PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK...

29
CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.355 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11 PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK (For Building & Area Development Work) 1.0 INDIAN STANDARDS Work shall be carried out to Indian Standards and Code of Practices. In absence International Standards shall be followed. These shall be latest issue. List given hereunder is not to be considered as conclusive and is for reference and guidance only. Any discrepancies / conflict noticed shall be directed to the Engineer for his direction/approval. However as a general rule more stringent specification shall take precedence. (1) IS 226 Specification for Structural steel standard quality (2) IS 269 Specification for ordinary and low heat portland cement (3) IS 383 Specification coarse and fine aggregates from natural sources for concrete. (4) IS 1077 Specification for common burnt clay building bricks (5) IS 1489 Specification for Portland Pozzolana cement (6) IS 2116 Specification for sand for masonry mortars (7) IS 2212 Code of practice for brick work (8) IS 2250 Code of practice for preparation and use of masonry mortars. (9) SP 27 Handbook of method of measurement for building works.

Transcript of PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK...

Page 1: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.355 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

PARTICULAR SPECIFICATIONS

MASONRY WORK – BRICK WORK

(For Building & Area Development Work)

1.0 INDIAN STANDARDS

Work shall be carried out to Indian Standards and Code of Practices. In

absence International Standards shall be followed. These shall be latest

issue. List given hereunder is not to be considered as conclusive and is for

reference and guidance only. Any discrepancies / conflict noticed shall be

directed to the Engineer for his direction/approval. However as a general

rule more stringent specification shall take precedence.

(1) IS 226 Specification for Structural steel standard

quality

(2) IS 269 Specification for ordinary and low heat portland

cement

(3) IS 383 Specification coarse and fine aggregates from

natural sources for concrete.

(4) IS 1077 Specification for common burnt clay building

bricks

(5) IS 1489 Specification for Portland Pozzolana cement

(6) IS 2116 Specification for sand for masonry mortars

(7) IS 2212 Code of practice for brick work

(8) IS 2250 Code of practice for preparation and use of

masonry mortars.

(9) SP 27 Handbook of method of measurement for

building works.

Page 2: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.356 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

2.0 MATERIALS

2.1 Bricks

2.1.1 Bricks shall be sound, hard, well-burnt, uniform in size, shape and

colour, homogeneous in texture, giving a metallic ringing sound, free

from flaws, cracks, holes, lumps or grit and arises should be square,

straight and sharply defined. They shall not break when struck against

each other and dropped flat from a height of 1 m to the ground. They

shall conform to IS 1077 giving classes of common burnt clay bricks.

2.1.2 Bricks shall be as specified and detailed in the BOQ. It shall have to be

approved prior to procurement. Bricks shall be obtained from an

approved source and shall be of uniform colour, size, shape. Bricks shall

have smooth rectangular faces with sharp straight right angle edges.

Maximum absorption shall not be more than 20% of its dry weight on

immersion in water for 24 hours. Minimum crushing strength shall be 35

kg/sq cm if not specified in the BOQ.

2.1.3 Bricks of approved quality and quantity shall have to be procured by the

contractor at the desired time. No delay or extra cost due to non-

availability shall be accepted. The contractor is obliged to carry out the

work as specified. It shall be the responsibility of the contractor to

procure sufficient quantities of bricks and stack them at site or elsewhere

to avoid delays.

2.2 Mortars

2.2.1 Mortars for masonry shall be prepared in accordance with IS 2250 code

of practice for preparation and use of masonry mortars.

2.2.2 Cement

Cement shall be ordinary Portland cement conforming to IS. Approved

blended cement shall be used for internal plaster, masonry, flooring,

waterproofing and plumbing works. For all RCC and PCC works,

approved fly ash shall be used. For external plaster approved fly ash as

per specification of item shall be used.

Page 3: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.357 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

It shall be received in bags of 50 kg (or in bulk carriers in case of

storage in silos) and each batch shall be accompanied with a test

certificate of the factory. Also it shall be tested before use to ascertain its

strength, setting time, etc. In case cement has been stored for over 6

months from date of manufacturer or for any reasons the stored cement

shows signs of deterioration or contamination, it shall be tested as

per the direction of the Engineer prior to use in the works.

2.2.3 Water

Water used for masonry shall be potable conforming to IS, clean and

free from injurious amounts of deleterious materials.

2.2.4 Fine aggregate (sand)

Sand shall conform to IS 2116 specification for sand for Masonry

Mortars. Only river sand shall be used.

2.3 Damp proof course

2.3.1 A layer of concrete shall be a 40 mm thick mix in the ratio of 1:2:4 (1

cement: 2 sand: 4 stone aggregate, 10 mm nominal size). The concrete

layer shall be provided with a water proofing treatment which may

either be a surface treatment or with approved integral waterproofing

compounds. The concrete shall be cured for 7 days after which it shall

be allowed to dry. For surface treatment of concrete, hot bitumen at the

rate of 1.7 kg/100 sqm shall be used. The temperature of the bitumen at

the time of application shall not be less than 121˚C and bitumen shall be

blown type confirming to IS 702 or bitumen confirming to IS 73. The

penetration of bitumen shall be tested in accordance with IS 1203.

2.3.2 Slate and cuddappa stone slabs used shall be of minimum 40 mm

thickness and shall have exposed edges finely dressed, true and square.

