Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur...

download Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

of 39

Transcript of Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur...

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    1/39

    car

    Plan 446: Transportation Planning Studio

    Parking Demand & Supply Analysis of Different Commercial

    Land Uses along Mirpur Road

    Submitted by:

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    2/39

    Parking Demand & Supply Analysis of Different

    Commercial Land Uses along Mirpur Road

    Course No: Plan 446

    Course Title: Transportation Planning Studio

    Submitted to:

    Suman Kumar Mitra, Assistant Professor, Dept. of URP

    Rezwana Rafiq, Lecturer, Dept. of URP

    Submitted by: Shancharpath

    Rifat Rahman (0615005)Nabila Nur Kuhu (0615009)

    Shahadat Hossain Shakil (0615020)

    Khaled Bin Abdul Quadir (0615030)

    Level-4, Term-1

    Date of Submission: 29th

    May, 2011

    Department of Urban and Regional Planning

    Bangladesh University of Engineering and Technology

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    3/39

    ii

    Acknowledgement

    The inspiration and help of the surrounding people and teachers is very much needed to complete

    a good report. First of all, thanks to the merciful and benevolent creator to give us patience,

    energy and capability to work hard for completing the report.

    We wish to express our earnest gratitude to our respectable course teachers Suman Kumar

    Mitra, Assistant Professor and Rezwana Rafiq, Lecturer, Department of Urban and Regional

    Planning, BUET for their intimate co-operation and support, valuable advice, comment, constant

    encouragement and supervision which have helped us to carry out this study successfully.

    We would not forget thanking the authority of Dhanmondi Plaza and Mamtaz Plaza along

    Mirpur Road for their cordial support.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    4/39

    iii

    Abstract

    Parking this term is one of the most important topics of discussion in the developing cities. Inthe cities like Dhaka where unplanned urbanization prevails in a greater extent; parking problem

    is the most common scenario there. In the developing countries cities are growing without

    considering the inherent increasing parking demand. Mirpur road is one of the most problematic

    roads of Dhaka city in context of parking problem. To assess the current scenario of the

    problems and to formulate some policy measures is the main focus of this study. In this study

    some major parking generators along Mirpur has been surveyed and their parking demand-

    supply situation has been analyzed. Considering the Parking Policy for the Dhaka Metropolitan

    Development Plan Area, 2002 and the results from the analysis some policy measures has been

    formulated to manage the parking demand more efficiently.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    5/39

    iv

    Table of Contents

    Contents Page NoTitle Page i

    Acknowledgement ii

    Abstract iii

    Table of Contents iv

    Lists of Illustration vi

    Chapter 01: Introduction (Page 1-4)

    1.1

    Background of the Study 1

    1.2

    Objectives`

    1

    1.3 Methodology 2

    1.4 Study Area Profile 4

    1.5 Scope of the Study 4

    1.6 Limitation of the Study 4

    Chapter 02: Conceptual Definition and Literature Review (Page 5-9)

    2.1 Parking Terms 5

    2.2 Parking Demand and Supply 6

    2.3 Prior Study of Parking Demand and Supply 7

    2.4 Parking Policy of Bangladesh 8

    Chapter 03: Analysis of Demand and Supply (Page 10-20)

    3.1 Dhanmondi Plaza 10

    3.1.1 Supply Scenario 10

    3.1.2 Demand Scenario 12

    3.2 Mamtaz Plaza 14

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    6/39

    v

    3.2.1 Supply Scenario 14

    3.2.2 Demand Scenario 18

    Chapter 04: Findings and Recommendations (Page 21-23)

    4.1 Dhanmondi Plaza 21

    4.2 Mamtaz Plaza 22

    4.3 Conclusion 23

    References

    Appendices (Page I-VIII)

    A-1. Dhanmondi Plaza On Street-Survey Data I

    A-2. Dhanmondi Plaza: On-Street-Parking Terms Calculation II

    A-3. Mamtaz Plaza On Street-Survey Data IV

    A-4. Mamtaz Plaza Off Street-Survey Data V

    A-5. Mamtaz Plaza: On-Street Parking and Off-Street Parking

    (Combined Calculation of Parking Terms)

    VII

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    7/39

    vi

    List of Illustration

    List of Figures Page No

    Figure-1: Methodology 3

    Figure-2: On-Street Parking Provision (Dhanmondi Plaza) 10

    Figure-3: Encroachment of Footpath (Dhanmondi Plaza) 10

    Figure - 4: Dhanmondi Plaza On-Street Parking Layout 11

    Figure-5: Parking Accumulation Curve of On-Street Parking (Dhanmondi Plaza) 12

    Figure-6: Vehicle-Hours of Occupation (Dhanmondi Plaza) 13

    Figure-7: Eastern Side On-Street Parking (Mamtaz Plaza) 14

    Figure-8: Northern Side On-Street Parking (Mamtaz Plaza) 14

    Figure - 9 : Mamtaz Plaza On-Street Parking Layout 15

    Figure-10: Off-Street Parking Provision-Entrance Ramp (Mamtaz Plaza) 16

    Figure-11: Off-Street Parking Provision -Driveway (Mamtaz Plaza) 16

    Figure-12: Off-Street Parking Provision -Parking Bays (Mamtaz Plaza) 16

    Figure-13: Off-Street Parking Provision -Restricted Parking Bays (Mamtaz Plaza) 16

    Figure - 14 : Mamtaz Plaza Off-Street Parking Layout 17

    Figure-15: Combined Parking Accumulation Curve (Mamtaz Plaza) 18

    Figure-16: On-Street Vehicle-Hours of Occupation (Mamtaz Plaza) 20

    Figure-17: Off-Street Vehicle-Hours of Occupation (Mamtaz Plaza) 20

    List of Tables Page No

    Table-1: Information about the Selected Parking Generators 4

    Table-2: Vehicle-Hours of Occupation (Dhanmondi Plaza) 13

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    8/39

    Chapter 01: Introduction

    1.1 Background of the Study

    Transportation is one of the most discussed issues for Dhaka city now-a-days. Due to lack of

    proper transport planning, lives of city dwellers have become really hard. A very significant

    part of transportation planning is parking. People have become habituated to park of cars just

    on the road for a long time which eventually degrades the efficiency of the road.

    Mirpur road is one of the most busiest and important roads in Dhaka city which generates a

    huge number of traffics. Commercial buildings can be treated to be mostly responsible for

    this traffic generation. This study aims at analyzing the demand and supply situation ofdifferent commercial land uses along Mirpur road. This will provide an overview on the

    actual parking scenario along Mirpur road.

    1.2 Objectives

    To analyze present parking demand and supply situation of different commercial

    land uses along Mirpur Road. To formulate some recommendations for the improvements of present parking

    situation.

    1.3 Methodology

    Project Identification and Selection of Study Area

    The second project under this course aims to study about parking. Considering that the course

    teachers identified Parking Demand Supply Analysis of Different Commercial Land Uses

    as the project title. Mirpur road has been selected as the potential study area for this project.

    Objective Formulation

    Relevant objectives of the study have been formulated by taking the scopes and limitations

    into account.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    9/39

    2

    Literature Review

    Related journals, reports and prior studies in abroad have been explored to get a clear

    concept about the parking demand supply analysis. The relevant parking terms have been

    identified and studied for the further analysis of the study.

    Reconnaissance Survey and Selection of Parking Generators

    The potential commercial buildings in context of parking generation have been identified

    along Mirpur road through group wise reconnaissance survey. Among the potential

    parking generator, 14 commercial buildings have been selected for this study by the

    course teachers. The selection has been done by keeping the type of parking provisions

    and their relative geographical location in mind. After selecting 14 buildings, each group

    have been provided 2 commercial buildings on the basis on lottery among the groups.

    Parking Inventory Survey

    Parking Inventory Survey has been done by each group at their own study buildings. Data

    about the width of road, width of footpath, length of curb, type of parking provisions (on-

    street or off-street or both), parking supply (no. of lots provided), parking signs, parking

    pattern (existing layout) etc. have been done in this step.

