Patient Care Tower Entry/Lobby Surgery Expansion Learning...
Transcript of Patient Care Tower Entry/Lobby Surgery Expansion Learning...
MEMORIAL MEDICAL CENTER
SCHEMATIC DESIGN PROGRESS SET - BOARD PACKET | 06 SEPTEMBER 2012
Patient Care Tower | Entry/Lobby | Surgery Expansion | Learning Institute | Infrastructure
Table of Contents
01 Executive Summary02 Campus Images
Project ScopeAerial Rendering
03 Entry / LobbySite PlanFloor Plan
04 Surgery ExpansionRenderingStacking DiagramPlans
05 Patient Care TowerRenderingStacking DiagramPlans3D Patient Room
06 Learning InstituteRenderingStacking DiagramPlans
07 InfrastructureOverview of Key Upgrades
Executive SummaryPATIENT CARE TOWER
After considerable study, the best location for new patient beds was determined to be the Patient Care Tower of E Building. This building was built in the late 1980’s with a lower level, street level and second level. However, the building was designed at that time to add up to six (6) additional floors in the future. As time passed and codes changed, the current seismic requirements will only allow for three (3) additional patient floors to be constructed on top of E Building. The building has an odd shape, but through careful planning, it was determined that each floor can effectively accommodate 38 patient beds with all of the necessary support areas needed. The three floors provide a total of 114 new private patient rooms, bringing the new total number of private patient rooms to 294. The Hospital plans to remove beds from current semi-private rooms to get 100% private beds once all of the moves have been made. This new addition will be approximately 103,000 gross square feet (GSF) (34,335 per floor). The new Penthouse will be approximately 12,000 GSF (includes elevator and stair).
SURGERY EXPANSION
In order to accommodate the new operating rooms and support functions necessary to improve efficiencies, the Surgery Department needs to be expanded. With the current department surrounded on all sides by either the street, or other hospital functions, it was determined early that the Wedeberg Conference Center will need to be relocated. The current space in this building is not sufficient for the needed addition, so it will be demolished and a new larger, two story space will be built in its place. This new addition will be approximately 34,360 BGSF (17,730 GSF Level 1, 16,630 Level 2). The new Penthouse will be approximately 7,900 GSF (includes stair).
The new addition will house six (6) new operating rooms, with all of the needed pre and post operative holding rooms. The existing Surgery Suite will require some renovation including additional PACU beds, locker room expansion, and expansion of some support areas. One existing operating room will be taken out of service to facilitate the renovated areas. The Renovation Expansion in the Lower Level will be approximately 14,825 GSF (8,370 SF Support, 5,225 SF Locker/Lounge, 1,230 SF ORs).The results are that current operating rooms go from 18 in the Surgery Suite to 23. With the simultaneous improvements to the flow before and after surgery, the efficiency of the surgery suite is expected to improve significantly, resulting in many more cases per year.
FRONT-ENTRY AND LOBBY
The front entry of the existing hospital does not engage patients and visitors in a way that reflects the organization’s principles. Additionally, the existing car stacking arrangement is confusing, and crowded. Once one enters the main lobby, the finishes are dated, lighting is muted, and location of services are not clear.
The project includes a new canopy and re-organization of the driveway and landscape features at the main entry to the hospital to improve site circulation, and the front image of the hospital. Also included is a renovation of the existing main lobby to incorporate new finishes, a relocated and somewhat smaller gift shop, a coffee shop, a new greeter station, a relocated vestibule, a new revolving door and new seating areas.
Executive SummaryINFRASTRUCTURE
As space is added to the Hospital, various aspects of infrastructure will need to be increased in capacity in order to support those additions. Simultaneously, it is identified that some of the systems needing increased capacities, are also reaching the end of their useful life, or otherwise ineffective or inefficient. Therefore, several strategies to improve the central energy plant for the Hospital and plan for future growth are included in the project. Some of these strategies and improvements are identified herein. To accommodate the improvements and growth in the infrastructure, a central utility plant two story addition of approximately 4,500 GSF is anticipated (2,250 GSF per level).Overall, one main goal for the project is to maintain current energy use levels, while adding the square footage required for the project. This will be a significant challenge, but the team has identified several strategies which, if implemented, can move the hospital close to succeeding in this endeavor.
