Patton kanban

32
Using Kanban Techniques to Control Incremental Development Jeff Patton AgileProductDesign.com [email protected] Download this presentation at: www.agileproductdesign.com/downloads/patton_kanban.ppt

description

hiiiiiii

Transcript of Patton kanban

Page 1: Patton kanban

Using Kanban Techniques to Control Incremental Development

Jeff Patton

AgileProductDesign.com

[email protected]

Download this presentation at: www.agileproductdesign.com/downloads/patton_kanban.ppt

Page 2: Patton kanban

In this short talk we’ll cover:

1. What is a Kanban System and how does it apply to software

development?

2. How to set up a development team Kanban System

3. Applying Lean thinking to software development

2

Page 3: Patton kanban

看板 – Kanban cards limit excess work in progress看板 – Kanban literally means “visual card,” “signboard,” or “billboard.”

Toyota originally used Kanban cards to limit the amount of inventory tied up in “work in progress” on a manufacturing floor

Not only is excess inventory waste, time spent producing it is time that could be expended elsewhere

Kanban cards act as a form of “currency” representing how WIP is allowed in a system. 3

Page 4: Patton kanban

Kanban simulation

Let’s simulate a simple process, then see if we can improve it by adding a Kanban

system.

I’ll need 5 volunteers to manufacture the latest in high-tech aircraft

4

Page 5: Patton kanban

Why use Kanban in Software

Development?(we’re not building aircraft – or anything tangible really)

5

Page 6: Patton kanban

Time-boxed iterative development has challenges Common problems include:•Short time-boxes give more frequent opportunity to measure progress and inspect software but force development items to be smaller•Smaller development items are often too small to be valuable and difficult to identify•Quality of requirements suffers as analysts rush to prepare for upcoming cycles•Quality of current development suffers when busy analysts are unable to inspect software or answer questions during development•Quality often suffers as testers race to complete work late in the development time-box

6

Page 7: Patton kanban

Inside an iteration, effort across roles is uneven

Development work often continues throughout a cycle while testing starts late and never seems to get enough time

7

Page 8: Patton kanban

Using a Kanban approach in software

drops time-boxed iterations in favor of

focusing on continuous flow.

8

Page 9: Patton kanban

How to set up a simple Kanban system for a

software development team.

9

Page 10: Patton kanban

1. Define a work process flow

Look at the typical flow for features, stories, or work packages and describe typical process steps

This simple process flow has the steps: 1.elaboration & acceptance criteria2.development3.test4.deployment

10

Page 11: Patton kanban

2. Lay out a visual Kanban board

Place a goals column on the left, then a waiting queue, the process steps, and a final “done” column to the right

Place an expedite track above the main left to right queue

Place “done and waiting” queues between each work queue(in this example they’re placed below)

11

Page 12: Patton kanban

3. Decide on limits for items in queue and work in progress

A good limit is a factor of the number of people in a role that can work on an item in a given process step. Start with number of people * 1.5

This board uses painters tape to indicate available “slots” for work in progress

12

Page 13: Patton kanban

4. Place prioritized goals on the left column of the board

A good goal describes the outcome we hope to achieve after software ships. Goals help keep focus on the larger outcome.

Having goals visible:•promotes focus •helps us prioritize•helps us manage feature scope & requirements

13

Page 14: Patton kanban

5. Start the board by placing stories or features in queue

Mark on the story or feature card the date it entered the queue. This begins our measurement of cycle time.

Product owners manage the waiting queue

14

Page 15: Patton kanban

6. Move features through the process flow as work is completed

As the story enters the first process step, mark that date on the card. This is the start date. As it’s finished, mark that date on the card. This is the finish date.

15

Page 16: Patton kanban

7. Use the dates on the cards to calculate cycle time

Use average cycle time to set wait times from different points on the board. Pay attention to flow and bottlenecks: relieving bottlenecks as quickly as possible.

Cycle time = finish date – start date

The average cycle time from the date the item enters the board is the wait time from this point in the queue

16

Page 17: Patton kanban

Display and manage cycle times

Reduce the number of Kanban slots allowed until cycle time remains unchanged

Reduce the size of development items

•Work in progress is actually the number of items * the average size of items

Identify and act on bottlenecks immediately

•Relieve repeated bottlenecks by changing the number and types of people in each role and cross training

Disneyland’s public display of cycle-times

17

Page 18: Patton kanban

Kanban Boards

18

Page 19: Patton kanban

Kanban Boards

19

Page 20: Patton kanban

Kanban Boards

20

Page 21: Patton kanban

Kanban Boards

21

Page 22: Patton kanban

Kanban Boards

22

Page 23: Patton kanban

Explode large process steps into tasks to improve visibilityWhen a feature, user story, or work item is large:

Takes longer than a couple days to complete Requires that multiple people collaborate on its completion

Decompose that step into cards to track independently

Feature to develop Tasks in queue

Tasks in progress

Tasks complete

Feature complete

23

Page 24: Patton kanban

Kanban Board with Task Decomposition

24

Page 25: Patton kanban

Use cumulative flow diagrams to visualize work in progress

www.agilemanagement.net/Articles/Papers/BorConManagingwithCumulat.html25

Page 26: Patton kanban

Use cumulative flow diagrams to visualize work in progress

www.agilemanagement.net/Articles/Papers/BorConManagingwithCumulat.html26

Page 27: Patton kanban

Keep time-boxed product and process inspectionKeep regular time-boxes in your process as a cue for product inspection:•Evaluate the quality of the growing product from a functional, engineering, and user experience perspective

Evaluate your pace of development:

•Look at the number of development items completed relative to goals•Look at the average cycle time per development item•Calculate the ratio of developer days per completed item. Use this ratio to estimate the completion time for undeveloped items•Adjust your development plan as necessary

Evaluate and adjust the process you’re using

•Use a process reflection session to identify changes you could make to improve your product or pace

Ending cycles right: http://www.stickyminds.com/s.asp?F=S14865_COL_2 27

Page 28: Patton kanban

Begin looking at your process using Lean thinking

Cockburn’s Software Engineering in the 21st Century: http://alistair.cockburn.us/Software+engineering+in+the+21st+century.ppt

28

Page 29: Patton kanban

Since we’re engaged in “knowledge work” look at the cycle time of validated decisions, or knowledge

Cockburn’s Software Engineering in the 21st Century: http://alistair.cockburn.us/Software+engineering+in+the+21st+century.ppt

29

Page 30: Patton kanban

Often the feedback loop is overlooked – it’s the invisible backed-up queue

Cockburn’s Software Engineering in the 21st Century: http://alistair.cockburn.us/Software+engineering+in+the+21st+century.ppt

30

Page 31: Patton kanban

Setting up a simple Kanban system starts to focus the team on the cycle-time of

delivered work and gives a way to detect and begin to

resolve bottlenecks

31

Page 32: Patton kanban

33

• Anderson, Kanban in Action: http://www.agilemanagement.net/Articles/Weblog/KanbaninAction.html

• Hiranabe, Kanban Applied to Software Development: from Agile to Lean: http://www.infoq.com/articles/hiranabe-lean-agile-kanban

• Ladas, Scrumban - Essays on Kanban Systems for Lean Software Development: http://www.lulu.com/content/3864767

• Ladas, Scrum-ban: http://leansoftwareengineering.com/ksse/scrum-ban/

• Belshee, Naked Planning, Kanban Simplified: http://joearnold.com/2008/03/naked-planning-kanban-simplified/

Kanban References: