pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Final Report Ravi Road.pdf · The project...
Transcript of pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Final Report Ravi Road.pdf · The project...
1
Punjab Cities Governance Improvement Project
Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab
REPORT Ravi Road Subdivision, Lahore
September 2015
NEC Consultants (Pvt.) Ltd.
2
Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab
September 2015 NEC Consultants Pvt. Ltd Perfect SITE, 22 KM Ferozepur Road, Near Gujju Matta Metro Bus Station, Lahore +92-42-35273741-46, www.nec.com.pk [email protected] This study was assigned by The Urban Unit, Punjab
3
DISCLAIMER No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying, recording or information storage and retrieval system, without prior written permission of the USPMSU. A publication of the Urban Sector Planning and Management Services Unit (Private) Limited, the opinion expressed in the document are solely those of the authors and publishing them does not in any way constitute an endorsement of the opinion by the USPMSU.
ACKNOWLEDGEMENTS This report has been prepared by The Urban Unit (Urban Sector Policy & Management Unit), P&D Department, Government of Punjab. The Urban Unit, under the Punjab Cities Governance Improvement Project (PCGIP)-DLI-4 is supporting WASA Lahore for implementing Energy Audit Management Opportunities. Energy management opportunities have been extracted from the energy audits of WASA pumps. The Team Dr. Nasir Javed Engr. Abid Hussainy Engr. Ali Raza Shafqat Ullah Muhammad Rizwan Kashif Shaukat Adnan Khan Editing & Layout By: Ms. Madiha Qamar Printed in Pakistan Copyright: Urban Sector Planning and Management Services Unit (Private) Limited.
4
CONTENTS Contents 4 List of Annexure 4 List of Figures 4 List of Tables 4 List of Acronyms and Abbreviations 5 Glossary 5 1.0 Introduction 7
1.1 Background 7 1.2 Methodology 7 1.3 Scope 8
2.0 Energy Audit Findings 9 2.1 Pumping system efficiency 10 2.2 Electricity consumption trend 11 2.3 Pumping system efficiency improvement potential 13 2.4 Interventions for the improvement of WASA stations 14
LIST OF ANNEXURE
I Energy Audit Reports 2 Selected Pictures
LIST OF FIGURES
I Pumping system efficiency category 11 2 Unit electricity consumption trend 13
LIST OF TABLES
1 Detail of WASAs pumps 8 2 Detail of Ravi Road subdivision 9 3 Typical overall pumping system efficiency classification 10 4 Detail of motor loading and pumping system efficiency 10 5 Detail of water discharge and electricity consumption 12 6 System energy efficiency potential of pumps 13
7A Interventions & investment required in WASA stations-Ravi Road Subdivision 15
7B Interventions & investment required in WASA stations-Ravi Road Subdivision 17
5
LIST OF ACRONYMS AND ABBREVIATIONS
Bhp Brake Horsepower Cusec Cubic Feet per Second Ehp Electrical Horsepower Gpm Gallon Per Minute Hp Horsepower kVA Kilo Volt Ampere kW Kilo Watt kWh Kilo Watt Hour LESCO Lahore Electric Supply Company m/s Meter Per Second m3/hr Cubic Meter Per Hour MCB Fuses or Miniature Circuit Breaker Mm Millimeter MS Mild Steel Psig Pound Per Square Inch (Gauge) RPM Revolution Per Minute TDH Total Dynamic Head VFD Variable Frequency Drive WASA Water and Sanitation Agency Whp Water Horsepower
GLOSSARY
Discharge Pressure
The pressure obtained at center line of pump discharge pipe using a calibrated gauge (psig). Discharge pressure is converted to feet and expressed as “Discharge Head”.
Brake Horsepower
The output horsepower of a motor to a pump; may also be used to refer to the required input horsepower to the pump itself.
Deep Well Turbine Pump
A turbine pump installed inside a well casing below the pumping water level in the well.
Discharge Head Head measured above center line of pump discharge pipe.
Drawdown The measured distance that a well’s water level changes from standing/static level to operating pumping level during observed test conditions.
Dynamic Head The sum of the pressure and the pumping head developed by a pump
Friction Head The head required to overcome the fluid friction in a pipe or water system
Friction Losses
Energy losses associated with moving water against rough surfaces. In water pumping applications, it is the water pressure lost as a result of contact between moving water and a pipeline or open channel.
GPM per Foot Drawdown
The ratio of capacity (GPM) to drawdown feet is useful in determining the well’s performance.
Head Alternate term for pressure. One pound per square inch (psi) = 2.31 feet of water head
Overall Plant The ratio of the water horsepower (the overall output of the plant)
6
or Pumping System Efficiency
to input horsepower (the power input). The overall output can also be defined as the amount of horsepower required to deliver the measured capacity (water gallons per minute) and the measured total head.
Pumping Water Level
The well’s operating water level below center line of discharge pipe as observed during test condition
Static Water Level The well’s water level obtained when pumping plant is at rest.
Suction Head Head measured above center line of pump suction intake. Most often obtained with calibrated bourdon tube pressure gauge (suction pressure) and converted to feet by conversion factor 2.31 ft. water/psi
Suction Lift The distance between pump discharge head and water level.
Total Head
The sum of the water head above and below the center line of the pump discharge pipe. For well applications, the Total Head is the sum of the Discharge Head and the Pumping Water Level. Total head is used in determination of water horsepower and pump performance.
Water Horsepower
The output horsepower of a water pump. It is the combination of flow rate and pressure.
7
1.0 Introduction 1.1 Background Energy Audit & Energy Efficiency Improvement gram Government of the Punjab, Pakistan with financial assistance from the World Bank, is implementing “Punjab Cities Governance Improvement Project (PCGIP)” for strengthening systems for improved planning, resource management, and accountability in five large cities of Punjab i.e. Lahore, Faisalabad, Multan, Gujranwala and Rawalpindi. The project utilizes a result-based approach and, consistent with this focus, the disbursement decisions to the city and its entities are based on achievement of pre-specified results, referred to as Disbursement linked Indicators (DLIs) which reflect priority elements in furthering the Government’s urban agenda, critical at the provincial level, within the existing legislative, regulative and policy framework of the Government. DLIs includes intermediate outcomes, incremental steps and results contributing to improved efficiency, effectiveness, accountability and service delivery during and beyond the project life by building capacities , system and processes . Disbursement Linked Indicator 4 (DLI -4) aims for improvements in own source revenue collection system that encourages the City Local Government (CDGs), Development Authorities (DAs) and Service providers (WASAs) to bring improved systems for revenue enhancement. This DLI is linked with the initiative of WASAs to carry out the Energy Audit for resources conservation and efficiency to improved service delivery, accountability and own source revenue. One of the proposed actions & initiatives to enhance revenue was to conduct energy audit of WASAs to reduce the power cost by various systematic analysis of the energy use and finding out the energy management opportunities. WASAs each year incur significant cost. It was Rs. 4,697 million in 2014 year for energy/Electricity bills, with an installed capacity of approximately 131 MW for 5,663 Million Gallons per Day (water management), which can be reduced through detailed energy audit and implementing its findings. In the context of existing scenario energy audit of WASAs is a technical and efficient way to obtain energy analysis and savings through improvements that optimize pumping systems of tube well stations and disposal stations to operate efficiently with significant cost saving. The Urban Planning and Management Services Unit, Pvt. Ltd. has assigned NEC Consultants Pvt. Ltd to conduct energy audits of WASAs in Punjab in five major cities of Lahore, Rawalpindi, Faisalabad, Multan and Gujranwala. This is the energy audit report of Ravi Road Subdivision of Lahore city. 1.2 Methodology The primary and secondary sources were used to collect data for different WASAs and pumps installed there. The Urban Unit provided information and contact detail of all the WASAs. An energy audit report template was developed to collect field data from each WASA subdivision. Prior to start the on field measurements of each subdivision, meetings were conducted with the respective WASA management and briefed them about the activity. The technical team then collected data by on field measurements of each pump and recorded in their energy audit report template. On the basis of this energy audit report template, The Urban Unit also developed Android based software to record data of each pump online. This data was also recorded on line in this Android based application. On the basis of field measurements, efficiency of the pumping system was calculated and
8
energy efficiency opportunities were identified. 1.3 Scope The scope of the this assignment is to conduct energy audits of about 1,600 fresh water supply and wastewater disposal pumps installed at different WASA stations in five major cities of Lahore, Rawalpindi, Multan, Faisalabad and Gujranwala. The detail of these pumps is given in Table-1.
Table-1: Detail of WASAs Pumps
WASA Population
Served (Million)
Total Water Connections
Total Sewerage
Connections
Total Supply
Stations
Total Disposal Stations
Total No. of Pump
Sets WASA Lahore 5.48 587,595 583,532 491 99 776
WASA Gujranwala 0.54 29,375 97,236 66 23 112
WASA Faisalabad 1.55 110,452 217,002 87 43 222
WASA Multan 1.2 43,996 175,615 102 21 161
WASA Rawalpindi 1.17 92,468 38,437 362 - 362
Total 9.94 863,886 1,111,822 1,108 186 1,633 The efficiency of each pumping system was evaluated and energy efficiency improvement opportunities were identified for those pumping systems whose efficiencies were not at required level. The detail of reports prepared is as under:
- The energy audit report of each pump was prepared. - On the basis of each pump report, summary report of findings of each WASA
subdivision was prepared. - On the basis of each subdivision summary report, one consolidated report of each city
for energy efficiency improvement opportunities of the WASAs was prepared.