    Parking Usage Survey by Patrol

    The parking Usage Survey has been the most important survey for this study. Three time

    frames have been selected for this survey: 11.00 AM -1.00 PM, 3.00 PM-5.00 PM and

    6.00 PM 7.00 PM. The survey has been done with 15 minutes interval. At a particular

    time, a surveyor recorded the registration number of the cars parking in the study

    buildings by going from one side to other side of the parking area. After 15 minutes

    interval, the surveyor again recorded the registration number and this time starting from

    the previous end point. The survey ended after completing the procedure stated above for

    20 times (four times per hour and total survey period was five hours). The survey has

    been done both at Dhanmondi Plaza and Momtaz Plaza and both for on-street and off-

    street parking provision.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    10/39

    3

    Demand Supply Analysis

    The calculation about Parking Volume, Parking Accumulation, Parking Load, Parking

    Duration, Parking Index, Parking Turn-over etc. have been done with the collected data.

    The demand and supply scenario have been analyzed from these terms.

    Findings

    From the analysis, the scenario in both of the study buildings has been identified whether

    there is parking deficit or parking surplus in those buildings.

    Recommendation

    Policy measures and required parking spaces have been recommended for the buildings

    by keeping the result in mind. Change in existing charge for off-street parking and

    imposition of deterrent charge for on-street parking has been recommended for

    improving the parking condition.

    Preparation of Final Report

    After combining all the procedures stated above, the final report has been prepared.

    Project Identification and Selection of Study Area

    Objective Formulation

    Literature Review

    Reconnaissance Survey and Selection of Study Parking Generators

    Parking Inventory Survey

    Parking Usage Survey by Patrol

    Demand-Supply Analysis

    Findings

    Recommendations

    Preparation of Final Report

    Figure-1: Schematic diagram of methodology

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    11/39

    4

    1.4 Study Area Profile

    Mirpur road plays a vital role in transportation network of Dhaka city. Its length is 8.05

    km from Azimpur to Gabtoli. In this project the study area was taken from Azimpur to

    Mirpur Technical which is around7.4km long.

    Selected Parking Generators

    The parking generator selected for this group was Mamtaz Plaza and Dhanmondi Plaza.

    Both of them are commercial buildings. Mamtaz plaza is situated nearby the science

    laboratory intersection and Dhanmondi plaza is situated opposite to Ganoshastho Nagar

    Hospital .The detail of these two buildings has been given below.

    Table-1: Information about the Selected Parking Generators

    Name Address Land use Storey Frontage

    (feet)

    Total floor area

    (Sq. ft.)

    Designated

    Parking Area

    Dhanmondi Plaza H18, R6 Commercial 5 153.7 54505.85 sq. ft -Nil-

    Momtaj Plaza H7, R4 Commercial 6 154.5 78304.83 sq.ft. 13050.80 sq.ft.

    1.5 Scope of the Study

    This study tends to find out the parking demand and supply scenario. Researchers,

    Planners, Policy Makers will get an idea about the parking situation along with one of the

    most important roads of Dhaka city, Mirpur road. As illegal parking severely affects the

    road efficiency, the study will also be help for transport engineers. It will can be an

    overview for taking decisions about implementing charge for on-street parking,

    prohibition of on-street parking, co-coordinating between the demand and surplus supply

    thus total parking management.

    1.6 Limitation of the Study

    The parking usage survey by patrol was done for only one day which can bring biased

    result due to weather condition or type of the day (working or holiday). Very small

    sample size used can bring possibility of large margin of error.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    12/39

    Chapter 02: Conceptual Definition and Literature Review

    2.1 Parking Terms

    To analyze the existing parking demand and supply condition and to formulate

    recommendation for the improvement, some terms are very important to be studied.

    Parking Volume

    Parking volume is the total number of vehicles parked at a given duration of time. This does

    not account for repetition of vehicles. The individual vehicle entered in the area is recorded.

    Parking Accumulation

    It is defined as the number of vehicles parked at a given instant of time. Normally this is

    expressed by accumulation curve. Accumulation curve is the graph obtained by plotting the

    number of bays occupied with respect to time.

    Parking Load

    Parking load gives the area under the accumulation curve. It can also be obtained by simply

    multiplying the number of vehicles occupying the parking area at each time interval with the

    time interval. It is expressed as vehicle hours.

    Parking IndexParking index is also called occupancy or efficiency. It is defined as the ratio of number of

    bays occupied in time duration to the total space available. It gives an aggregate measure of

    how effectively the parking space is utilized. Parking index can be found out as follows:

    Average Parking Duration

    It is the ratio of total vehicle hours to the number of vehicles parked.

    Parking Turnover

    It is the ratio of number of vehicles parked in duration to the number of parking bays

    available. This can be expressed as number of vehicles per bay per time duration.

    Parking Spillover

    It is the difference between the parking demand and the available parking supply in any

    certain period of time. Its value indicates no. of parking deficit in that time period.(Rao & Mathew, 2007)

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    13/39

    6

    2.2 Parking Demand and Supply

    Parking Demand

    It refers to the amount of parking that would be used at a particular time, place and price. It is

    a critical factor in evaluating parking problems and solutions. Parking demand is affected by

    vehicle ownership, trip rates, mode split, duration (how long motorists park), geographic

    location (i.e., downtown, regional town centre or suburban), the quality of travel alternatives,

    type of trip (work, shopping, recreational), and factors such as fuel and road pricing.

    There are usually daily, weekly and annual demand cycles. For example, parking demand

    usually peaks on weekdays at office buildings and on weekend evenings at theaters and

    restaurants. Parking demand can change with transportation, land use and demographic

    patterns. For example, a particular building may change from industrial to residential or

    office use, neighborhood demographics and density may change, and the quality of transit

    service may change, all of which affects parking demand.

    Different types of trips have different types of parking demand, and different types of parking

    facilities tend to serve different types of trips. For example, commuters need long-term

    parking, and because they park all day they are relatively price sensitive. Many commutersare willing to walk several blocks for cheaper parking. Off-street parking leased by the month

    tends to serve commuters. Customers need shorter-term parking that is located as close as

    possible to their destination, and are often willing to pay a relatively high hourly price for

    increased convenience. On-street parking that is metered or regulated to maximize turnover

    tends to serve customers (Victoria Transport Policy Institute, 2011).

    Parking Supply

    It refers to availability of parking space. Parking is a major urban land use. Availability of

    parking (parking supply) usually depends in large measure on intensity of development and

    cost of land. It may be governed by building codes or ordinances, and it may be controlled to

    achieve some strategic economic or policy purpose.

    The adjustment of parking supply outside the normal processes of the private marketplace to

    achieve strategic objectives is often referred to as parking management. Management of

    parking supply is a balancing act. If too much parking is provided in surface lots, it uses

    valuable land resources and often results in widely-spaced and disconnected development

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    14/39

    7

    patterns. Too little parking or poorly designed or located parking can result in parking

    spillover to adjacent areas, lead travelers to choose alternate destinations, and/or inhibit

    development (Transport Research Board, 2003).

    2.3 Prior Study of Parking Demand and Supply

    Downtown Huntington Parking Study

    The study has been carried out at the CBD area of the Town of Huntington. The objective of

    this study was to provide details on the efficiency of existing parking facilities and determine

    the need for revising the existing parking supply. To gather information on existing parking

    supply and its use, parking inventories have been done. Accumulation (or occupancy) checks

    and license plate checks are the two types of usage studies used in this study. A total of 124

    parking spaces were identified in the downtown area. The parking survey was performed for

    one day. The study started at 7.00 AM and was performed every half hour until 8.00 PM. The

    number of occupied parking spaces was recorded at the beginning of each interval. In

    addition, parking turnover information was collected by recording the last three license plate

    characters. From the survey result, the parking in downtown Huntington did not seem overly

    problematic. Most streets and lots did not reach their full capacity at any time during the day.

    In addition, many of these areas could withstand a much higher volume of automobiles.

    (Pioneer Valley Metropolitan Planning Organization, 2006)

    Case Study on Supply and Demand for University Parking Facilities in

    College of Engineering UNITEN

    This study was carried out at the main campus of Universiti Tenaga Nasional (UNITEN). The

    objectives were to identify the current parking supply and next five years parking demand in

    the university area and gave suggestions or recommendations to solving the problem. The

    study consist parking inventory, parking usage survey using license

    Plate numbers method and parking interview for determination the current parking supply.

