REF_CE_18012018 Page 1/12 PARTICULATE MATTER (PM) EMISSION CONTROL Examples of Hurricane and ReCyclone® Systems in Existing Installations Hurricane HR cyclone system ( 8 x Ø900mm ) to reduce particulate matter emissions from 20ton/h coal boiler Gas flow: 38 880m 3 /h at 220°C | Type of Particles: Coal fly ashes | Emissions: <110mg/Nm 3 at 10% O2 Client: Associated Energy Services | Location: Durban, South Africa | Year: 2017 HT3175 Hurricane HR cyclone system ( 8 x Ø700mm ) to reduce particulate matter emissions from a rotary dryer Gas flow: 26.175 m 3 /h at 64ºC| Type of Particles: Coffee grounds | Emissions: <150 mg/Nm 3 at 13% O2 Client: Industrias Aliadas S.A.S.| Location: Cartagena, Colombia | Year: 2017 RF3132 Hurricane HC cyclone system ( 2 x Ø2500mm ) to reduce particulate emissions from a sawdust dryer. Gas flow: 65 000m 3 /h at 60°C | Type of Particles: fly ash | Emissions: <60mg/Nm 3 dry Client: Vertdeshy | Location: Meximieux, France| Year: 2017 HT2782 Hurricane RE cyclone system ( 4 x Ø1000mm ) optimized to reduce pm emissions after a boiler burning coal. Gas flow: 11,500m 3 /h at 140°C | Type of Particles: fly ash | Emissions: <75mg/Nm 3 dry at 6% O2 Client: JAKSA | Location: Warsaw, Poland | Year: 2017 PA3021 Hurricane MK cyclone system ( 8 x Ø900mm ) to reduce particulate matter from a biomass boiler (coal / wood) Gas flow: 11 520m 3 /h at 220°C | Type of Particles: coal/wood shavings Emissions: < 95mg/Nm 3 Client: Southpine, Windsor | Location: Nelson, New Zeland | Year: 2017 RF3079 Hurricane RX cyclone system ( 32 x Ø1050mm ) to reduce emissions from a biomass boiler burning wood Gas flow: 188 861m 3 /h at 153°C | Type of Particles: fly ash | Emissions: <100mg/Nm 3 dry at 8% O2 Client: SSB Energia Renovável. | Location: Limeira, SP, Brazil | Year: 2017 DB3269 Hurricane HR cyclone system ( 2 x Ø1800mm ) to reduce particulate matter from a coal boiler. Gas flow: 39 000m 3 /h at 120°C | Type of Particles: wood shavings | Emissions: 42mg/Nm 3 Client: Sugimat | Location: Valencia, Spain | Year: 2017 HT3285 Hurricane HR cyclone system ( 4 x Ø750mm ) to reduce particulate matter emissions from 8 ton/h coal boiler Gas flow: 12 096m 3 /h at 220°C | Type of Particles: Coal fly ashes | Emissions: <110mg/Nm 3 at 10% O2 Client: Associated Energy Services | Location: Durban, South Africa | Year: 2017 HT3155 Hurricane HR_MK cyclone system ( 16 x Ø900mm ) to reduce PM emissions from a Coal Bubbling Fluidized Bed (BFB) 10 ton/h boiler. Gas flow: 22 500m 3 /h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm 3 Client: Basuki | Location: Indonesia | Year: 2017 PA3140 Hurricane RE cyclone system ( 4 x Ø725mm ) to reduce particulate matter from a 3ton/h of steam biomass boiler,burning wood chips. Gas flow: 6 500m 3 /h at 108°C | Type of Particles: Wood fly ashes| Emissions: <75mg/Nm 3 Client: Avipronto | Location: Azambuja, Portugal | Year: 2017 HT2690

Transcript of PARTICULATE MATTER (PM) EMISSION … Basuki | Location: Indonesia | Year: 2017 0 Hurricane RE...

REF_CE_18012018 Page 1/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Hurricane HR cyclone system ( 8 x Ø900mm ) to reduce particulate matter emissions from 20ton/h coal boiler Gas flow: 38 880m3/h at 220°C | Type of Particles: Coal fly ashes | Emissions: <110mg/Nm3 at 10% O2

Client: Associated Energy Services | Location: Durban, South Africa | Year: 2017

HT3

17

5

Hurricane HR cyclone system ( 8 x Ø700mm ) to reduce particulate matter emissions from a rotary dryer Gas flow: 26.175 m3/h at 64ºC| Type of Particles: Coffee grounds | Emissions: <150 mg/Nm3 at 13% O2 Client: Industrias Aliadas S.A.S.| Location: Cartagena, Colombia | Year: 2017

RF3

13

2

Hurricane HC cyclone system ( 2 x Ø2500mm ) to reduce particulate emissions from a sawdust dryer. Gas flow: 65 000m3/h at 60°C | Type of Particles: fly ash | Emissions: <60mg/Nm3

dry

Client: Vertdeshy | Location: Meximieux, France| Year: 2017

HT2

78

2

Hurricane RE cyclone system ( 4 x Ø1000mm ) optimized to reduce pm emissions after a boiler burning coal. Gas flow: 11,500m3/h at 140°C | Type of Particles: fly ash | Emissions: <75mg/Nm3

dry at 6% O2

Client: JAKSA | Location: Warsaw, Poland | Year: 2017

PA

302

1

Hurricane MK cyclone system ( 8 x Ø900mm ) to reduce particulate matter from a biomass boiler (coal / wood)

Gas flow: 11 520m3/h at 220°C | Type of Particles: coal/wood shavings Emissions: < 95mg/Nm3

Client: Southpine, Windsor | Location: Nelson, New Zeland | Year: 2017

RF3

079

Hurricane RX cyclone system ( 32 x Ø1050mm ) to reduce emissions from a biomass boiler burning wood Gas flow: 188 861m3/h at 153°C | Type of Particles: fly ash | Emissions: <100mg/Nm3

dry at 8% O2

Client: SSB Energia Renovável. | Location: Limeira, SP, Brazil | Year: 2017

DB

326

9

Hurricane HR cyclone system ( 2 x Ø1800mm ) to reduce particulate matter from a coal boiler.