9
2.0 Energy Audit Findings There are 20 WASA water supply stations and 09 wastewater disposal pumps in Ravi Road Subdivision. The detail of these stations along with pumps installed capacity and actual discharge is given in Table-2:
Table-2: Detail of Ravi Road Subdivision
# WASA Station
No. of Water Supply Pumps
Installed
Installed Capacity (Cusec)
Actual Discharge (Cusec)
1 Gulshan Riaz Colony 01 2.0 3.12 2 Shafiq Abad 01 2.0 0.68 3 Karim Park Old 01 4.0 5.04 4 Karim Park Block-03 01 4.0 4.10 5 Allah Wali Masjid 01 4.0 3.38 6 Rehmat Flour Mill 01 4.0 3.48 7 Yaseen Road 01 2.0 1.71 8 Ameen Park 01 2.0 2.20 9 Bagh Munshi Ladha 01 4.0 4.41 10 Shesh Mahal Road 01 3.0 4.62 11 Umer Park Old 01 2.0 0.15 12 Umer Park New 01 2.0 2.74 13 Adda Bajri Wala 01 4.0 2.94 14 Ravi Park-01 01 4.0 4.50 15 Munshi Hospital 01 4.0 4.73 16 Ibrahim Road 01 2.0 1.37 17 Salamat Mohallah 01 4.0 1.00 18 Sardar Chappal 01 4.0 0.26 19 Main Outfall New 01 5.0 4.65 20 Main Outfall Old 01 4.0 4.88 Total 20 66.0 59.96 Wastewater Disposal Pumps
21 Bagh Munshi Disposal-01 01 10.0 2.59 22 Bagh Munshi Disposal-02 01 20.0 7.49 23 Bagh Munshi Disposal-03 01 10.0 4.05 24 Bagh Munshi Disposal-04 01 20.0 7.95 25 Bagh Munshi Disposal-06 01 15.0 11.55 26 Marzi Pura disposal-01 01 5.0 1.66 27 Outfall Disposal-01 01 25.0 18.48 28 Outfall Disposal-02 01 25.0 19.85 29 Outfall Disposal-03 01 25.0 19.98 Total 09 155.0 93.60
The installed capacity of WASA tube wells of Ravi Road Subdivision is 39.31 million m3 per annum whereas actual discharge is 35.71 million m3 per annum, for average 16 hours per day operation and 365 days per year. This actual discharge is about 9% lesser than the installed capacity. The installed capacity of WASA disposal pumps of Ravi Road Subdivision is 69.24 million m3 per annum whereas actual discharge is 41.81 million m3 per annum, for average 12 hours per
10
day operation and 365 days per year. This actual discharge is about 40% lesser than the installed capacity. 2.1 Pumping System Efficiency Pumping plant performance can be classified as “Low”, “Fair”, “Good”, or “Excellent” by referring to the following table, which is based upon the results of thousands of pump tests conducted by Pacific Gas & Electric Company, USA. This classification is used to categorize WASA pumps.
Table-3: Typical Overall Pumping System Efficiency Classification
Motor HP Low Fair Good Excellent 3-7.5 <44.0 44-49.9 50-54.9 >54.9
10 <46.0 46-52.9 53-57.9 >57.9 15 <47.1 48-53.9 54-59.9 >59.9
20-25 <48.0 50-56.9 57-60.9 >60.9 30-50 <52.1 52.1-58.9 59-61.9 >61.9 60-75 <56.0 56-60.9 61-65.9 >65.9 100 <57.3 57.3-62.9 63-66.9 >66.9 150 <58.1 58.1-63.4 63.5-68.9 >68.9 200 <59.1 59.1-63.8 63.9-69.4 >69.4 250 <59.1 59.1-63.8 63.9-69.4 >69.4 300 <60 60-64.0 64.1-69.9 >69.9
Source: Pacific Gas & Electric Company, USA The detail of pumping system efficiency and motor loading of each WASA station is given in Table-4. The calculations for the efficiency determination are given in the energy audit report of each pump in Annexure-1.
Table-4: Detail of Motor Loading and Pumping System Efficiency
WASA Station Motor Load (%)
Pumping System Efficiency (%)
Pumping System Efficiency Rating
Gulshan Riaz Colony 81 84 EXCELLENT Karim Park Old 90 79 EXCELLENT Karim Park Block-03 74 72 EXCELLENT Ameen Park 80 68 EXCELLENT Bagh Munshi Ladha 88 81 EXCELLENT Umer Park New 97 83 EXCELLENT Ravi Park-01 89 69 EXCELLENT Main Outfall New 84 84 EXCELLENT Main Outfall Old 91 74 EXCELLENT Munshi Hospital 90 77 GOOD Shafiq Abad 30 58 FAIR Rehmat Flour Mill 85 59 FAIR Shesh Mahal Road 98 63 FAIR Sardar Chappal 22 13 LOW Allah Wali Masjid 93 48 LOW Yaseen Road 85 49 LOW Umer Park Old 25 13 LOW Adda Bajri Wala 87 44 LOW Ibrahim Road 91 33 LOW Salamat Mohallah 60 21 LOW
11
Disposal Pumps Bagh Munshi Disposal-02 44 33 LOW Bagh Munshi Disposal-01 31 26 LOW Bagh Munshi Disposal-03 48 31 LOW Bagh Munshi Disposal-04 47 27 LOW Bagh Munshi Disposal-06 91 50 LOW Marzi Pura disposal-01 39 37 LOW Outfall Disposal-01 86 30 LOW Outfall Disposal-02 93 31 LOW Outfall Disposal-03 94 31 LOW About 50% of the tube wells are under excellent and good category of pumping system efficiency whereas remaining 50% are under fair and low category as illustrated in Fig-1.
Figure-1: Pumping System Efficiency Category
All the operational disposal pumps are under low category of pumping system efficiency. 2.2 Electricity Consumption Trend The detail of annual water discharge and correspondingly electricity consumption and unit electricity consumption of each WASA station is given in Table-5.
Excellent 45%
Good 5%
Fair 15%
Low 35%
12
Table-5: Detail of Water Discharge and Electricity Consumption
# WASA Station Annual Water
Discharge (m3)
Annual Electricity Consumption
(kWh)
Unit Electricity Consumption
(kWh/m3) 1 Gulshan Riaz Colony 1,862,960 285,346 0.15 2 Shafiq Abad 357,700 90,932 0.25 3 Karim Park Old 2,631,650 513,740 0.19 4 Karim Park Block-03 2,141,090 417,671 0.19 5 Allah Wali Masjid 1,762,950 522,474 0.29 6 Rehmat Flour Mill 1,814,050 484,303 0.26 7 Yaseen Road 894,250 262,007 0.29 8 Ameen Park 1,396,125 302,119 0.21 9 Bagh Munshi Ladha 2,299,500 497,300 0.21
10 Shesh Mahal Road 3,101,040 707,420 0.22 11 Umer Park Old 87,600 83,336 0.95 12 Umer Park New 1,533,000 313,033 0.20 13 Adda Bajri Wala 1,314,000 422,735 0.32 14 Ravi Park-01 2,014,800 431,542 0.21 15 Munshi Hospital 2,820,720 578,912 0.20 16 Ibrahim Road 868,700 340,610 0.39 17 Salamat Mohallah 483,990 314,849 0.65 18 Sardar Chappal 157,680 142,849 0.90 19 Main Outfall New 3,294,125 650,505 0.19 20 Main Outfall Old 3,453,630 701,402 0.20 Total 34,289,560 8,063,085 0.23 Disposal Pumps
21 Bagh Munshi Disposal-01 1,450,875 94,290 0.06 22 Bagh Munshi Disposal-02 4,182,900 218,303 0.05 23 Bagh Munshi Disposal-03 2,266,650 147,517 0.06 24 Bagh Munshi Disposal-04 4,440,225 288,593 0.06 25 Bagh Munshi Disposal-06 6,455,025 299,987 0.04 26 Marzi Pura disposal-01 931,298 97,207 0.10 27 Outfall Disposal-01 1,376,050 84,400 0.06 28 Outfall Disposal-02 1,478,250 91,886 0.06 29 Outfall Disposal-03 1,487,740 92,473 0.06 Total 24,069,013 1,414,656 0.05 Total annual energy cost of Ravi Road subdivision is about Rs. 123 million. The unit electricity consumption trend for each WASA station tube wells is illustrated in Fig-2. From figure, it is clear that 0.20 kWh/m3 is considered to be optimum figure for water supply pumps. This figure is based on NEC experience of conducting water turbine audits of different industries. WASA audits also reflect the similar figure.
13
Figure-2: Unit Electricity Consumption Trend
About 65% of the tube wells consume electricity more than the 0.20 kWh/m3. In case if all the 20 tube wells consume optimum electricity, then annually Rs. 16 million (15%) can be saved. 2.3 Pumping System Efficiency Improvement Potential The 10 tube wells and 09 disposal pumps having system efficiency in the category of FAIR to LOW, as given in Table-4, have the potential of efficiency improvement into the GOOD category. Table-6 gives detail of this efficiency improvement potential.
Table-6: System Energy Efficiency Potential of Pumps
WASA Station Existing Pumping Efficiency
(%)
Improved Pumping Efficiency
(%)
Annual
(kWh)
Saving
(Rs)
Impeller
Adjustment /Repair &
Maintenance
Intervention
Motor Replace
Pump Replace
Shafiq Abad 58 65 9,298 120,880 × Allah Wali Masjid
47 65 138,096 1,795,252 ×
Rehmat Flour Mill
59 65 44,597 579,759 ×
Yaseen Road 49 65 65,114 846,479 × Shesh Mahal Road
63 65 23,031 299,408 ×
Umer Park Old 13 68 67,251 874,260 × × Adda Bajri Wala 44 68 152,272 1,979,538 × Ibrahim Road 32 65 169,650 2,205,453 × Salamat Mohallah
21 65 211,381 2,747,954 ×
Sardar Chappal 13 68 115,682 1,503,860 × × Bagh Munshi Disposal-01
26 61 53,567 696,369 ×
Bagh Munshi 33 64 105,734 1,374,542 ×
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
kWh/m3
Optimum
14
Disposal-02 Bagh Munshi Disposal-03
31 61 72,669 944,697 ×
Bagh Munshi Disposal-04
27 64 166,201 2,160,616 ×
Bagh Munshi Disposal-06
50 61 56,064 728,830 ×
Marzi Pura disposal-01
37 61 38,790 504,275 ×
Outfall Disposal-01
30 63 44,078 573,013 ×
Outfall Disposal-02
31 63 47,324 615,206 ×
Outfall Disposal-03
31 63 47,504 617,547 ×
Total 1,628,303 21,167,938
2.4 Interventions for the Improvement of WASA Stations Energy audit activity of Ravi Road subdivision revealed that there are certain areas of electrical, mechanical and housekeeping which needs improvement. Table-7 presents detail of interventions and investment requirement in each WASA station for better, efficient and safe operation of WASA station. About Rs. 34.83 million are required to improve WASA stations of Ravi Road subdivision, Lahore.