2.4 Metal reinforcement

Metal reinforcement used in brick masonry shall conform to the

following Indian Standard Specifications.

a) IS 226 Specification for steel standard quality

Page 4: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.358 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

b) IS 412 Specification for Expanded metal steel sheet for

general purpose

c) IS 432 Specification for Mild steel and Medium tensile steel

bars

d) IS 1566 Specification for Steel fabric or hard drawn steel wire

3.0 MORTAR

3.1 Mortar shall be prepared by using antishrinkage compound (as specified

by manufacturer of approved chemical) mixing fine graded aggregate

with cement in the proportion specified for respective items of work as

detailed in the BOQ. Mixing of mortar shall be done by mechanical

mixers or by hand mixing. Non shrinking compound shall be added to

the mortar as per direction of approved manufacturer.

3.2 Mortars shall be specified by proportion. Volumetric mixing shall be

based on dry volumes of each ingredient. For convenience, measurement

shall correspond to volume of one cement bag i.e. 0.035 cu m. Boxes

shall be of size 40 X 35 X 25 cm. These shall be marked as mortar

mixing boxes by red paint and shall be used throughout the contract.

Hand mixing or mechanical mixing proportions shall be done with the

use of these boxes.

3.3 Cement mortar shall be prepared by mixing cement, sand and non-

shrinking compound in specified proportions. Proportioning shall be

carried out as detailed above. Sand shall be added suitably to allow for

bulkage if required. Bulkage shall be determined as specified in IS 2386

Part III. Cement and sand added to mixer shall be thoroughly mixed and

water shall be added to it gradually. After addition of water the mixer

shall run for a minimum of 3 minutes. The mortar mixed shall be

consumed within 30 minutes of its mixing.

Page 5: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.359 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

4.0 WORKMANSHIP

4.1 Bricks used for masonry in cement mortar shall be soaked by immersing

in water or by hosing of water (so as to prevent bubbling.) at least one

hour prior to start of actual laying.

4.2 Bricks shall be laid in English bond unless otherwise specified. Half or

cut bricks shall be used only for the purpose of bond and at no other

place.

4.3 Work shall be true to horizontal lines and perfect plumb. Vertical joints

shall be truly vertical and those in alternate courses shall be in the same

vertical line. Joints of each course shall be within the limit of 6 mm to

10 mm depending upon the size of bricks. Total height of 9 cm brick

with 5 courses and 5 mortar joints shall be 50 cm. In no case shall joint

thickness of horizontal and vertical be more than stated above. Joints

should be filled to full depth and checked each time. Prior to start of

work it must be noted and checked that bricks on top are full-size bricks

(flat or brick on edge). To achieve this, precautions should be taken

from the start of the first layer. Thickness of joints shall be so adjusted

so as to have full bricks on top. Also it must be noted and checked that

all horizontal joints on every floor are at the same level, so as to allow

proper bonding at junctions. For avoiding any crack specially at

junctions of RCC columns, walls, soffit of beams etc. use mortar mixed

with non shrinking compound mortar (as per manufacturers

specification).

Required datum levels must be established throughout the floor and only

then should work start.

It is equally important to take into account levels of window sills, lintels,

etc. while finalising courses and joint thickness.

In normal practice architects do take care of these while finalising

levels, but it is difficult to expect the ideal situation at all places. In such

Page 6: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.360 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

situations, the decision of the Engineer shall be taken such as providing

brick on edge, concrete sills, etc.

In addition, for convenience and speed, gauge boards of exact width

shall be fixed at the edges of masonry to correct line and plumb. These

boards shall be marked with course levels to achieve exact height of

each course and full bricks at the top.

4.4 One or half brick thick wall shall have minimum one face in true plumb.

4.5 It is imperative to raise the brick work uniformly over complete Work

joined together. If this is not possible, raked brick work shall be done at

45 degrees to the vertical. Toothing shall not be accepted.

4.6 All iron fixtures, pipe outlets, hold-fasts for doors and windows shall be

fixed when the brick work is in progress. It must be embedded in cement

mortar or concrete as specified or as directed by the Engineer. Required

treatment to fixtures shall be carried out prior to embedding.

4.7 To achieve better results and proper working, the following tools should

be available with masons working at site :

1. Spirit level

2. Wooden/Aluminium straight edge 3 m long

3. 3 metre steel tape

4. Right angle 1/2 metre long

5. Line and pin strings

6. Plumb

7. Storey rods

4.8 Joint thicknesses shall be provided as discussed above. Joints shall be

filled to full depth before second course is laid. Frogs shall be upward at

all times. Joints shall be raked back to a minimum 10 to 15 mm while

the mortar is green. Surface of brick work shall be cleaned with coir

string, wire brushes, etc. to keep the surface free for the next operation.

All dropped and spoiled mortar, brickbats, etc. shall be cleared from the

floor before work is closed for the day.

Page 7: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.361 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

4.9 Protection and curing

Green work shall be protected from rains by suitable covering. Masonry

in cement mortar shall be kept constantly moist on all the faces for a

minimum period of ten days. The top of masonry shall be left flooded

with water at close of the day.

4.10 Scaffolding

Scaffolding independent of brick work i.e. double scaffolding shall be

provided. It should be tied to brick work or structure at suitable intervals

in both directions. Two rows of planks shall be provided all around.

Planks shall be at least 50 mm thick and well-tied to scaffolding. Railing

to the outside face shall be provided. While erecting scaffolding, the

following points must be noted and closely followed :

1. Minimum number of holes in the horizontal direction. Holes

shall be formed by omitting header brick.

2. No holes in pillars under 1 metre in width.

3. No holes near the skew backs of arches.

4. Scaffolding must be sound and strong and easy to maintain.

5. Holes left must be closed while finishing the plaster.

5.0 TYPES OF BRICK WORK

5.1 Walls 230 mm thick or more

5.1.1 Walls of 230 mm thickness or more shall be constructed with approved

and selected bricks. Mortar shall be as specified in the BOQ.

Points discussed above shall be followed for workmanship.

Brick wall of 230 mm thickness shall be constructed from one side and

one face shall be true and plumb. Thicker walls shall be constructed with

masons on both faces and both the faces shall be true and plumb.

5.2 150mm (6") thick brick masonry

5.2.1 Walls shall be constructed with approved and selected bricks. Mortar

shall be as specified in the BOQ.

Page 8: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.362 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

Points discussed above shall be followed for workmanship.

Brick wall shall be constructed such that both faces shall be true and

plumb.

5.3 Half brick work - plain or reinforced

5.3.1 115 mm thick brick work shall be called as half brick work. It shall be

built by laying bricks in stretcher bond. Mortar shall be as specified in

the BOQ.

These walls may be used for forming cavities or partition walls inside

buildings. Brick work shall be reinforced with either of following

methods:

1) With 8 mm dia bars, 2 bars at every third layer.

2) GI metal lath / GI hoop iron 25 mm X 1.6 mm shall be used at

every third layer as detailed by layer as detailed by the

manufacturer.

3) Patli Beams of 115 x 100 mm high in M20 grade concrete shall

be casted. Beam shall be reinforced with 2 nos. of 8 mm dia Tor

bars and 6mm dia M.S. links at 300mm C/C. Patli beams shall be

at every 900 mm interval in height.

Embedding of reinforcement shall be done very carefully. All

precautions shall be taken so that edges are not exposed. Lapping of bars

and lath shall be proper and staggered.

5.3.2 Reinforcement and shuttering shall be part of the item.

5.4 Brick on edge coping

The top course of all plinths, parapets, steps and tops of walls below

R.C.C. slabs or beams shall be laid with brick on edge, unless otherwise

specified. Proper care shall be taken that the bricks forming the top

corners and end of walls shall be properly rediated and keyed into

position.

Page 9: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.363 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

6.0 ITEM INCLUDES

6.1 The item shall include the cost of all the materials including all wastages

and labour as described in their respective items of work and for all the

operations as detailed in the respective specifications for the various

items of work. Brick on edge courses, cut brick corners, splays, reveals,

cavity walls, shall be included in BRICK WORK - for the purpose of

payment.

6.2 The following operations shall be included in the item for BRICK

WORK -:

a) Raking out joints for plastering or for pointing done as a separate

process or for finishing joints flush as work proceeds;

b) Preparing tops and sides of existing walls and the like for

raising;

c) Rough cutting and waste for forming gables, cores of arches,

splays at caves and the likes and all rough cutting in the body of

brick- work, unless otherwise stated;

d) Plumbing to angles and battered surfaces;

e) Forming reveals to jambs where fair cutting on exposed faces is

not involved;

f) Leaving holes for pipes, etc.;

g) Building-in holdfasts, air bricks, fixing bricks, etc.;

h) Building-in ends of beams, joists, slabs, lintels, sills, trusses,

etc.;

i) Forming openings and flues for which no deduction is made;

j) Bedding wall plates, lintels, sills, roof tiles, corrugated sheets,

etc., in or on walls, if not covered in their respective trade.

k) Leaving chases of section not exceeding 50 cm in girth.

l) Curing.

* * * * *

Page 10: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.364 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

PARTICULAR SPECIFICATIONS

MASONRY WORK – CONCRETE BLOCK WORK

1.0 GENERAL

1.1 Indian Standards

Work shall be carried out to Indian Standards and Code of practices. In

absence International standards shall be followed. These shall be latest

issue. List given hereunder is not to be considered as conclusive and is

for reference, guidance only. Any discrepancies / conflict noticed shall

be directed to the Engineer for his direction / approval. However as a

general rule more stringent specification shall take precedence.

(1) IS 269 Specification for ordinary and low heat portland

cement grade 33

(2) IS 383 Specification for coarse and fine aggregates from

natural sources for concrete.

(3) IS 456 Code of Practice for plain and reinforced concrete.

(4) IS 1489 Specification for Portland Pozzolana cement

(5) IS 2185 Specification for concrete masonry units hollow and

solid cement blocks.

(6) IS 8112 Specification for ordinary portland cement grade 43.

(7) IS 9103 Specifications for admixtures for concrete.

(8) IS 13757 Burnt clay fly ash building bricks

2.0 MATERIAL

2.1 Cement

2.1.1 Cement shall be ordinary Portland cement conforming to IS. Approved

blended cement shall be used for internal plaster, masonry, flooring,

waterproofing and plumbing works. For all RCC and PCC works,

Page 11: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.365 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

approved fly ash shall be used. For external plaster approved fly ash as

per specification of item shall be used.

2.1.2 It shall be received in bags of 50 kg (or in bulk carriers in case of

storage in silos) of one brand and one grade with consistency certificate

of the manufacturer. Also it shall be tested before use to ascertain its

strength, setting time, etc. In case cement has been stored for over 6

months from date of manufacture or for any reasons the stored cement

shows signs of deterioration or contamination, it shall be tested as

per the direction of the Engineer prior to use in the works. In case

blended cement is used, it shall be factory blended only (fly ash only

upto 25%).

2.2 Aggregates

2.2.1 Aggregate shall conform to IS 383 requirements. Coarse aggregate shall

be obtained from natural sources such as stone, gravel etc. crushed or

uncrushed from identified and approved quarries. Aggregate shall be

hard, durable, clean and free from adherent coatings. The seasonal

changes shall be well guarded. Grading shall be as indicated in IS 383.

Fineness modules of the combined aggregates shall be between 3.6 and

4. The maximum size of the aggregates shall be 10mm-6mm.

Coarse aggregates shall be free from harmful materials such as iron,

pyrites, coal, mica, shale or similar laminated material, clay, alkali, soft

fragments sea shells, organic impurities etc. Impurities present within

acceptable limits shall not adversely affects strength and durability.

2.2.2 Fine aggregates

Sand shall be well graded, hard, durable, clean and free from adherent

coatings and organic matter and shall not contain any appreciable

amount of clay. Sand shall not contain harmful impurities such as iron,

pyrites, coal particles, lignite, mica shale or similar laminated material,

alkali, and organic impurities in such form or quantities as to affect the

strength or durability of concrete or mortar. The seasonal changes shall

Page 12: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.366 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

be well guarded. Sand shall be invariably washed using screw-type sand

washing machine only if the silt content is not within the permissible

limits.

When tested as per IS 2386 part I & II, fine aggregate shall not exceed

permissible quantities of deleterious materials as given.

2.3 Water

2.3.1 Water used for mixing and curing shall be clean reasonably clear and

free from objectionable quantities of shell, silts, alkalies, acids etc.

2.3.2 Water tested shall be in accordance with IS 3025. Maximum

permissible limits of deleterious materials in water shall be as given in

IS 456.

2.4 Concrete block

Factory made solid concrete block, hydraulically pressed, machine

vibrated, steam cured only shall allow to be used in the work. The

approval of Engineer shall be obtained before placing the order.

Concrete blocks shall be solid and shall be referred to by its nominal

dimension. The term nominal dimension includes the thickness of the

mortar joint. Actual dimensions shall be 10 mm short of the nominal

dimensions. Blocks shall be made in sizes and shapes to fit different

construction needs. It includes stretcher, corner, double corner or pier,

jambs, header, bullnose, partition block and concreted floor units.

Nominal dimensions of concrete blocks shall be,

Length - 390 mm

Height - 190 mm

Width - 90 or 140 or 190 mm

Maximum variations in length shall be 5% in length and 3% in width

and height.

Face shells and webs shall not be less than the values given in the

reproduced table 15 of Annexure.

Page 13: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.367 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

2.4.2 Grade of concrete for block shall be M10 with maximum water cement

ratio of 0.35 for concrete. Concrete shall be mixed in the mechanical

mixer. Blocks shall be moulded, laid and compacted with automatic

machines only. No hand/manual compaction shall be permitted. Care

shall be taken to see that the mix is placed in layers and each layer

thoroughly tamped until the whole mould is filled up. Blocks shall be

protected until they are sufficiently hardened to permit handling without

damage. Naphtha based super plasticizer; admixtures of doses

prescribed by the manufacturer shall be used. Mixed designed shall be

done and established with sufficient trial mixes.

Cured blocks shall be allowed to dry for a period of 30 days before

being used. The blocks shall be allowed to complete their initial

shrinkage before they are laid in the wall.

2.4.3 All blocks shall be sound and free of cracks or other defects. For

exposed construction face or faces shall be free of chips, or other

imperfections, and the overall dimensions of the blocks shall be in

accordance to tolerance as specified.

2.4.4 Blocks shall be considered as per IS if requirements of conditions

mentioned in 11.2 to 11.5 of IS 2185 (Part I) are satisfied.

1. The number of blocks with dimensions outside the tolerance

limit and/or with visual defects, among those inspected shall not

be more than two.

2. Density and compressive strength shall be greater than or equal

to the minimum limit specified in table 2 of IS 2185 (part I)

(table 16 of Annexure)

3. Drying shrinkage shall not exceed 0.1 percent.

4. Water absorption shall not be more than 10 percent by mass.

2.5 Mortar

2.5.1 Mortar shall be prepared by using antishrinkage compound (as specified

by manufacturer of approved chemical) mixing fine graded aggregate

Page 14: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.368 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

with cement in the proportion specified for respective items of work as

detailed in the BOQ. Mixing of mortar shall be done by mechanical

mixers or by hand mixing. Non shrinking compound shall be added to

the mortar as per direction of approved manufacturer.

2.5.2 Mortars shall be specified by proportion. Volumetric mixing shall be

based on dry volumes of each ingredient. For convenience, measurement

shall correspond to volume of one cement bag i.e. 0.035 cu m. Boxes

shall be of size 40 X 35 X 25 cm. These shall be marked as mortar

mixing boxes by red paint and shall be used throughout the contract.

Hand mixing or mechanical mixing proportions shall be done with the

use of these boxes.