LEARNING INSTITUTE
With the demolition of the existing Wedeberg Conference Center, a new place needed to be identified for that function. Simultaneously, the space currently occupied by the surgical skills laboratory was identified as needed space for the Surgery Renovation. Since that function needed to move, a decision was made to combine all simulation aspects of the Hospital, with the Conference Center into a single new building. After studying multiple locations for the building, taking into account parking considerations, adjacency and ease of access from the hospital, and good space utilization practices, the property to the south of Miller Street was identified as the best location for this function. The Hospital currently owns the property which is used as a surface parking lot. The new facility will be approximately 50,000 gross square feet (GSF) and will connect to the existing parking facility on the north side of Miller Street through the use of a connector bridge. Parking for this facility was studied in depth, and we believe the required number of parking spaces for the campus will not exceed the current level of parking existing. However, the addition of this building and the parking spaces displaced by the building will likely cause stress on the current parking situation, requiring patients and staff to park farther away from the hospital. Therefore, new surface lots are planned nearby, and the new garage at Springfield Clinic First North is being redesigned to support an additional 100 spaces. The costs of these two projects are outside of this project budget.
Q2 Q3 Q4
2012 2013 2014 2015
Q1 Q2Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q3Q4 Q4
Project Schedules
LEARNING INSTITUTE
SCHEMATIC DESIGN: 02 Jul 2012 – 24 Sep 2012DESIGN DEVELOPMENT: 25 Sep 2012 – 14 Jan 2013CONSTRUCTION DOCUMENTS: 15 Jan 2013 – 15 Apr 2013BIDDING: 16 Apr 2013 – 13 May 2013CONSTRUCTION: 12 Jun 2013 – 18 Jul 2014
SURGERY EXPANSION
SCHEMATIC DESIGN: 02 Jul 2012 – 24 Sep 2012DESIGN DEVELOPMENT: 25 Sep 2012 – 28 Jan 2013CONSTRUCTION DOCUMENTS: 29 Jan 2013 – 20 May 2013BIDDING: 21 May 2013 – 02 Jul 2013CONSTRUCTION: 18 Jul 2013 – 12 Nov 2014
Q2 Q3 Q4
2012 2013 2014 2015
Q1 Q2Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q3Q4 Q4
INFRASTRUCTURE
SCHEMATIC DESIGN: 02 Jul 2012 – 24 Sep 2012DESIGN DEVELOPMENT: 25 Sep 2012 – 21 Dec 2012CONSTRUCTION DOCUMENTS: 24 Dec 2012 – 18 Mar 2013BIDDING: 19 Mar 2013 – 11 Jun 2013CONSTRUCTION: 12 Jun 2013 – 01 Jun 2015
PATIENT CARE TOWER (INCLUDING LOBBY/ENTRY)
SCHEMATIC DESIGN: 04 Jun 2012 – 24 Sep 2012DESIGN DEVELOPMENT: 25 Sep 2012 – 25 Feb 2013CONSTRUCTION DOCUMENTS: 26 Feb 2013 – 16 Sep 2013BIDDING: 17 Sep 2013 – 11 Nov 2013CONSTRUCTION: 12 Nov 2013 – 01 Dec 2015
Project Schedules
INFRASTRUCTURE
PATIENT CARE TOWER
SURGERY EXPANSIONENTRY/LOBBYLEARNING INSTITUTE
Project Scope
Aerial Rendering
Entry/Lobby - Site Plan
Entry/Lobby - Floor Plans
DNUP
COFFEEBAR
LOUNGE
WAITING /LOUNGE
GREETER
EXIST.STAIR
LOBBY
LOBBY
ELEV. EXIST. ELEV.EXIST. ELEV.