15
Table-7A: Interventions & Investment Required in WASA Stations- Ravi Road Subdivision
Intervention WASA Stations Gulshan
Riaz Shafiq Karim
Old Karim New
Allah Wali
Outfall New
Rehmat Flour
Yaseen Road
Ameen Park
Bagh Munshi
Shesh Mahel
Umer Old
Umer New
Adda Bajri
Ravi Park01
Electrical Install VFD × × × × × × × × × × × × × × × Install hour meter × × × × × × × × × × × × × × × Replace ampere meter × × × × × × × × × × Replace volt meter × × × × × × × Replace over current relays Replace over voltage relay Install/maintain PFI plant × × × × × × × × × × × × Install/connect capacitors at PFI plant
Install PFI control/relay × Install/replace motor terminal box /Improve open and loose motor connection
Improve panel condition × × × × × × Improve wiring condition × × × × × × Replace de-rated capacitors Relocate panel away from bore hole
Replace electrical motor Install fan in the panel Replace PFI HRC fuses Replace PFI display meter Correct date & time of electrical meter
Replace/correct electrical meter × Replace change over Replace main circuit breaker Mechanical Replace damaged/install new flow meter
× × × × × × × × × × × × × × ×
16
Intervention WASA Stations Gulshan
Riaz Shafiq Karim
Old Karim New
Allah Wali
Outfall New
Rehmat Flour
Yaseen Road
Ameen Park
Bagh Munshi
Shesh Mahel
Umer Old
Umer New
Adda Bajri
Ravi Park01
Replace damaged/install new digital pressure gauge
× × × × × × × × × × × × × × ×
Control gland leakage × × × × × × × × × × × × × × × Make operational/install new chlorinator
× × × × × × × × × × × ×
Maintain ratchet plate × × × Adjust impeller × × × × × × Repair & maintenance of pump × × × Replace existing pumping system × Maintain/install new non return valve
× ×
Housekeeping Improve general housekeeping × × × × Install shades on motor & pump Rain protection of motor & pump Fix panel properly Proper support of discharge pipeline
Maintain monthly record of fuel consumption
Station Wise Investment (M. Rs)
0.78 0.80 0.71 0.89 0.76 0.83 0.78 0.55 0.44 0.94 0.84 3.2 0.45 0.77 0.80
Annual Saving (M. Rs) 0.12 1.8 0.58 0.85 0.29 0.87 1.9 Payback (Year) 6.66 0.42 1.34 0.64 2.89 3.6 0.4
17
Table-7B: Interventions & Investment Required in WASA Stations- Ravi Road Subdivision Intervention WASA Stations Munshi Ibrahim Salamat Sardar Outfall
Old Bagh Disp-
01
Bagh Disp-02
Bagh Disp-03
Bagh Disp-
04
Bagh Disp-
06
Marzipur Disp-01
Outfal. Disp-
01
Outfal Disp-
02
Outfal. Disp-
03 Electrical Install VFD × × × × × Install hour meter × × × × × × × × × × × × × × Replace ampere meter × × × × Replace volt meter × × × × × × Replace over current relays Replace over voltage relay Install/maintain PFI plant × × × × × × × × × × × × Install/connect capacitors at PFI plant
Install PFI control/relay Install/replace motor terminal box /Improve open and loose motor connection
Improve panel condition × × × × Improve wiring condition × × × Replace de-rated capacitors Relocate panel away from bore hole Replace electrical motor Install fan in the panel Replace PFI HRC fuses Replace PFI display meter Correct date & time of electrical meter
Replace/correct electrical meter × Replace change over Replace main circuit breaker Mechanical Replace damaged/install new flow meter
× × × × × × × × × × × × × ×
18
Intervention WASA Stations Munshi Ibrahim Salamat Sardar Outfall
Old Bagh Disp-
01
Bagh Disp-02
Bagh Disp-03
Bagh Disp-
04
Bagh Disp-
06
Marzipur Disp-01
Outfal. Disp-
01
Outfal Disp-
02
Outfal. Disp-
03 Replace damaged/install new digital pressure gauge
× × × × × × × × × × × × × ×
Control gland leakage × × × × × Make operational/install new chlorinator
× ×
Maintain ratchet plate × × × Adjust impeller × × × × × × × Repair & maintenance of pump × × × Replace existing pumping system × × × × × Maintain/install new non return valve
× × ×
Housekeeping Improve general housekeeping × × × Install shades on motor & pump Rain protection of motor & pump Fix panel properly Proper support of discharge pipeline Maintain monthly record of fuel consumption
Station Wise Investment (M. Rs)
0.72 2.5 3.7 4.9 0.71 3.2 0.18 0.18 4.0 0.08 0.28 0.48 0.18 0.18
Annual Saving (M. Rs) 2.2 2.7 1.5 0.69 1.3 0.94 2.1 0.73 0.50 0.57 0.61 0.61 Payback (Year) 1.13 1.37 3.26 4.63 0.13 0.19 1.9 0.10 0.56 0.84 0.29 0.29 Total Investment of Subdivision (M.Rs) = 34.83
19
ANNEXURE-1
Energy Audit Reports
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Gulshan Riaz Colony
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Ameer M Khan
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B12 B/5 Serial 21-8-10-10312
iii) Certification Mark
iv) Year of Manufacture 2009
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) 2.3 Psig
viii) Power / HP / BHP 59.5 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 115
v) Power Factor (Cos ɸ) 0.85
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 31467.7
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator NA
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping fair
Motor Terminal Fair
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 319 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.73 m/sec
Pressure
i) Pressure at Discharge Side of Pump 2.3 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 381 382.8 383.5
ii) Ampere 93 86 91
iii) Power Factor 0.79 0.78 0.83
iv) Appearant Power (kVA) 61 58 60.3
v) Running Power (kW) 48.6
vi) Reactive Power (kVAr) 37 35.5 33.5
vi) Motor Working on Loading Basis 81 %
Oversize Undersize Properly Sized
Poor/ Faulty A meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 88.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 5.313 ft
vi) Discharge Side Frictional Head 18.85 ft
vii) Dynamic Discharge Head (v+vi) 24.16 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 155.36 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 85.64
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,235
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 55.10 hp
xiv) Brake Horsepower (bhp) (OEM Data) 59.5 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 65.15 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 92.61 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 84.58 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.15 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 5,104 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,862,960 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 285,346 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,709,496 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 256 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.19 kWh/m3
9 Summary of Findings
Pumping system efficiency is 84%. For 80 HP motor efficiency >62% is considered to be excellent. This pumping system is efficient and requires no intervention.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 783,500 PKR
Replace A meter Defective A meter
Pressure gauge is not installed Install digital pressure gauge at discahrge pipeline
Install flowmeter No flowmeter
Replace PFI control unitPFI control is defective
No VFD installed Install VFD
There is moderate leakage at pump gland Remove leakage
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Shafiq Abad
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 250
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B12/B5 Serial 21-06-10-48/3
iii) Certification Mark
iv) Year of Manufacture 2006
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) 220 ft
vii) Discharge Pressure (P) 19.8 Psig
viii) Power / HP / BHP 62.93 BHP
ix) Speed (n) 1,475 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data NA
i) Manufacturer
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ)
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,480 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 33391.4
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator NA
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring POOR
Housekeeping Poor
Motor Terminal No terminal box
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 70 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 0.60 m/sec
Pressure
i) Pressure at Discharge Side of Pump 19.8 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 359.4 361.2 362.4
ii) Ampere 101 102 101
iii) Power Factor 0.49 0.46 0.47
iv) Appearant Power (kVA) 37 37 36.5
v) Running Power (kW) 17.7
vi) Reactive Power (kVAr) 32.63
vi) Motor Working on Loading Basis 29.6 %
Oversize Undersize Properly Sized
Poor
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,475 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 45.738 ft
vi) Discharge Side Frictional Head 0.95 ft
vii) Dynamic Discharge Head (v+vi) 46.69 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 177.89 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 18.79
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 532
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 13.85 hp
xiv) Brake Horsepower (bhp) (OEM Data) 62.93 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 23.73 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 22.00 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 58.35 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.25 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 980 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 357,700 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 90,932 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,182,116 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 78 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
xxix) Potential of Energy Reduction 10.23 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 9,298 kWh/yr
xxxi) Annual Financial Saving on Pumping 120,880 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 58%. For pump attached with 150 HP motor, efficiency <58% is LOW. This pumping system requires ampeller adjustment to increase the efficiency upto 65% which is GOOD. This intervention will save 120,880 Rs annually.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 803,000 PKR
Pressure gauge is not installed Install digital pressure gauge at discahrge pipeline
Install flowmeter Flow meter is not available
Install PFIPFI is not installed
No VFD installed Install VFD
There is moderate leakage at pump gland Remove leakage
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Karim Park new
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Aamir Iqbal 0300-4688433
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Picture
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14/B4 Serial 9972688500/300
iii) Certification Mark
iv) Year of Manufacture 2014
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 15
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 118.2 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 3368
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator ok
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Excellent
Housekeeping Good
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 515 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.82 m/sec
Pressure
i) Pressure at Discharge Side of Pump 15 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 388 388 389
ii) Ampere 166 173 163
iii) Power Factor 0.91 0.88 0.89
iv) Appearant Power (kVA) 111 116 110
v) Running Power (kW) 100
vi) Reactive Power (kVAr) 46 58 51
vi) Motor Working on Loading Basis 90 %
Oversize Undersize Properly Sized
Excellent
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,475 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 34.65 ft
vi) Discharge Side Frictional Head 19.25 ft
vii) Dynamic Discharge Head (v+vi) 53.90 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 185.10 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 138.26
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,400
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 105.99 hp
xiv) Brake Horsepower (bhp) (OEM Data) 118.2 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 134 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 89.67 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 79.07 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 7,210 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,631,650 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 513,740 kWh/yr
xxv) Annual Energy Expenditure on Pumping 6,678,619 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 443 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
9 Summary of Findings
Pumping system efficiency is 80%. For pump attached with 150 HP motor, efficiency >69% is considered to be excellent. This pumping system does not require any energy efficiency measure.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 710,000 PKR
No flowmeter Install Flowmeter
Pressure gauge is not installed Install digital pressure gauge at discahrge pipeline
Install pressure guageNo pressure guage
No VFD installed Install VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Karim Park Blk #3
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand Flow Pak Country
ii) Model 14 FMC/4SI Serial 14-1988
iii) Certification Mark
iv) Year of Manufacture 2014
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / 18.5 118.2 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading Out of order
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator Defected
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Good
Housekeeping fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 419 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.30 m/sec
Pressure
i) Pressure at Discharge Side of Pump 10.5 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 423 414 428
ii) Ampere 131 184 154
iii) Power Factor 0.63 0.67 0.86