Gas flow: 39 000m3/h at 120°C | Type of Particles: wood shavings | Emissions: 42mg/Nm3 Client: Sugimat | Location: Valencia, Spain | Year: 2017

HT3

285

Hurricane HR cyclone system ( 4 x Ø750mm ) to reduce particulate matter emissions from 8 ton/h coal boiler Gas flow: 12 096m3/h at 220°C | Type of Particles: Coal fly ashes | Emissions: <110mg/Nm3 at 10% O2

Client: Associated Energy Services | Location: Durban, South Africa | Year: 2017

HT3

15

5

Hurricane HR_MK cyclone system ( 16 x Ø900mm ) to reduce PM emissions from a Coal Bubbling Fluidized Bed (BFB) 10 ton/h boiler. Gas flow: 22 500m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia | Year: 2017

PA

3140

Hurricane RE cyclone system ( 4 x Ø725mm ) to reduce particulate matter from a 3ton/h of steam biomass boiler,burning wood chips. Gas flow: 6 500m3/h at 108°C | Type of Particles: Wood fly ashes| Emissions: <75mg/Nm3 Client: Avipronto | Location: Azambuja, Portugal | Year: 2017

HT2

690

REF_CE_18012018 Page 2/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Hurricane HR_MKi cyclone system, optimized to reduce the particle emission from an 12ton/h ICAVI boiler burning wood chips. Gas flow: 23 660m3/h at 200°C | Type of Particles: Wood chips fly ashes | Emissions: <70mg/Nm3 Client: Icavi | Location: Estação, Rio Grande Do Sul, Brasil | Year: Ongoing

JB3

00

2

Hurricane HR_MKi cyclone system, optimized to reduce the particle emission from an 15ton/h BREMER boiler burning wood chips. Gas flow: 40 203m3/h at 170°C | Type of Particles: Wood chips fly ashes | Emissions: <65mg/Nm3 Client: Bremer | Location: Estação, Rio Grande Do Sul, Brasil | Year: Ongoing

JB2

92

8

Hurricane HR_MK cyclone system optimized to reduce the amount of PM (toasted coffee) from a grinder tower. Gas flow: 456m3/h at 32°C | Type of Particles: Toasted coffee | Emissions: <150mg/Nm3 Client: Colcafé | Location: Medellín, Colombia | Year: 2017

JB2

94

3

ReCyclone® HR optimised to reduce particulate matter from a biomass boiler burning wood shavings after a multicyclone. Gas flow: 10 300m3/h at 236°C | Type of Particles: Wood fly ash | Emissions: <100mg/Rm3@ 7%O2 Client: Resolute | Location: Quebec, Canada | Year: 2017

MW

279

6

Hurricane HR_MKi cyclone system optimised to reduce the quantity of particulate material leaving from a coal boiler Gas flow: 25 485m3/h at 104°C | Type of Particles: Coal fly ashes | Emissions: <50mg/Nm3 Client: Agrosan | Location: Sabaneta, Antioquia, Colombia | Year: 2017

JB28

02

Hurricane HR_AT cyclone system to reduce PM from a Heizomat biomass boiler (300kW) Gas flow: 1 165m3/h at 180°C | Type of Particles: Wood fly ashes Biomass | Emissions: <50mg/Nm3 Client: Saelen Energie | Location: St Fulgent, France | Year: 2017

HT2

741

Hurricane HR_AT cyclone system to reduce PM from 2 Heizomat biomass boilers (500kW + 850kW) Gas flow: 1 800m3/h at 180°C | Type of Particles: Wood fly ashes | Emissions: <50mg/Nm3 Gas flow: 2 455m3/h at 180°C | Type of Particles: Biomass | Emissions: <50mg/Nm3 Client: Saelen Energie | Location: Thouars, France | Year: 2017

HT2

781

Hurricane HR_MK cyclone system to reduce PM from 2 Heizomat biomass boilers (300kW + 500kW) Gas flow: 1 165m3/h at 180°C | Type of Particles: Wood fly ashes | Emissions: <50mg/Nm3 Gas flow: 1 800m3/h at 180°C | Type of Particles: Biomass | Emissions: <50mg/Nm3 Client: Saelen Energie | Location: Verneuil-sur-Avre , France | Year: 2017

HT2

770

Hurricane HR cyclone system optimised to reduce the amount of particulate material (coffee grounds) from a rotating dryer. Gas flow: 32 796m3/h at 79°C | Type of Particles: Coffee grounds | Emissions: <50mg/Nm3 Client: Colcafé | Location: Medellín, Colombia | Year: 2016

JB24

43

Hurricane HR hurricane cyclone system to separate particulate matter from pyrolysis gases at high temperature. Gas flow: 392m3/h at 450°C | Type of Particles: Paper sludge PM | Separation efficiency: [97.5 – 99.0%] Client: Alucha | Location: Arnhem, Netherlands | Year: 2016

HT2

531

REF_CE_18012018 Page 3/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Hurricane HR_MK type cyclone system for reducing particulate matter from a 15ton/h Coal Bubbling Fluidized Bed (BFB) boiler flue gases. Gas flow: 34 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia | Year: 2016

