Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

30
Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011

Transcript of Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

Page 1: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

Pawan Sarang, P.E.

District Drainage Engineer

Northern Virginia District

May 18, 2011

Page 2: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

2

VDOT - Stormwater Management Requirements

Update

Page 3: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

3

Virginia Stormwater Management Law is codified in Title 10.1, Chapter 6 of the Code of Virginia and the Virginia Stormwater Management Regulations are found at Chapter 60 and Chapter 30 of the Virginia Administrative Code (4VAC50-60-50, 4VAC50-30-40, 4VAC50-60-60, 4VAC50-60-70 & 4VAC50-60-80). The Law and Regulations together provide the authority and the technical criteria for the Virginia Stormwater Management Program (SWM Program).

VDOT is a MS-4 Permit Holder and executes Annual Agreement for its Standards and Specifications with DCR which includes SWM Program and Erosion and Sediment Control Program.

DCR reserves the right to randomly select projects for review (in either the design or construction phase) to ensure compliance with the VDOT approved Program.

Page 4: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

4

The Virginia Stormwater Management Regulations are applicable to all Regulated Land Disturbance Activities (RLDA) undertaken by or for VDOT including, but not limited to projects and activities developed under the following plan processes: RAAP

SAPP

Minimum

No Plan

PPTA

Design Build

Capital Outlay

Rural Rustic

Non Routine/Routine Maintenance Activities *

• All routine maintenance activities exempted by 2011 G.A.

changes to the VSMP Law (Section 10.1-603.8)

Page 5: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

5

Land Disturbance (as defined in the VSMP Regulations):

A manmade change to the land surface that potentially changes its runoff characteristics including any clearing, grading or excavation associated with the proposed activity

Grading of gravel surfaces to maintain travel way generally exempt *

Pavement milling and/or overlay generally exempt *

* Changes by the 2011 G.A to the VSMP Law (Section 10.1-603.8) classifies paving an impervious surface and the associated shoulder and ditch restoration as routine maintenance activities and, therefore, exempt from

VSMP Regulation requirements.

Page 6: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

6

Current SWM Requirements

SWM Requirements are applicable for those regulated land disturbance activities that disturb one acre or greater except in those areas designated as a Chesapeake Bay Preservation Area in which case the land disturbance threshold is 2500 square feet or greater.

The following land disturbance activities are exempt for the VSMP Regulations for linear development projects (i.e., highway construction projects) where all the following conditions are met: Less than one acre will be disturbed per outfall or watershed.

There will be insignificant increases in peak flow rates downstream of the discharge point.

There is no existing or anticipated erosion problems downstream of the discharge point.

There is no existing or anticipated flooding problems downstream of the discharge point.

Typically applied on an outfall by outfall basis

• Routine maintenance that is performed to maintain the original line and grade, hydraulic capacity or original construction of the project and which disturbs less than five acres of land.

Page 7: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

7

Current SWM Requirements

As part of VDOT Annual Agreement with DCR, following are design criteria addressing water quality under VDOT SWM Requirements:

Using Technology Approach: 1. Base the percent impervious cover on the entire post construction

impervious area within the right of way plus permanent easement area per outfall.

2. Determine the required BMP based on the percent impervious calculated from No. 1 above.

Using Performance Approach:Design the BMP for a water quality volume based on the net increase in impervious

area plus 10% of the pre-construction impervious area. The goal is to determine BMP that would remove pounds of phosphorus to 10% less then existing loading.

Water quantity control shall be governed by the Virginia Erosion and Sediment Control Regulation Minimum Standard - 19 (MS-19) that requires an adequate receiving channel for stormwater outfalls

http://www.virginiadot.org/business/locdes/hydra-drainage-manual.asp

Page 8: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

8

WATER QUALITY ANALYSISLINEAR DEVELOPMENT PROJECTS

(BASED ON AN INDIVIDUAL OUTFALL ANALYSIS)TECHNOLOGICAL BASED CRITERIA

Step 1 – Is there one acre or more of land disturbance within the site draining to the outfall?

Yes – Not Exempt - Go to Step 5 No - Go to Step 2

Step 2 - Is the land disturbance activity generating a significant increase in discharge

downstream of the outfall point? (Note: The adequacy of the downstream channel to accommodate any increased discharge without causing flooding and erosion problems can be used as one measure of whether or not there is a “significant” increase in discharge.

