Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
LHCb
Install Meeting 20/04/05
TS / CV / Detector Cooling Installations
Detector Cooling activities for the
LHCb experiment
Project Leader: Paolo Guglielmini
Inner Tracker cooling unit
IT-3314 Tracker Trigger cooling unit
RICH 1 & 2 cooling unit
Outer Tracker cooling unit
Primary cooling system modifications
Backup chiller for IT, TT and VELO stations
SPD/PS detectors air cooling
Others Muon on-detector air cooling
Gas compressors cooling
Cooling systems from mixed water network
IT-3307
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT-3314: Inner TrackerTracker Trigger
DESCRIPTION Both cooling systems at fluorocarbon C6F14 in liquid state are based on a water condensed chiller connected to CERN mixed water network. They shall remove respectively some 2 kW and
1.65 kW heat power at -15°C from IT and TT detectors.
BUDGET CODE T757000
SCHEDULE Contract signature April 2005Installation at Contractor’s premises July 2005Installation of pipelines
and manifolds in the UX85 October 2005Installation of the unit in the UX85 End 2005Performance tests in the UX85 February 2006Commissioning March 2006
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
DESCRIPTION The cooling system running fluorocarbon C6F14 in liquid state is based on a heat exchanger connected to CERN chilled water network and shall remove some 4 kW heat power at 10°C from both detectors.
BUDGET CODE T753000 (70%) and 32551 (30%)
SCHEDULE Contract signature April 2005Installation at Contractor’s premises July 2005Installation of pipelines
and manifolds in the UX85 October 2005Installation of the unit in the UX85 End 2005Performance tests in the UX85 February 2006Commissioning March 2006
IT-3314: RICH 1 & 2
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
1
2
1. Location of the cooling stations
Metallic platform on the protected area of the RB84 side.
2. Transfer lines path along the cavern
Grouped supply/return pipelines around the shielding wall, across the vault, down to detector zone.
IT-3314
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT-3314
3
4
3. TT distribution manifolds
Inner cooling circuits fed by ten independent lines with different flows.
4. IT distribution manifolds
Inner cooling circuits fed by twelve independent lines with equal flow.
No distribution manifolds provided for RICHes lines.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT3307: Outer Tracker
DESCRIPTION The cooling system running demineralised water is based on a heat exchanger connected to CERN mixed water network and shall remove some 23 kW heat power at 19°C from the detector.
BUDGET CODE T229900
SCHEDULE Contract signature April 2005Installation of pipelines
and manifolds in the UX85 June – July 2005Installation at Contractor’s premises September 2005Installation of the unit in the UX85 End 2005
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT3307: Primary cooling system modifications
DESCRIPTION The already existing pipelines for chilled and mixed water (on RB86 side), compressed air (on both sides) and demineralised water (on RB84 side) shall be prolonged. The counting houses cooling lines shall be installed and equipped. Metallic supports for the transfer lines of detector cooling units shall be constructed on the RB84 side of the UX85.
BUDGET CODE 32560
SCHEDULE Contract signature April 2005Installation of the pipelines for primary
networks in the UX85, including installation and electrical tests on related equipments June – July 2005
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT-3307
RB84
RB86
2
1
RB86
RB84
1. Compressed air (in white)
Demineralised water (in light blue)
2. Chilled water (in light blue)
Mixed water (in green)
RB84
2
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT-3307
1
2 3
Connections to:
1. barracks D1 and D2
2. barracks D3/A and D3/B
3. detector cooling systems
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Others (1/5): Backup chiller for IT, TT and
VELO cooling stations
DESCRIPTION An air chilled fridge unit (32 kW cooling capacity) shall be provided as a backup for the IT, TT and VELO cooling systems, in order to supply mixed water at 13°C in case of breakdown or maintenance of the standard network. The chiller will be located on top of the barracks and equipped with automatic valves.
BUDGET CODE 32560
SCHEDULEInstallation and commissioning of unit
and related pipeworksJuly 2005
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Others (2/5): SPD/PS detectors air cooling
DESCRIPTION The electronic acquisition cards for the SPD and PS, dissipating a total heat power of about 4.4 kW shall be cooled down with a
dried and filtered air flow at 6 bar pressure. All components of the cooling system shall be positioned into a zone of the protected area still to be defined according to technical
and integration matters.
SCHEDULE Cooling system tested and
commissionedFebruary 2006
PSSPD
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Others (3/5): Muon on-detector air cooling
DESCRIPTION The on-detector electronic, fitted with the Muon chambers in stations M1-M5 shall be cooled by means of a forced air circulation. The air will be taken form the bulk by a fan, and exhausted to the bulk, the cooling capacity being assured by the cavern ventilation system.
The heat dissipated by on-detector electronic is 3.5 kW for station M1, 3 kW for stations M2 and M3 and 2 kW for stations M4 and M5.
SCHEDULE Cooling system tested and
commissionedFebruary 2006
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Others (4/5): Gas compressor cooling
DESCRIPTION Two gas compressors located in building 2870/R-004 release during normal functioning a heat power of about 8 kW each. An independent cooling unit shall be connected to both compressors in order to dissipate such heat power.
SCHEDULE Cooling system tested and
commissionedFebruary 2006
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Balcony racks
LVPS on bunker
Gas racksIT/TT
service boxes
Muon racks
Calorimeter racks
VELO vacuum pump
Total heat dissipated
[kW]40 96
8 (RB86)
4 (RB84)
4 (IT)
4.5 (TT)24 30 3
Others (5/5): Cooling systems from mixed
water network
DESCRIPTION Different heat sources in the UX85 shall be cooled down with systems running mixed water coming from CERN network.
SCHEDULE Cooling systems (pipeworks and supply/return equipped manifolds) installed, tested and commissioned
February 2006
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Others (5/5): Cooling systems from mixed
water network
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005
IT3307 – Installation matters
JUNE – JULY 05
1. cooling pipes integration in the detector area (RB84 side): to be finished and approved for the 6th of May
2. work sequence: primary system RB86 side barracks lines
supports RB84 side OT transfer lines3. storage area for Contractor’s material to be reserved (SG8 2870?)4. cable trays around the new pipelines for chilled water, mixed water
and compressed air to be dismounted (RB86)5. metallic platform on left side of the vault area to be dismounted, all
RB84 side to be prepared for installation6. new metallic structure behind counting houses:
to be finished in three weeks7. positioning of the OT unit on the platform (autumn):
dimensional constraints, to be studied how to lift it up