PA

28

41

Hurricane HR_MK cyclone system to recover particles of borosilicate glass from air stream, on the grind milling process line 2. Gas flow: 1 250m3/h at 80°C | Type of Particles: Borosilicate glass | Separation efficiency: [99.6 – 99.7] Client: Le Creuset | Location: Fresnoy le Grand, France | Year: 2016

HT1

98

7

Hurricane HR cyclone system to reduce particles from a 700kW biomass boiler (wood panels), after a multicyclone. Gas flow: 1 557m3/h at 132°C | Type of Particles: Wood fly ashes | Emissions: <50mg/Nm3 Client: Coulidoor | Location: Verson, France | Year: 2016

HT2

77

9

ReCyclone® EH cyclone system to reduce particles from a 1.7MW biomass boiler (wood panels), after a multicyclone. Gas flow: 4 164m3/h at 135°C | Type of Particles: Wood fly ashes | Emissions: <50mg/Nm3 Client: Loire Compost Environnement | Location: Cizay La Madelaine, France | Year: 2016

HT2

751

Hurricane HR cyclone system optimized to reduce particulate matter from a 600HP biomass bark boiler after a multicyclone. Gas flow: 27 959m3/h at 254°C | Type of Particles: Bark fly ash | Emissions: <150mg/Rm3@ 7%O2 Client: KMW Energy | Location: Quebec, Canada | Year: 2016

MW

263

6

Hurricane HR_MK type cyclone system for reducing particulate matter from a 6ton/h Coal Bubbling Fluidized Bed (BFB) boiler flue gases. Gas flow: 14 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <70mg/Nm3 Client: Basuki | Location: Jawa Timur, Indonesia | Year: 2016

PA

2816

Hurricane HR_MKi for particulate matter abatement downstream of an existing multicyclone, installed on 3.5 MWth LHV biomass boiler running on clean wood chips. Gas flow: 8 250m3/h at 140°C | Type of Particles: Wood fly ashes | Emissions: <45mg/Nm3 Client: Ignis | Location: Wick, United Kingdom | Year: 2016

HT2

755

Hurricane HR_AT_MS cyclone systems (2x6 cyclones of ø2800mm) to reduce particulate matter emissions, remove silica and sparks particulates before the 2 dryers and allowing the units to safely work at full capacity. Gas flow: 2x580 000am3/h at 500°C | Type of Particles: Biomass fly ash (silica & sparks) | Emissions: <400mg/Nm3

dry Client: Tafisa| Location: Quebec, Canada | Year: 2017

MW

258

8

Hurricane HR cyclone system used to capture particles from a biomass boiler. Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <40mg/Nm3 Client: Norbidel, Adafios | Location: Felgueiras, Portugal | Year: 2016

RF2

720

Hurricane HR cyclone system used to capture particles from a biomass boiler. Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <40mg/Nm3 Client: Norbidel, Frulact | Location: Maia, Portugal | Year: 2016

RF2

716

REF_CE_18012018 Page 4/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Hurricane MK cyclone system to reduce particulate matter from a biomass boiler burning cork powder. Gas flow: 23 000m3/h at 250°C | Type of Particles: Cork fly ashes | Emissions: <100mg/Nm3 Client: Flucal, Amorim Irmãos | Location: Valongo, Portugal | Year: 2016

H26

56

Hurricane HR cyclone system, to separate iron oxide particulates from compressed air Gas flow: 104 342Nm3/h AT 6.9 Bar(A), 40°C. | Type of Particles: Iron Oxide | Efficiency: >89,8% Client: Air Liquide | Location: Dabrowa Górnicza, Poland | Year: 2016

H21

23

Hurricane HR_MK for to recover particles of borosilicate glass from air stream, on the grind milling process line 1 Gas flow: 2 350m3/h at 90°C | Type of Particles: Borosilicate glass powder| Efficiency: 99.7-99.8 % Client: Le Creuset | Location: Freynoy-Le-Grand, France | Year: 2016

H19

69

Hurricane HR Cyclone system to capture biomass fly ash and sawdust particles from rotary dryer in a wood pellet plant, placed after pre-separator.

Gas flow: 8 074m3/h at 110°C | Particles: Sawdust| Emissions: <150mg/Nm3

Client: Vimasol | Location: Celourico da Beira, Portugal | Year: 2016

H26

46

Hurricane HR_MK type cyclone system for reducing particulate matter from a 20 ton/h Coal Bubbling Fluidized Bed (BFB) boiler flue gases. Gas flow: 45 039m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki, Tirtha Freshindo Jaya | Location: West Java, Indonesia | Year: 2016

P24

53

Hurricane HR_MK type cyclone system for reducing particulate matter from a 15ton/h Coal Bubbling Fluidized Bed (BFB) boiler flue gases. Gas flow: 34 000m3/h at 230°C| Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki, Tirtha Freshindo Jaya | Location: West Java, Indonesia | Year: 2016

P25

58

Hurricane HR cyclone system to separate a mixture of steam and solid biomass. Gas flow: 1 554m3/h at 124°C | Type of Particles: Biomass | Expected efficiency (%) 99.5 - 99.6 Client: Axens / Tereos | Location: France | Year: 2016

RF2

508

Hurricane HR_MK to reduce PM emissions from a Rice Husk Bubbling Fluidized Bed (BFB) 4 ton/h boiler Gas flow: 9300m3/h at 230°C | Type of Particles: Rice Husk fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia | Year: 2016

PA

219

5

Recyclone® MH to reduce particulate matter from a biomass boiler burning a mixture of palm kernel shell and mesocarp fiber. Gas flow: 122.328m3/h at 270°C | Type of Particles: Biomass fly ashes | Emissions: <150mg/Nm3 Client: Kulim, Pasir Panjang | Location: Kota Tinggi, Malaysia | Year: 2016