iv) Appearant Power (kVA) 96 132 112
v) Running Power (kW) 81.3
vi) Reactive Power (kVAr) 74.6 98.4 55
vi) Motor Working on Loading Basis 73.9 %
Oversize Undersize Properly Sized
Good/Defective A meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,475 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 87.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 24.255 ft
vi) Discharge Side Frictional Head 12.80 ft
vii) Dynamic Discharge Head (v+vi) 37.06 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 168.26 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 112.49
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,356
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 78.39 hp
xiv) Brake Horsepower (bhp) (OEM Data) 118.2 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 109 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 66.32 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 71.93 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 5,866 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,141,090 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 417,671 kWh/yr
xxv) Annual Energy Expenditure on Pumping 5,429,717 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 71%. For pumping system with motor 150 HP efficiency >69% is excellent. This pumping system doest not require any energy efficiency measure
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 893,500 PKR
Pressure gauge is not installed Install digital pressure gauge at discahrge pipeline
Install chlorinatorFaulty chlorinator
PFI plant of 50 KVAR is recommendedPFI plant is not installed
No VFD installed Install VFD
Defective A meter Install A meter
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Allah Wali Masjid
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Ameer Afzal
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B1/B4 Serial 21-05-10-4631
iii) Certification Mark
iv) Year of Manufacture 2005
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 220 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 122.63 BHP
ix) Speed (n) 1,485 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 48456.61
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 kvar
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator Faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate Faulty
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 345 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.89 m/sec
Pressure
i) Pressure at Discharge Side of Pump 13 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 381 380 381
ii) Ampere 175 183 173
iii) Power Factor 0.9 0.8 0.87
iv) Appearant Power (kVA) 115 120 114
v) Running Power (kW) 101.7
vi) Reactive Power (kVAr) 50 62.9 55
vi) Motor Working on Loading Basis 92.8 %
Oversize Undersize Properly Sized
Good/ Defective A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,475 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.3
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 30.03 ft
vi) Discharge Side Frictional Head 8.72 ft
vii) Dynamic Discharge Head (v+vi) 38.75 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 169.95 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 92.62
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,221
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 65.19 hp
xiv) Brake Horsepower (bhp) (OEM Data) 122.63 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 136 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 53.16 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 47.82 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.30 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 4,830 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,762,950 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 522,474 kWh/yr
xxv) Annual Energy Expenditure on Pumping 6,792,156 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 469 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.22 kWh/m3
xxix) Potential of Energy Reduction 26.43 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 138,096 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,795,252 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 47%. For pump attached with 150 HP motor, efficiency below <58% is considered to be LOW (>68.9 is excellent). This pumping system requires impeler adjustment, repair and maintenance. This intervention will save 1,795,252 Rs annually
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 759,000 PKR
Install flow meter No flow meter
Replace PFI control unitDefective PFI control
No VFD installed Install VFD
There is moderate leakage at pump gland Remove leakage
Pressure gauge is not installed Install digital pressure gauge at discahrge pipeline
Install A and V meter Defective A and V meter
Defective chlorinator Install chlorinator
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Main Outfall NEW
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Shaukat Ali 0300 4266838
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 19 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country
ii) Model B14 D/2 Serial 6102
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 5 Cusec 510 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 153.2 BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 10 (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 350 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Significant
Non Return Valve Faulty
Chlorinator Faulty
Flow Meter NA'
Pressure Gauge NA'
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok'
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 475 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.60 m/sec
Pressure
i) Pressure at Discharge Side of Pump 22 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 363 365 375
ii) Ampere 167 168 174
iii) Power Factor 0.87 0.88 0.87
iv) Appearant Power (kVA) 105 106 109
v) Running Power (kW) 93.3
vi) Reactive Power (kVAr) 56 60 58
vi) Motor Working on Loading Basis 84 %
Oversize Undersize Properly Sized
Fair
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 50.82 ft
vi) Discharge Side Frictional Head 16.41 ft
vii) Dynamic Discharge Head (v+vi) 67.23 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 198.43 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 127.53
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,254
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 104.80 hp
xiv) Brake Horsepower (bhp) (OEM Data) 153.2 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 125 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 68.40 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 83.79 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 19 hrs
xxi) Daily Pump flow 9,025 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,294,125 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 650,505 kWh/yr
xxv) Annual Energy Expenditure on Pumping 8,456,563 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 89%. For pump attached with 150 HP motor, efficiency >68.9 is excellent. This pumping system requires no intervention
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 833,000 PKR
No pressure guage Digital pressure guage is recommended
Flow meter is recommendedNo flow meter
Install chlorinatorFaulty chlorinator
No VFD VFD is recommended
Defective PFI control Install PFI control unit
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station REHMAT FLOOR MIL
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Ameer Afzal 0344-4824971
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14/B4 Serial 21-05-10-4338
iii) Certification Mark
iv) Year of Manufacture 2006
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 220 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 122.63 BHP
ix) Speed (n) 1,485 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 46400.76
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 355 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.95 m/sec
Pressure
i) Pressure at Discharge Side of Pump 21 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 384.5 383 384.5
ii) Ampere 164 163 167
iii) Power Factor 0.85 0.85 0.86
iv) Appearant Power (kVA) 109 109 111
v) Running Power (kW) 94.27
vi) Reactive Power (kVAr) 57 56 55
vi) Motor Working on Loading Basis 85 %
Oversize Undersize Properly Sized
Fair/Faulty A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,475 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 48.51 ft
vi) Discharge Side Frictional Head 9.22 ft
vii) Dynamic Discharge Head (v+vi) 57.73 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 188.93 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 95.31
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,144
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 74.58 hp
xiv) Brake Horsepower (bhp) (OEM Data) 122.63 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 126 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 60.81 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 59.01 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.27 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 4,970 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,814,050 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 484,303 kWh/yr
xxv) Annual Energy Expenditure on Pumping 6,295,934 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 391 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.24 kWh/m3
xxix) Potential of Energy Reduction 9.21 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 44,597 kWh/yr
xxxi) Annual Financial Saving on Pumping 579,759 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 59%. For pump attached with 150 HP motor, efficiency below 58% is considered to be LOW (>68.9 is excellent). This pumping system requires impeler adjustment. It is estimated that this intervention will save 579,759 Rs annually.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 784,000 PKR
Install new PFI controlDefective PFI control
Replace A and V meter with correct oneFaulty A and V meter
No VFD installed VFD is recommended
No flow meter Flow meter is recommended
Pressure gauge is not installed Digital pressure guage is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Yasin Road
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Inamul Haq
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data NA
i) Make / Brand KSB Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.87
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not Installed
Panel Condition/Issues
Gland Leakage yes
Non Return Valve ok
Chlorinator Faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate Faulty
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 175 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.50 m/sec
Pressure
i) Pressure at Discharge Side of Pump 15 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 375 369 364
ii) Ampere 98 98 89
iii) Power Factor 0.82 0.85 0.87
iv) Appearant Power (kVA) 64 60.5 59
v) Running Power (kW) 51
vi) Reactive Power (kVAr) 35.8 31 27.8
vi) Motor Working on Loading Basis 85 %
Oversize Undersize Properly Sized
Poor/No A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,475 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.6
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 34.65 ft
vi) Discharge Side Frictional Head 5.77 ft
vii) Dynamic Discharge Head (v+vi) 40.42 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 171.62 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 46.98
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 863
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 33.39 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 68 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 48.85 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.29 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 2,450 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 894,250 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 262,007 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,406,096 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 233 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.22 kWh/m3
xxix) Potential of Energy Reduction 24.85 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 65,114 kWh/yr
xxxi) Annual Financial Saving on Pumping 846,479 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 48%. For pump attached with 150 HP motor, efficiency below 58% is considered to be LOW (>68.9 is excellent). This pumping system requires impeler adjustment, repair and maintenace to increase efficiecy upto 65% which is GOOD. This intervention will save 846,479 Rs annually.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 554,000 PKR
New Chlorinator is recommendedFaulty Chlorinator
Pressure gauge is not installed Digital pressure guage is recommended
Install flow meter
Install A and V meter
No water flow meter
No VFD installed VFD is recommended
No A and V meter
PFI plant of 25 KVAR is recommendedNo PFI plant
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Amin Park
ii) Name of Subdivision Ravi Road, Lahore
iii) Operator Name & Contact Mr. Umer Agha
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 17 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B12/B5 Serial 9972122091/390
iii) Certification Mark
iv) Year of Manufacture 2012
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) 210
vii) Discharge Pressure (P) 17 Psig
viii) Power / HP / BHP 59.78 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 115
v) Power Factor (Cos ɸ) 0.85
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,480 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 12458.41
