PARS Activation Readiness Maintenance Mid-Florida P&DC. 237. Participate in Site Survey for CFPS/CFS. 238. Clear space for Scanner Installation for CFPS. CFS NE corner prepped and wired for new Scanner, OSW, and KFP workstation. - PowerPoint PPT Presentation

Transcript of PARS Activation Readiness Maintenance Mid-Florida P&DC

Page 1: PARS  Activation Readiness Maintenance Mid-Florida P&DC

PARS Activation Readiness

Maintenance

Mid-Florida P&DC

Page 2: PARS  Activation Readiness Maintenance Mid-Florida P&DC

237. Participate in Site Survey for CFPS/CFS

Page 3: PARS  Activation Readiness Maintenance Mid-Florida P&DC

238. Clear space for Scanner Installation for CFPS

CFS NE corner prepped and wired for new Scanner, OSW, and KFP workstation.

Page 4: PARS  Activation Readiness Maintenance Mid-Florida P&DC

239. Make required changes at CFPS site:

* Electrical Power - Relocate & moveequipment as needed for timelines. Wire for CIOSS #1 & #2* Mechanical - Base line equipment* Telecommunications. - MPI wiring,new FCS & Firewall

Page 5: PARS  Activation Readiness Maintenance Mid-Florida P&DC
Page 6: PARS  Activation Readiness Maintenance Mid-Florida P&DC
Page 7: PARS  Activation Readiness Maintenance Mid-Florida P&DC

*

240. Participate in Site Survey for P&DC

Page 8: PARS  Activation Readiness Maintenance Mid-Florida P&DC

246. Develop plan for:Installation/Modification of electricaland mechanical in P&DC

- CIOSS Power requirements

- CIOSS Communication drops

- Baseline MPE

Page 9: PARS  Activation Readiness Maintenance Mid-Florida P&DC

MP workroom Site Prep for CIOSS

Page 10: PARS  Activation Readiness Maintenance Mid-Florida P&DC

242. Identify and Schedule target group of employees for specific Maint. - Training

Trained ScheduledDBCS 12 3DBCS/EC 3 5DBCS/DIOSS 6 3CIOSS - F.A.T.A+ Comp. Fund. 2 3Network + 1 1 ?MPI Wiring 5 (on-site)

Page 11: PARS  Activation Readiness Maintenance Mid-Florida P&DC

243. Determine Site Prep Funding Requiredfor P&DC

- all FAT team items submitted & approved by HQ Finance for allocation of funds for CFD Admin Service procurements

#PERSONNEL; FLOOR AREA / ROOM COMPLETION DATE:FAT SUPPORT ITEM S TO BE OBTAINED BY SITE:

ELECTRICAL SHOP OUTLETELECTRICAL WALL OUTLETSPOWER STRIPSPARTITION WALL (4' HIGH; U-SHAPE)DOOR W/ LOCKKEYS - # INDIVIDUALKEYS - # SETS (ALL ROOMS)AREA / DOOR SIGNAGE (E.G., USPS TEST TEAM)30" X 60" TABLESTACKING CHAIRARM CHAIRCOMPUTER CHAIRDESKCOMPUTERS - VERIFICATION (FROM HQ ENGRG)MNS (BLDG) LAN ACCESS PHONE LINE - T1 (TEMP; SIEMENS PAY)PHONE LINE - VOICE (local w/ toll free access only unless spec.)PHONE LINE - ANALOGFAX MACHINE (DESK TOP)COPIER - HEAVY DUTY FLOOR MODEL; FASTCOPIER - MEDIUM DUTY DESK TOPTONERS FOR HEAVY DUTY COPIERTONERS FOR DESK TOP COPIERPAPER (COPIER; LASER PRINTER)MISCELLANEOUS DESK SUPPLIESWHITEBOARD - WALL MOUNTEDWHITEBOARD MARKERS/ERASERS - # SETSSMALL B/W DESK TOP LASER PRINTERTONERS FOR B/W DESK TOP LASER PRINTER4-DRAWER LOCKING CABINET W/ KEYS8-DRAWER LOCKING CABINET W/ KEYSLOCKING STORAGE CABINET W/ KEYSCOAT RACKS (IF SEASON REQUIRES)LARGE WASTEBASKETSMALL WASTEBASKETCOFFEEMAKER W/ AUTO LIGHT (& SUPPLIES)VISITOR LOG BOOK RADIO/BATTERY BACKUP (COMMUNICATIONS)