P21

93

Several Hurricane HR cyclone systems in two sizes HR_TMø275mm and HR_TMø400mm to capture the pharmaceutical waste particles from the combined flow of a deduster and tablet press for product waste compliance. Gas flow: 416m3/h & 850 m3/h at 25°C | Type of Particles: Waste particles | Efficiency: >98% Client: Actavis | Location: New Jersey, USA | Year: 2016

MW

221

5

REF_CE_18012018 Page 5/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

ReCyclone® MH to reduce PM emissions from a coal Bubbling Fluidized Bed (BFB) 4 ton/h boiler Gas flow: 9300m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia | Year: 2016

PA

21

68

Recyclone® MH to reduce particulate matter from a biomass boiler burning a mixture of mesocarp fibre and palm kernel shell Gas flow: 120 000m3/h at 260°C | Type of Particles: Biomass fly ashes | Emissions: <150mg/Nm3 Client: MPOB, Sindora Pall Oil Mill | Location: Kluang, Malaysia | Year: ongoing

P1

99

3

ReCyclone® MH optimized to reduce particles emission from a biomass boiler burning wood chips. Gas flow: 101 206m3/h at 160°C | Type of Particles: Biomass fly ashes | Emissions: <150mg/Nm3

dry Client: Combio Energias Renovaveis | Location: Minas Gerais, Brasil | Year: ongoing installation, prevision in January 2017

JB2

44

1

ReCylone® MH to reduce particulate matter from a biomass boiler burning a mixture of mesocarp fibre and palm kernel shell Gas flow: 183 600m3/h at 320°C | Type of Particles: Biomass fly ashes | Emissions: <100mg/Nm3

dry Client: LKPP Corporation Sdn. Bhd | Location: Pahang, Malaysia | Year: ongoing

P23

04

Hurricane MK for reducing particulate matter from Coal Bubbling Fluidized Bed (BFB) 4 ton/h boiler boiler flue gas. Gas flow: 9 300m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3

dry Client: Basuki | Location: Jawa Barat, Indonesia | Year: 2016

P26

00

Hurricane HR cyclone system used to capture particles from a biomass boiler. Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <40mg/Nm3

dry Client: Norbidel | Location: V.N.Famalicão, Portugal | Year: 2016

PA

2626

Hurricane HR cyclone system used to capture particles from a biomass boiler. Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <40mg/Nm3

dry Client: Norbidel | Location: Braga, Portugal | Year: 2016

PA

26

25

Hurricane MK cyclone system optimized to reduce particulate matter from a biomass boiler burning wood. Gas flow: 12 900m3/h at 209°C | Type of Particles: Biomass fly ashes | Emissions: <50mg/Nm3

dry Client: L. Solé S.A. | Location: Bavaro, Dominican Republic | Year: 2016

JB2

492

Hurricane MK cyclone system optimized to reduce particulate matter from a biomass boiler burning wood pellets. Gas flow: 28 558m3/h at 180°C | Type of Particles: Biomass fly ashes | Emissions: <150mg/Nm3

dry Client: L. Solé S.A. | Location: Costa Rica | Year: 2016

P25

64

Hurricane MK cyclone system for reducing particulate matter from a pyrolysis process. Gas flow: 184m3/h at 450°C | Type of Particles: Lithium Iron Phosphate | Emissions Guarantee: <325mg/Nm3

dry Client: Confidential | Location: Quebec, Canada| Year: 2016

MW

194

8

REF_CE_18012018 Page 6/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Recyclone® MH_MK optimized to reduce the emission of particles of a biomass boiler burning eucalyptus wood. Gas flow: 13 176m3/h at 178°C | Type of Particles: Biomass fly ashes | Emissions: <70mg/Nm3 Client: Florestal, S.A.| Location: Rio Grande do Sul, Brasil| Year: 2016

JB2

12

8

Hurricane MK cyclone system optimized to reduce particulate matter from a biomass boiler. Gas flow: 8 760m3/h at 328°C | Type of Particles: Biomass fly ashes | Emissions: <50mg/Nm3 Client: Britton Timbers | Location: Tasmania, Australia | Year: 2016

RF2

43

7

Hurricane HR cyclone system for cleaning particulate matter from the gas entrainment in the pipes working at a pressure of 16BAR.

Gas flow: 16016 Nm3dry/h (16 Bar) at 11°C | Type of Particles: Iron oxide dust | Efficiency: > 94%

Client: EDP Gás | Location: Porto, Portugal | Year: 2015

RF2

36

9

Hurricane MK for reducing particulate matter from Coal Bubbling Fluidized Bed (BFB) 4 ton/h boiler boiler flue gas.

Gas flow: 9300m3/h at 230°C. | Type of Particles: Coal fly ashes | Emissions: <68mg/Nm3 Client: Basuki | Location: Indonesia| Year: 2015

P22

45

Hurricane HR cyclone system for particulate matter abatement on 420hpb biomass boiler downstream existing multicyclone

Gas flow: 14 400m3/h at 171°C | Type of Particles: Wood fly ashes | Emissions: <150mg/Nm3

Client: Cargill | Location: San Pedro Sula, Honduras | Year: 2015

H21

36

Hurricane HC series for dust collection on two lines of wet wood chips grinding (hammermill).

Gas flow: 8 000m3/h at 20°C | Type of Particles: Wood dust | Expected Emissions: 15mg/Nm3

Client: Verdo| Location: Andover, UK | Year: 2015

H16

98

Hurricane MK type cyclone system for reducing particulate matter from 30ton/h coal BFB boiler flue gas

Gas flow: 68 000m3/h at 230°C. | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia, Jakarta | Year: 2015

P2

239

Hurricane HR cyclone system with hurricane SD pre-separation to reduce particulate matter from a biomass boiler.