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator NA
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 225 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.93 m/sec
Pressure
i) Pressure at Discharge Side of Pump 8 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 41 meter
ii) Pumping Water Level 45 meter
Electric Measurements
i) Voltage 398 398 394
ii) Ampere 91 90 87
iii) Power Factor 0.78 0.8 0.78
iv) Appearant Power (kVA) 63 62.2 59.5
v) Running Power (kW) 48.43
vi) Reactive Power (kVAr) 40 37 37
vi) Motor Working on Loading Basis 80 %
Oversize . Undersize Properly Sized
Speed
Good
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91.7
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 18.48 ft
vi) Discharge Side Frictional Head 9.70 ft
vii) Dynamic Discharge Head (v+vi) 28.18 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 175.78 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 75.51
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 945
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 43.97 hp
xiv) Brake Horsepower (bhp) (OEM Data) 59.78 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 65 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 73.56 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 67.74 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.22 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 17 hrs
xxi) Daily Pump flow 3,825 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,396,125 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 302,119 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,927,553 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 64 %
xxvii) Water Flow after Efficiency Improvement 213 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
9 Summary of Findings
Pumping system efficiency is 67%. For pump attached with 150 HP motor, efficiency >65% is considered to be EXCELLENT. This pumpinbg system requires no intervention
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 443,000 PKR
Chlorinator is recommemdedNo chlorinator
No VFD installed VFD is recommended
No water flow meter Water flow meter is recommended
Pressure gauge is not installed Digital pressre guage is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Bagh Munshi Ladha
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr.Sumair Yousaf 0322-7275732
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand FlowPak Country Pakistan
ii) Model 14FMC/4ST Serial 11 1961
iii) Certification Mark
iv) Year of Manufacture 2014
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 150 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 29059.36
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 20 KVARPanel Condition/Issues
Gland Leakage yes
Non Return Valve ok
Chlorinator NA
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 450 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 3.85 m/sec
Pressure
i) Pressure at Discharge Side of Pump 18 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 402 405 395
ii) Ampere 151 169 174
iii) Power Factor 0.8 0.9 0.78
iv) Appearant Power (kVA) 105 119 125
v) Running Power (kW) 96.8
vi) Reactive Power (kVAr) 62 54
vi) Motor Working on Loading Basis 88.4 % 77
Oversize Undersize Properly Sized
Speed
Fair
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93.4
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 41.58 ft
vi) Discharge Side Frictional Head 37.16 ft
vii) Dynamic Discharge Head (v+vi) 78.74 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 209.94 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 120.81
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,170
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 105.04 hp
xiv) Brake Horsepower (bhp) (OEM Data) 150 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 130 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 70.03 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 80.95 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.22 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 6,300 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,299,500 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 497,300 kWh/yr
xxv) Annual Energy Expenditure on Pumping 6,464,903 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 361 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.27 kWh/m3
9 Summary of Findings
Pumping system efficiency is 80%. For pump attached with 150 HP motor, efficiency >68.9 is excellent. This pumping system requires no intervention
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 938,000 PKR
Installed PFI is of 20 KVAR, which is under capacity PFI of 50 KVAR is recommended
Chlorinator is recommended No Chlorinator
Digital pressure guage is recommendedNo pressure guage
No VFD installed VFD is recommended
No water flow meter Water flow meter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Sheshmehl Road
ii) Name of Subdivision .
iii) Operator Name & Contact Mr. Intikhab Haider
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14/B4 Serial 21-07-10-7708
iii) Certification Mark
iv) Year of Manufacture 2007
v) Flowrate (Q) 3 Cusec 306 m3/hr
vi) Head (H) 250 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 106.82 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 20938.97
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator NA
Flow Meter NA'
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping Poor
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 472 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 4.04 m/sec
Pressure
i) Pressure at Discharge Side of Pump 0 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 399 396 394
ii) Ampere 172 192 191
iii) Power Factor 0.89 0.86 0.78
iv) Appearant Power (kVA) 119 131 130
v) Running Power (kW) 107.1
vi) Reactive Power (kVAr) 65 66 81
vi) Motor Working on Loading Basis 97.8 %
Oversize Undersize Properly Sized
Speed
Poor. No A and V meter
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 0 ft
vi) Discharge Side Frictional Head 40.83 ft
vii) Dynamic Discharge Head (v+vi) 40.83 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 172.03 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 126.72
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,392
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 90.28 hp
xiv) Brake Horsepower (bhp) (OEM Data) 106.82 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 144 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 84.52 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 62.88 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.23 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 18 hrs
xxi) Daily Pump flow 8,496 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,101,040 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 707,420 kWh/yr
xxv) Annual Energy Expenditure on Pumping 9,196,459 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 488 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.22 kWh/m3
xxix) Potential of Energy Reduction 3.26 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 23,031 kWh/yr
xxxi) Annual Financial Saving on Pumping 299,408 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 62%. For pump attached with 150 HP motor, efficiency below between 58-63% is considered to be FAIR (>63.5% is GOOD). This pumping system requires impeler adjustment. This intervention will save 299,408 Rs annually.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financia Estimated Investment for Improvement Plan
12 844,000 PKR
Water flow meter is recommended No water flow meter
Install A and V meter No A and V meter
No VFD installed Install VFD
Defective PFI with no capacitors PFI of 50 KVAR is recommended
No pressure guage Digital pressure guage is recommended
New chlorinator is recommendedFaulty chlorinator
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Umer Park Old
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Rizwan Saleem 0300-4624314
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 115
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 1794.19&65470.8
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not Installed
Panel Condition/Issues
Gland Leakage Moderate
Non Return Valve ok
Chlorinator Faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Poor
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 16 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 0.14 m/sec
Pressure
i) Pressure at Discharge Side of Pump 8 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 388 381 378
ii) Ampere 41.2 48.2 53.6
iii) Power Factor 0.68 0.48 0.66
iv) Appearant Power (kVA) 35.26 31.81 27.54
v) Running Power (kW) 15.14
vi) Reactive Power (kVAr) 20 27 25
vi) Motor Working on Loading Basis 25 %
Oversize Undersize Properly Sized
Fair/ No A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 94.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 18.48 ft
vi) Discharge Side Frictional Head 0.05 ft
vii) Dynamic Discharge Head (v+vi) 18.53 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 149.73 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 4.30
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 284
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 2.66 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 20 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 13.13 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.95 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 240 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 87,600 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 83,336 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,083,367 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 83 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.18 kWh/m3
xxix) Potential of Energy Reduction 80.70 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 67,251 kWh/yr
xxxi) Annual Financial Saving on Pumping 874,260 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 13%. For pump attached with 80 HP motor, efficiency below 58% is considered to be LOW. This pumping system requires pump and motor replacement (motor is very old which needs to be replaced). This intervention will save 874,260 Rs annually.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 3,174,000 PKR
Replace pump (2 CUSEC)Pump is inefficient
Replace motor (80 HP)Motor is inefficient
No VFD VFD is recommended
No water flow meter water flow meter is recommended
No pressure guage Digital pressure guage is recommended
PFI plant of 25 KVAR is recommendedNo PFI plant
Chlorinator is recommendedNo chlorinator
No A and V meter A and V meter is rcommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Umer Park New
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. M Asghar
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B12 B/5 Serial 21-07-10-7259
iii) Certification Mark
iv) Year of Manufacture 2007
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 59.63 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,480 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 1794.19
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator ok
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal
Foundation/Civil work ok
Ratchet Plate OK
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 280 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.40 m/sec
Pressure
i) Pressure at Discharge Side of Pump 25 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 390 388 404
ii) Ampere 108 101 116
iii) Power Factor 0.84 0.81 0.81
iv) Appearant Power (kVA) 74 68 71
v) Running Power (kW) 56.87
vi) Reactive Power (kVAr) 40 40 41
vi) Motor Working on Loading Basis 97.4 %
Oversize Undersize Properly Sized
Fair. No A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 57.75 ft
vi) Discharge Side Frictional Head 14.57 ft
vii) Dynamic Discharge Head (v+vi) 72.32 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 203.52 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 75.17
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 945
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 63.36 hp
xiv) Brake Horsepower (bhp) (OEM Data) 59.63 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 76 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 106.26 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 83.12 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 4,200 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,533,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 313,033 kWh/yr
xxv) Annual Energy Expenditure on Pumping 4,069,426 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 229 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.25 kWh/m3
9 Summary of Findings
Pumping system efficiency is 80%. For pump attached with 80 HP motor, efficiency >68.9% is excellent. This pumping system requires no intervention.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 451,000 PKR
No pressure guage Digital pressure guage is recommended
Replace defective A and V meter with correct oneFaulty A and V meter
Install PFI controlDefective PFI control
No VFD VFD is recommended
No water flow meter Water flow meter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Adda Bajri Wala
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. M Sarfaraz 0346-4544690
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14 B/4 Serial 21-04-10-2862
iii) Certification Mark
iv) Year of Manufacture 2005
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 220 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 122.63 BHP
ix) Speed (n) 1,485 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 24993.5
iii) Meter Time and Date .