Page 12: PARS  Activation Readiness Maintenance Mid-Florida P&DC

- HQ QA- Verif. Rm- Del. Ops- Siemens- Siemens- Visitors

PARS FAT Verification Items

Page 13: PARS  Activation Readiness Maintenance Mid-Florida P&DC

243. Determine Site Prep Funding Required for P&DC

-Additional P&DC site prep funding requested for:

- Maintenance prep workhours2,542 hours

- Power and Communication drops- Materials for equipment moves

$21,300

Page 14: PARS  Activation Readiness Maintenance Mid-Florida P&DC

248. Send Site Prep Docs to Acq. Mgmt forApproval.

Page 15: PARS  Activation Readiness Maintenance Mid-Florida P&DC

245. Place order for spare parts cabinets, if required.

- Order stockroom cabinets as needed

- Remote hot spares cabinet in CFS

Page 16: PARS  Activation Readiness Maintenance Mid-Florida P&DC

247. Prepare / Update Maintenance StaffingPlan.

-Change positions for PM window and tour.

-Post ET job: 0500-1350 N/S: Sat/Fri

-Will Complete Daily & Senior PM windows

Page 17: PARS  Activation Readiness Maintenance Mid-Florida P&DC

249. Develop an SOP for updating PARSsoftware / In MOS Cabinets.

-All PARS software and directory updates will be setup in VMARS for Daily, Weekly, and Monthly routes.

-Will follow RBCS procedures.

-Assigned to T-2 ET positions.

-Software will be stored in the Maintenance software cabinet and at the VMF according to the Crisis Management Plan.

Page 18: PARS  Activation Readiness Maintenance Mid-Florida P&DC

Directory Updates Local Updates From Plant’s RIC

• Generated From CFPS Scanning of COA Cards

• P&DC CARS Systems Only Daily Updates From NCSC (Electronically)

• All Local COA Updates Bundled Together

• Updates on Universal Mailer File (UMF)

• Directories

• Bitmap Exclusion Table Weekly Updates (DVD From NCSC) by an ET

• National Change of Addresses

• Directories

Page 19: PARS  Activation Readiness Maintenance Mid-Florida P&DC

251. Develop a Process and Schedule for performing weekly PARS databaseupdates.

- During Daily PM window, 5:00 - 9:00

- Senior PM Routes will be Sunday CIOSS#1 and Monday CIOSS#2

Page 20: PARS  Activation Readiness Maintenance Mid-Florida P&DC

250. Develop an Escalation procedure forCFPS Scanner Mechanical / Electricalfailures.

-Call contractor Bell & Howell

-24hr Warranty contract

* OSW scanner requires optics cleaning

Page 21: PARS  Activation Readiness Maintenance Mid-Florida P&DC

252. Identify any Article 32 issues and workwith Labor Relations to resolve.

-NONE

-All MPE moves and Power/Comm drop nearly completed.

Page 22: PARS  Activation Readiness Maintenance Mid-Florida P&DC

253. Coordinate maintenance schedules withnew Processing Operations Operating Plan.

-New ET Bid. BT: 0500-0150

-N/S: Sat/Fri

- CFS FFTs available: 01:00 - 12:30

Page 23: PARS  Activation Readiness Maintenance Mid-Florida P&DC

254. Contractor finalizes asbestos disposalplans/activities with DistrictEnvironmental compliance Coordinatorand appropriate local landfill authorities,etc., as required by local, state, and ornational codes.