Gas flow: 298 921m3/h at 170°C | Type of Particles: Sugar cane bagasse fly ashes | Emissions: <50mg/Nm3 Client: Azunosa| Location: El Progreso, Yoro, Honduras| Year: 2015

H21

19

Hurricane HR Cyclone systems and dust evacuation system to reduce sinter dust from extraction air of cooling section of sinter strand

Gas flow: 651 864m3/h at 350°C | Type of Particles: Sinter Dust | Emissions: <100mg/Nm3 Client: Arcelor Mittal | Location: Gent, Belgium | Year: 2015

H19

53

Hurricane HR Cyclones system to capture fine fly ash particulate enabling the use of wood waste fired thermal oil heater for Sonae Indústria (one of the largest wood-based panel producers in the world ) Gas flow: 247 088m3/h at 330°C | Type of Particles: Wood waste residues | Emissions: <77mg/Nm3

dry

Efficiency: 91,2% Client: EDP Comercial / Sonae Indústria| Location: Viseu, Portugal | Year: 2015

P2

25

4

REF_CE_18012018 Page 7/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Hurricane MK for particulate reduction emissions in the biomass boiler (chicken beds in rice husk). Gas flow: 56 012m3/h at 150°C| Type of Particles: Chicken beds fly ashes| Expected Emissions: <150mg/Nm3 Client: Campoaves | Location: Viseu, Portugal | Year: 2015

H77

6

Recyclone® MH system to reduce particulate matter from a biomass boiler burning a mixture of mesocarp fibre and palm kernel shell

Gas flow: 137 620m3/h at 320°C | Type of Particles: Biomass fly ashes | Emissions: <150mg/Nm3 Client: TradeWinds | Location: Sarawak, Malaysia | Year: 2015

P2

23

7

Hurricane HR cyclone system to capture PM emissions from a biomass boiler burning wood pellets

Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <40mg/Nm3 Client: Norbidel, Racentro | Location: Leiria, Portugal| Year: 2015

RF2

39

6

Hurricane HR cyclone system to capture PM emissions from a biomass boiler burning wood pellets

Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <40mg/Nm3 Client: Norbidel, Facol| Location: Guimarães, Portugal| Year: 2015

RF2

395

Hurricane MK cyclone for reducing particulate matter from a syngas flow. Gas flow: 603m3/h at 223oC | Type of Particles: Tar and Particles escaping a wood gasifier | Guaranteed Emissions: <500mg/Nm3 Client: Biosus Energy | Location: Aberdeenshire, UK| Year: 2015

MW

226

9

Hurricane MK for reducing particulate matter from 15ton/h coal BFB boiler flue gas. Gas flow: 34 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Surabaya, Indonesia| Year: 2015

P23

07

Hurricane MK for reducing particulate matter from 6ton coal BFB boiler flue gas.

Gas flow: 14 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Surabaya, Indonesia| Year: 2015

P2

306

Hurricane HR for product recovery and emission control of an organic fertilizer dryer. Gas flow: 14 519m3/h at 60°C | Type of Particles: Organic fertilizer dust| Emissions: <200mg/Nm3 Client: Nutrofertil | Location: São Tiago de Besteiros, Portugal | Year: 2014

H20

73

Hurricane MK for fly ash PM emission control of a coal BFB boiler.

Gas flow: 24 000m3/h at 350°C | Type of Particles: Coal fly ashes| Emissions: <150mg/Nm3

Client: Basuki | Location: Surabaya, Indonesia | Year: 2014

P20

87

Hurricane HR Cyclone systems to reduce emissions of dryer cyclones in Glowood pellet plant. Gas flow: 71 839m3/h at 87°C | Particles: Fines of mill sawdust | Emissions: <15mg/Nm3 Client: Glowood| Location: Cercal do Alentejo, Portugal| Year: 2014

P1

68

5

REF_CE_18012018 Page 8/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

ReCyclone® MH to reduce pm emissions from a coal bubbling fluidized bed (bfb) 6 million kilocalories per hour heater. Gas flow: 46 175m3/h at 380°C | Type of Particles: Coal fly ahes | Emissions: <159mg/Nm3

Client: Basuki | Location: Batam, Indonesia | Year: 2014

P1

92

3

Hurricane HR Cyclone system for reducing particulate matter from a syngas. Gas flow: 3 611m3/h at 400°C | Type of Particles: Biomass PM from gasification| Emissions: <41mg/Nm3

Client: KB Energy | Location: Etoliko, Greece | Year: 2014

JB2

14

7

Hurricane MK for fly ash PM emission control of a 4ton/h coal BFB boiler. Gas flow: 9 300m3/h at 230°C | Type of Particles: Coal fly ashes| Emissions: <54mg/Nm3

Client: Basuki | Location: Cikarang – West Java, Indonesia | Year: 2014

P1

99

6

Hurricane MK for fly ash PM emission control of a grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator. Gas flow: 3 200m3/h at 190°C | Type of Particles: Cork fly ashes| Emissions: <30mg/Nm3 at 11%O2

Client: Scierie de Miremont | Location: Lanouaille, France | Year: 2014

P19

72

Hurricane HR cyclone system to capture PM emissions from a grate type biomass boiler burning wood pellets Gas flow: 12 543m3/h at 220°C | Type of Particles: Biomass fly ashes| Emissions: <30mg/Nm3 Client: Norbidel Artemalhas | Location: Fafe, Portugal | Year: 2014

P20

41

Hurricane HR cyclone system for PM emission control from a grate type biomass boiler burning wood pellets Gas flow: 8 042m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <30mg/Nm3

