(sigma/20)0.2

     

    = 0.4*(19.3/20)0.2

     

    = 0.397159956 (No measurable change)

    Vapour velocity term (Un) = 0.4/(sqrt(rhoV/(rhoL-rhoV)))= 0.4/((sqrt(0.08/(47.1645-0.08)))

    = 9.704071311 fps

    Take flooding = 75%

    Net tray area (An) = (1/0.75)*(88.82292/9.704071311)

    = 12.20933562 ft2 

    Take 12% for downcomerColumn cross section area (At) = An/0.88

    = 13.87424503 ft2

    Dt = sqrt(4*At/pie)

    = 4.203003381 ft

    Next available standard diameter, Dn = 6 ft

    From [1] Table 14.5, we get 24 inch tray spacing is suitable for a 6 ft diameter

    tower

    Area (new), An = pie* Dn2/4

    = 28.27433388 ft2 

    From [1] Table 14.2, we get REVERSE FLOW

    We take,

    Riser area 0.1 * At

    Down flow area 0.12 * At 

  • 8/19/2019 PED 2 Report Group 8

    9/21

     

    Max. active area 0.88 * At 

    Side weir length 0.62 * Dn

    Max liq. flow path 0.3 * Dn 

    Dynamics slot submergence of 1.5 inch (Assumed)

    Estimated tray pressure drop (ht)

    = 0.53*(rhoV/rhoL)*(V/(0.1*An))+0.8*1.5+1

    = 0.53*(0.08/47.1645)*(88.82292/(0.1*28.27433388))+0.8*1.5+1

    = 2.228241208 inch of fluid

    Tray Layout

    Tower diameter, Dn = 6 ft

    Tray spacing = 24 inch

    Flow Type = Reverse Flow

    Layout = Triangular

    Bubble Cap Calculations

    Bubble cap diameter = 4 inch

    Area of 1 cap = pie*42/4

    = 12.56637061 in2 

    Total bubble area, ABt = 0.7*An 

    = 19.79203372 ft2 

    Total number of bubble caps = ABt*144/area of 1 cap

    = 226.8

    Actual number of bubble caps = 227

    Service is non-corrosive. We use CARBON STEEL – A 53B

  • 8/19/2019 PED 2 Report Group 8

    10/21

  • 8/19/2019 PED 2 Report Group 8

    11/21

     

    Summary (areas) 

    Area  Formulae Per tray (ft2) % of An

    Riser Area 4.8*227/144 7.566666667 26.76160895

    Slot Area 8.12*227/144 12.80027778 45.27172181Downcomer Area 0.12*An 3.392920066 12

    Active Area 0.88*An  24.88141382 88

    Area under apron Area under baffle 0.5 1.768388257

    Tower area An 28.27433388 100

    Net area 0.88*An 24.88141382 88

    Flooding

    Vapour velocity based on net area, U = V/An 

    = 88.82292 cfs/24.88141382 ft2 

    = 3.569850062 ft/s

    % flooding = U/Un = 36.787 % (Under limits)

    Entrainment

    Phi = 0.055 [1] (Figure 14.5)

    It is well within limits

    Shape factor = Rs = 0.167/0.333 = 0.501501502

    For Rs = 0.50, we have Cs = 0.74 [1] (Figure 14.6)

    Q max = Cs*Slot area*sqrt(slot height*(rhoL-rhoV)/rhoV)

    = 229.7973954 cfs

    Vapour load = 100*V/Q max = 38.65 % of slot capacity

    Slot opening = 55% [1] (Figure)

    Slot height = 1*0.55 = 0.55 inch

  • 8/19/2019 PED 2 Report Group 8

    12/21

     

    Liquid crest over weir

    Liquid load = 39.32 gpm

    HOW = 0.48*(L/lw)2/3

     = 0.51 inch

    From Figure 14.7 [1],

    L/lw2.5

     = 2.2522

    Weir correction = Fs = 1.04

    HOW (corrected) = Fs*HOW = 0.53 inch

    Liquid gradient

    Arithmetic average flow width = 2.5 ft (approximated)Liquid load per unit width = L/2.5 = 15.728 gpm/ft

    CD = 0.75 [1] (Figure 14.9 and 14.10)

    Hl = 2.75+0.53+1 = 5 (approximated)

    Del = 0.5 inch (using figure 14.9 and 14.10)

    Vapour pressure Drop

    hcd = 0.53*(0.08/47.1645)*(D15/(0.1*B30)) = 0.03 inch of liquid

    Mean dynamic slot seal, hda = 0.5+0.53+0.5/2 = 1.28 inch of liquid

    Fva = 1.62 [1](Equation 14.40)

    hal = 0.6*hda = 0.98 inch of liquid [1](figure 14.15 and equation 14.37)

    Total tray pressure drop, ht = 0.03+0.51+0.98 = 1.52 inch of liquid

    Vapour distribution Ratio

    hc = 0.03+0.51 = 0.54 inch of liquid

    Rcd = 0.5/0.54 = 0.925

  • 8/19/2019 PED 2 Report Group 8

    13/21

     

    Downcomer dynamics

    had = 0.2 inch of liquid [1](using Equation 14.41 and 14.42)

    hdc = 6.2 inch of liquid [1](using Equation 14.43)

    hfd = 6.2/.4 =15.5 inch of liquid

    tdc = 3.8 seconds [1](using Equation 14.47)

    TRAY AND BUBBLE CAP DESIGN (all dimensions in mm)

  • 8/19/2019 PED 2 Report Group 8

    14/21

     