2.5.3 Cement mortar shall be prepared by mixing cement, sand and non-

shrinking compound in specified proportions. Proportioning shall be

carried out as detailed above. Sand shall be added suitably to allow for

bulkage if required. Bulkage shall be determined as specified in IS 2386

Part III. Cement and sand added to mixer shall be thoroughly mixed and

water shall be added to it gradually. After addition of water the mixer

shall run for a minimum of 3 minutes. The mortar mixed shall be

consumed within 30 minutes of its mixing.

2.6 Admixtures

Additives or admixtures may be added to the cement or concrete mix

conforming to the following Indian Standard specifications.

1. IS 9103 Specifications for admixtures for concrete.

2. IS 3812 Specification for fly ash for use as pozzolana and

admixture.

3. IS 2645 Specifications for integral water proofing compound.

Other additives or admixtures not being governed by Indian Standards

shall be tested and checked that the same are not detrimental to

durability. Any usage shall only be after the approval of the Engineer.

Page 15: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.369 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

2.7 Joint Fillers

Bituminous impregnated, premoulded joint filler board shall be of

approved quality, manufacturer and conform to IS 1838 part I.

2.8 Metal reinforcement

Expanded metal used shall comply IS 412.

2.9 Delivery / Storage

2.9.1 Load, unload deliver, store all concrete blocks with due care, at site to

be free from damage, dirt, intrusion of foreign materials etc.

2.9.2 Store all concrete block units on raised solid platforms.

2.9.3 Protect block from any excess of weather conditions.

3.0 SCOPE OF WORK

Provide, construct with specified strength, quality concrete block

masonry or burnt clay fly ash brick masonry conforming to IS Code of

Practices, approved method of statement by Engineer, including

providing leveling course PCC M20 grade to adjust with full size

blocks/bricks, approved mix of mortar, construction and expansion joint

fillers, metal reinforcement wherever required of type, size and shape,

providing special bond adjusting blocks, reinforced patli (course runner)

beams of concrete M 20 required double – legged scaffolds etc

complete.

4.0 WORKMANSHIP

4.1 Concrete blocks shall not be wetted like brick masonry prior to use. In

total dry climate top and sides may be slightly moistened to avoid

absorption of water from mortar. The column surface and beam bottom

shall be prepared properly by hacking to avoid debonding.

4.2 Concrete block work shall be laid in English bond. Joints shall not be

bigger than 10 mm and will be perfectly horizontal and vertical. Joints

shall be raked 10 mm deep while mortar is green.

Page 16: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.370 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

4.3 Cut blocks shall not be used. Special solid precast blocks at site shall be

cast well in advance to be used as spacers and to adjust breaking of

vertical joints.

4.4 Cracks in block masonry are due to shrinkage or expansion of

blocks or due to load settlement, thermal expansion or changes in

moisture content in the structural members enclosing the block walls.

The following measures are recommended to prevent formation of

cracks.

a. While curing, the block masonry should be lightly sprinkled with

water and not made excessively wet.

b. Expansion joints shall be provided in walls exceeding 30 m in

length.

c. Reinforcement of 8mm dia 3 Nos. 600mm c/c bothsides or

weldmesh, should be provided in the bed joints in block work,

one course above and one course below windows and above

doors in order to distribute the shrinkage/ temperature stresses

occurring at the corners of openings, more uniformly

throughout the walls.

d. In framed structures, erection of partition and panel walls should

be delayed to take care of deformations due to structural loads.

e. Partition walls should be suitably reinforced in lower courses

to strengthen against excessive deflections of floor slabs and

should be separated from the ceiling by a layer of resilient

material. Joint shall be carried out in plaster or any other finish.

4.5 The last layer of block Masonry shall be laid by keeping groove of

15mm x 12 mm on the external side, which should be filed up with

epoxy mortar and Metal.

4.6 Where required damp proof course layer shall be laid as specified.

4.7 Exposed faces and corners of masonry damaged during construction

shall be removed and repaired as acceptable to Engineer.

Page 17: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.371 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

4.8 Scaffolding :

Scaffolding independent of block work i.e. double legged single /

multiple staging scaffolding shall be provided. It should be tied to block

work or structure at suitable intervals in both directions. Two rows of

planks shall be provided all around. Planks shall be at least 50 mm thick

and well-tied to scaffolding. Railing to the outside face shall be

provided. While erecting scaffolding, the following points must be noted

and closely followed :

1. Minimum number of holes in the horizontal direction.

2. No holes near the skew backs of arches.

3. Scaffolding must be sound and strong and easy to maintain.

4. Holes left must be closed while finishing the plaster.

4.9 Raking back shall be carried out at an angle not steeper than 45

degrees in case all the block work is not raised together.

4.10 The block should be of full height and no cut pieces shall be allowed.

PCC leveling course shall be laid to fill up the gap.

5.0 ITEM INCLUDES

Items shall include followings -

a. Material including all wastages and labour, for the completion of

items as specified including any centering, shuttering, curing etc.

b. Raking out of joints.

c. Preparing the tops and sides.

d. Forming and preparing expansion, contraction or construction

joints as detailed above or specified in the BOQ or drawings.

e. Making holes, openings, etc. for outlets, embedding down take

pipes, etc. wherever necessary during construction, and finishing

exposed surfaces as per instruction of the Engineer.

f. Curing and protection as specified.

Page 18: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.372 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

g. Making holes, openings, outlets, etc. embedding pipes, ends of

beams, joists, slabs, trusses, sills, etc. whatever required during

construction and neatly finishing the exposed surfaces and

opening as per instructions of the Engineer.

h. For masonry use of approved non-shrinking compound in

cement mortar.