Yes – Not Exempt – Go to Step 5 No – Go to Step 3

Step 3 - Is there existing or potential flooding issues downstream of the outfall point? Yes – Not Exempt - Go to Step 5 No – Go to Step 4

Step 4 - Is there existing or potential erosion issues downstream of the outfall point? Yes – Not Exempt - Go to Step 5 No – Outfall exempt – Go to Step 1 for next outfall

Step 5 - Determine pre-developed impervious area within the site draining to outfall.Step 6 - Determine post developed impervious area within the site draining to outfall.Step 7 - Determine net increased impervious area within the site draining to outfall:

o Step 6 answer minus Step 5 answer

Page 9: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

9

WATER QUALITY ANALYSISLINEAR DEVELOPMENT PROJECTS

(BASED ON AN INDIVIDUAL OUTFALL ANALYSIS)

Step 8 – Is Step 7 answer zero or a negative number? Yes – Outfall exempt – Go to Step 1 for next outfall No – Go to Step 9

Step 9 – Determine the post development site area of the site draining to the outfall.

Step 10 - Determine percent impervious of the site:

o Step 7 answer divided by Step 9 answer

Step 11 – Is the Step 10 answer 16% or greater? Yes – Go to Step 12 No – Outfall exempt – Go to Step 1 for next outfall

Step 12 - Determine required BMP from BMP Table based on percent impervious from Step 10 (this time from Total Impervious Area draining to outfall)

Step 13 - Determine WQV:

o Step 6 answer times 0.5”

Step 14 - Determine BMP volume:

o Step 13 answer times appropriate value for the selected BMP

Step 15 – Go to Step 1 for next outfall.

Page 10: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

10

WATER QUALITY ANALYSISLINEAR DEVELOPMENT PROJECTS

(BASED ON AN INDIVIDUAL OUTFALL ANALYSIS)

PERFORMANCE BASED CRITERIAStep 1 – Is there one acre or more of land disturbance within the site draining to the outfall?

Yes – Not Exempt - Go to Step 5 No - Go to Step 2

Step 2 - Is the land disturbance activity generating a significant increase in discharge downstream of the outfall point? (Note: The adequacy of the downstream channel to accommodate any increased discharge without causing flooding and erosion problems can be used as one measure of whether or not there is a “significant” increase in discharge.)

Yes – Not Exempt - Go to Step 5 No – Go to Step 3

Step 3 - Is there existing or potential flooding issues downstream of the outfall point? Yes – Not Exempt - Go to Step 5 No – Go to Step 4

Step 4 - Is there existing or potential erosion issues downstream of the outfall point? Yes – Not Exempt - Go to Step 5 No – Outfall exempt – Go to Step 1 for next outfall

Step 5 – Determine the post development area of the site draining to the outfall. Step 6 - Determine pre-developed impervious area from the site draining to outfall.Step 7 - Determine post developed impervious area from the site draining to outfall.Step 8 – Determine pre-developed percent impervious of the site:

o Step 6 answer divided by the Step 5 answer

Page 11: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

11

WATER QUALITY ANALYSISLINEAR DEVELOPMENT PROJECTS

(BASED ON AN INDIVIDUAL OUTFALL ANALYSIS)

Step 9 – Determine post developed percent impervious of the site:o Step 7 answer divided by the Step 5 answer

Step 10 - Is the Step 8 answer 16% or less and the Step 9 answer less than 16%? Yes – No reduction in post development pollutant load required – Go to Step 1 for next outfall. No – Go to Step 11

Step 11 - Is the Step 8 answer 16% or less and the Step 9 answer greater than 16%?

Yes – The post development pollutant discharge shall not exceed the pre-development pollutant discharge based on 16% imperviousness. Go to Step 14

No – Go to Step 12

Step 12 - Is the Step 8 answer greater than 16%? Yes – Go to Step 13 No - Go to Step 10

Step 13 - Determine WQV:o Step 6 answer times 0.5”

Step 14 - Determine BMP volume:o Step 13 answer times appropriate value for the selected BMP*

Step 15 – Go to Step 1 for next outfall.