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator ok
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping ok
Motor Terminal open motor connections
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 300 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.64 m/sec
Pressure
i) Pressure at Discharge Side of Pump 13 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 361.3 364.3 362.7
ii) Ampere 183 191 185
iii) Power Factor 0.81 0.79 0.81
iv) Appearant Power (kVA) 117 120 122
v) Running Power (kW) 96
vi) Reactive Power (kVAr) 69 74 70
vi) Motor Working on Loading Basis 87 %
Oversize Undersize Properly Sized
Poor/Faulty A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 30.03 ft
vi) Discharge Side Frictional Head 6.61 ft
vii) Dynamic Discharge Head (v+vi) 36.64 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 167.84 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 80.54
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,130
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 55.99 hp
xiv) Brake Horsepower (bhp) (OEM Data) 122.63 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 129 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 45.65 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 43.51 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.32 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 3,600 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,314,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 422,735 kWh/yr
xxv) Annual Energy Expenditure on Pumping 5,495,550 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 469 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxix) Potential of Energy Reduction 36.02 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 152,272 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,979,538 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 43%. For pump attached with 150 HP motor, efficiency below 58% is considered to be LOW (>68.9 is excellent). This pumping system requires impeler adjustment, repair and maintenace. This intervention will save 1,979,535 Rs annually
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 776,000 PKR
No pressure guage Digital pressure guage is recommended
Install flow meter No flowmeter
Install new A and V meter
No VFD VFD is recommended
Faulty A and V meter
Defective PFI control Replace PFI control by new PFI control
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Ravi Park-1
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Khurram Shehzad
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14 B/4 Serial 21-04-10-286
iii) Certification Mark
iv) Year of Manufacture 2005
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 220 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 122.63 BHP
ix) Speed (n) 1,485 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 32832.5
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve Faulty
Chlorinator Faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping Poor
Motor Terminal No terminal box
Foundation/Civil work ok
Ratchet Plate Faulty
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 460 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.52 m/sec
Pressure
i) Pressure at Discharge Side of Pump 13 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 385.2 387 386.4
ii) Ampere 183.6 176.3 163.9
iii) Power Factor 0.79 0.88 0.84
iv) Appearant Power (kVA) 122.4 118.3 110
v) Running Power (kW) 98
vi) Reactive Power (kVAr) 74 60
vi) Motor Working on Loading Basis 89 % 58
Oversize Undersize Properly Sized
Poor/ Defective A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 98.6
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 30.03 ft
vi) Discharge Side Frictional Head 15.40 ft
vii) Dynamic Discharge Head (v+vi) 45.43 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 176.63 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 123.50
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,347
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 90.34 hp
xiv) Brake Horsepower (bhp) (OEM Data) 122.63 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 131 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 73.67 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 68.77 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.21 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 5,520 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,014,800 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 431,542 kWh/yr
xxv) Annual Energy Expenditure on Pumping 5,610,040 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 455 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.22 kWh/m3
9 Summary of Findings
umping system efficiency is 68%. For pump attached with 150 HP motor, efficiency >63.5% is GOOD. This pumping system requiresn no intervention
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 803,500 PKR
Chlorinator is recommended No chlorinator
Water flow meter is recommendedNo water flow meter
No VFD VFD is recommended
Defective PFI control Install new PFI control
No pressure guage Digital pressure guage is recommended
Replace A and V meter by correct one Faulty A and V meter
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Munshi Hospital
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. M Saleem Butt
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14 B/4 Serial 997267125/300
iii) Certification Mark
iv) Year of Manufacture 2014
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 118.12 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 8137.8
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kvar
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve ok
Chlorinator Faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Fair
Housekeeping Fair
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 483 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.65 m/sec
Pressure
i) Pressure at Discharge Side of Pump 18 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 379.3 371.5 386.2
ii) Ampere 146.5 197 170.7
iii) Power Factor 0.87 0.83 0.95
iv) Appearant Power (kVA) 95 126 114
v) Running Power (kW) 98.6
vi) Reactive Power (kVAr) 54 70 33
vi) Motor Working on Loading Basis 90 %
Oversize Undersize Properly Sized
Good
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93.1
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 41.58 ft
vi) Discharge Side Frictional Head 16.96 ft
vii) Dynamic Discharge Head (v+vi) 58.54 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 189.74 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 129.67
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,308
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 101.89 hp
xiv) Brake Horsepower (bhp) (OEM Data) 118.12 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 132 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 86.26 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 77.09 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.21 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 7,728 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,820,720 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 578,912 kWh/yr
xxv) Annual Energy Expenditure on Pumping 7,525,850 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 426 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
9 Summary of Findings
Pumping system efficiency is 77%. For pump attached with 150 HP motor, efficiency >68.9 is excellent. This pumping system requires no intervention.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 718,000 PKR
No pressure guage Digital pressure guage is recommended
Chlorinator is recommended Faulty chlorinator
No VFD VFD is recommended
No water flowmeter Water flowmeter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Ibrahim Road
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Imran Butt 0323-5024864
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 17 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 250
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2 Cusec 204 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,480 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 4231.9
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve Faulty
Chlorinator Faulty
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping Poor
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate Faulty
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 140 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.20 m/sec
24
Pressure
i) Pressure at Discharge Side of Pump 8 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 384.6 373.4 389.7
ii) Ampere 95.4 89 88.3
iii) Power Factor 0.9 0.89 0.93
iv) Appearant Power (kVA) 64.3 57 59
v) Running Power (kW) 54.6
vi) Reactive Power (kVAr) 26.3 26 21
vi) Motor Working on Loading Basis 91 %
Oversize Undersize Properly Sized
Speed
Poor/ Defective A and V meter
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 96.6
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 18.48 ft
vi) Discharge Side Frictional Head 3.72 ft
vii) Dynamic Discharge Head (v+vi) 22.20 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 153.40 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 37.59
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 826
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 23.88 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 73 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 32.62 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.39 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 17 hrs
xxi) Daily Pump flow 2,380 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 868,700 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 340,610 kWh/yr
xxv) Annual Energy Expenditure on Pumping 4,427,925 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 279 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.20 kWh/m3
xxix) Potential of Energy Reduction 49.81 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 169,650 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,205,453 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 33%. For pump attached with 150 HP motor, efficiency below 58% is considered to be LOW (>68.9 is excellent). This pumping system requires replacement of pump. It is estimated that the new pump will have efficiency of about 65%. This efficiency improvement will save about Rs.2,205,453 annually.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 2,479,000 PKR
Flow meter is recommendedNo flow meter
Replave A and V meter Faulty A and V meter
No VFD VFD is recommended
Defective PFI control Install PFI control unit
No pressure guage Digital pressure guage is recommended
Replace pump (2 Cusec)Pump is inefficient
Faulty NRV Replace NRV
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Salamat Mohallah
ii) Name of Subdivision Ravi Road , Lahore 0301-4027664
iii) Operator Name & Contact Mr. Saleem Faisal Khan
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 13 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 1360.01
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve Faulty
Chlorinator ok
Flow Meter NA
Pressure Gauge NA
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping Poor
Motor Terminal open motor terminals
Foundation/Civil work ok
Ratchet Plate Faulty
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 102 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 0.56 m/sec
Pressure
i) Pressure at Discharge Side of Pump 15 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 374.9 370.2
ii) Ampere 112.3 146
iii) Power Factor 0.66 0.83
iv) Appearant Power (kVA) 73 91
v) Running Power (kW) 66
vi) Reactive Power (kVAr) 54 52
vi) Motor Working on Loading Basis 60 %
Oversize Undersize Properly Sized
Speed
Poor
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 34.65 ft
vi) Discharge Side Frictional Head 0.79 ft
vii) Dynamic Discharge Head (v+vi) 35.44 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 166.64 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 27.38
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 663
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 18.90 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 88 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 21.36 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.65 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 13 hrs
xxi) Daily Pump flow 1,326 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 483,990 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 314,849 kWh/yr
xxv) Annual Energy Expenditure on Pumping 4,093,040 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 310 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxix) Potential of Energy Reduction 67.14 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 211,381 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,747,954 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 21%. For pump attached with 150 HP motor, efficiency below 58% is considered to be LOW (>68.9 is excellent). This pumping system requires replacement of pump. It is estimated that the new pump will have efficiency of about 65%. This efficiency improvement will save about Rs. 2,747,954 per year.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 3,750,000 PKR
Replace pump (4 Cusec)Pump is inefficient
Faulty NRV Replace NRV
No pressure guage Digital pressure guage is recommended
Flow meter is recommendedNo flow meter
Replave A and V meter Faulty A and V meter
No VFD VFD is recommended
Defective PFI control Install PFI control unit
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Sardar Chappal
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Mr. Ghulam Dastgir 0324-9422532
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model B14 B/4 Serial 15--1097
iii) Certification Mark
iv) Year of Manufacture 1998
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 118.59 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 8 (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 210
v) Power Factor (Cos ɸ) 0.8
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 2150.9
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Normal
Non Return Valve Faulty
Chlorinator OK
Flow Meter NA'
Pressure Gauge NA'
Bore Hole in Front of Panel No
Wiring Poor
Housekeeping Poor
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate Faulty
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 27 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 0.15 m/sec
Pressure
i) Pressure at Discharge Side of Pump 4 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 382.9 408.1 421.2
ii) Ampere 83 87.2 74
iii) Power Factor 0.28 0.45 0.5
iv) Appearant Power (kVA) 54 64 53
v) Running Power (kW) 24.33
vi) Reactive Power (kVAr) 51 55 46
vi) Motor Working on Loading Basis 22.2 %
Oversize Undersize Properly Sized
Poor/ Defective A and V meter
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93.1
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 9.24 ft
vi) Discharge Side Frictional Head 0.06 ft
vii) Dynamic Discharge Head (v+vi) 9.30 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 140.50 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 7.25
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 387
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 4.22 hp
xiv) Brake Horsepower (bhp) (OEM Data) 118.59 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 33 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 3.56 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 12.93 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.91 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 432 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 157,680 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 142,849 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,857,038 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 68 %
xxvii) Water Flow after Efficiency Improvement 142 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.17 kWh/m3
xxix) Potential of Energy Reduction 80.98 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 115,682 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,503,860 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 14.3%. For pump attached with 150 HP motor, efficiency below 58% is considered to be LOW (>68.9 is excellent). This pumping system requires replacement of pump and motor (motor is very old which need to be replaced). It is estimated that the new pump and motor will have efficiency of about 65%. This efficiency improvement will save about Rs. 1,326,018 Rs per year.