* * * * *

Page 19: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.373 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

PARTICULAR SPECIFICATIONS

MASONRY WORK – STONE MASONRY

1.0 INDIAN STANDARDS

Work shall be carried out to Indian Standards and Code of Practices. In

absence International Standards shall be followed. These shall be latest

issue. List given hereunder is not to be considered as conclusive and is

for reference and guidance only. Any discrepancies / conflict noticed

shall be directed to the Engineer for his direction/approval. However as

a general rule more stringent specification shall take precedence.

(1) IS 1121 Methods of test for determination of strength

properties of natural building stones.

Part 1 Compressive strength

Part 2 Transverse strength

Part 3 Tensile strength

Part 4 Shear strength

(2) IS 1124 Methods of test for determination of water

absorption apparent specific gravity and

porosity of natural building stone.

(3) IS 1127 Recommendations for dimensions and

workmanship of natural building stones for

masonry work.

(4) IS 1489 Specification for Portland Pozzolana cement

(5) IS 1597 Code of Practice for Part 1 construction of stone

masonry : Rubble stone masonry

(6) SP 27 Handbook of method of measurement of

building works.

Page 20: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.374 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

2.0 MATERIAL

2.1 Cement

2.1.1 Cement shall be ordinary Portland cement conforming to IS. Approved

blended cement shall be used for internal plaster, masonry, flooring,

waterproofing and plumbing works. For all RCC and PCC works,

approved fly ash shall be used. For external plaster approved fly ash as

per specification of item shall be used.

2.1.2 It shall be received in bags of 50 kg (or in bulk carriers in case of

storage in silos) and each batch shall be accompanied with a test

certificate of the factory. Also it shall be tested before use to ascertain its

strength, setting time, etc. In case cement has been stored for over 6

months from date of manufacturer or for any reasons the stored cement

shows signs of deterioration or contamination, it shall be tested as

per the direction of the Engineer prior to use in the works.

2.2 Fine aggregate

2.2.1 Natural sand deposited by stream or glacial agencies as a result of

disintegration of rock is the best form of fine aggregate. The fine

aggregate shall conform to following standards.

(i) For plain and reinforced concrete IS 383 Specification for coarse

and fine aggregates from

natural sources for concrete.

(ii) Mortar and grout IS 2116 Specification for sand

for masonry mortars.

(iii) For plastering IS 1542 Specification for sand

for plaster (Class A grading).

2.2.1.2 Sea sand should not be used unless approved by the Engineer. If

approved, the required treatment shall be done at the contractor's cost.

2.2.2 Sand shall be hard, durable, clean and free from adherent coatings and

organic matter and shall not contain any appreciable amount of clay.

Sand shall not contain harmful impurities such as iron, pyrites, coal

Page 21: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.375 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

particles, lignite, mica shale or similar laminated material, alkali, and

organic impurities in such form or quantities as to affect the strength or

durability of concrete or mortar. Also it should not contain any

material liable to attack the steel reinforcement.

2.2.2.1 When tested as per IS 2386 Part I and Part II, fine aggregate shall not

exceed permissible quantities of deleterious materials.

2.2.2.2 Fine aggregate shall be thoroughly washed at site with clean fresh water

such that the percentage of all deleterious material is within the

permissible limits laid down.

2.2.3 Aggregate shall be stored in such a way that it does not get mixed with

mud, grass, vegetables and other foreign matter. The best way is to

have a hard surface platform made out of concrete, bricks or planks. It

should be to the approval of the Engineer.

2.3 Water

2.3.1 Water used for mixing and curing shall be clean, reasonably clear and

free from objectionable quantities of silt, oils, alkalis, acids, salts so as

not to weaken mortar, or concrete or cause efflorescence or attack the

steel in RCC While curing. It shall be free of elements, which

significantly affects the hydration reaction or otherwise interferes with

hardening of concrete during curing, or those elements which produce

objectionable stains or deposits. Potable water is generally satisfactory

but it shall be tested prior to use in the works.

2.3.2 Water tested shall be in accordance with IS 3025. Maximum

permissible limits of deleterious materials in water as given in IS 456.

2.4 Stone

2.4.1 Stone to be used in masonry shall be trap, granite, quartzite, gneiss,

laterite or any other type of good stone as specified in the BOQ or as

approved by the Engineer. For all practical purposes good trap, granite,

quartzite or gneiss shall be used unless specified otherwise in the BOQ.

Page 22: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.376 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

2.4.2 All stones shall be free from defects like cavities, cracks, sand holes,

flaws, injurious veins, patches of loose or soft materials, etc. The

percentage of water absorption shall generally not exceed 5%.

2.4.3 The strength of building stones should be adequate to carry the loads

imposed. Table 1 of IS 1597 gives the minimum crushing strength of

approved stones. Minimum strength shall be 200 kg/sqcm unless

specified otherwise.

2.4.4 Stones used shall be small enough to be lifted and placed by hand.

Length of the stones shall not exceed three times their height, and the

breadth of the base shall not be greater than three-fourths of the

thickness of wall or less than 150 mm. The height of stones for rubble

masonry may be upto 300 mm.