    MECHANICAL DESIGN 

    Shell ID (Di) 1828.8 mm

    No. of trays 20

    Tray spacing (t) 609.6 mm

    Hole Diameter (dh) 101.6 mm

    Plate Thicknes (tp) 101.6 mm

    Weir height (hw) 69.85 mm

    Material for tray Carbon Steel A 53B

    A 53BShell material Carbon Steel

    Allowable stress for shell mat.(Pa) 1.03E+08 PaDensity of shell mat 7850 kg/m3

    skirt height 25.4 Mm

    Operating pr (p) 112405 Pa

    Design pr (pD) 123645.5 Pa

    Operating temp 64.7 to 100 *C

    Design temp 110 *C

    Top disengaging space 609.6 mm

    Bottom separator space 1000 mmInsulation material taken Asbestos

    Insulation thickness considered 50 mm

    Density of insulation 270 kg/m3

    Formulae source: [2] and [6]

    Shell thickness

    J = 0.8

    Minimum shell thickness, ts = p*Dt/(2*f*J-p)

    = 1.367819 mm

    After adding corrosion allowance, ts = 8mm

    Do = Di+2*ts 

    = 1844.8 mm

    th = pD*Di/(2*J*Pa-0.2*pD)

    = 1.367001 mm

  • 8/19/2019 PED 2 Report Group 8

    15/21

     

    Adding corrosion allowance, th = 8 mm

    Column height = (t + 19*t + 20*tp + 1000)/1000 = 15.224 m

    (Refer to Excel sheet along with this file for the calculations)

    Stresses developed in column

    Formulae

    Source [2]

    Axial Stress (f as) 8910204 Pa Eq. 9.3.1

    Circumferential Stress (f cs) 17820408 Pa Eq. 9.3.1

    Compressive stresses caused by dead loads

    Wshell  54066.25 N

    Mshell  6620.357 kg

    f(dead wt shell) 29434.89 Pa Eq. 9.3.2

    M(insulation) 1191.137 kg

    f(dead wt insulation) 955285 Pa Eq. 9.3.3

    Active Area 2.31 m2

    Liquid depth on trays 83.2977 mm

    Mass of liquid 5002.86 Kg

    f(dead wt liquid) 4012265 Pa Eq. 9.3.4

    Stress induced by column attachments

    f(dead wt attachments) 5309488 Pa Eq. 9.3.5

    f(dead total) 10306473 Pa Eq. 9.3.6

    f(dead total)

  • 8/19/2019 PED 2 Report Group 8

    16/21

     

    Below the guy ring

    (Formulae used, [2] Eq. 9.3.8-9.4.4)

    M(w,H,guy)(max) 26723.1 N

    f(wind,H,below guy) 5269799 Pa

    f(com guy) 641969.5 Pa

    Analysis of stress

    For upwind side

    Total stress 82920516 Pa

    For downwind side

    Total stress 92472689 Pa

    Torispherical Head has a range of 0.1 to 1.5 MPa. It is, therefore,

    suitable to use for our column design.

    Design of head

    Do  1844.8 mm

    ro  110.688 mm 0.06*Do 

    ho  312.394 mm Eq. 4.2.22

    Do2/4*Ro  461.2 mm

    (Do*ro/2)^0.5 319.5287 mm

    hE, the minimum of above 3 312.394 mm

    hE/Do  0.169338 mm

    As the diameter of the vessel is not very large, head can be fabricated

    from single plate, therefore J = 1

    t/DoC 0.000544

    C 3.679807 Table 4.1A

    t/Do  0.002

    t 3.689856 mm Eq. 4.2.20Corrosion allowance 2 mm

  • 8/19/2019 PED 2 Report Group 8

    17/21

     

    Uncorroded plate thickness 6 mm

    Torispherical Head Volume 0.623133 m3

    Skirt Support Design

    Mshell  6620.357 Kg

    Wshell  64879.5 N

    Desity of Carbon Steel 7850 Kg/m3

    WD  47937.64 N

    Wmin  112817.1 NWi  11673.14 N

    Wl  391901.7 N

    Wmax  516392 N

    Period of vibration at min dead wt

    Tmin  0.178766 s

  • 8/19/2019 PED 2 Report Group 8

    18/21

     

    Tmax  0.382461 s

  • 8/19/2019 PED 2 Report Group 8

    19/21

     

    Design of skirt bearing plate

    Stress_max(compressive) 0.099138 MN/m2

    Thickness of bearing plate, tbp 5.363147 mm

    According to IS code [3] 7 mm

    As thickness is

  • 8/19/2019 PED 2 Report Group 8

    20/21

     

    Area available from shell reinforcrment

    As 0.003650572 m2

    Area available from nozzle

    reinforcrment, An 2H1(tn-tr'-c)

    tr' 0.004160723 m

    H1 0.05396295 m

    An 0.000953987 m2

    Reinforcement area available from shell and

    nozzle is

    As+An 0.004604559 m2

    Area remained to be

    compansated

    A-(As+An) 0.00227287 m2

    Ar >= 0.00227287 m2

    tp 0.010538229

    Ring Pad dimension

    Inner Diameter, do 0.25 m

    Outer diameter 0.448 m

    Thickness 0.025 m

  • 8/19/2019 PED 2 Report Group 8

    21/21

     

    REFERENCES 

    [1] Smi, B.D., “Dig f Eqiibim Sg P”, MGw-Hill Book Co.

    [2] Introduction to Chemical Equipment Design by B.C Bhattacharya, 2012

    [3] IS : 2825-1969, the Indian Standard codes

    [4] Plant Design and Economics for Chemical Engineers Fourth Edition

    by Max S. Peters & Klaus D. Timmerhaus

    [5] R.H.Py, D.W.G; Py’ Cmi Egi’ Hbk7 Eii 

    [6] R. K. Si, C Ri’ Chemical Engineering: Chemical

    Engineering Design (vol. 6), Butterworth-Heinemann, 3rd ed. 1999