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 4,916,000 PKR
Replace motor (150 HP)Motor is inefficient
Replace pump (4 Cusec)Pump is inefficient
Faulty NRV Replace NRV
No pressure guage Digital pressure guage is recommended
Flow meter is recommendedNo flow meter
Replave A and V meter Faulty A and V meter
No VFD VFD is recommended
Defective PFI control Install PFI control unit
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Main Outfall Old
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Shaukat Ali 0300 4266838
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 19 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
3 Pump Nameplate Data
i) Make / Brand KSB Country
ii) Model B14 B/4 Serial 9972673821/700
iii) Certification Mark
iv) Year of Manufacture 2014
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 118.2 BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
4 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 10 (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
5 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 350 S
6 Electrical & Mechanical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues
Gland Leakage Significant
Non Return Valve ok
Chlorinator ok
Flow Meter NA'
Pressure Gauge NA'
Bore Hole in Front of Panel No
Wiring Excellent
Housekeeping Good
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
7 Field Measurements
Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 498 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.73 m/sec
Pressure
i) Pressure at Discharge Side of Pump 13 Psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Levels
i) Static Water Level 35 meter
ii) Pumping Water Level 40 meter
Electric Measurements
i) Voltage 350 353 349
ii) Ampere 182 189 190
iii) Power Factor 0.87 0.9 0.89
iv) Appearant Power (kVA) 110 115 114
v) Running Power (kW) 100.6
vi) Reactive Power (kVAr) 53 48 51
vi) Motor Working on Loading Basis 91 %
Oversize . Undersize Properly Sized
Excellent
Speed
i) Speed of Motor 1,495 RPM
ii) Speed of Pump Impeller 1,450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91.3
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
8 Calculations
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 30.03 ft
vi) Discharge Side Frictional Head 18.01 ft
vii) Dynamic Discharge Head (v+vi) 48.04 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 179.24 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 133.70
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,386
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 99.25 hp
xiv) Brake Horsepower (bhp) (OEM Data) 118.2 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 135 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 83.97 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 73.60 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 19 hrs
xxi) Daily Pump flow 9,462 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,453,630 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 701,402 kWh/yr
xxv) Annual Energy Expenditure on Pumping 9,118,224 PKR/Yr
9 Summary of Findings
Pumping system efficiency is 74%. For pump attached with 150 HP motor, efficiency >68.9 is excellent. This pumping system requires no intervention
10 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 710,000 PKR
No pressure guage Digital pressure guage is recommended
Flow meter is recommendedNo flow meter
Install chlorinatorFaulty chlorinator
No VFD VFD is recommended
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Bagh munshi Ladha Disposal Station Pump no 1
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Safdar
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 5
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
Submersible Disposal Pump Qty 6
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model KRTK 300-400/506 UNGI-K Serial
iii) Certification Mark
iv) Year of Manufacture 2009
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H)35
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n)981
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 2
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
9971428577/000100
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 55 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 75 hp 56 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 400 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues good
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring fair
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 957 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 265 m3/hr 4.4167 m3/min
Velocity in Pipe 1.01 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 17 meter
Electric Measurements Volt 400.3 401.5 400.9
Ampere 48.7 58.4 43
kW 17.13 Power Factor 0.65
vi) Motor Working on Loading Basis 31 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 79.7
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 2.53 ft
viii) Total Dynamic Head of Pump (TDH) 20.53 ft
x) Specific Speed of PumpNs = RPM x GPM0.5 / H0.75 impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 6.05 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 22.96 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 26.35 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 3,975 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,450,875 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 94,290 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,225,765 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 614 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 56.81 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 53,567 kWh/yr
xxxi) Annual Financial Saving on Pumping 696,369 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 26.35%. For pump attached with 75 HP motor, efficiency < 56% is considered to be LOW, (above 61% is Good). This pumping system efficiency is less than 30% so pump must be changed to improve efficiency from 26.35% to 61% with annual savings of 696,369 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 3,285,500 PKR
No water flow meter Install water flow meter
voltmeter is not installed
PFI of 100 kvar is recommanded for disposalno PFI PANEL
No pressure gauge Install digital pressure gauge
install new voltmeter
pumping system efficiency is less than 30% installed new pump
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Bagh munshi Ladha Disposal Station Pump no 2
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Safdar
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 5
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
Submersible Disposal Pump Qty 6
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 02
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model KRTK 350-500/908 UNGI-K Serial
iii) Certification Mark
iv) Year of Manufacture 2009
v) Flowrate (Q) 20 Cusec 2,040 m3/hr
vi) Head (H)35
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n)735
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 20
ii) Enter Length of Suction Pipe (ft) 2
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
9971428577/000300
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 20
ii) Length of Discharge Pipe (ft) 55 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 120 hp 90 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 400 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues good
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring fair
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 20 inches
v) Pipe Perimeter 1,595 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 764 m3/hr 12.733 m3/min
Velocity in Pipe 1.05 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 17 meter
Electric Measurements Volt 391.4 393.6 392.2
Ampere 123 120 87
kW 39.66 Power Factor 0.66
vi) Motor Working on Loading Basis 44 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 2.65 ft
viii) Total Dynamic Head of Pump (TDH) 20.65 ft
x) Specific Speed of PumpNs = RPM x GPM0.5 / H0.75 impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 17.54 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 53.16 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 33.00 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 11,460 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 4,182,900 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 218,303 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,837,936 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 64 %
xxvii) Water Flow after Efficiency Improvement 1,482 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 48.43 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 105,734 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,374,542 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 33.%. For pump attached with 120 HP motor, efficiency < 58% is considered to be LOW, (above 64% is Good). This pumping system need impeller adjustment and need repair and maintenance which will improve efficiency from 33% to 64% with annual savings of 1,374,542 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 185,500 PKR
install voltmetervolt meter is not available
No pressure gauge Install digital pressure gauge
pumping syetem need impeller adjustment adjust impeller and aslo need maintenance and repair
No water flow meter Install water flow meter
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Bagh munshi Ladha Disposal Station Pump no 3
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Safdar
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 5
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
Submersible Disposal Pump Qty 6
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 03
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model KRTK 300-400/506 UNGI-K Serial
iii) Certification Mark
iv) Year of Manufacture 2009
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H)35
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) 981 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 2
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
9971428577/000101
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 55 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 75 hp 56 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 400 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues good
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring fair
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 957 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 414 m3/hr 6.9 m3/min
Velocity in Pipe 1.58 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 17 meter
Electric Measurements Volt 396.8 396.8 395.2
Ampere 61 54.7 60
kW 26.8 Power Factor 0.65
vi) Motor Working on Loading Basis 48 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 6.16 ft
viii) Total Dynamic Head of Pump (TDH) 24.16 ft
x) Specific Speed of PumpNs = RPM x GPM0.5 / H0.75 impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 11.12 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 35.92 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 30.95 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 6,210 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,266,650 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 147,517 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,917,718 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 816 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 49.26 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 72,669 kWh/yr
xxxi) Annual Financial Saving on Pumping 944,697 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 30.95.%. For pump attached with 75 HP motor, efficiency < 56% is considered to be LOW, (above 61% is Good). This pumping system need impeller adjustment and need repair and maintenance which will improve efficiency from 30.95% to 61% with annual savings of 944,697 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 185,000 PKR
No water flow meter Install water flow meter
No pressure gauge Install digital pressure gauge
pumping syetem need impeller adjustment adjust impeller and aslo need maintenance and repair
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Bagh munshi Ladha Disposal Station Pump no 4
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Safdar
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 5
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
Submersible Disposal Pump Qty 6
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 04
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model KRTK 350-500/908 UNGI-K Serial
iii) Certification Mark
iv) Year of Manufacture 2009
v) Flowrate (Q) 20 Cusec 2,040 m3/hr
vi) Head (H)35
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) 735 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 20
ii) Enter Length of Suction Pipe (ft) 2
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
9971428577/000301
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 20
ii) Length of Discharge Pipe (ft) 55 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 400 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues good
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring fair
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 20 inches
v) Pipe Perimeter 1,595 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 811 m3/hr 13.517 m3/min
Velocity in Pipe 1.11 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 17 meter
Electric Measurements Volt 390.4 392.5 394.6
Ampere 122 120 104.4
kW 52.43 Power Factor 0.65
vi) Motor Working on Loading Basis 47 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 2.99 ft
viii) Total Dynamic Head of Pump (TDH) 20.99 ft
x) Specific Speed of PumpNs = RPM x GPM0.5 / H0.75 impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 18.93 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 70.28 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 26.93 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 12,165 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 4,440,225 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 288,593 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,751,714 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 64 %
xxvii) Water Flow after Efficiency Improvement 1,912 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 57.59 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 166,201 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,160,616 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 26.93%. For pump attached with 150 HP motor, efficiency < 58% is considered to be LOW, (above 63% is Good). This pumping system efficiency is less than 30% so pump must be changed to improve efficiency from 26.93% to 63% with annual savings of 2,160,616 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 4,085,000 PKR
No pressure gauge Install digital pressure gauge
pumping system efficiency is less than 30% installed new pump
No water flow meter Install water flow meter
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Bagh munshi Ladha Disposal Station Pump no 6
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Safdar
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 5
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
Submersible Disposal Pump Qty 6
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 06
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model EPL 0100478913 Serial
iii) Certification Mark
iv) Year of Manufacture 2013
v) Flowrate (Q) 15 Cusec 1,530 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 18
ii) Enter Length of Suction Pipe (ft) 2
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
5731208
