PATHLOSS GUIDELINES Page 1 of 19 I. GUIDELINES IN PREPARATION OF PATH PROFILE A. REQUIREMENTS 1. PathLoss Tool User must be familiar with the basic microwave transmission concept. 2. PathLoss Tool User must be provided with site information such as Site Name & Site Coordinates, together with link propagation criteria (i.e. K-factor & Fresnel Zone Criteria) that is being followed by the end-user/customer. B. PROCEDURE 1. From the Summary Module, input the Site Name and Site Coordinates of both stations.

Transcript of PathLoss Guidelines 13Mar06

Page 1: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 1 of 19

I. GUIDELINES IN PREPARATION OF PATH PROFILE

A. REQUIREMENTS

1. PathLoss Tool User must be familiar with the basic microwave transmissionconcept.

2. PathLoss Tool User must be provided with site information such as Site Name & Site Coordinates, together with link propagation criteria (i.e. K-factor & Fresnel

Zone Criteria) that is being followed by the end-user/customer.

B. PROCEDURE

1. From the Summary Module, input the Site Name and Site Coordinates of bothstations.

Page 2: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 2 of 19

** In case of Multiple links, Site Name and Coordinates can be entered on the Site List from the Grid Module.

2. Generate the path profile from the Terrain Data Module by clicking generateprofile button. Be sure to set the primary terrain data and its directory firstbefore generating the profile.

Page 3: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 3 of 19

**Be sure to set the primary terrain data and its directory first before generating the profile.

Page 4: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 4 of 19

3. In cases where additional vegetation or building is needed, input thecorresponding data on the terrain data sheet.

Page 5: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 5 of 19

4. Assign antenna heights for both stations on the Antenna Height Module. Be sureto consider tower height and loading for existing station when assigning theantenna height.

Page 6: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 6 of 19

5. Counter-check the visual display of the profile on the Print Profile Module.

6. In case of obstruction, adjust the tower height on one station accordingly untilthe desired clearance is achieved.

Page 7: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 7 of 19

Page 8: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 8 of 19

II. GUIDELINES IN PREPARATION OF LINK BUDGET

A. REQUIREMENTS

1. PathLoss Tool User must be provided with the following information:

- Region (North, Center or South)- Site Names / Site Codes- Coordinates (Latitude, Longitude)- Radio Capacity (2E1, 4E1, 8E1,16E1 or STM1)- Radio Configuration (Unprotected or Protected)- Building Height (if roof-mounted)- Tower Height- Antenna Height- Antenna Type (Andrew, RFS or other)- Frequency Band to be Used- Approved Frequency Channel to be used- For Protected Configuration using 2-Antenna System, type of RF Cable (Low Loss Cable) or Waveguide to be used.

2. PathLoss Tool User must be provided with the required availability criteria for each link as well as desired fade margin and other design factors if necessary.

** Example for Pakistan Project: Link Availability (at least 99.999%) and Fade Margin (30dB for SDH and 35dB for PDH).

B. PROCEDURE 1. From the Summary Module, input the Site Name and Site Coordinates of both stations.

2. Input the frequency band to be used on the frequency potion on the Summary Module.

Page 9: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 9 of 19

3. Generate the path profile from the Terrain Data Module by clicking generate profile button. Be sure to set the primary terrain data and its directory first before generating the profile (see Procedure No.2, Path Profile Guidelines).

4. Assign antenna heights for both stations on the Antenna Height Module. Be sure to consider tower height and loading for existing station when assigning the

antenna height (see Procedure No.3, Path Profile Guidelines).

5. From the Worksheet Module, perform the following items.

a). Assign the corresponding Rain Region based from ITU Standard.

** ITU has designated Rain Region N for Luzon and some portion Visayas while Rain Region P for Mindanao and rest of Visayas.

Page 10: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 10 of 19

b). Select the Antenna Polarization to be used.

c). Select the Antenna Type to be used. Click both to apply to both station the selected antenna type.

**Antenna type to be selected must be applicable on the same frequency band that will be used.

Page 11: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 11 of 19

d). From the equipment list, choose the equipment type to be used with consideration of the required Radio capacity(4,8 or16E1) and Configuration (1+0 or 1+1).

**In case of 1+1 HS Configuration. Hybrid Loss must be considered for direct mount configuration and RF Cable/Waveguide Loss must be distinct for indirect mount configuration.

Hybrid Loss=3dB/station Waveguide Loss is depending on the type of cable to be used.

