PDO xxxxxxxxx PRE-START-UP AUDIT
description
Transcript of PDO xxxxxxxxx PRE-START-UP AUDIT
MSE/4- PRE START UP
PDO xxxxxxxxx
PRE-START-UP AUDIT
MSE/4- PRE START UP
AgendaAgenda
the audit team audit objectives schedule recommendations reporting
MSE/4- PRE START UP
Team membersTeam members
xxxxxxxxxx PDO PDO (Leader)(Leader)
MSE/4- PRE START UP
HSE PerformanceHSE Performance
“There must always be a gap between … aspirations and performance … But a gap between policy and performance is unacceptable”
Phil Watts - Shell EP HSE Conference 22 September 1997
MSE/4- PRE START UP
Terms of ReferenceTerms of Reference
Objective To assess the readiness of all To assess the readiness of all
resources, controls, procedures and resources, controls, procedures and services to support the operation of services to support the operation of the new facility.the new facility.
MSE/4- PRE START UPM-15 07/03/98
Generic Objective & StrategyGeneric Objective & Strategy
Objective:Objective: To provide independent assurance that HSETo provide independent assurance that HSE
management system is effectivemanagement system is effective
StrategyStrategy Look for previously unidentified problemsLook for previously unidentified problems
Focus on gaps between areas of responsibilityFocus on gaps between areas of responsibility
Investigate identified deficiencies in depthInvestigate identified deficiencies in depth
assess any residual risksassess any residual risks
find underlying causesfind underlying causes
Record all areas investigated, noting anyRecord all areas investigated, noting anyomissionsomissions
MSE/4- PRE START UP
StandardsStandards
Applicable Oman laws and regulations Group HSE policies and commitments PDO and contractor policies, standards
and procedures Group and SIEP HSE guidelines such
as EP95 000
MSE/4- PRE START UP
Audit ProcessAudit Process
• Terms of referenceTerms of reference• Audit programmeAudit programme• EP95-0130 EP95-0130
FamiliarisationFamiliarisation
Review & TestingReview & Testing
ReportingReporting
Site visit Interviews Test findings
Drafting EditingReport
Finalisation Agree findingsPresentFindings
StudyDocumentation
MSE/4- PRE START UP
Terms of ReferenceTerms of Reference
ScopeThe scope is limited to those The scope is limited to those
facilities, resources and controls facilities, resources and controls necessary to operate the xxxxxxxxxx necessary to operate the xxxxxxxxxx Expansion Facilities. Expansion Facilities.
Exclusions:Exclusions:Corporate HSE issues not directly Corporate HSE issues not directly
related to the Facilities.related to the Facilities.
MSE/4- PRE START UP
Specific issues Specific issues 11Demonstration that HSE risks are ALARP Demonstration that HSE risks are ALARP
Design, installation, commissioning Design, installation, commissioning Future operationFuture operation
HSE CaseHSE Case
Close out of audits and reviewsClose out of audits and reviewsHAZOP close outHAZOP close out
Fitness for purpose hardwareFitness for purpose hardwareConstructed to designConstructed to design
Effectiveness of change controlEffectiveness of change control
MSE/4- PRE START UP
Specific issues 2Specific issues 2
CommissioningCommissioningPlans & ProceduresPlans & ProceduresPersonnelPersonnelConcurrent operations risksConcurrent operations risks
ProceduresProceduresOperating, MaintenanceOperating, Maintenance
Availability and adequacy Availability and adequacy
Emergency Emergency Understood and exercisedUnderstood and exercised
MSE/4- PRE START UP
Specific issues 3Specific issues 3
Operations plans for start-upOperations plans for start-upOrganisationOrganisationResponsibilitiesResponsibilities
Contractor / PDO Contractor / PDO
InterfacesInterfaces CommunicationsCommunications
Resources & servicesResources & servicesPersonnelPersonnelSpares, consumablesSpares, consumables
Environmental compliance Environmental compliance
MSE/4- PRE START UP
Audit ProgrammeAudit Programme
Sat 31/5 Opening Presentations
Doc. Review
Sun 1/6 Coastal Interviews
Mon 2/6 Visit Site - Compile notes
Tue 3/6 Return from Site
Wed 4/6 Compile Report
Sat 7/6 Draft Report/Final Presentation
Wed 11/6 Issue Final Report
MSE/4- PRE START UP
Audit opinionsAudit opinions
The IAC defines 4 possible audit opinions:GoodFairPoor (equivalent to IAG Unsatisfactory)Unacceptable
The definitions are in terms of:the level of concernthe inference for senior management
MSE/4- PRE START UP
Audit opinion derivationAudit opinion derivation
Based principally upon an assessment of severity and number of Findings
Definition of Few and Many:
Few 20
Many 40
each Finding to contain only one weakness
MSE/4- PRE START UP
AUDIT OPINIONAUDIT OPINION
Serious High MediumHigh +
Medium
Nil Nil Many -Nil Few Nil or Few -
Nil Few Few or Many Many1 or 2 Nil or Any Nil or Any -
Nil Many Nil or Any ->2 Any Any -
Fair
Poor
Unacceptable
Good
Classification of FindingsMost Favourable
Audit Opinion
Nil Nil Nil or Few -
Few Few 20 Findings Many 20 Findings Many 40 40 FindingsFindings
MSE/4- PRE START UPM-11 07/03/98
HSE Management SystemHSE Management SystemLeadership and Commitment
Policy and StrategicObjectives
Management Review
Corrective Action &Improvement
Audit
Organisation, ResponsibilitiesResources, Standards & Doc.