    From the result of current data, the next five years future parking demand had been estimated

    by study and information from the administration data, questionnaire, and parking space

    zoning regulation and parking generation. This study did not find any problem except with

    one lot which was totally opposite of what the students of the university claimed. For future

    parking demand 1540 parking spaces should be provided in five years time. As

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    15/39

    8

    recommendation, besides built a new parking area, which is more costly, law enforcement

    must done strictly to restrict the non-sticker userspark at the university parking.

    (Ismail & Norhisham, 2008)

    2.4 Parking Policy of Bangladesh

    In order to reduce congestion and improve the traffic movement within the DMDPA, the

    DTCB has taken the initiative to outline strategies to reduce the negative effects of parking.

    This is to be achieved by formulating a parking policy. First draft of this policy was prepared

    by DTCB in February 2002 and was reviewed by the World Bank. Based on their

    suggestions, the policy document was revised with the assistance of a specialist and was

    circulated among concerned agencies in mid October 2002. The basic policy sectors were:Jurisdiction, Demand for Parking Spaces, Supply of Parking Spaces, Parking Regulation,

    Enforcement of Regulations, Operation and Maintenance, Institutional Setup and

    Strengthening Supportive Legislation. Some related issues regarding demand for parking

    spaces were: spatial growth trends within DMDPA, work centers, spatial development

    policies for Dhaka, increasingvehicle ownership, heteroginity of vehicles etc.there were also

    issues discussed regarding parking supply. Those were: supply of off-street parking spaces,

    parking standards, supply of on-street parking spaces, slow augmentation of road capacity,

    parking for non-motorized vehicles etc (DTCB, 2005).

    The relevant and selected segment of parking policy which is duly considered during forming

    recommendations is provided below

    Policies on Managing Parking Demand

    1.Non-restrictive parking shall be adopted in residential areas where the demand for parking

    is much less than the available of parking spaces.

    2. Restrictive parking shall be adopted in areas where the demand exceeds the available

    parking spaces. These shall be enforced through pricing and regulatory mechanisms.

    3.Two types of parking charges shall be levied at public parking places in the restrictive

    parking areas. Normal charges aimed to recover of operation and maintenance expenses,

    shall be levied in locations where the parking provision does not adversely affect the

    movement of traffic. Deterrent parking charges shall be more than the normal charges and

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    16/39

    9

    shall be adopted in areas where parking demand is in excess of supply or in places where

    parking is observed to adversely affect the movement of traffic.

    4.Regulations shall include parking restrictions to specific or all types of vehicles either by

    time of day or by duration or for specific purpose of travel or for vehicles carrying less than

    specified number of passengers per vehicle or by location.

    Policies on Supply of Parking Spaces

    5.Parking standards shall be reviewed once every five years. Necessary modifications shall

    be incorporated in the building rules.

    6. There shall be regular monitoring of parking provisions in all buildings. Buildings found to

    be deficient in parking provisions vis--vis current building rules shall be required to pay a

    parking facility fees. This shall be in proportion to the extent of violation with respect to the

    required provision. The revenue from this source shall be used for augmenting parking

    facilities (on-street / off-street) in the area.

    Policies on Operation and Maintenance of Parking Facilities

    7. Concerned local authorities shall be responsible for the efficient operation and

    maintenance of public parking facilities.

    Policies on Parking Regulation

    8. In restrictive parking areas, on-street parking shall be prohibited on all roads within the

    area except at places where it is specifically permitted by authorized road signs and markings.

    Policies on Enforcement of Regulations

    9.The Local Police shall be responsible for enforcing parking regulations as notified by the

    Police Chief.

    10. They shall assign adequate number of police personnel of appropriate rank for

    surveillance and enforcement of parking regulations in each zone. Each zone shall have a

    tow truck to facilitate eviction of offending vehicles.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    17/39

    Chapter 03: Analysis of Demand and Supply

    In this chapter demand and supply scenario of the two selected parking generator along

    Mirpur road has been portrayed. Each generator has been analyzed separately according to

    on-street and off-street parking supply and demand. The parking characteristics of these two

    generators along Mirpur road have been figured out through various parking terms.

    3.1 Dhanmondi Plaza

    Dhanmondi plaza is a medium scale commercial complex. Parking pressure of this generator

    is moderate. Majority of its parking demand is from the ground floor retail shops.

    3.1.1 Supply Scenario

    There is no designated off-street parking provision for Dhanmondi plaza. Vehicles are parked

    in the designated spaces just in front of the market. Vehicles are parked on the Footpath and

    Concrete Slab (property boundary) together because their altitude is same as the road surface.

    Though these on street parking spaces are approved by the market authority but its illegal;

    because of encroachment public facilities (footpath). Vehicles are parked in an angular

    arrangement (300- 450) in one layer or row. Total 12 vehicles can be parked at a time. There

    is no parking charge and parking regulatory sign.

    Existing on-street parking provision is explained below with the help of the figures.

    Figure-2: On-Street Parking Provision

    (Dhanmondi Plaza)

    Figure-3: Encroachment of Footpath

    (Dhanmondi Plaza)

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    18/39

    12

    3.1.2 Demand Scenario

    Parking usage survey by patrol for on-street parking has been conducted for five hour. Survey

    data and calculation is shown in Appendix (Page I- Page III). The demand for parking has

    been explained through various parking terms in the following section.

    Parking Volume

    Total parking volume over a period of five hour is 78 vehicles. That means total 78 individual

    vehicles has been experienced during the survey period. So per hourly average volume of

    vehicular parking are 15.6; which means on an average in every hour 15.6 new vehicles come

    into this market.

    Parking Accumulation

    Parking accumulation curve gives the information that parking demand is in peak position

    during the time period 12:00 AM 1:00 PM and 6:00 PM 7:00 PM. Average

    accumulation of parking is 8.5 vehicles per 15 minutes; which means in every 15 minutes 8.5

    vehicles are expected to present as the parking demand. (Parking Accumulation Table:

    Appendix - Page II)

    Figure-5:Parking Accumulation Curve of On-Street Parking (Dhanmondi Plaza)

    Parking Index and Spillover

    Provision of the on-street parking supply is illegal but its efficiency has been calculated to

    know whether the present provision is sufficient or not. Average parking index is 70.83. It

    means 70.83% capacity is being utilized. (Parking Index and Spillover Table: Appendix -

    Page III)

    0

    5

    10

    15

    TotalParkedVehicle

    Time

    Parking Accumulation

    Total Parked Vehicle Average Accumulation

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    19/39

    13

    Parking spill over has been occurred for only one time period 12:45 AM 1:00 PM (peak

    period); which indicates sufficiency of the existing parking supply.

    Parking Turnover

    Total parking volume is 78 vehicles over a time period of 5 hour. No. of space available is

    12. So parking turnover is 6.5(78/12) vehicles per space over a time period of 5 hour. It

    indicates every space is used by 6.5 vehicles over the time period. This turnover figure

    represents that available parking spaces are used quite efficiently used.

    Vehicle-Hour Occupation

    Table-2: Vehicle-Hours of Occupation (Dhanmondi Plaza)

    Average Duration

    (Hour)

    Total Vehicle

    Parked

    % Vehicle-Hours of Occupation %

    0.25 48 61.54 (48*0.25) = 12 35.82

    0.50 14 17.95 (14*0.50) = 7 20.90

    0.75 11 14.10 (11*0.75) = 8.25 24.63

    1.00 1 1.28 (1*1) = 1 2.99

    1.25 3 3.85 (3*1.25) = 3.75 11.19

    1.50 1 1.28 (1*1.5) =1.5 4.48

    78 100.00 33.5 100.00

    Average Vehicle-Hour of Occupation 33.5/78 = 0.43

    Maximum amount of vehicles (61.5%) average duration of parking is 15 minutes. This is

    because customers come into the market only for the grocery shopping which usually dont

    take so much time. The average vehicle-hour occupation is 0.43 hour/vehicle. It indicates that

    on an average one vehicle is expected to stay on the parking area 0.43 hour (26 minutes).

    Figure-6: Vehicle-Hours of Occupation (Dhanmondi Plaza)

    0.00

    20.00

    40.00

    60.00

    80.00

    15 min 30 min 45 min 1 hour 1 hour 15 min 1 hour 30 min

    Percentage(%)

    Averge Duration of Vehicle

    Vehicle-Hours of Occupation

    Total Parked Vehicle Vehicle-Hours of Occupation

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    20/39

    14

    3.2 Mamtaz Plaza

    Its a moderately large scale commercial complex along the Mirpur road. Parking pressure of

    this generator is moderate. Ground floor retail shops contribute much in the parking demand.