*Refer to DCR SWM Handbook for load removal worksheets.

Page 12: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

12

Current BMP Selection Table 11-1 VDOT Drainage Manual

Water Quality BMP Treatment VolumeTarget Phosphorus Removal

EfficiencyPercent Impervious

Cover**

Vegetated filter stripGrassed swale

10%15% 16-21%

Constructed wetlandsExtended detention Retention basin I

2xWQV2xWQV3xWQV

20%35%40%

22-37%

Bioretention basinBioretention filterExtended detention-enhancedRetention basin II Infiltration

4xWQV1xWQV

50%50%50%50%50%

38-66%

Sand filterInfiltration Retention basin III withaquatic bench

2xWQV4xWQV

65%65%65% 67-100%

*Innovative or alternate BMPs not included in this table may be allowed at the discretion of DCR and VDOT.**Percent Impervious Cover: The ratio of the new impervious area and the area within the right-of-way and easements per project outfall.

Page 13: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

13

Current IIM-195.7 HighlightsEntire lIM has been revised to add better clarity and organization tocontent. Definition section added to clarify meaning of various terms as they relate to

VDOT activities. "Site area" is defined for both linear and non-linear projects. Provides guidance on the use permanent easements for determining site area. Provides guidance on SWM requirements for work being performed on VDOT

rights of way under a Land Use Permit.o Based on the requirements of State and local regulatory programs such as MS4,

TMDL, Tributary Strategy, etc. Guidance on SWM requirements for roadways being developed by other but

which will come into the VDOT system for maintenance/operation (e.g., Subdivision Streets).

o Based on the requirements of State and local regulatory programs such as MS4, TMDL, Tributary Strategy, etc.

Provides guidance on exemption for milling and/or overlaying/reconstruction of existing impervious surfaces.

o Area of existing pavement exempt.o Shoulder or ditch grading/filling not exempt.

Clarifies use of individual outfall analysis in determining application of VSMP Regulations requirements for linear projects

Page 14: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

14

Current IIM-195.7 Highlights (cont.) Provides separate sections defining criteria/requirements for:

o Stream channel erosion

o Flooding Water quality requirements Provides guidance for both linear and non-linear projects. Provides guidance on both Performance Based and Technology Based

water quality criteria. For Technical Based criteria for linear projects:

o Post development percent impervious based on net increase in

Impervious area . Same as IIM-195.6 guidance . Good until 1/11/2012.

Water Quality Volume for required BMPs based on total post development impervious area from within site draining to BMP . Change from IIM-195.6 requirement.

Page 15: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

15

Projects, such as subdivision streets, industrial access roads, etc., which are designed and constructed by other parties and which are eligible for acceptance into the state roadway system for maintenance after completion of construction are not considered state agency projects and must, typically, conform to appropriate local regulations.

Prior to the issuance of a VDOT Land Use Permit or the acceptance of a roadway facility into the state roadway system, land disturbing activities which occur in a designated MS4 area or a watershed with an approved TMDL plan shall be reviewed by the appropriate VDOT personnel for compliance with the conditions of the MS4 General Permit and/or the approved TMDL plan and the requirements of the VDOT Implementation Plan for the MS4 General Permit conditions. Those activities found not to comply with the conditions of the MS4 General Permit or an approved TMDL plan or the VDOT MS4 Implementation Plan requirements and responsibilities shall not be issued a Land Use Permit nor be accepted into the state system of roadways until such compliance is demonstrated.

Current SWM Requirements

Page 16: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

16

Current Directive on Low Impact Development (LID) Practices use within VDOT Maintained Right of Way

Currently, DCR has no published credits for LID practices in meeting water quality requirements. However, such practices are being requested as a means to improve water quality. If there is a proposal to use LID practices to meet water quality requirements, VDOT would need to get DCR concurrence on a project by project basis.

Language in the VDOT Subdivision Street Acceptance Policies is encouraging LID practices, even to the allowance of such inside VDOT right of way (with acceptable maintenance agreements with the locality). For those items inside the right of way, either our maintenance personnel would have to agree to the future maintenance requirements or we would have to execute agreements with the locality for them to maintain such facilities (assuming the facilities are constructed in conjunction with a subdivision development or County project).

