     Payment Claim

    Payment claims made by the Head

    Contractor to Principal must includesupporting statement

    10 business days or time required bythe contract, whichever is less, to

    provide Payment Schedule

    Payment Schedule

    received?

     After Due Date passes, issue a17(2) Notice. Claimant has 20

    business days from Due Date toissue notice

    Payment Schedule

    received?

    Respondent has 5 business days afterreceiving notice to provide schedule

    10 business days to submit

     Adjudication Application

    Adjudication Application

    Amount is less than

    claimed or $NIL

    Claimant does not dispute

    Schedule but Respondent

    fails to pay by Due Date

    10 business days to submit

     Adjudication Application

    20 business days to submit

     Adjudication Application

    Adjudication Application

    Adjudication response from

    respondent

    If respondent lodges Adjudication response,

    must lodge response within 5 business daysfrom receiving application or 2 businessdays from receiving notice of adjudicator

    acceptance, whichever is later 

    Adjudicator DecisionDue within 10 business days of the adjudicator’s acceptance

    Pay Adjudicator’s feesMust be paid before decision is released

    Respondent has 5 business days from releaseof the decision to pay the adjudicated amount

    No

    No

    Yes

    Yes

    Yes No

    Security of payment claim and adjudication process flow chart