VESTIBULE VESTIBULEPICKUPWAITING
WHEELCHAIRS& STORAGE
STAIR
ELEV.LOBBY
GIFT SHOP
CORRIDORCORRIDOR
EXIST.STAIR
WAITING/LOUNGE
RESOURCECENTER
CAFE
PICKUPWAITING
MEN'S
WOMEN'S
GIFT SHOP
STAFFLOUNGE
STAFFLOUNGE
S. TLT.
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Pho
ne 3
14.7
54.6
306
/ Fax
314
.754
.445
2bs
alife
stru
ctur
es.c
omC
onfid
entia
l and
Pro
prie
tary
Info
rmat
ion
© 2
012
BSA
Life
Stru
ctur
es
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/27/12
1st Floor Lobby Option 1MEMORIAL MEDICAL CENTER/ PATIENT CARE TOWER
1/32" = 1'0"1 FIRST FLOOR PLAN
Surgery Expansion
Surgery Expansion - Images
Surgery Expansion - Building Section
OR EXPANSION SURGERY OR | RENOVATION
PRE/POST EXPANSION LOBBY
IMC
ORTHOPEDICS
CARDIOLOGY
PENTHOUSE
ONCOLOGYPENTHOUSE
SURGERY EXPANSION E BUILDING PATIENT CARE TOWER
LOWER LEVEL: 88’-0”
FIRST LEVEL: 101’-0”
ROOF NEW: 114’-6”
ROOF LEVEL: 192’-3”
7.5 LEVEL: 175’-3”
SIXTH LEVEL: 159’-0”
4.5 LEVEL: 136’-0”
THIRD LEVEL: 124’-6”SECOND LEVEL: 113’-0”
LOBBY: 101’-0”
OR EXPANSION: 88’-0”
Surgery Expansion - First Level Plan
STRETCHER
STRETCHER
P-TUBE
CRASHCART
266 SFSTAIR
109 SF
PRE/POSTOP
107 SFELEC
299 SFSTAIR
128 SF
PRE/POSTOP
122 SF
PRE/POSTOP
130 SFISO
287 SFELEVATOR
121 SF
PRE/POSTOP
120 SFISO
48 SFANTE
53 SFP. TLT.
33 SFANTE
64 SFNOURISH
127 SFISO
33 SFANTE
53 SFP. TLT.
83 SF
MGR.OFFICE
108 SF
PRE/POSTOP
56 SFS. TLT.55 SF
P. TLT.
185 SF
EQUIP.STOR.
156 SFCLEAN
53 SFP. TLT.
53 SFP. TLT.
53 SFP. TLT.
53 SFP. TLT. 225 SF
SOILEDUTILITY
81 SFJAN.
73 SFMEDSALCOVE
527 SF
STAFFLOUNGE
131 SFDATA
490 SF
NURSESTATION
123 SFCONSULT
82 SFCONSULT
81 SFCONSULT
PASSAGE
167 SFRECEPTION
2448 SFWAITING
230 SF
NURSESTATION
53 SFP. TLT.
53 SFP. TLT.
53 SFP. TLT.
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Phon
e 31
4.75
4.63
06 /
Fax
314.
754.
