Parsons Slough Project, Elkhorn Slough,CA
Moving the crane barge into position at the start of the project
Preparation on the RR tie-in at the southern end of the sill
Completion of the RR tie-in at the southern end of the sill
Work on the RR tie-in at the northern end of the sill, includinginstallation of sheet pile with the vibratory hammer
Installation of sheet pile across Parsons channel with the vibratory hammer
Surveying the sill across the channel before dropping the sheets to grade
Installation of the H pileswith the impact hammer
Placing the rock ramp
The marine mammal monitoring post on the west side of the sill