Client: Norbidel Mirafios | Location: Santo Tirso, Portugal | Year: 2014

P20

42

Hurricane HR cyclone system for PM emission control from a grate type biomass boiler. Gas flow: 8 360m3/h at 220°C | Type of Particles: Pellets fly ashes| Emissions: <30mg/Nm3

Client: Norbidel Vicaima | Location: Vale de Cambra, Portugal | Year: 2014

P2

066

Recyclone® MH to reduce PM emissions from a Coal or Rice Husk Bubbling Fluidized Bed (BFB) 4 ton/h boiler Gas flow: 34 000m3/h at 230°C | Type of Particles: Coal or Rice Husk fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia | Year: 2016

PA

166

4

Hurricane HR cyclone system for reducing particulate matter emissions from black liquor recovery boiler before ventury scrubber. Gas flow: 37 000m3/h at 238°C | Type of Particles: Pellets fly ashes| Expected separation efficiency: 78.5 - 79.3% Client: Celesa | Location: Tortosa, Spain | Year: 2014

H17

82

Hurricane MK cyclone system for PM emission control from a grate type biomass boiler burning wood pellets Gas flow: 12 500m3/h at 220°C | Type of Particles: Biomass fly ashes | Emissions: <55mg/Nm3

Client: Norbidel | Location: Riba D´ave, Portugal | Year: 2014

P2

18

2

REF_CE_18012018 Page 9/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Recyclone® MH for fly ash PM emission control of a 6ton/h coal BFB boiler. Gas flow: 14 000m3/h at 230°C | Type of Particles: Coal fly ashes| Expected efficiency: <114mg/Nm3

Client: Basuki | Location: Tambun West Java, Indonesia| Year: 2014

P1

58

9

Hurricane HR for fly ash PM emission control of a grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator. Gas flow: 12 500m3/h at 100°C | Type of Particles: Wood chip fly ashes| Emissions: <50mg/Nm3

Client: Flucal | Location: Valongo, Portugal | Year: 2014

H19

34

Hurricane HR cyclone system to capture PM emissions from a grate type biomass boiler. Gas flow: 12 543m3/h at 220°C | Type of Particles: Wood chip fly ashes| Emissions: <40mg/Nm3

Client: Sorgal | Location: Ovar, Portugal | Year: 2014

P1

94

6

Recyclone® MK for fly ash PM emission control of a 10ton/h coal BFB boiler. Gas flow: 22 500m3/h at 230°C | Type of Particles: Coal fly ashes| Emissions: <100mg/Nm3 Client: Basuki | Location: Surabaya – East Java, Indonesia | Year: 2013

P18

57

Hurricane HR cyclone system to capture waste particules from a tablet pressing process and reduce load into HEPA filter. Gas flow: 234m3/h at 25°C | Type of Particles: Pharma particles | Guaranteed emissions: <50mg/Nm3

Client: Bluepharma | Location: Coimbra, Portugal | Year: 2014

MW

182

5

Hurricane MK system to reduce particulate matter emissions from straw burning boilers’ flue gases (850kW) Gas flow: 2 552m3/h at 152°C | Type of Particles: Straw fly ashes| Expected efficiency: 93.3–97.6% Client: Topling | Location: Scotland, UK | Year: 2013

H16

44

Hurricane HR cyclone system to capture at high temperature PM emissions from the off-gases of an MBM gasification unit. Gas flow: 8 000m3/h at 700°C | Type of Particles: MBM PM from gasification| Efficiency: 91.2 - 98.1% Client: Careco | Location: São João da Madeira, Portugal | Year: 2013

H18

69

Hurricane HR cyclone system to reduce particulate matter emissions from syngas

Gas flow: 3 250m3/h at 375°C | Type of Particles: tar and particles escaping a wood gasifier Expected efficiency: 97.2 - 98.4% | Expected Emissions: 24mg/Nm3

dry

Client: Storm Energy | Location: Plovdiv, Bulgary | Year: 2013

MW

183

8

Hurricane HR Cyclone system for reducing particulate emissions from heavy fuel oil boiler.

Gas flow: 7 241m3/h at 296°C | Type of Particles: Fly ash from HFO combustion | Emissions: 94 - 128mg/Nm3 at 11% O2

Client: Babcock Wanson | Location: Ilha Terceira Açores, Portugal | Year: 2013

P66

8

ReCyclone® MH for fly ash PM emission control of 6ton/h coal BFB boiler.

Gas flow: 14 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <150mg/Nm3

Client: Basuki | Location: Jakarta, Indonesia | Year: 2013

1795

REF_CE_18012018 Page 10/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

ReCyclone® MH for fly ash PM emission control on 4ton/h boiler burning palm shell. Gas flow: 6 972m3/h at 230°C | Type of Particles: Palm shell fly ashes| Emissions: <100mg/Nm3

Client: Basuki | Location: Sumatera, Indonesia | Year: 2013

17

91

Hurricane HR cyclone system for PM emission control from a grate type biomass boiler (2ton/h). Gas flow: 4 500m3/h at 230°C | Type of Particles: Pellets fly ashes | Efficiency: 85% | Emissions: <30mg/Nm3 at 11% O2

Client: Norbidel | Location: Coimbra, Portugal | Year: 2013

P1

78

5

Hurricane HR cyclone system to reduce particulate matter in a gasification process

Gas flow: 1 000m3/h at 450°C | Type of Particles: Tar and particles escaping a wood gasifier | Fuel: wood

Expected efficiency: 96.8 – 98.6%

Client: Biosus Energy | Location: Aberdeenshire, UK | Year: 2013

P1

66

6

Hurricane HR cyclone system for PM reduction of clinker fine and petroleum coke fly ash in a cement plant. It was installed downstream of the last existing cyclone of the pre-heater to reduce fines emissions Gas flow: 37 513m3/h at 327°C | Type of Particles: Fly ash from petroleum coke kiln | Expected efficiency: 87.15 - 92.92% Client: Duna Drava Cement | Location: Beremend, Hungary | Year: 2013