4452
bsal
ifest
ruct
ures
.com
Con
fiden
tial a
nd P
ropr
ieta
ry In
form
atio
n©
201
2 BS
A Li
feSt
ruct
ures
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/28/12
FIRST LEVEL PLANMEMORIAL MEDICAL CENTER/ SURGERY ADDITION AND REVNOVATION
1/32" = 1'-0"1 SA_FIRST FLOOR SCHEMATIC DESIGN PLAN_1_32
LOBBY
Mi l l e
r S
tr
ee
t
EXISTING SIDEWALK
PROPOSED NEW SIDEWALK
Surgery Expansion - Lower Level Plan
DNUP
UP
269 SFSTAIR
287 SFELEVATOR
101 SF
SOILEDUTILITY
130 SFDATA
108 SFELECTRIC
217 SFSTAIR
752 SFOR ROBOT
755 SFOR ROBOT
608 SFOR
608 SFOR
58 SFANTE
58 SFANTE
29 SFANTE
32 SFANTE
67 SFP. TLT.
126 SF
CLEANUTILITY
61 SFS. TLT.
53 SFS. TLT.
48 SFS. TLT.
272 SFLOUNGE
487 SF
EQUIPMENTSTORAGE
462 SF
EQUIPMENTSTORAGE
206 SF
SUB-STERILE
206 SF
SUB-STERILE
100 SFDICT.
140 SF
EQUIP.STORAGE
107 SF
MGR.OFFICE
165 SF
MEDS/NOUR. 294 SF
NURSESTATION
299 SFNURSE
158 SFJAN.
175 SFSTAIR
340 SFIP HOLD
137 SF
CASECARTS
280 SF
PROCEDURECARTS
180 SFN.S.
388 SF
ANES.WORK
271 SF
CLEANROOM
NON-STERILE766 SF
STERILESUPPLY
213 SFSUB-STERILE
95 SFOFFICE
127 SFOFFICE
263 SFPHARMACY
266 SF
ANES.LOUNGE
1134 SF
BEDS/POSITIONINGDEVICES/MICROSCOPES
626 SFOR
637 SFOR
388 SFSOILED
109 SFMECH.
105 SF
COVERGOWNS/
LINEN
386 SF
EXIST.CYSTO
470 SFEXIST. OR 3
473 SFEXIST. OR 4
464 SF
EXIST. OR18
484 SF
EXIST. OR17
879 SF
EXIST.LOGISTICS
556 SF
EXIST.EQUIP.STOR.
395 SF
EXIST. OR16CRASH
CART
CRASHCART
GEM
C-ARM
1
2
3
4
5
6
7 8 910
11 12 13 1415
16 17
20 19 18
21
22
23
1178 SF
EXITPASSAGE
PACU
PACU
PACU
ISO
PACU
ISO
ISO
ISO
ELEVATORLOBBY
EXISTMECHANICAL
EXISTINGMECHANICAL
EXIST.TELEPHONE
EQUIP.
149 SFSCRUBS
108 SFSCRUBS
1268 SF
MALELOCKERS
1238 SF
FEMALELOCKERS
552 SF
STAFFLOUNGE
469 SF
PHYSICIANLOUNGE
PASSAGE
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Phon
e 31
4.75
4.63
06 /
Fax
314.
754.
4452
bsal
ifest
ruct
ures
.com
Con
fiden
tial a
nd P
ropr
ieta
ry In
form
atio
n©
201
2 BS
A Li
feSt
ruct
ures
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/21/12
LOWER LEVEL PLANMEMORIAL MEDICAL CENTER/ SURGERY ADDITION AND REVNOVATION
1/32" = 1'-0"1 SA_ LOWER LEVEL SCHEMATIC DESIGN PLAN_1_32
Patient Care Tower
Patient Care Tower - Images
Patient Care Tower - Stacking Diagram
LOBBY / CANCER CENTER
ONCOLOGY
MED / SURG
ORTHO
PSYCH (SECURE UNIT)
CARDIOLOGY
OB
ADMIN
IMC
ORTHO
CARDIOLOGY
PENTHOUSE
FIRST LEVEL: 101’-0”
SECOND LEVEL: 113’-0”
THIRD LEVEL: 124’-6”
4.5 LEVEL: 141’-9”FIFTH LEVEL: 147’-6”
SIXTH LEVEL: 159’-0”
SEVENTH LEVEL: 170’-6”
EIGHTH LEVEL: 182’-0”
FOURTH LEVEL: 136’-0”
PENTHOUSE LEVEL: 174’-0”
ROOF LEVEL: 189’-0”
Patient Care Tower - Typical Floor PlanUP
UP
DN
ROUNDS /COLLAB.
PATIENTROOM 1
PATIENTROOM 13
PATIENTROOM 14
(LIFT)
PATIENTROOM 15
PATIENTROOM 16
PATIENTROOM 17
PATIENTROOM 18
PATIENTROOM 19
ANTE
PATIENTROOM 20
(LIFT)
PATIENTROOM 21
PATIENTROOM 22
PATIENTROOM 23
PATIENTROOM 25
(LIFT)
PATIENTROOM 24
PATIENTROOM 38
(LIFT)
PATIENTROOM 37
PATIENTROOM 36
PATIENTROOM 35
PATIENTROOM 34
(LIFT) (EEGCAM. RM.)