2.4.5 Stones with round faces shall not be used.

2.5 Metal fittings

2.5.1 Metal fittings shall be non-corrosive/non-ferrous. Use of iron clamps

and similar fittings for embedding into the masonry work shall be

avoided. If permitted by the Engineer, they shall be treated with anti-

corrosive treatment.

2.6 Mortar

2.6.1 The cement, sand and water used shall meet the Indian Standards

specifications.

2.6.1.1 Mortars shall be prepared by mixing fine graded aggregate with

cement in the proportion specified for respective items of work as

detailed in the BOQ. Mixing of mortars shall be done by mechanical

mixers or by hand mixing. Hand mixing shall not be permitted.

2.6.1.2 Mortars shall be specified by proportion. Volumetric mixing shall be

based on dry volumes of each ingredient. For convenience,

measurement shall correspond to volume of one cement bag i.e. 0.035

cu m. Boxes shall be of size 40 X 35 X 25 cm. These shall be marked

as mortar mixing boxes by red paint and shall be used throughout the

Page 23: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.377 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

contract. Mechanical mixing proportions shall be done with the use of

these boxes.

2.6.1.3 Cement mortar shall be prepared by mixing cement and sand in

specified proportions. Proportioning shall be carried out as detailed

above. Sand shall be added suitably to allow for bulkage if required.

Bulkage shall be determined as specified in IS 2386 Part III. Cement

and sand added to mixer shall be thoroughly mixed and water

shall be added to it gradually. After addition of water the mixer shall

run for a minimum of 3 minutes. The mortar mixed shall be consumed

within 30 minutes of its mixing.

3.0 WORKMANSHIP

3.1.1 Dressing and shaping of stone shall be done before being used in

masonry. Quality of dressing and shaping shall be as approved by the

Engineer.

3.1.2 All necessary chases for joggles, dowels and cramps should be formed

in stone beforehand.

3.1.3 Sufficiently wetted, cleaned stone shall be laid to lines, levels, curves

and shapes as shown in the plans. Stones shall be laid on their broadest

face in mortar and settled carefully in place with a wooden mallet. Clean

chips and spells, carefully selected to fit in the spaces shall be wedged to

avoid thick beds or joints of mortar.

3.2 All connecting walls shall be raised together. In case one part is

required to be left behind, raking back at an angle of 45 degrees or less

shall be done.

3.3 It is imperative to adjust levels right at the start to achieve correct levels

of window sill, roof, etc. But as this is quite difficult to achieve, it shall

be part of the stone masonry work to provide cement concrete sill of

mix in a ratio of 1:4:8 (1 cement, 4 sand and 8 20 mm graded

Page 24: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.378 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

aggregate) of 100 to 150 mm thickness in consultation with the

Engineer.

3.4 Maximum thickness of joint shall be 20 mm for random rubble and 10

mm for course. Stones shall be set and laid by wooden hammer

(mallet) and voids, if any, packed and consolidated by stone

chips. Chips used shall not be more than 15% by volume of masonry.

3.5 Stones of full width of wall thickness shall be provided at every 600

mm centre to centre in each layer and staggered. For walls thicker than

600 mm two through stones overlapping each other at a minimum of

150 mm shall be placed.

3.6 The work shall be in perfect plumb or battered as specified.

3.7 Corner stones shall be well-dressed and chiseled. These shall be

laid header and stretcher alternate. They shall not be smaller than

0.025 cu m and 300 mm in length. Further it must be noted that 25%

of the above shall not be shorter than 500 mm in length.

3.8 Jambs shall be made from dressed corner stones.

3.9 Work of the day shall be raked to a depth of 20 mm while the mortar is

green and cleaned with a coired string brush or wire brush. Stone

surfaces shall be free of mortar or cement coats.

3.10 Vertical joints shall be staggered.

3.11 At angular junctions, stones at each alternate course shall be well-

bonded into the respective courses of the adjacent wall.

3.12 Masonry construction with very thin faces, tied up with occasional

through stones or filled up with dry packing or small-size aggregates

shall be strictly prohibited.

3.13 Storey rods showing the heights of all doors and windows and other

necessary information should be used at the time of construction of

masonry.

3.14 Door and window frames shall be fixed with hold-fast of adequate size

and strength. Iron hold-fast shall be treated with anti- corrosive coating

Page 25: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.379 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

and timber to prevent attack from insects and termites. In addition, hold-

fast shall be securely embedded in chases with cement-concrete in a

ratio of 1:2:4. Frames shall preferably be fixed simultaneously as work

proceeds.

4.0 SCAFFOLDING

4.1 Scaffolding, independent of masonry work i.e. double scaffolding, shall

be provided. It should be tied to masonry work or structure at suitable

intervals in both directions. Two rows of planks shall be provided all

around. These shall be at least 50 mm thick and well-tied to the

scaffolding. Railing to outside faces shall be provided. While erecting

scaffolding, the following points must be noted and closely followed.

1. Minimum number of holes in horizontal direction. Holes shall be

formed by omitting header.

2. No holes in pillars under 1 metre in width.

3. No holes near the skew backs of arches.

4. Scaffolding must be sound and strong and easy to maintain.

4.2 Protection and Curing

Green work shall be protected from rains by suitable covering. Masonry

in cement or composite mortar shall be kept constantly moist on all

the faces for a minimum period of seven days. The top of masonry

shall be left flooded with water at close of the day. Care shall be taken

not to disturb or wash out green mortar.

In case of stone work in lime mortar, curing shall commence two days

after laying of masonry and shall continue for the next seven days.