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 18
ii) Length of Discharge Pipe (ft) 55 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 400 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues good
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring fair
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 18 inches
v) Pipe Perimeter 1,436 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 1,179 m3/hr 19.65 m3/min
Velocity in Pipe 1.99 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 17 meter
Electric Measurements Volt 384.5 385 385
Ampere 91.3 105.9 104.7
kW 54.5 Power Factor 0.81
vi) Motor Working on Loading Basis 91 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 9.64 ft
viii) Total Dynamic Head of Pump (TDH) 27.64 ft
x) Specific Speed of PumpNs = RPM x GPM0.5 / H0.75 impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 36.24 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 73.06 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.60 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 17,685 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 6,455,025 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 299,987 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,899,837 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 1,450 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.04 kWh/m3
xxix) Potential of Energy Reduction 18.69 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 56,064 kWh/yr
xxxi) Annual Financial Saving on Pumping 728,830 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 49.60%. For pump attached with 80 HP motor, efficiency < 56% is considered to be LOW, (above 61% is Good). This pumping system need impeller adjustment which will improve efficiency from 49.06% to 61% with annual savings of 728,830 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 85,000 PKR
No water flow meter Install water flow meter
No pressure gauge Install digital pressure gauge
pump needs impeller adjustment adjust impeller
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Marzipura Disposal Station Pump no 1
ii) Name of Subdivision Ravi Road , Lahore
iii) Operator Name & Contact Pervez Naseem
iv) Total Number of Pumps Installed 3
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 2
Submersible Disposal Pump Qty 1
vi) Operational Scheme of Pumps Qty
Independent 3
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day Estimated
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model KWPZ2007315 Serial
iii) Certification Mark
iv) Year of Manufacture 1994
v) Flowrate (Q) 5 Cusec 510 m3/hr
vi) Head (H)76
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 8
ii) Enter Length of Suction Pipe (ft) 80
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 8
ii) Length of Discharge Pipe (ft) 30 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 85 ft
Suction Side Elevation 45 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues poor
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring fair
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches
v) Pipe Perimeter 638 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 170 m3/hr 2.835 m3/min
Velocity in Pipe 1.46 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 34 meter
Electric Measurements Volt 388.4 390.4 387.5
Ampere 42.7 35.6 36
kW 17.66 Power Factor 0.65
vi) Motor Working on Loading Basis 39 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 45 ft
v) Static Discahrge Head 85 ft
vi) Frictional Head (Suction and Discahrge) 5.88 ft
viii) Total Dynamic Head of Pump (TDH) 45.88 ft
x) Specific Speed of PumpNs = RPM x GPM0.5 / H0.75 impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 8.68 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 23.67 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 36.66 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.10 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 2,552 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 931,298 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 97,207 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,263,690 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 283 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.06 kWh/m3
xxix) Potential of Energy Reduction 39.90 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 38,790 kWh/yr
xxxi) Annual Financial Saving on Pumping 504,275 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 36.66%. For pump attached with 80 HP motor, efficiency < 56% is considered to be LOW, (above 61% is Good). This pumping system need impeller adjustment and need repair and maintenance which will improve efficiency from 33.66% to 61% with annual savings of 504,275 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 286,000 PKR
no PFI PLANT PFI of 50 KVAR is recommanded for disposal
No water flow meter Install water flow meter
ammeter is not available
install voltmetervolt meter is not available
No pressure gauge Install digital pressure gauge
install ammeter
pumping syetem need impeller adjustment adjust impeller and aslo need maintenance and repair
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Out fall Disposal Station pump no 1
ii) Name of Subdivision Ravi road , Lahore
iii) Operator Name & Contact Abbas
iv) Total Number of Pumps Installed 3
v) Total Number of Pumps in Operation 3
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 3
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 3
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 2 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
3344338052
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 25 Cusec 2,550 m3/hr
vi) Head (H) 40 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 104 BHP
ix) Speed (n) 740 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 28
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 28
ii) Length of Discharge Pipe (ft) 25 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 180 hp 134 kW
iii) Voltage Range 380 Volts
iv) Current 245 Amperes
v) Power Factor (Cos ɸ) 0.84
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 888 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 630 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues Excellent
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring Good
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 28 inches
v) Pipe Perimeter 2,233 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 1,885 m3/hr 31.417 m3/min
Velocity in Pipe 1.32 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 14 meter
Electric Measurements Volt 365
Ampere 231
kW 115 Power Factor 0.77
vi) Motor Working on Loading Basis 86 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 888 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 4.14 ft
viii) Total Dynamic Head of Pump (TDH) 22.14 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 46.40 hp
xiv) Brake Horsepower (bhp) (OEM Data) 103.77 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 154.16 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 44.71 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 30.10 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 2 hrs
xxi) Daily Pump flow 3,770 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,376,050 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 84,400 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,097,202 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 3,946 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 52.22 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 44,078 kWh/yr
xxxi) Annual Financial Saving on Pumping 573,013 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 30.10%. For pump attached with 180HP motor, efficiency <59% is considered to be low (> 69 is excellent). This pumping system requires impeller adjustment. It is estimated that this impeller adjustment would increase pumping efficiency from 30.10% to 63% which is in the range of GOOD efficiency. This efficiency improvement will save about Rs. 573,013 per year.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 485,000 PKR
No water flow meter Install water flow meter
PFI of 150 kvar is recommanded for disposalNo PFI installed
No pressure gauge Install digital pressure gauge
pump needs impeller adjustment adjust impeller,repair and also need maintenance
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Out fall Disposal Station pump no 2
ii) Name of Subdivision Ravi road , Lahore
iii) Operator Name & Contact Abbas
iv) Total Number of Pumps Installed 3
v) Total Number of Pumps in Operation 3
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 3
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 3
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 2 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
3344338052
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 02
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 25 Cusec 2,550 m3/hr
vi) Head (H) 40 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 104 BHP
ix) Speed (n) 740 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 28
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 28
ii) Length of Discharge Pipe (ft) 25 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 180 hp 134 kW
iii) Voltage Range 380 Volts
iv) Current 245 Amperes
v) Power Factor (Cos ɸ) 0.84
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 888 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 630 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues Excellent
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring Good
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 28 inches
v) Pipe Perimeter 2,233 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 2,025 m3/hr 33.75 m3/min
Velocity in Pipe 1.42 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 14 meter
Electric Measurements Volt 384 384
Ampere 253 253
kW 125.2 Power Factor 0.82
vi) Motor Working on Loading Basis 93 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 888 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 4.77 ft
viii) Total Dynamic Head of Pump (TDH) 22.77 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 51.28 hp
xiv) Brake Horsepower (bhp) (OEM Data) 103.77 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 167.83 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 49.41 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 30.55 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 2 hrs
xxi) Daily Pump flow 4,050 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,478,250 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 91,886 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,194,519 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 4,175 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 51.50 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 47,324 kWh/yr
xxxi) Annual Financial Saving on Pumping 615,206 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 30.55%. For pump attached with 180HP motor, efficiency <59% is considered to be low (> 69 is excellent). This pumping system requires impeller adjustment. It is estimated that this impeller adjustment would increase pumping efficiency from 30.55% to 63% which is in the range of GOOD efficiency. This efficiency improvement will save about Rs. 615,206 per year.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 185,000 PKR
No pressure gauge Install digital pressure gauge
pump needs impeller adjustment adjust impeller,repair and also need maintenance
No water flow meter Install water flow meter
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Out fall Disposal Station pump no 3
ii) Name of Subdivision Ravi road , Lahore
iii) Operator Name & Contact Abbas
iv) Total Number of Pumps Installed 3
v) Total Number of Pumps in Operation 3
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 3
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 3
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 2 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
3344338052
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 03
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 25 Cusec 2,550 m3/hr
vi) Head (H) 40 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 104 BHP
ix) Speed (n) 740 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 28
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 28
ii) Length of Discharge Pipe (ft) 25 estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 35 ft
Suction Side Elevation 17 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 180 hp 134 kW
iii) Voltage Range 380 Volts
iv) Current 245 Amperes
v) Power Factor (Cos ɸ) 0.83
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 888 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 630 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues Excellent
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring Good
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 28 inches
v) Pipe Perimeter 2,233 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 2,038 m3/hr 33.967 m3/min
Velocity in Pipe 1.43 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 14 meter
Electric Measurements Volt 362
Ampere 244
kW 126 Power Factor 0.81
vi) Motor Working on Loading Basis 94 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 888 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 17 ft
v) Static Discahrge Head 35 ft
vi) Frictional Head (Suction and Discahrge) 4.84 ft
viii) Total Dynamic Head of Pump (TDH) 22.84 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 51.75 hp
xiv) Brake Horsepower (bhp) (OEM Data) 103.77 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 168.90 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 49.87 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 30.64 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 2 hrs
xxi) Daily Pump flow 4,076 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,487,740 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 92,473 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,202,151 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 4,191 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.03 kWh/m3
xxix) Potential of Energy Reduction 51.37 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 47,504 kWh/yr
xxxi) Annual Financial Saving on Pumping 617,547 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 30.64%. For pump attached with 180HP motor, efficiency <59% is considered to be low (> 69 is excellent). This pumping system requires impeller adjustment. It is estimated that this impeller adjustment would increase pumping efficiency from 30.64% to 63% which is in the range of GOOD efficiency. This efficiency improvement will save about Rs. 617,547 per year.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 185,000 PKR
No water flow meter Install water flow meter
No pressure gauge Install digital pressure gauge
pump needs impeller adjustment adjust impeller,repair and also need maintenance
ANNEXURE-2
Selected Pictures
Poor housekeeping at Outfall disposal 1
View of pump at Outfall disposal 1
Poor panel with defective PFI at Bajri Adda
Open motor connections at Bajri Adda
Good electric panels at Bagh Musnhi Ladha disposal
Poor View of discharge pipe line at Gulshan Riaz Colony
Poor housekeeping at Ibrahim Road
Poor pump at Merzipura disposal
Outdated electric wiring at Merzipura disposal Close view of outdated wiring at Merzipura disposal
Open pump at motor at Ravi Park 1 Cloth washing and bathing at Ravi Park 1
.
Poor housekeeping at Ravi Park 1
Gland leakage at Salamat Mohalla
Poor electric panel at Salamat Mohalla
Open motor connections at Shafiqabad