    3.2.1 Supply Scenario

    Parking supply of this commercial parking generator can be seen from two perspectives.

    They are: illegal on-street parking practice and designated off-street parking provision.

    Theoretically the illegal on-street parking spaces will not be treated as supply in this study.

    Only the designated off-street parking spaces will be counted as supply in the later portion.

    Illegal On-Street Parking

    There is no designated on-street parking provision for this commercial complex. Vehicles are

    parked on two sides of the building; at the eastern side (on Mirpur road) and at the northern

    side (on Road No. 04). At the front side vehicles are parked just on the Mirpur road in one

    lane parallel to the road. At the northern side vehicles are parked both angular (90 0) and

    parallel to the road. Parking regulatory sign (No Parking) is presentbut its not followed.

    There is no parking charge. Vehicles are unable to park on the footpath because of the high

    altitude (1-0) from the road surface.Total 14-16 vehicle can be parked in both sides.

    Existing on-street parking provision is enlightened below with the help of the figures.

    Figure-7: Eastern Side On-Street Parking

    (Mamtaz Plaza)

    Figure-8: Northern Side On-Street Parking

    (Mamtaz Plaza)

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    21/39

    16

    Figure-12: Off-Street Parking Provision

    -Parking Bays (Mamtaz Plaza)

    Figure-11: Off-Street Parking Provision

    -Driveway (Mamtaz Plaza)

    Figure-10: Off-Street Parking Provision

    -Entrance Ramp (Mamtaz Plaza)

    Figure-13: Off-Street Parking Provision

    -Restricted Parking Bays (Mamtaz Plaza)

    Off-Street Parking Provision

    At the basement of Mamtaz plaza there is off-street parking provision. Parking provision is

    for one floor consisting with the total parking area 13050 sq. ft. Total capacity of this

    underground parking is 28 vehicles at a time. Parking charge is applicable here. The amount

    is 10 taka per hour fixed by the market authority. Restriction on parking at certain parking

    bays/lots (2) is imposed for maneuvering purpose. This reduces the capacity of this parking

    provision. Parking lots are arranged in a grid-iron pattern. Bays are arranged in two lanes

    separated by a driveway. The air ventilation is not up to the mark and light is not sufficient.

    Existing off-street parking provision is clarified below with the help of the figures.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    22/39

    18

    3.2.2 Demand Scenario

    To assess the total parking demand of this commercial generator parking usage survey by

    patrol has been conducted both in the on-street and off-street parking spaces. Survey data and

    calculation is shown in Appendix (Page IV- PageVIII). Later total number of vehicles arrived

    in a day in both spaces has been added to find out the gross parking demand for this

    commercial land use. The parking demand is clarified with various parking terms in the

    following section.

    Parking Volume

    Parking volume is 154 vehicle in on-street and 31 vehicle in off-street over the time period of

    five hour. Combined gross parking demand for this commercial land use is 185 vehicles in

    duration of five hour.

    Parking Accumulation

    Combined parking accumulation curve shows that both the on-street and off-street parking is

    in peak position during the time period of 11.00 AM 12.30 PMand 3.00 PM 4.00 PM. In

    this two time period the combined accumulation crossed the combined average accumulation

    (26.55 vehicle/15 minutes). The combined average accumulation indicates that if the parkingdemand is treated as combined; in every 15 minutes 26.55 vehicles have to be supplied with

    parking bays to fulfill the demand. (Parking Accumulation Table: Appendix-VII)

    Figure-15: Combined Parking Accumulation Curve (Mamtaz Plaza)

    0

    5

    10

    15

    20

    25

    30

    35

    TotalParkedVehicle

    Time

    Parking Accumulation

    On Street Off Street Combined Average(Combined)

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    23/39

    19

    Parking Index and Spillover

    Parking index is calculated to find out the utilized capacity of the off-street parking bays in

    separate time frame. This calculation is based on the assumption that on-street parking

    demand is diverted along with off-street parking demand in the underground parking

    provision. From the parking index and spillover table in Appendix (Page VII) it can be seen

    that parking bays are utilized most efficiently during the peak period (11.00 AM 12.30 PM

    and 3.00 PM 4.00 PM). It also indicates that parking pressure will be tough to handle if the

    parking volume is increased in the future during this time period.

    Parking spillover has been calculated to find out the deficiency in the existing parking

    provision in any certain time period. For the combined parking demand spillover has been

    experienced during the peak period (11.00 AM -11.15 AM, 11.45 AM 12.30 PM and 3.30

    PM 3.45 PM). The spillover is ranging from 1-3 parking space deficiency at a time. There

    is possibility of occurring spillover during the time period 11.15 AM 11.45 AMand 3.00

    PM3.15 PMif the future parking demand increases just a unit.

    Parking Turnover

    Combined parking volume is 185 vehicles over a time period of 5 hour. No. of space

    available in the underground parking provision is 28 at a time. So parking turnover is 6.61

    (185/28) vehicles per space over a time period of 5 hour. It indicates every space is used by

    6.61 vehicles over the time period. This turnover figure represents that available parking

    spaces will be used quite efficiently, if the on-street parking demand is shifted towards

    underground along with the off-street parking demand.

    Vehicle-Hour Occupation

    Vehicles are classified according to their average duration of stay. Then their contribution in

    the total parking load over the time period (5 hour) is calculated through vehicle-hours of

    occupation. Vehicle-Hours of occupation has been calculated separately both for the on-street

    and off-street parking (Appendix-Page VIII). From this calculation specific type of vehicles

    (based on duration) can be identified, contributing most in the parking load. Which time

    durations (15 min, 30 min, 1 hour etc.) parking occurs most can be also identified from this

    calculation; which is an important decision for parking planning.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    24/39

    20

    Vehicle-Hours of occupation for both the on-street and off-street parking is clarified in the

    next section.

    Figure-16: On-Street Vehicle-Hours of Occupation (Mamtaz Plaza)

    In case of on-street parking average duration 15 min is the most contributing sector in

    vehicle-hour occupation. This is because people usually park for short time in on-street

    parking spaces when they come to this commercial complex for short term. This short term

    parking is contributed much by the ground floor retail shops.

    Reverse situation has been experienced in case of underground/off-street parking. In this casea long term parking or high average duration (2 hour and 5 hour) vehicle contributes much.

    This is because people usually use the underground parking bays in case of long term parking

    to avoid the hassle in on-street parking.

    Figure-17: Off-Street Vehicle-Hours of Occupation (Mamtaz Plaza)

    0.00

    20.00

    40.00

    60.00

    80.00

    15 min 30 min 45 min 1 hour 1 hour 15 min 1 hour 30 min

    Percentage(%)

    Average Duration of Vehicle

    Vehicle-Hours of Occupation(On-Street)

    Total Parked Vehicle Vehicle-Hours of Occupation

    0.00

    5.00

    10.00

    15.00

    20.0025.00

    30.00

    35.00

    40.00

    45.00

    15 min 30 min 1 hour 2 hour 3 hour 4 hour 5 hour

    Percenta

    ge(%)

    Average Duration of Vehicles

    Vehicle-Hours of Occupation(Off-Street)

    Total Parked Vehicle Vehicle-Hours of Occupation

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    25/39

    21

    Chapter 04: Findings and Recommendations

    In this chapter the major findings from the previous chapters demand supply analysis will be

    sorted. Some recommendations will be formulated to manage the existing parking demand in

    guidance with the Parking Policy for the Dhaka Metropolitan Development Plan Area

    (DTCB, 2002). In the major findings segment the sources of the data is mentioned inside the

    bracket. In case of recommendations the related segment of the Parking Policy for DMDP

    Area, 2002 has been mentioned in a bracket form.

    4.1 Dhanmondi Plaza

    Major Findings

    Absence of any kind of legal parking supply (Field Survey).

    Designated but illegal on-street parking-12 parking spaces (Field Survey).

