Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del...

13
STRATEGIC CONSULTING SERVICES Paseo del Volcan Funding and Financing Workshop April 4, 2014 www.pbworld.com

Transcript of Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del...

Page 1: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

S T R A T E G I C C O N S U L T I N G S E R V I C E S

Paseo del VolcanFunding and Financing WorkshopApril 4, 2014

www.pbworld.com

Page 2: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

AgendaAgenda

– Introduction: Parsons BrinckerhoffBackground / Considerations

• Dave Pennington: Albuquerque Area Manager• Nick Amrhein: Strategic Consulting Group (DEN)

– Project Background: Important Considerations

SC / Finance Introduction

Project– Project Background: Important Considerations– Other Project Examples

• C-470 Managed Lanes, Denver, Colorado

Project Examples

Paseo del Volcan

• Southern Parkway, St. George, Utah– Paseo del Volcan

• Goals / Challenges

Process / Framework

g• Potential Strategies

– Recommended next steps for project development and acceleration

Questions / Next Steps

2

development and acceleration

Page 3: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Paseo del Volcan CorridorPaseo del Volcan Corridor

3

Page 4: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

HistoryHistory

• 30.6 miles from I-40 to US 550Background / Considerations30.6 miles from I 40 to US 550

• Location study/preliminary engineering (1990s) developed:

SC / Finance Introduction

Project( ) p– freeway facility with interchanges– frontage roads

Project Examples

Paseo del Volcan

– adequate r/w for other modal facilities Process /

Framework

Questions / Next Steps

4

Page 5: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

HistoryHistory

• 1997 -- Draft EIS publishedBackground / Considerations1997 Draft EIS published

• 2001 -- Final EIS• 2002 -- ROD signed

SC / Finance Introduction

Project2002 -- ROD signed• ROD Approved

– 2-lane roadway with specific access locations

Project Examples

Paseo del Volcan2 lane roadway with specific access locations

– 400 ft. right-of-way• ROD prescribed commitments for design

Process / Framework

ROD prescribed commitments for design and construction

Questions / Next Steps

5

Page 6: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Introduction:

• Parsons Brinckerhoff’s StrategicBackground / ConsiderationsParsons Brinckerhoff s Strategic

Consulting Group– Finance, Policy, Economics, Management,

SC / Finance Introduction

ProjectOperations, Transaction Due Diligence

• Funding – Money to Spend

Project Examples

Paseo del Volcan

– New Taxes, Value Capture, Grants, Bond Proceeds, etc.

• Financing Tools to accelerate funding

Process / Framework

• Financing – Tools to accelerate funding– GO, TIFIA, Revenue Bonds

• Public Private PartnershipsQuestions / Next Steps

6

• Public-Private Partnerships

Page 7: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Project Example: C-470 Managed Lanes (Denver, Colorado)Lanes (Denver, Colorado)

Background / Considerations

SC / Finance Introduction

ProjectProject Examples

Paseo del Volcan

Process / Framework

Questions / Next Steps

7

Page 8: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Project Example: C-470 Managed Lanes (Denver, Colorado)Lanes (Denver, Colorado)Local stakeholder-led project development process

P li C itt (PC)

Background / Considerations

- Policy Committee (PC)- Technical Working Group (TWC)

SC / Finance Introduction

ProjectProject Examples

Paseo del Volcan

Process / Framework

Questions / Next Steps

8

Page 9: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Project Example: C-470 Managed Lanes (Denver, Colorado)Lanes (Denver, Colorado)

Background / Considerations

SC / Finance Introduction

ProjectProject Examples

Paseo del Volcan

Process / Framework

Questions / Next Steps

9

Page 10: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Project Example: Southern Parkway, (St. George, Utah)(St. George, Utah)

• MapIntroduction

(PB / SC)Interstate 15

Hurricane, Utah

Map• Process• Funding Sources Considered

Project Examples

Paseo DelFunding Sources Considered– Auto Registration Fee– Value Capture

Paseo Del Volcan

Payment Structures

St. George, Utah

p– Tolling Process /

Framework

Questions / Next Steps

10

Page 11: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Paseo del VolcanPaseo del Volcan • Challenge:

Lack of FundingBackground / Considerations

– Lack of Funding – Need to Accelerate the Project

• Strategy:SC / Finance Introduction

Project– Use Local Framework to Develop the Project

Funding Plan and Scope

Project Examples

Paseo del Volcan

• Initial Thoughts for Paseo del Volcan:– Tolling is a Poor Fit.

Process / Framework

– Value Capture Appears Viable.– Who can Issue Local Revenue Bonds?– Phasing Plan is Needed to “Right Size” the

Questions / Next Steps

11

Phasing Plan is Needed to Right Size the Project.

Page 12: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Suggested Next StepsSuggested Next Steps

• Form Technical Working Group (hire Background / Considerations

support as needed) that can Develop Options– Perform economic benefits analysis to show value of

th j t t t k h ld

SC / Finance Introduction

Projectthe project to stakeholders– Develop preliminary cost estimates / phasing strategy – Develop funding / financing options

Project Examples

Paseo del Volcan

• Options are Vetted through the Steering Committee

• Stakeholder Support through SteeringProcess /

Framework

Stakeholder Support through Steering Committee

• Develop business plan for moving the project forward

Questions / Next Steps

12

project forward

Page 13: Paseo del Volcan - City of Albuquerque...Volcan • Southern Parkway, St. George, Utah – Paseo del Volcan • Goals / Challenges Process / Framework • Potential Strategies –

Questions / DiscussionQuestions / Discussion

Thank You!Background / ConsiderationsThank You!

Dave Pennington (ABQ)

SC / Finance Introduction

ProjectDave Pennington (ABQ)[email protected]

Project Examples

Paseo del Volcan

Nick Amrhein (DEN)amrhein@pbworld com

Process / Framework

[email protected] / Next Steps

13