P80

6

ReCyclone® MH for fly ash PM emission control of a 10ton/h coal BFB boiler, placed after multicyclone/ cyclone pre-separator. Gas flow: 22 500m3/h at 230°C | Type of Particles: Coal and palm shell fly ashes| Emissions: <150mg/Nm3

Client: Basuki | Location: Makati City, Philippines | Year: 2013

P16

38

ReCyclone® MH to reduce PM emission from a Coal Bubbling Fluidized Bed (BFB) 6 Million Kilocalories Per Hour Heater. Gas flow: 42 638m3/h at 330°C | Type of Particles: Coal fly ashes | Emissions: <150mg/Nm3

Client: Basuki | Location: Batam Island, Indonesia | Year: 2013

P16

39

ReCyclone® MH for fly ash PM emission control of a 15ton/h coal BFB thermal oil heater, placed after multicyclone/cyclone pre-separator. Gas flow: 34 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <150mg/Nm3

Client: Basuki | Location: Cikarang – West Java, Indonesia | Year: 2013

P1

640

ReCyclone® MH type cyclone system for reducing particulate matter from a Coal/Palm Shell Bubbling Fluidized Bed (BFB) boiler flue gases. Gas flow: 22 500m3/h at 230°C | Type of Particles: Coal and Palm shell| Emissions: <150mg/Nm3

Client: Basuki | Location: Makati City, Philippines | Year: 2013

P18

60

Hurricane MK cyclone system for fly ash PM emission control of 3 grate type biomass boilers, placed after existing multicyclone/cyclone pre-separators Gas flow: 54 000m3/h at 175°C | Type of Particles: Cork dust fly ashes| Emissions: <100mg/Nm3

Client: Amorim Cork Composits | Location: Mozelos, Portugal | Year: 2013

H28

0

Two single Hurricane MK cyclones to reduce PM emissions from laser cutting machines Gas flow: 650m3/h at 20°C | Type of Particles: Paper particles from cutting | Emissions: <23mg/Nm3

Client: Laser Automation, Switzerland | Location: USA & Poland | Year: 2013

MW

169

1

REF_CE_18012018 Page 11/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

Hurricane HR cyclone system for fly ash PM emission control of a 25ton/h grate type biomass boiler, placed after multicyclone/cyclone pre-separator. Gas flow: 85 127m3/h at 256°C | Type of Particles: Palm shell and fibers fly ashes | Emissions: <150mg/Nm3 at 11% O2

Client: Jaremar – Caicesa | Location: Tela, Honduras | Year: 2012

P1

86

4

Hurricane HR Cyclone system for fly ash PM emission control of a 35ton/h grate type biomass boiler, placed after multicyclone/cyclone pre-separator.

Gas flow: 114 935m3/h at 204°C | Type of Particles: Palm shell and fibers fly ashes | Emissions: <150mg/Nm3 at 11% O2

Client: Jaremar – Agrotor | Location: Villanueva, Honduras | Year: 2012

P1

49

9

Recyclone® EH for fly ash PM emission control of a grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator.

Gas flow: 25 306m3/h at 250°C | Type of Particles: Wood pellet grat fly ashes | Emissions: <30mg/Nm3 at 11% O2

Client: L Solé | Location: Santo Domingo, Dominican Republic | Year: 2012

P1

65

0

ReCyclone® MH type cyclone system for reducing particulate matter from a Coal Bubbling Fluidized Bed (BFB) boiler flue gases.

Gas flow: 6 972m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3

Client: Basuki | Location: Bali, Indonesia | Year: 2012

P15

07

Hurricane HR Cyclone system to reduce PM from Syngas in a gasification process.

Gas flow: 425m3/h at 160°C | Type of Particles: Biomass fly ash and calcium carbonate | Emissions:

<50mg/Nm3

Client: Anguil | Location: Milwaukee, USA | Year: 2012

P13

98

Hurricane HR Cyclone system to recover fine particles from a calcination kiln reducing concentration to the final dust collector (bag filter).

Gas flow: 22 408m3/h at 131°C | Type of Particles: Quicklime and dolomitic Lime | Separation efficiency: 97%

Client: Microlime | Location: Seixal, Portugal | Year: 2012

H12

75

Hurricane HR Cyclone system to reduce tobacco fine particles in a tobacco drying line

Gas flow: 4 720m3/h at 180°C | Type of Particles: Tobacco particle | Emissions: <100mg/Nm3

Client: Garbuio Dickinson | Location: Hannover, Germany | Year: 2012

P1

556

ReCyclone® MH for PM emission control of two grate type biomass boilers, placed after multicyclone/ cyclone pre-separator

Gas flow: 90 000m3/h | Type of Particles: Wood waste and wood chips fly ashes | Emissions: <100mg/Nm3

Client: Sonae Novobord | Location: Nelspruit, South Africa | Year: 2012

H12

45

Hurricane HR Cyclone system for sinter PM emission control in a sintering process

Gas flow: 84 500m3/h at 150°c | Type of Particles: Sinter fines | Emissions: <70mg/Nm3

Client: Tecnosulfur, S.A. | Location: Sete Lagoas, Brazil | Year: 2012

P11

93

ReCyclone® MH for PM emission control of a grate type biomass boiler (6MWth), placed after multicyclone/cyclone pre-separator.