Corrective Action &Improvement
Monitoring
Planning & Procedures
Hazard and EffectsManagement
Implementation
Corrective Action
MSE/4- PRE START UP
Audit Recommendations Audit Recommendations
For a Pre Start-Up audit, an indication is given, in the classification of Findings of: those that should be closed out prior to the
introduction of hydro-carbons - classified (I)those that should be closed out prior to
close out of this project - classified (C)those that are not directly related to project
close out - classified (F)
MSE/4- PRE START UP
123
Weakness Classification Matrix Weakness Classification Matrix
High: Though not serious, essential to be brought to Management attention. Includes medium weaknesses as repeat from previous reports.
Low: No major HSE impact at process level, correction will assure greater effectiveness/efficiency in process concerned.
Serious: Exposes OU to a major extent in terms of achievement of corporate HSE objectives or results.
Medium: Could result in perceptible and undesirable effect on achievement of HSE objectives.
People Assets Environ-ment
Repu-tation
Severity
0
1
2
3
4
5
Noinjury
Slightinjury
Minorinjury
Majorinjury
Singlefatality
Multiplefatalities
Nodamage
Slightdamage
Minordamage
Localdamage
Majordamage
Extensivedamage
Noeffect
Noimpact
Slighteffect
Slightimpact
Minoreffect
Minorimpact
Localisedeffect
Consider-able
impact
Majoreffect
Nationalimpact
Inter-nationalimpact
Massiveeffect
Never heard of in
EP industry
A
LowLow
MediumMedium
HighHigh
Has occurred in EP industry
B
Has occurred inthe audited OU
C DHappens
several times a year in the audited OU
EHappens
several times a year in the
audited facility
SeriousSerious
MSE/4- PRE START UP
Report PrinciplesReport Principles
Report is collective view of teamReport is collective view of team no reference to sourcesno reference to sources whole team review whole reportwhole team review whole report facts reported are as agreed by all the teamfacts reported are as agreed by all the team judgements are by consensus as far as practicablejudgements are by consensus as far as practicable wording agreed to as to intended meaningwording agreed to as to intended meaning audit leader has casting vote in case of disagreementaudit leader has casting vote in case of disagreement where possible, root causes identifiedwhere possible, root causes identified
Final draft report before team disbandsFinal draft report before team disbands no later changes, only minor (punctuation, grammar) editing in COno later changes, only minor (punctuation, grammar) editing in CO final report within two weeks final report within two weeks
MSE/4- PRE START UP
THE END THE END
MSE/4- PRE START UP
Structure of QuestionnairesStructure of Questionnaires
Subsidiary Subsidiary QuestionnaireQuestionnaire
FacilitiesFacilities
Subsidiary Subsidiary QuestionnaireQuestionnaire
Start-UpStart-Up
Subsidiary Subsidiary QuestionnaireQuestionnaire
DrillingDrilling
Subsidiary Subsidiary QuestionnaireQuestionnaire
EnvironmentEnvironment
Subsidiary Subsidiary QuestionnaireQuestionnaire
HealthHealth
Subsidiary Subsidiary QuestionnaireQuestionnaire
FacilitiesFacilities
Subsidiary Subsidiary QuestionnaireQuestionnaire
SeismicSeismic
Generic Questionnaire (Generic Questionnaire (common to all HSE Audits)common to all HSE Audits)
Leadership & CommitmentLeadership & Commitment Policy & Strategic ObjectivesPolicy & Strategic Objectives Organisation, Responsibilities, Resources, Contractor Management.Organisation, Responsibilities, Resources, Contractor Management. Communications, HSE-MS Documentation, Standards & Change ControlCommunications, HSE-MS Documentation, Standards & Change Control Hazards and Effects ManagementHazards and Effects Management Planning & ProceduresPlanning & Procedures Implementation & MonitoringImplementation & Monitoring Audit Audit Management ReviewManagement Review
MSE/4- PRE START UP
EP-HSE Audit Method EP-HSE Audit Method
Focus on RiskFocus on Risk OU Staff involvedOU Staff involved Based on OU / Contractor standardsBased on OU / Contractor standards Bottom up ApproachBottom up Approach Significance & breadth of findings Significance & breadth of findings Assessment of the 33 HSE MS sub elements of Assessment of the 33 HSE MS sub elements of
the HSE MS Self Assessment Questionnaire the HSE MS Self Assessment Questionnaire (levels 1-4)(levels 1-4)
Follow up: OU responsibilityFollow up: OU responsibility
Audit of HSE MS, fully covering H, S and Audit of HSE MS, fully covering H, S and Sampling ProcessSampling Process Questionnaire basedQuestionnaire based
MSE/4- PRE START UP
Auditors will:Auditors will: operate in pairs operate in pairs (sometimes three)(sometimes three) make an appointment to see youmake an appointment to see you
no surprise visitsno surprise visits
try to make it as easy as possibletry to make it as easy as possible be only interested in facts, not speculationbe only interested in facts, not speculation
(interested in your view in how to improve)(interested in your view in how to improve) possibly use a questionnaire in the interviewpossibly use a questionnaire in the interview ask open ended questions ask open ended questions
like “How ..”, “In what way…”like “How ..”, “In what way…”
interview a “vertical slice” of the organizationinterview a “vertical slice” of the organization look for the good as well as the less than adequatelook for the good as well as the less than adequate
HSE Audit OverviewHSE Audit Overview