    Highest parking demand is 13 vehicles in 15 minutes interval (Parking Accumulation)

    On an average 70% of the existing capacity is being used (Parking Index)

    Majority of the parking demand come for short term - 60% for 15 minutes (Vehicle-

    Hours of Occupation)

    Recommendations

    On-Street parking should be banned and provision of off-street parking for the

    existing parking demand in the shortest possible of time (Policies on Parking

    Regulation).

    Total 15 parking bays should be provided in the underground considering the highest

    present demand and the changing demand in the future.

    Until the provision of underground parking deterrent parking charge (50 taka for 10

    minutes) should be imposed for on-street parking to discourage it (Policies on

    Managing Parking Demand).

    In the underground parking provision parking charge should be applicable (30 taka

    per hour) to bear the maintenance cost and to discourage long term parking (Policies

    on Managing Parking Demand).

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    26/39

    22

    4.2 Mamtaz Plaza

    Major Findings

    Illegal on-street parking reduces the effective carriageway width (33-0 reduces to

    29-0) thereby causing congestion on the road (Field Survey).

    Total capacity of the underground parking provision is 28 vehicles at a time (Field

    Survey).

    Highest combined demand will be 31 vehicles in a time period of 15 minutes

    (Parking Accumulation).

    On an average 95% of the existing parking capacity will be used if parking demand is

    treated as combined. Presently only 55% of the capacity has been used by the off-

    street parking demand (Parking Index).

    Spillover will be likely to experience during the peak period (11.00 AM 12.30 PM

    and 3.00 PM 4.00 PM) if the parking demand is treated as combined (Parking

    Spillover)

    On-street parking is dominated by the short term parking characteristics and off-street

    parking is dominated by the longer parking duration.(Vehicle-Hours of Occupation)

    Recommendations

    On-Street parking should be strictly prohibited through the law enforcing agencies

    (Policies on Enforcement of Regulations). As an alternate option they should be

    shifted and encouraged towards off-street parking through regulatory sign and low

    parking charge (10 taka per hour) during the off-peak period.

    Parking charge should vary during the peak (30 taka per hour) and off-peak (10 taka

    per hour) period to manage the parking demand with respect to the available capacity(Policies on Managing Parking Demand).

    Parking area should be improved in terms of ventilation and maintenance by the local

    authority with the revenue money collected in the form of parking charge (Policies on

    Operation and Maintenance of Parking Facilities).

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    27/39

    23

    4.3 Conclusion

    Parking demand management is now an important issue all over the world. As more as the

    world getting modernized and mechanized the no. of vehicles are increasing. To provide

    parking spaces for all this vehicles in the working hour and in the free hour is a tough job.

    Various strategies such as- restriction, pricing, fixation of time duration etc are practiced all

    over the world to minimize this problem. In the worlds most densely populated city like

    Dhaka space for parking is some kind luxury. To manage the huge parking demand in the

    peak period limited spaces should be used fruitfully. Through practicing effective and

    suitable strategies according to Parking Policy for the Dhaka Metropolitan Development

    Area, 2002 this can be achieved. Parking policy should be strictly maintained and the

    regularly updated according to the emerging changing situation.

    .

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    28/39

    Works Cited

    Dhaka Transport Co-Ordination Board. (2002).Parking Policy for the Dhaka Metropolitan

    Development Plan Area.Retrieved May 20, 2011, from

    ib.pmo.gov.bd/legalms/pdf/parking_policy-Dhaka.pdf

    Ismail N. and Norhisham S. (2008). Case Study on Supply and Demand for University

    Parking Facilities in College of Engineering UNITEN.Retrieved May 21, 2011, from

    Universiti Tenaga Nasional:

    www.uniten.edu.my/.../UNITEN%20ICCBT%2008%20Case%20Study%20on%20Su

    pply%...

    Pioneer Valley Metropolitan Planning Organization. (2006).Downtown Huntington Parking

    Study.Retrieved May 18, 2011, from Pioneer Valley Planning Comission:

    www.pvpc.org/resources/transport/Huntington_Report_Web.pdf

    Rao K. V. K Mathew V. T. and., Introduction to Transport Engineering, Chapter-38(page:

    38.1-38.10); Retrieved May 20, 2011 from: Centre for Distance Engineering

    EducationProgram,IIT,Bombay;URL:http://books.atishji.com/Transportation%20Engi

    neering/Introduction%20to%20Transportation%20Engineering%20by%20Tom%20V

    .%20Mathew%20and%20K%20V%20Krishna%20Rao%20(BOOK)/nptel_ceTEI_L3

    8.pdf

    Transport Research Board. (2003). TCRP Report 95:Traveler Response to Transportation

    System Changes;(Chapter 18Parking Management and Supply).Washington.

    Victoria Transport Policy Institute. (2011, May 10). Parking Evaluation. Retrieved May 18,

    2011, from Victoria Transport Policy Institute: www.vtpi.org/tdm/tdm73.htm

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    29/39

    Bibliography

    Black, J. (1981). Urban Transport Planning: Theory and Practice. Baltimore and London:

    The Johns Hopkins University Press.

    Kadiyali L.R. (2003), Traffic Engineering and Transport Planning Sixth Edition, Khanna

    Publishers, New Delhi.(page: 67-78)

    O'Flaherty, C. (1974).Highways and Traffic (2nd ed., Vol. 1). Frome and London: Edward

    Arnold Publishers Ltd.

    Rahman M. M. (2006), Study of Parking Facility for the New Market Shopping Zone in

    Dhaka CityUnpublished MURP Thesis, Department of Urban and Regional

    Planning, Bangladesh University of Engineering and Technology, Dhaka.

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    30/39

    Appendix

    Page | I

    Dhanmondi Plaza(5 Storied, Commercial Uses, Total Floor Area:54505.85 sq. ft.)