- NONE

Page 24: PARS  Activation Readiness Maintenance Mid-Florida P&DC

255. Establish Stock-Rotation / climitizationplan for CIOSS labels.

-Will Follow existing procedure currently in place for CFS FFT labels

Page 25: PARS  Activation Readiness Maintenance Mid-Florida P&DC

256. Develop SOP for Waste Mail.

-Follow existing procedure currently in place with Custodial workforce.

-Waste volumes still generated within CFS workroom

-Waste containers staged in CFS/CIOSS verification area

Page 26: PARS  Activation Readiness Maintenance Mid-Florida P&DC

259. Train Custodial workforce on newWaste Mail Procedures.

- Completed as part of FAT operations

(from CFS & CIOSS waste verification workarea)

Page 27: PARS  Activation Readiness Maintenance Mid-Florida P&DC

257. Clear space in P&DC for equipmentdelivery and modification.

-Complete and Ready for CIOSS Modification

[ Ray Oakley ]

Page 28: PARS  Activation Readiness Maintenance Mid-Florida P&DC
Page 29: PARS  Activation Readiness Maintenance Mid-Florida P&DC

DBCS #11, ready for the CIOSS modification

Workroom floor ready for 25’ addition

Page 30: PARS  Activation Readiness Maintenance Mid-Florida P&DC

258. Receive install Team Tool Kits, signreceipt for them upon delivery, and place them in a secured maintenancearea around PARS equipment location.

- East end of CIOSS machine

Page 31: PARS  Activation Readiness Maintenance Mid-Florida P&DC

Mail Processing Equipment modifications for PARS processing:

AFC = Replace hardware STP with PC software STP- start Friday, Aug 22nd @ 06:00 (4)

OCR = New computer software STP- start Saturday, Aug 23rd @ 06:00 (3)

DBCS = Replace PC, monitor, cards and firmware- start Wednesday, Aug 20th, 07:00 (15)

MPBCS = New software loaded- start Tuesday, Aug 19th @ 07:00 (6)

Final Modification completed on Sept 6th for last DBCS (#12)

Page 32: PARS  Activation Readiness Maintenance Mid-Florida P&DC

New CIOSS LAM Module Two High Speed Label Applicators (HSLA) One Label Verifier Two Vacuum Turbine Units One Doubles Detector (DD) One Other Side Reader (OSR) One Change Of Address Scitex Ink Jet

Printer (COA IJP)

Page 33: PARS  Activation Readiness Maintenance Mid-Florida P&DC

High Speed Label Applicators Two HLSA Per CIOSS Speed of Three Meters

Per Second Each HLSA Can Produce

15,000 Labels Per Hour Provides Status

• Almost Empty Indicator• Empty Status Indicator

Page 34: PARS  Activation Readiness Maintenance Mid-Florida P&DC

Scitex Ink Jet Printer

Prints Up To Seven Lines of Information Process 30,000 PPH Expensive Ink Cartridge Limited Life Span

Page 35: PARS  Activation Readiness Maintenance Mid-Florida P&DC

PARS MAJOR COMPONENTS

Redirection Image Controller (RIC) Advanced Forwarding Reader (AFR) Change of Address Record Server (CARS) Forwarding Storage Unit (FSU) Change of Address Forms Processing System

(CFPS) Change of Address Reporting System (COARS) PARS Video Coding Desks (VCD)

Page 36: PARS  Activation Readiness Maintenance Mid-Florida P&DC

PARS MAJOR COMPONENTS

Page 37: PARS  Activation Readiness Maintenance Mid-Florida P&DC

260. Provide or confirm the TransmissionControl Protocol/Internet Protocol(TCP/IP) address for PARS equipmentto the contractor install team (unlessprovided at Site Survey)

* completed* MPI wiring* Firewall installation

Page 38: PARS  Activation Readiness Maintenance Mid-Florida P&DC

261. Update VMARS to reflect changes due to PARS.

-Develop routes for CIOSS.

-Input Spare Parts into VMARS.

Page 39: PARS  Activation Readiness Maintenance Mid-Florida P&DC

264. Complete inventory of spares kits andadvise Site Coordinator of status.

265. Inform contractor of any missing spares parts.