Page 12: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 12 of 19

Page 13: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 13 of 19

e). Input the channel frequency to be used. (Approved frequency channel must be secured first from end user/customer before assigning).

**High or Low Side must also be selected during selecting desired frequency. **For Multi-links, PathLoss Tool User shall decide the point frequency and polarization appropriate for the link based on existing frequencies within respectable distance from subject link. Interference report should be checked to confirm possible interference.

Page 14: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 14 of 19

f. Check the Link Availability

**For short distance hops, additional attenuation can be assigned in order to protect the ODU from receiving very high receive levels.

**PathLoss Tool User shall decide the antenna diameter size required for the link based on the Link Availability (at least 99.999%) and Fade Margin (30dB for SDH and 35dB for PDH).

Page 15: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 15 of 19

C. Commonly Used Standards on Pathloss Designing/Updating (Reference: Pakistan Project)

1. Proper legends should be followed for the site/link layers and link attributes.

Example:

Table 1 - PathLoss Layers

Site LayersOn-Air : NEC and other vendor sites which are On-AirPlanned : NEC and other vendor sites which are planned

(Other vendor planned sites should be informed by Customer)Micro/Dart : Small-capacity (other vendor) sites which are On-AirDTE : PTCL SiteBSC : BSC SiteMSC : MSC Site

Link LayersNEC Installed : NEC links which are currently operationalNEC Planned : NEC links which are still under planning

Other Installed : Other vendor links which are currently operational Other Planned : Other vendor links which are still under planning

Page 16: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 16 of 19

2. Below are the legends commonly used in PathLoss Tool.

Table 2 – Legends for PathLoss Layers

Page 17: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 17 of 19

3. Link Planning Form

Table 3 - Link Planning Form

Page 18: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 18 of 19

** PathLoss Tool User shall attach the Link Budget to the Link Planning Form, wherein copies shall be provided to,

a. Project Managerb. Person-in-Charge, Customer Side (Txn Dept.)c. NESIC SV & Installation Teamd. NEC, if necessary

During Pre-Test/Installation:

1. NESIC Installation Team shall confirm the data in the Link Planning Form and the attached Link Budget.

2. If any parameter has to be changed, the person/party modifying the data should accomplish a new Link Planning Form using the same Reference No. indicating the Revision No. and place comments/notes regarding the changes. The newly accomplished Link Planning Form has to be attached to the previous Link Planning Form and provide a copy to the PathLoss Tool User in order to prepare the revised Link Budget. New Link Planning Form with revised Link Budget will be provided to:

a. Project Managerb. Person-in-Charge, Customer Side (Tx Dept.)c. NESIC SV on sited. NEC, if necessary

During PAT:

1. NESIC Installation Team should have a copy of both the Link Planning Form andLink Budget. All data in the Link Planning Form should be reconfirmedat the site by both Customer/Client and NESIC Testing Team. Othermissing data in the Link Planning Form should be completed (no blanksshould be left-out).

2. Both parties shall fix their signature on the attached Link Budget.

3. After PAT, NESIC Installation Team shall give a copy of the completed LinkPlanning Form with the attached signed Link Budget to Project Manager or PlanningGroup for filing and record purposes.

Page 19: PathLoss Guidelines 13Mar06

PATHLOSS GUIDELINESPage 19 of 19

Updating of PathLoss Tool

1. PathLoss Tool User shall immediately update the PathLoss Dataafter receiving Link Planning Form. PathLoss Data shall be updated withthe information provided in the Link Planning Form with attached signed LinkBudget. Layers and Link attributes should be observed in reference to Table2.

2. PathLoss Tool User shall provide duplicate copies of the final Link PlanningForm to:

a. Project Managerb. Person-in-Charge, Customer Side (Tx Dept.)c. NESIC SV on sited. NEC, if necessarye. Warehouse, if logistics is part of SOW.

3. Customer TXN Planning Department may update their planning tool usingthe same procedure and forms.

Modifications Required in the Future

**When a link is to be modified for any parameters in the future, the Link PlanningForm should be used. The Reference No. shall remain the same, the Revision No.should be indicated with comments/notes regarding the modification. Examples oflink modifications are,

a. Change of antenna heightsb. Change of frequency channel assignmentc. Change of radio capacityd. Link is dismantled/removed

PathLoss Tool Updated

**After updating the PathLoss Data, a Check Mark (√) has to be placed on the tick

box beside “Final” and place the date when the final confirmed parameters whereentered into the PathLoss Data. This shall be the confirmation that PathLoss Toolwas updated.