Page 17: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

17

Use of Manufactured Best Management Practices (BMP)

VDOT prefer to only use manufactured BMPs (and the oil grit separators are just one of many types) as a last resort. Use of such facilities requires review and approval by VDOT Central Office - Location and Design - Hydraulic Section.

Other conventional (and not so conventional) surface facilities are preferred where VDOT will have maintenance responsibility.

Page 18: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

18

Stormwater Pollution Prevention Plan (SWPPP)

A Stormwater Pollution Prevention Plan (SWPPP) identifies potential sources of pollutants which may reasonably be expected to affect the stormwater discharges from the construction site and any off site support areas and describes and ensures implementation of practices which will be used to reduce pollutants in such discharges.

Page 19: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

19

Stormwater Pollution Prevention Plan (SWPPP)

Required for all Land Disturbing Activities

Needing VSMP Construction Permit Coverage (VSMP Law and Regulations)

Needing ESC Plan (VDOT R&B Specification 107.16(e))

VDOT Guidance – IIM-LD-246 (latest version)

Page 20: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

20

Things on the Horizon*

*Following Slides from Mr. Roy Mills earlier presentation.

Page 21: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

21

New VSMP Regulations (DCR)

Items Impacting VDOT Projects

New water quality requirements

New BMP facilities

New water quantity requirements for channel erosion and flooding (replaces MS19)

Projects with allocated funds in Six Year Program grandfathered until 7/1/2019

Page 22: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

22

Effluent Limitation Guidelines (EPA) For Construction Site Run-off.

Implemented by EPA November 2009

Requires best available BMP’s for land disturbances less than 20 acres initially, then less than 10 acres.

Requires numeric turbidity limits (NTU) to be met for construction site runoff from land disturbances 20 acres or greater initially, then 10 acres or greater.

Requires monitoring to demonstrate compliance with numeric limits.

Page 23: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

23

Effluent Limitation Guidelines (EPA) (Cont.)

Home Builders Association challenged EPA in court on numeric limit values.

EPA delayed implementation of numeric limitations until further study (18 months).

Effluent Limitation Guidelines (ELGs) will have to be included by DCR in VSMP General Construction Permit before they are required on land disturbance activities in Virginia. Current General Construction Permit expires on June 30, 2014.

Page 24: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

24

TMDL Plans for Impaired Waters (DEQ)

Mandated by EPA as a result of court decree.

Implemented through the VSMP MS4 and Construction Permits

10 implementation plans approved for current VSMP MS4 and Construction Permit cycles.

Hundreds of additional implementation plans required to be addressed during next 5 year permit cycles.

Page 25: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

25

TMDL Plans for Impaired Waters (DEQ) (Cont.)

Defines the pollutant of concern and develops a WLA for Permittee.

Typical pollutants are sediment, bacteria, nutrients, etc.

Flow TMDL now being used as a surrogate . Limitations placed on the amount of flow that can be released from site (e.g., 50% of one year 24 hour storm).

Page 26: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

26

Chesapeake Bay Total Maximum Daily Load (TMDL)

Mandated by EPA by way of Presidential Executive Order

Pollutants of concern – phosphorus, nitrogen and sediment

Limitations placed on Agriculture, Urban Development, CSOs and Onsite Septic Systems

Impacts over 50% of the area of the State

Page 27: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

27

Chesapeake Bay TMDL (Cont.)

Draft Va. Watershed Implementation Plan (WIP) submitted to EPA in September 2010

EPA approved TMDL on 12/29/10

Approved TMDL Includes Va. WIP (Phase I)

Virginia Phase II WIP currently under development (due for completion by end of this year)

Page 28: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

28

Chesapeake Bay TMDL (Cont.)

Interim evaluation and course correction as needed in 2017

Target completion date of 2025 for full implementation of the CB TMDL program

Will potentially require BMP retrofits on roadways and facilities without any current BMPs and modifications to existing BMPs to achieve greater pollutant removal efficiency.

Page 29: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

29

Impacts On VDOT Projects

MORE design time and cost

MORE right of way cost

MORE construction time and cost

MORE maintenance time and cost

Page 30: Pawan Sarang, P.E. District Drainage Engineer Northern Virginia District May 18, 2011.

30

QUESTIONS ?