5.0 TYPES OF STONE MASONRY

5.1.1 Uncoursed / Random Rubble Masonry

Masonry constructed by selecting stones from quarry, more or less at

random, of all sizes and shapes. Cutting of stones restricted to remove

inconvenient corners with scabbling or spelling hammer.

Page 26: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.380 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

5.1.2 Construction

1. Individual stones shall have thickness and width of not less than

150 mm and length not less than 1.5 times its height. Stones

shall be dressed with a mason's hammer by knocking off weak

corners and edges.

Face stone shall be so dressed that bushing on the exposed face

shall not project by more than 40 mm from the general wall

surface. In case plastering is to be done, projection shall be

limited to 19 mm and depression to 10 mm.

50% stone shall be 0.010 cu m (10 litres) in walls upto 500 mm.

Walls thicker than 500 mm shall have 50% stone bigger than

0.015 cu m (15 litres).

2. Bond or through stones shall be 2 pieces (nos.) per sq m, face

area shall be 0.03 sq m and for full width of masonry for walls

upto 600 mm stones shall be marked distinctly.

3. For massive work with a width of a metre and above, vertical

headers 450 mm long or with a depth of two courses whichever

is more shall be provided at the rate of one for every sq m of area

in the plan.

4. Quoins (corners) shall be dressed square to the face and rough

tooled to 100 mm from face, and vertical joints dressed to 40

mm from face. No quoins shall be smaller than 0.025 cu m in

volume and they shall also not be less than 300 mm in length,

25% of them being not less than 500 mm in length.

5. Hearting stone shall not be less than 150 mm in any direction. In

walls upto 500 mm a minimum of 30% stone shall be 0.010 cu m

(10 litres). For thicker walls minimum 30% stone shall be 0.015

cu m (15 litres).

6. The jambs shall be made with stones specified for quoins except

that stones provided on the jambs shall have their length equal to

Page 27: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.381 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

the thickness of the wall. For walls upto 600 mm, a line of

headers shall be provided as specified for bond.

7. A plum stone at about 900 mm intervals shall be provided.

8. Stones shall be laid with or without courses as specified. Quoins

shall be laid header and stretcher alternatively. Laying shall be

carefully done to form neat and close joints. Face stone shall

extend and bond well in the back. These shall be arranged to

break joints.

5.2 Coursed Masonry

Course walling shall be built in courses which may vary in height from

150 mm to 400mm but the stones in any one course shall roughly be

square and of the same height.

5.2.1 Construction

1. Stones received from quarry shall be dressed to have the vertical

and horizontal sides perfectly straight, parallel and at right

angles to adjacent sides. Bushing on the face shall not project

more than 40 mm. Beds and tops shall be tooled at least 100 mm

from the face. Faces of vertical joints shall be square to the face

and rough tooled at least 50 mm from the face.

2. Stones shall be longer in breadth than in height and shall run

back into the masonry not less than 1.5 times the height. 30% of

the stones shall have tailing twice their height. Further 30% of

these face stones shall not be less than 0.02 cu m or 20 litres.

The height shall not be less than 150 mm or as specified in the

pattern in the drawing.

3. Hearting stones shall consist of flat bedded stones, carefully laid

on their proper beds in mortar, chips and spells of stone,

avoiding excess use of mortar and hollow spaces in masonry.

These shall be limited to 10% in the first sort and 15% in the

second sort. 30% of the stones shall not be less than 0.010 cu m

Page 28: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.382 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

or 10 litres for walls 500 mm or less in thickness. For walls

thicker than 500 mm, 30% of them shall not be less than 0.015

cu m or 15 litres.

4. Quoins (corner) stones shall be twice their height or minimum

440 mm long whichever is more and shall be of the same height

as that of the course. They shall be laid alternately as stretcher

and header.

5. Through stones shall be a minimum 450 mm long and shall be

180 mm centre to centre for every course. They shall be about

0.05 sq m in face area and 0.03 sq m in average cross sectional

area. For thicker walls (above 600 mm) they shall over-lap by at

least 150 mm.

6. Thickness of joint shall be maximum 10 mm. When pointing is

to be done, joints shall be raked to a depth of not less than 10

mm while the mortar is green.

6.0 ITEM INCLUDES

6.1 The various items shall include the cost of the followings, irrespective

of whether it is stated in the BOQ or not.

a) Material and labour for proper execution as per specification

and site requirement including temporary erections like

scaffolding, centering, shuttering and removal of the same.

Curing and protection shall also be included as directed.

b) Racking out of joints and cleaning of stone surfaces.

c) Preparing tops and sides of existing walls.

d) Bond stones.

e) Making grooves and rebates in the adjoining work for fixing jali.

f) Extra labour involved in dressing of corner stones and jamb-

stones wherever required.

Page 29: PARTICULAR SPECIFICATIONS MASONRY WORK – BRICK WORK …cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/TND... · MASONRY WORK – BRICK WORK (For Building & Area Development

CIDCO OF MAHARASHTRA LIMITED Sl.Pg.No.383 C.A.NO.10/CIDCO/SE(ULWE)/EE(B&U-I)/2010-11

g) Making holes, openings, outlets, etc. embedding pipes, ends of

beams, joists, slabs, trusses, sills, etc. whatever required during

construction and neatly finishing the exposed surfaces and

opening as per instructions of the Engineer.

* * * * *