PATIENTROOM 33
(EEG CAM.RM.)
PATIENTROOM 32
PATIENTROOM 31
PATIENTROOM 29
PATIENTROOM 28
PATIENTROOM 27
PATIENTROOM 26
STAFFLOUNGE
STAFFTOILET
BUSINESSCENTER
PATIENTROOM 12
(LIFT)
PATIENTROOM 11
PATIENTROOM 10
(LIFT)
PATIENTROOM 9
UNASSIGNED
STAFFTOILET
EQUIP
CLEAN
ELEC.
I.T. HOUSEKEEPING MANAGER
MEDS.
NOURISH. /ICE MULTI
DISCIPLINARYWORKROOM
CLEAN
ELEC
I.T.
MEDS.
NOURISH. /ICE
EQUIP
PUBLICTOILET
CONSULT
ROUNDS /COLLABORATION
STAFFTOILET
SOILEDWORKROOM
CLASSROOM
UNASSIGNED
PATIENTROOM 30
(LIFT)
ROUNDS /COLLABORATION
ROUNDS /COLLAB.
FAMILY
ROUNDS /COLLABORATION
ROUNDS /COLLABORATION
CLASSROOM
OFFICE
CLASSROOM
EMERG.EQUIP.
PATIENTROOM 2
PATIENTROOM 3(LIFT)
PATIENTROOM 4
PATIENTROOM 5
PATIENTROOM 6
FAMILY
PATIENTROOM 8
?
EEG OFFICE
CONSULT
PUBLICTOILET
CONFERENCE/ MULTI
PURPOSE
SOILEDWORKROOM 02 STOR. RESP.
THERAPY
EMERGENCYEQUIPMENT
ELEC.
CHARGENURSE
RECEPTION/ UNIT
SECRETARY
LOCKERS
FAMILY
ELEC.
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Pho
ne 3
14.7
54.6
306
/ Fax
314
.754
.445
2bs
alife
stru
ctur
es.c
omC
onfid
entia
l and
Pro
prie
tary
Info
rmat
ion
© 2
012
BSA
Life
Stru
ctur
es
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/21/2012
3rd LEVEL IMCMEMORIAL MEDICAL CENTER/ PATIENT CARE TOWER
0' 16' 32' 64'
SCALE: 1/32" = 1'0"
3rd FLOOR PLAN1/32" = 1'0"
Patient Care Tower - 3D Patient Room Study
FAMILY ZONE
PATIENT ZONE
CAREGIVER ZONE
Learning Institute
Learning Institute - Images
Learning Institute - Stacking Diagram
CONFERENCE CENTER
LEARNING Institute
SIMULATION CENTER & SURG. SKILLS LAB
BRIDGE
LOWER
FIRST
SECOND
THIRD
LEARNING INSTITUTE BRIDGE PHYSICIANS GARAGE
FIRST LEVEL: 592.5’
SECOND LEVEL: 613.83’
THIRD LEVEL: 627.83’
ROOF LEVEL: 641.83’
LOWER LEVEL: 591.5’
FIRST LEVEL: 602.83’
SECOND LEVEL: 614.17’
THIRD LEVEL: 625.5’
Learning Institute - Level One Plan
UP
UP
DN
4178 SF
LARGELECTURE
182 SFSTOR
192 SFSTAIR
666 SFMEP
825 SF
SMALLCONFERENCE
242 SFELEVATORS
287 SFSTAIR
228 SFKITCHEN
134 SF
OFFICE/WORK
1739 SFLOBBY
428 SF
SERVICECORRIDOR
229 SFSERVING
780 SFCAFE
128 SFWORK
88 SFELEC.
88 SFTELE.
336 SFCATERING
674 SFSTORAGE
90 SFJAN
459 SF
BUSINESSCENTER
739 SF
PRE-FUNCTION/GATHERING
110 SFHUDDLE
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Pho
ne 3
14.7
54.6
306
/ Fax
314
.754
.445
2bs
alife
stru
ctur
es.c
omC
onfid
entia
l and
Pro
prie
tary
Info
rmat
ion
© 2
012
BSA
Life
Stru
ctur
es
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/29/2012
MMC/ LEARNING INSTITUTELEVEL ONE
1/16" = 1'-0"1 FIRST FLOOR COLOR PLANSCALE: 1/16" = 1'-0"
0' 8' 16' 32'
Learning Institute - Level Two Plan
DN
UP
UP
DN
UP
1364 SFCLASSROOM
??