    Address: House No. 18, Road-06, Dhanmondi, Dhaka-1205

    Survey:Parking Usage Survey by Patrol-On Street

    Date:13/05/2011; Day:Friday; Weather:Sunny and Humid

    11.00 AM -1.00 PM 3.00 PM - 5.00 PM 6.00 PM - 7.00 PM

    11.00-

    11.15

    11.15-

    11.30

    11.30-

    11.45

    11.45-

    12.00

    12.00-

    12.15

    12.15-

    12.30

    12.30-

    12.45

    12.45-

    1.00

    3.00-

    3.15

    3.15-

    3.30

    3.30-

    3.45

    3.45-

    4.00

    4.00-

    4.15

    4.15-

    4.30

    4.30-

    4.45

    4.45-

    5.00

    6.00-

    6.15

    6.15-

    6.30

    6.30-

    6.45

    6.45-

    7.00

    GA 15-

    0568

    GA 17-

    6706

    MA 51-

    4651

    CHA 13-

    9594

    GA 21-

    6535

    KHA 12-

    4479

    GA-17-

    7815

    GA 23-

    1636

    KHA

    13-

    1569

    KHA

    13-

    1569

    KHA

    13-

    1569

    KHA

    13-

    1569

    KHA

    19-

    1312

    KHA

    19-

    1312

    KHA

    19-

    1312

    KHA

    19-

    1312

    CHA

    29-

    6169

    CHA

    29-

    6169

    THA

    57-

    3366

    THA

    57-

    3366

    KHA 11-

    4506

    GHA 11-

    0018

    GA 31-

    1158

    GA 14-

    4781

    GA 25-

    1515

    CHA 14-

    0416

    GA 15-

    2461

    GA 17-

    7815

    GA 19-

    6763

    GA 19-

    6763

    CHA

    23-

    8621

    CHA

    23-

    8621

    CHA

    23-

    8621

    CHA

    23-

    8621

    CHA

    23-

    8621

    CHA

    23-

    8621

    KA 11-

    5713

    KA 11-

    5713

    KA 21-

    6871

    KA 21-

    6871

    GA 19-

    5949

    TTHA

    11-0973

    GA 15-

    3726

    GA 12-

    7212

    GA 31-

    1158

    GA 25-

    3527

    KHA 13-

    0764

    GA 15-

    2461

    GA 17-

    2328

    GA 17-

    2328

    GA 17-

    2328

    GA 17-

    2328

    GA 17-

    2328

    GA 17-

    2328

    CHA

    29-

    1335

    KA 17-

    5117

    KHA

    25-

    7900

    KHA

    25-

    7900

    KHA

    25-

    7900

    KHA

    25-

    7900GA 31-

    1158

    GA 21-

    1281

    KA 11-

    2991

    GA 31-

    1158

    GA 12-

    7212

    GHA 11-

    5100

    GHA 13-

    2615

    KHA 13-

    0764

    CHA

    17-

    2111

    CHA

    17-

    2111

    CHA

    17-

    2111

    CHA

    17-

    2111

    KA 17-

    5117

    KA 17-

    5117

    KA 17-

    5117

    GA 11-

    7630

    GA 27-

    8123

    GA 21-

    1160

    GA 21-

    1160

    GA 23-

    3547

    GA 31-

    3387

    KA 11-

    2991

    GA 21-

    1281

    GA 19-

    9543

    GA 25-

    5466

    GA 21-

    3141

    GA 12-

    7212

    GHA

    13-2615

    KA 12-

    5232

    KA 12-

    5232

    KA 12-

    5232

    KA 12-

    5232

    KA 12-

    5232

    KA 12-

    5232

    GA 11-

    7630

    PA 53-

    7453

    GA 21-

    1160

    GHA

    14-

    9318

    GHA

    14-

    9318

    KA 17-

    2378

    GA 15-

    3726

    GA 11-

    3726

    TTHA

    11-0973

    GA 19-

    5784

    GHA 11-

    5100

    MA 51-

    4673

    GA 19-

    8713

    GA 12-

    7212

    GA 17-

    1315

    KHA

    25-

    2903

    KHA

    25-

    2903

    KHA

    25-

    2903

    GA 11-

    7630

    GA 11-

    7630

    KA 31-

    6936

    GHA

    14-

    9318

    KA 17-

    4306

    KA 17-

    4306

    KA 17-

    4306

    GA 23-

    9181

    GA 31-

    1158

    CHA 14-

    0416

    GA 17-

    8475

    GA 25-

    3527

    GHA 11-

    6614

    KHA

    25-

    2903

    GA 11-

    7630

    GA 11-

    7630

    GA 11-

    7630

    KA 17-

    4306

    KA 19-

    4596

    KA 19-

    4596

    KA 19-

    4596

    GA 21-

    1281

    KHA 11-

    4506

    GHA 14-

    0045

    GA 12-

    7212

    GA-21-

    2521

    GA 19-

    8713

    GA 11-

    7630

    KA 17-

    5117

    KA 19-

    4596

    CHA

    17-

    3539

    CHA

    17-

    3539

    CHA

    17-

    3539

    TTHA

    11-0973

    MA 51-

    4651

    CHA 11-

    8757

    GA 31-

    1158

    GA 29-

    7388

    GA 19-

    6338

    CHA

    17-

    3539

    GA 13-

    4690

    GA 13-

    4690

    GA 13-

    4690

    GA 26-

    1677

    GA 15-

    0467

    GA 25-

    3527

    GA 13-

    4690

    GA 15-

    1377

    GA 13-

    6804

    KHA 11-9338

    GA 17-7815

    GA 17-3048

    GA 15-1377

    GA-17-

    6706

    GA 29-

    7607

    GA 21-

    2521

    CHA

    17-

    7731

    GA 17-

    7377

    Arrival 3 0 5 7 8 6 5 8 0 1 2 1 0 1 2 12 0 2 3

    Departure 6 3 5 4 5 10 0 13 1 1 0 4 0 2 1 6 2 3 2

    Total 12 9 6 6 9 12 8 13 8 7 7 9 6 6 5 6 12 10 9 10

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    31/39

    Appendix

    Page | II

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    32/39

    Appendix

    Page | II

    Dhanmondi Plaza: On-Street Parking (Parking Terms Calculation)

    Total Arrived Vehicle 78

    Parking Volume 78 vehicle/5 hour

    Parking Accumulation

    Time Total Parked Vehicle

    11.00-11.15 12

    11.15-11.30 9

    11.30-11.45 6

    11.45-12.00 6

    12.00-12.15 9

    12.15-12.30 12

    12.30-12.45 8

    12.45-1.00 13

    3.00-3.15 83.15-3.30 7

    3.30-3.45 7

    3.45-4.00 9

    4.00-4.15 6

    4.15-4.30 6

    4.30-4.45 5

    4.45-5.00 6

    6.00-6.15 12

    6.15-6.30 10

    6.30-6.45 9

    6.45-7.00 10

    Average Accumulation 8.5(per 15 minutes)

    Parking Index and Spillover

    Time Total Parked Vehicle No. of Space Available Parking Index Parking Spill Over

    11.00-11.15 12 12 100.00 0

    11.15-11.30 9 12 75.00 0

    11.30-11.45 6 12 50.00 0

    11.45-12.00 6 12 50.00 0

    12.00-12.15 9 12 75.00 0

    12.15-12.30 12 12 100.00 0

    12.30-12.45 8 12 66.67 0

    12.45-1.00 13 12 108.33 1

    3.00-3.15 8 12 66.67 0

    3.15-3.30 7 12 58.33 0

    3.30-3.45 7 12 58.33 0

    3.45-4.00 9 12 75.00 0

    4.00-4.15 6 12 50.00 04.15-4.30 6 12 50.00 0

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    33/39

    Appendix

    Page | III

    Parking Index and Spillover

    Time Total Parked Vehicle No. of Space Available Parking Index Parking Spill Over

    4.30-4.45 5 12 41.67 0

    4.45-5.00 6 12 50.00 0

    6.00-6.15 12 12 100.00 0

    6.15-6.30 10 12 83.33 0

    6.30-6.45 9 12 75.00 06.45-7.00 10 12 83.33 0

    Average Parking Index 70.83

    No. of Times

    Seen

    Average Duration(hour) Total Vehicle

    Parked

    % Vehicle-Hours of

    Occupation

    %

    1 0.25 48 61.54 12 35.82

    2 0.50 14 17.95 7 20.90

    3 0.75 11 14.10 8.25 24.63

    4 1.00 1 1.28 1 2.99

    5 1.25 3 3.85 3.75 11.19

    6 1.50 1 1.28 1.5 4.48

    78 100.00 33.5 100.00

    Parking Turnover (78/14)= 5.57 vehicles per space in a period of 5 hours

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    34/39

    Appendix

    Page | IV

    Momtaz Plaza (6 Storied, Commercial Uses, Total Floor Area: 78304.83 sft.)

    Address:House No. 7, Road-04, Dhanmondi, Dhaka-1205

    Survey:Parking Usage Survey by Patrol-On Street; Date:13/05/2011;

    Day:Friday; Weather:Sunny and Humid11.00 AM -1.00 PM 3.00 PM - 5.00 PM 6.00 PM - 7.00 PM