Gas flow: 30 000m3/h at 280°C | Type of Particles: Crushed pallets and bush residues | fly ashes Emissions: <100mg/Nm3 at 11% O2 Client: L. Solé. | Location: Los Angeles, Chile | Year: 2011

P1

18

9

REF_CE_18012018 Page 12/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

ReCyclone® MH type cyclone system for reducing particulate matter from a Coal Bubbling Fluidized Bed (BFB) boiler flue gases. Gas flow: 14 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3 Client: Basuki | Location: Indonesia | Year: 2011

PA

14

76

Recyclone® EH for fly ash PM emission control of a grate type biomass boiler, placed after multicyclone/ cyclone pre-separator.

Gas flow: 3 900m3/h at 180°C | Type of Particles: Pine residues fly ashes | Emissions: <30mg/Nm3 at 11% O2

Client: L. Solé | Location: Poitiers, France | Year: 2011

P1

16

9

Recyclone® EH Pilot System for PM emission control of a CaSi kiln.

Gas flow: 11 300m3/h at 150°C | Type of Particles: Casi | Emissions: <100mg/Nm3

Client: Bozel | Location: São João Del Rey, Brazil | Year: 2011

P9

89

Hurricane HR Cyclone system for PM emission control, working as a pre-filtering solution upstream of electrical power engines. Aim is to increase the life of cartridge filters.

Gas flow: 2 109m3/h at 30°C | Type of Particles: Sider Gas (GLD) PM| Emissions: <10mg/Nm3

Client: HC Energía | Location: Astúrias, Spain | Year: 2011

H15

5

ReCyclone® MH for fly ash PM emission control of a coal BFB boiler.

Gas flow: 14 000m3/h at 230°C | Type of Particles: Coal fly ashes | Emissions: <100mg/Nm3

Client: PT Basuki | Location: Jawa Barat, Indonesia | Year: 2011

P11

98

Hurricane HR Cyclone system to capture biomass fly ash and sawdust particles from rotary dryer in a wood pellet plant, placed after pre-separator.

Gas flow: 8 074m3/h at 110°C | Type of Particles: Sawdust and fly ash | Emissions: <150mg/Nm3

Client: Vimasol | Location: Celourico da Beira, Portugal | Year: 2011

H12

99

ReCyclone® MH convertible to a ReCyclone® EH for fertilizer dust emission control after a tunnel dryer

Gas flow: 50 400m3/h at 40°C | Type of Particles: Animal fertilizer dust | Emissions: <40mg/Nm3

Client: Plateau ASP | Location: Ferrol, Spain | Year: 2010

P1

139

Hurricane HR Cyclone system for dedusting of card board particles from cutting operations

Gas flow: 16 400m3/h at 30°C | Type of Particles: Card board from cutting | Emissions: <10mg/Nm3

Client: Efacec Energia | Location: Leça do Bailio, Portugal | Year: 2010

H12

22

ReCyclone® MH for for fly ash PM emission control of a biomass boiler

Gas flow: 9 500m3/h at 320°C | Type of Particles: Cork waste fly ashes | Emissions: < 100mg/Nm3 at 11% O2 Client: Granorte | Location: Avintes, Portugal | Year: 2008

ReCyclone® MH for fly ash PM emission control of a grate type biomass boiler

Gas flow: 9 600m3/h at 250°C | Type of Particles: Wood waste fly ashes | Emissions: <100mg/Nm3 at 11% O2

Client: CSC (Portuguesa) | Location: Varaize, France | Year: 2008

REF_CE_18012018 Page 13/12

PARTICULATE MATTER (PM) EMISSION CONTROL

Examples of Hurricane and ReCyclone® Systems in Existing Installations

ReCyclone® MH for fly ash PM emission control of a grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator

Gas flow: 27 000m3/h at 200°C | Type of Particles: Wood waste fly ashes | Emissions: <100mg/Nm3 at 11% O2

Client: Laminar, S.A. | Location: Pedroso, Portugal | Year: 2006

ReCyclone® MH for fly ash PM emission control of a 6MWth grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator

Gas flow: 50 000m3/h at 280°C | Type of Particles: Cork dust fly ashes | Emissions: <150mg/Nm3 at 11% O2

Client: MJO Lda. | Location: Vendas Novas, Portugal | Year: 2007

ReCyclone® MH for fly ash PM emission control of a 9MWth grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator

Gas flow: 57 000m3/h at 280°C | Type of Particles: Wood waste fly ashes | Emissions: <100mg/Nm3 at 11% O2

Client: Plysorol – Epernay | Location: Magenta, France | Year: 2006

ReCyclone® MH for fly ash PM emission control of a grate type biomass boiler

Gas flow: 8 000m3/h at 280°C | Type of Particles: Cork dust fly ashes | Emissions: 30 - 90mg/Nm3 at 11% O2

Client: Amorim & Irmãos, S.A. | Location: Vendas Novas, Portugal | Year: 2003

ReCyclone® MH for fly ash PM emission control of a grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator.

Gas flow: 15 000m3/h at 220°C | Type of Particles: Cork waste fly ashes | Emissions: <150mg/Nm3 at 11% O2

Client: Corkart Lda. | Location: Vendas Novas, Portugal | Year: 2003

ReCyclone® MH for fly ash PM emission control of a grate type biomass boiler, placed after existing multicyclone/cyclone pre-separator.

Gas flow: 9 500m3/h at 320°C | Type of Particles: Cork waste fly ashes | Emissions: <50mg/Nm3 at 11% O2

Client: Granorte, Lda. | Location: Rio Meão, Portugal | Year: 2002

H32

2

Hurricane HR cyclone system for fly ash PM emission control in a fuel oil boiler Gas flow: 4 000m3/h at 160°C | Type of Particles: HFO fly ashes | Emissions: <10mg/Nm3

Client: RAR, S.A. | Location: Porto, Portugal | Year: 2005