1764 SF
INFORMALCLASSROOM
322 SFSTAIR
412 SFCOMPUTER
91 SFTELE.
99 SFSTORAGE
91 SFELEC.
1120 SF
FORMALCLASSROOM
1099 SFCLASSROOM
149 SFOFFICE
124 SFOFFICE
124 SFOFFICE
1816 SFOPEN WORK
76 SFJAN.
242 SFCONFERENCE
228 SF
STAFFBREAK
321 SFOPEN CONF.
1
2
3
4
5
6
710
9 814
13
12
15
1116
17
18
125 SFCOPY/PRINT
332 SFCOMPUTER
837 SFCLASSROOM
81 SFSTORAGE
1196 SFLOBBY
PEDESTRIANBRIDGE TO
EXISTING GARAGE
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Pho
ne 3
14.7
54.6
306
/ Fax
314
.754
.445
2bs
alife
stru
ctur
es.c
omC
onfid
entia
l and
Pro
prie
tary
Info
rmat
ion
© 2
012
BSA
Life
Stru
ctur
es
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/29/12
MMC/ LEARNING INSTITUTELEVEL TWO
1/16" = 1'-0"1 SECOND FLOOR COLOR PLANSCALE: 1/16" = 1'-0"
0' 8' 16' 32'
Learning Institute - Level Three Plan
DN
DN
UP
DN287 SFSTAIR
1026 SFCLASSROOM
981 SF
SURGICALSKILLS LAB
230 SFPREP
287 SFSTAIR
129 SFOFFICE
607 SFOPEN WORK
859 SFCLASSROOM
162 SFDEBRIEF
165 SFCLINIC
165 SFED/TRAUMA
158 SFN.S.
320 SFMED SURGE
356 SFICU
443 SFOR
481 SFED
634 SF
SHAREDCONTROL
517 SF
SURGICALSKILLS
SIMULATIONTEST
391 SFSTORAGE
100 SFHOLD
91 SFELEC.
91 SFTELE.
76 SFJAN.
263 SFDEBRIEF
129 SFOFFICE
487 SFSTORAGE
119 SFMOULAGE
158 SFW. LCKRS.
159 SFM. LCKRS.
100 SFSIM.
127 SFCONTROL
100 SFSIM.1 2 3
4
120
S. C
entra
l Ave
nu, S
uite
110
0 / S
t. Lo
uis,
MO
631
05.1
746
Pho
ne 3
14.7
54.6
306
/ Fax
314
.754
.445
2bs
alife
stru
ctur
es.c
omC
onfid
entia
l and
Pro
prie
tary
Info
rmat
ion
© 2
012
BSA
Life
Stru
ctur
es
PATIENT CARE TOWER | SURGERY EXPANSION | INFRASTRUCTURE | LEARNING INSTITUTE
08/29/2012
MMC/ LEARNING INSTITUTELEVEL THREE
SCALE: 1/16" = 1'-0"
0' 8' 16' 32'
1/16" = 1'-0"1 THIRD FLOOR COLOR PLAN
Infrastructure
Infrastructure - Overview of Key Upgrades
» High efficiency heating hot water boilers and heat recovery chillers
» VFD chiller, variable primary pumping, and VFD tower fans
» Tower sump as a storage sump only
» Relocation and repair of bulk oxygen site
» Centralized, redundant emergency power system
In addition to creating capacity to serve expansion, improvements include:
» Consolidation of electrical utility services
» Partial chilled water on emergency power
» Additional fuel oil storage
» Summer boilers for low seasonal loads