    11.00-

    11.15

    11.15-

    11.30

    11.30-

    11.45

    11.45-

    12.00

    12.00-

    12.15

    12.15-

    12.30

    12.30-

    12.45

    12.45-

    1.00

    3.00-

    3.15

    3.15-

    3.30

    3.30-

    3.45

    3.45-

    4.00

    4.00-

    4.15

    4.15-

    4.30

    4.30-

    4.45

    4.45-

    5.00

    6.00-

    6.15

    6.15-

    6.30

    6.30-

    6.45

    6.45-

    7.00

    GHA 31-

    9067

    KHA 11-

    5217

    GA 31-

    6116

    GA 15-

    7169

    GA 15-

    7159

    GA 15-

    7159

    PA-

    142281

    GA 29-

    9661

    GA 23-

    8546

    GA 66-

    9526

    KA 57-

    8975

    KA 57-

    8975

    KHA

    97-

    7990

    KA 87-

    3355

    KA 87-

    3355

    GHA

    97-

    2266

    KA 09-

    4666

    KHA

    89-

    7778

    KA 00-

    9987

    KA 00-

    9987

    CHA 13-

    0065

    CHA 13-

    0065

    GA 13-

    1823

    KHA 12-

    4020

    KHA 12-

    4020

    KHA 14-

    0349

    GA 15-

    3149

    GA 15-

    3149

    GHA

    43-

    2108

    GA 15-

    8766

    KA 78-

    9996

    KHA

    98-

    8867

    KHA

    98-

    8867

    KHA

    98-

    8867

    GA 78-

    0667

    GA 78-

    0667

    GHA

    08-

    0060

    GHA

    08-

    0060

    GA 00-

    2345

    GHA

    20-

    2040

    GA 25-

    1226

    GA 25-

    1226

    GA 25-

    1226

    GA 25-

    1226

    GA 27-

    1671

    GA 13-

    0222

    GA 13-

    0222

    GA 13-

    0222

    KA 67-

    4532

    KHA

    97-

    0592

    GA 07-

    6782

    GHA

    95-

    4788

    GA 65-

    5779

    GA 65-

    5779

    GA 65-

    5779

    KA 74-

    2254

    KHA

    94-

    4550

    CHA

    04-

    4998

    KA 05-

    4776

    KA 05-

    4776

    GA 78-

    9998

    GA 11-

    4698

    DA 14-

    1707

    DA 14-

    1707

    DA 14-

    1707

    DA 14-

    1707

    DA 14-

    1707

    GA 27-

    5448

    CHA

    32-4432

    GHA

    55-0874

    GHA

    55-0874

    GHA

    55-0874

    KA 45-

    0579

    KHA

    55-3568

    KA 95-

    0579

    KHA

    85-6586

    KA 05-

    6778

    KA 05-

    6778

    KA 04-

    9831

    KA 99-

    9960

    GA 32-

    2751

    KA 11-

    2991

    THA 13-

    2893

    GA 17-

    3883

    GA 17-

    3883

    GA 17-

    3883

    GA 17-

    3883

    GA 17-

    3883

    KA 21-

    0076

    KHA

    91-

    9960

    GA 01-

    9570

    GHA

    11-

    8590

    GA 71-

    5783

    GHA

    56-

    4779

    GHA

    86-

    2288

    GHA

    86-

    2288

    GHA

    97-

    0908

    GHA

    80-

    9978

    GHA

    80-

    9978

    GHA

    80-

    9978

    GA 14-

    7792

    GHA 11-

    7299

    KHA 12-

    8492

    KHA 13-

    0883

    GA 25-

    1226

    GA 25-

    1226

    GA 25-

    1226

    KHA 13-

    1840

    PA 12-

    5643

    GA 82-

    0749

    GA 82-

    0749

    GA 82-

    0749

    GHA

    32-

    4767

    GHA

    32-

    4767

    GHA

    32-

    4767

    GA 52-

    0065

    GHA

    02-

    0944

    GHA

    02-

    0944

    GA 02-

    9984

    CHA

    01-

    0045

    GA 14-

    1707

    GA 14-

    1707

    GA 12-

    0023

    GA 25-

    0616

    GA 28-

    4070

    GA 14-

    0045

    KHA

    12-317

    GA 14-

    5698

    GHA

    22-

    5032

    KHA

    92-

    5476

    KHA

    92-

    5476

    KHA

    92-

    5476

    GA 82-

    0496

    GA 82-

    0496

    GA 82-

    0496

    KA 02-

    0998

    KHA

    00-

    1195

    KHA

    00-

    1195

    KHA

    00-

    1195

    KA 08-

    6540

    VA 11-

    1510

    GA 21-

    4618

    THA 13-

    3518

    GA 13-

    6681

    GA 17-

    5490

    CHA

    11-

    7865

    CHA

    11-

    7865

    CHA

    11-

    7865

    CHA

    11-

    7865

    CHA

    11-

    7865

    CHA

    11-

    7865

    KA 51-

    7899

    KHA

    51-

    7504

    KA 51-

    6754

    KHA

    41-

    7774

    GA 11-

    0945

    GHA

    12-

    7865

    GA 19-

    4516

    GA 19-

    4516

    GA 19-

    4516

    GA 19-

    4516

    GA 19-

    4516

    GA 19-

    4516

    GA 32-

    9854

    PA 72-

    0789

    KA 08-

    1982

    GA 78-

    4975

    GA 48-

    4968

    GHA

    58-

    7896

    GHA

    58-

    7896

    GHA

    58-

    7896

    GA 48-

    7778

    GHA

    98-

    0099

    GHA

    98-

    0099

    GA 99-

    2239

    CHA 45-

    8799

    GA 29-

    8591

    GA 29-

    8591

    GA 29-

    8591

    GA 29-

    8591

    GA 29-

    8591

    GA 12-

    3456

    GA 12-

    3456

    GA 12-

    3456

    GHA

    55-

    9498

    CHA

    75-

    9490

    KA 45-

    3780

    KHA

    65-

    0991

    KA 25-

    8956

    KHA

    05-

    7765

    KA 95-

    9985

    KHA

    05-

    8731

    KA 07-

    7789

    GA 45-

    9832

    GA 25-

    3336

    GHA 11-

    9700

    PA 11-

    5270

    CA 02-

    2993

    PA 13-

    3221

    PA 13-

    3221

    GA 43-

    8297

    KA 03-

    9972

    GHA

    43-5979

    GHA

    73-8993

    GHA

    56-9887

    CHA

    00-5598

    KA 00-

    9996

    KA 24-

    2424

    KHA

    94-5456

    KHA 12-

    5169

    GA 15-

    3709

    GA 27-

    3708

    GA 43-

    8477

    GA 43-

    8477

    GHA

    73-

    0499

    GA 54-

    8976

    KHA

    90-

    8775

    KHA

    90-

    8775

    KA 99-

    8666

    KA 99-

    8666

    KHA

    89-

    9665

    GA 19-

    4516

    PA 32-

    2134

    GA 45-

    0087

    GA 45-

    0087

    PA 44-

    9832

    Arrival 5 7 8 7 6 3 3 11 9 8 8 8 8 6 8 12 9 8 9

    Departure 6 6 7 6 7 8 4 6 8 7 10 12 7 7 8 11 8 11 8

    Total 11 10 11 12 13 12 7 6 11 12 13 12 10 12 11 12 13 12 12 13

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    35/39

    Appendix

    Page | V

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    36/39

    Appendix

    Page | V

    Momtaz Plaza (6 Storied, Commercial Uses, Total Floor Area: 78304.83 sq. ft.,

    Total Parking Area:13050.80)Address:House No. 7, Road-04, Dhanmondi, Dhaka-1205

    Survey:Parking Usage Survey by Patrol-Off Street

    Date:13/05/2011; Day:Friday; Weather:Sunny and Humid

    11.00 AM -1.00 PM 3.00 PM - 5.00 PM 6.00 PM - 7.00 PM No

    Of

    Times

    Seen

    Car No. 11.00-

    11.15

    11.15-

    11.30

    11.30-

    11.45

    11.45-

    12.00

    12.00-

    12.15

    12.15-

    12.30

    12.30-

    12.45

    12.45-

    1.00

    3.00-

    3.15

    3.15-

    3.30

    3.30-

    3.45

    3.45-

    4.00

    4.00-

    4.15

    4.15-

    4.30

    4.30-

    4.45

    4.45-

    5.00

    6.00-

    6.15

    6.15-

    6.30

    6.30-

    6.45

    6.45-

    7.00

    1 CHA 53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA

    53-

    2194

    CHA 53-

    2194

    CHA 53-

    2194

    CHA 53-

    2194

    19

    2 KHA 11-

    0998

    KHA

    11-

    0998

    KHA

    11-

    0998

    KHA

    11-

    0998

    KHA

    11-

    0998

    KHA

    11-

    0998

    KHA

    11-

    0998

    KHA

    11-

    0998

    8

    3 GA 31-

    1391

    GA 31-

    1391

    GA 31-

    1391

    GA 31-

    1391

    GA 31-

    1391

    GA 31-

    1391

    GA 31-

    1391

    GA 31-

    1391

    GA

    31-

    1391

    GA

    31-

    1391

    GA

    31-

    1391

    GA

    31-

    1391

    GA

    31-

    1391

    GA

    31-

    1391

    GA

    31-

    1391

    15

    4 GA 19-

    6462

    GA 19-

    6462

    2

    5 GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA

    25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    GA 25-

    5495

    20

    6 GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA

    25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    GA 25-

    3908

    20

    7 GA 13-

    7005

    GA 13-

    7005

    GA 13-

    7005

    GA 13-

    7005

    GA 13-

    7005

    GA 13-

    7005

    GA 13-

    7005

    GA 13-

    7005

    8

    8 CHA 51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    CHA

    51-

    5792

    15

    9 GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA

    31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    GA 31-

    3774

    19

    10 GA 29-

    5121

    GA 29-

    5121

    GA 29-

    5121

    GA 29-

    5121

    GA 29-

    5121

    GA 29-

    5121

    GA 29-

    5121

    GA 29-

    5121

    GA

    29-

    5121

    9

    11 GA 23-

    8438

    GA 23-

    8438

    GA 23-

    8438

    GA 23-

    8438

    GA 23-

    8438

    GA 23-

    8438

    GA 23-

    8438

    GA 23-

    8438

    GA

    23-

    8438

    GA

    23-

    8438

    GA

    23-

    8438

    GA

    23-

    8438

    GA

    23-

    8438

    GA

    23-

    8438

    GA

    23-

    8438

    15

    12 KA 11-

    0845

    KA 11-

    0845

    KA 11-

    0845

    KA 11-

    0845

    KA 11-

    0845

    KA 11-

    0845

    KA 11-

    0845

    KA 11-

    0845

    8

    13 KHA 11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA

    11-

    0015

    KHA 11-

    0015

    KHA 11-

    0015

    KHA 11-

    0015

    KHA 11-

    0015

    20

    14 GA 23-

    6162

    GA 23-

    6162

    GA 23-

    6162

    GA 23-

    6162

    GA 23-

    6162

    GA 23-

    6162

    GA 23-

    6162

    7

    15 GA 31-

    4761

    GA 31-

    4761

    GA 31-

    4761

    GA 31-

    4761

    GA 31-

    4761

    5

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    37/39

    Appendix

    Page | VI

    16 KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA

    04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    KA 04-

    0781

    20

    17 GA 27-

    4453

    GA 27-

    4453

    GA 27-

    4453

    GA 27-

    4453

    GA 27-

    4453

    GA 27-

    4453

    GA 27-

    4453

    GA 27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    GA

    27-

    4453

    16

    18 GA 19-

    1814

    GA 19-

    1814

    GA 19-

    1814

    GA 19-

    1814

    GA 19-

    1814

    GA 19-

    1814

    6

    19 GA 15-

    2091

    GA 15-

    2091

    GA 15-

    2091

    GA 15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA

    15-

    2091

    GA 15-

    2091

    GA 15-

    2091

    GA 15-

    2091

    15

    20 GA 21-

    9459

    GA 21-

    9459

    GA 21-

    9459

    GA

    21-

    9459

    GA

    21-

    9459

    GA

    21-

    9459

    GA

    21-

    9459

    GA

    21-

    9459

    8

    21 CHA

    45-

    8976

    CHA

    45-

    8976

    CHA

    45-

    8976

    CHA

    45-

    8976

    CHA

    45-

    8976

    CHA

    45-

    8976

    CHA

    45-

    8976

    CHA

    45-

    8976

    CHA 45-

    8976

    9

    22 KA

    67-

    8997

    KA

    67-

    8997

    KA

    67-

    8997

    3

    23 GA

    14-

    7887

    GA

    14-

    7887

    GA

    14-

    7887

    GA

    14-

    7887

    GA

    14-

    7887

    GA

    14-

    7887

    GA

    14-

    7887

    7

    24 KHA

    56-

    0976

    KHA

    56-

    0976

    KHA

    56-

    0976

    KHA

    56-

    0976

    KHA

    56-

    0976

    KHA

    56-

    0976

    KHA

    56-

    0976

    KHA 56-

    0976

    8

    25 KA

    56-

    5564

    KA

    56-

    5564

    2

    26 GHA

    45-

    3456

    GHA 45-

    3456

    GHA 45-

    3456

    GHA 45-

    3456

    GHA 45-

    3456

    5

    27 KA 45-

    3476

    KA 45-

    3476

    KA 45-

    3476

    KA 45-

    3476

    4

    28 GHA29-

    1659

    GHA29-

    1659

    GHA29-

    1659

    GHA29-

    1659

    4

    29 GA 43-

    6543

    GA 43-

    6543

    GA 43-

    6543

    GA 43-

    6543

    4

    30 KHA 78-

    0453

    KHA 78-

    0453

    KHA 78-

    0453

    KHA 78-

    0453

    4

    31 GHA 22-

    3412

    1

    Arrival 0 0 0 1 1 0 0 2 2 0 0 0 0 1 1 4 0 0 1

    Departure 0 1 0 0 1 1 1 3 1 0 1 0 1 0 3 3 2 0 3

    Total 18 18 17 17 18 18 17 16 15 16 16 15 15 14 15 13 14 12 12 10

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    38/39

    Appendix

    Page | VII

    Momtaz Plaza: On-Street Parking Off-Street Parking (Parking Terms Calculation)

    Parking Volume

    On Street Off Street Combined

    154 vehicle/5 hour 31 Vehicle/5hour 185 Vehicle/5hour

    Parking Accumulation

    Time On Street Off Street Combined

    11.00-11.15 11 18 29

    11.15-11.30 10 18 28

    11.30-11.45 11 17 28

    11.45-12.00 12 17 29

    12.00-12.15 13 18 31

    12.15-12.30 12 18 30

    12.30-12.45 7 17 24

    12.45-1.00 6 16 223.00-3.15 11 15 26

    3.15-3.30 12 16 28

    3.30-3.45 13 16 29

    3.45-4.00 12 15 27

    4.00-4.15 10 15 25

    4.15-4.30 12 14 26

    4.30-4.45 11 15 26

    4.45-5.00 12 13 25

    6.00-6.15 13 14 27

    6.15-6.30 12 12 24

    6.30-6.45 12 12 24

    6.45-7.00 13 10 23

    Combined Average Accumulation 26.55(per 15 minutes)

    Parking Index and Spillover

    Time Total Parked

    Vehicle(Combined)

    No. of Space

    Available

    Parking Index Parking Spill Over

    11.00-11.15 29 28 103.57 1

    11.15-11.30 28 28 100.00 0

    11.30-11.45 28 28 100.00 0

    11.45-12.00 29 28 103.57 1

    12.00-12.15 31 28 110.71 3

    12.15-12.30 30 28 107.14 2

    12.30-12.45 24 28 85.71 0

    12.45-1.00 22 28 78.57 0

    3.00-3.15 26 28 92.86 0

    3.15-3.30 28 28 100.00 0

    3.30-3.45 29 28 103.57 1

    3.45-4.00 27 28 96.43 0

  • 8/9/2019 Parking Demand Supply Analysis Ofdifferent Commerciall and Uses Along Mirpur Road-131127200452-Phpapp01

    39/39

    Appendix

    Parking Index and Spillover

    Time Total Parked

    Vehicle(Combined)

    No. of Space

    Available

    Parking Index Parking Spill Over

    4.00-4.15 25 28 89.29 0

    4.15-4.30 26 28 92.86 0

    4.30-4.45 26 28 92.86 0

    4.45-5.00 25 28 89.29 06.00-6.15 27 28 96.43 0

    6.15-6.30 24 28 85.71 0

    6.30-6.45 24 28 85.71 0

    6.45-7.00 23 28 82.14 0

    Combined Average Parking Index 94.82

    Parking Turnover (185/28)= 6.607 vehicles per space in a period of 5 hours

    On-Street Parking

    No. of Times

    Seen

    Average Duration(hour) Total Vehicle

    Parked

    % Vehicle-Hours of

    Occupation

    %

    1 0.25 119 75.32 29.75 51.74

    2 0.50 19 12.03 9.5 16.52

    3 0.75 14 8.86 10.5 18.26

    4 1.00 1 0.63 1 1.74

    5 1.25 3 1.90 3.75 6.52

    6 1.50 2 1.27 3 5.22

    158 100.00 57.5 100.00

    Off-Street Parking

    No. of

    Times Seen

    Average Duration(hour) Total Vehicle

    Parked

    % Vehicle-Hours of

    Occupation

    %

    1 15 min 1 3.23 0.25 0.33

    2 30 min 2 6.45 1 1.313-4 1 hour 5 16.13 4.75 6.21

    5-8 2 hour 10 32.26 17.5 22.88

    9-12 3 hour 2 6.45 4.5 5.88

    13-16 4 hour 5 16.13 19 24.84

    17-20 5 hour 6 19.35 29.5 38.56

    31 100.00 76.5 100.00