Page 1 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 1 of 76
Minutes of the 311th meeting of the State Level Expert Appraisal Committee held on 24/10/2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.
The 311th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 24th October, 2016 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Vice Chairman, SEAC.
3. Shri R. J. Shah, Member, SEAC
4. Dr. V. K. Jain, Member, SEAC
5. Dr. Mayuri Pandya, Member, SEAC
6. Shri Rajesh I Shah, Member, SEAC.
7. Shri Natrajan Pratap, Member, SEAC
The agenda of TOR/Scoping/Category 8 (a) cases, Appraisal & Reconsideration cases was taken up. Fourteen (14) cases of TOR/Scoping/Category 8 (a), and three (3) cases of Appraisal was taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A, EIA report and other reports.
1. Salasar Textile Market
Block No. 66, O.P.No.34, F.P.No.50 paikee, Sub division – B, T.P.S.No. 19 (Parvat - Magob), Ta: Choryasi, Dist: Surat.
Screening/scoping
Details of the proposed project as presented before the committee are described below:
Sr. No. Particulars Details 1. Proposal is for New Project [SIA/GJ/NCP/58985/2016] 2. Type of Project Commercial project.
3. Project / Activity No. [8(a) or 8(b)]
8(a)
4. Name of the project
Salasar Textile Market
5. Name of Developer
Mr. Bhagubhai Viththalbhai
6. Estimated Project Cost (Rs. In Crores)
Rs. 95 Crore
7. Whether construction work has been initiated at site? If yes, details thereof
No
8. Project Details Land / Plot Area (m2): 12,543.0 FSI area (m2): 50,104.68 Total BUA (m2) : 76,651.06 Permissible Proposed FSI Area (m2) 50,172.0 50,104.68 Ground Coverage (m2) 6,271.50 6,123.58 Common Plot Area (m2) 1,254.30 1,261.0
Page 2 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 2 of 76
Max. building height (m) -- 47.97
9. Building Details No. of Buildings: 1 No. of Blocks: 1 Scope of buildings/blocks: 2level basement + ground floor + 8
floors. No. & size of Residential Units: -- No. & type of Commercial Units: 590 Textile Houses Details of amenities if any: --
10. No. of expected residents / users
Expected residents: -- Expected shop users: 1770 Expected visitors: 800
11. Water & waste water details during construction phase
Water requirement (KL/day): 14.50 Source of water: Borewell Waste water generation quantity (KL/day): 2.16 Mode of disposal: Soak pit Details of reuse of water, if any: W/W generated from washing
of equipment will be reused for curing after necessary treatment.
12. Water & waste water details during operation phase
Total water requirement (KL/day): 97.0
Fresh water requirement (KL/day): 55.0
Source of water: Water supply from Surat Municipal Corporation (SMC)
Waste water generation quantity (KL/day): 74.0
Mode of disposal: Sewage to be generated will be treated in the proposed onsite STP. Treated sewage will be reused for gardening & flushing purposes within premises and only remaining quantity of treated sewage will be discharged into the drainage line of Surat Municipal Corporation (SMC).
In case of STP provision, capacity of STP: 100 KL/day
Purposes for treated sewage utilization: Flushing & Gardening
Quantity of treated sewage to be reused: 1.Gardening (KL/day): 5.0, 2. Flushing (KL/day): 37.0
Provision of dual plumbing system (Yes/No): Yes
Quantity and type (treated/untreated) of sewage to be discharged: Sewage to be generated will be treated in the proposed onsite STP. Treated sewage will be reused for gardening & flushing purposes within premises and only remaining quantity of treated sewage will be discharged into the drainage line of Surat Municipal Corporation (SMC).
Mode of disposal: as above.
13. Status of water supply and drainage line
Applied for connection of water supply line and drainage line in S.M.C. SMC water supply & drainage line is passing 70 m away from the plot boundary.
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Page 3 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 3 of 76
Top Soil 630.50 630.50 Reuse for developing garden area
Other excavated earth
1,02,432.84 1,02,237.99 m3 will be used for
back filling & raising the plinth level.
Remaining will be send to other project site for back filling & raising the plinth level in consultation with SMC.
Construction debris
805 383
Reused as a filler up to plinth level and remaining will be reused in outer road development
Steel scrap 31 -- Sold to local scrap vendors
Discarded packing materials
19 -- Sold to local
vendors
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 212.40 Blue colour bucket
Final disposal through door to door waste collection system of SMC
Wet waste 161.60 Green colour bucket
Final disposal through door to door waste collection system of SMC
STP Sludge 10 On SDB Reuse in gardening as manure within project premises
Details of segregation if to be done: Separate bins will be provided to collect dry and wet waste.
Capacity and no. of community bins to be placed within premises: Two separate community bins for the building to collect dry & wet waste.
Landfill site where waste will be ultimately disposed by local authority: Khajod landfill site of S.M.C.
15. Parking Details Total parking area requirement for the project as per GDCR: 15,031.40 m2
Parking area requirement for Commercial units as per GDCR: 15,031.40 m2
Total number of CPS requirement for the project as per NBC : 1002
Number of CPS requirement for commercial units as per NBC:
Page 4 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 4 of 76
1002 Total Parking area provided (m2) & No. of CPS: 32,484.50 m2
& 1026 CPS Parking area provided in basement (m2) & No. of CPS:
21,070.0 m2 & 658 CPS Parking area provided as open surface (m2) & No. of CPS:
921.0 m2 & 40 CPS Parking area provided as mechanical parking in upper
basement (m2) & No. of CPS: 10,493.50 m2 & 328 CPS 16. Traffic
Management Width of adjacent public roads: 24.0 m wide road. Number of Entry & Exit provided on approach road/s: 2 nos.
entry/exit will be provided. Width of Entry & Exit provided on approach road/s: 7.50 m Minimum width of open path all around the buildings for easy
access of fire tender (excluding the width for the plantation): 6 m
Width of all internal roads: 7.5 m & 3.60 m. 17. Details of Green
Building measures proposed.
Use of fly ash based material, flush tank instead of direct flushing in toilets, foam type aerated coke, rain water harvesting, use of LED lights for common areas, solar lights for landscape lighting, reflective/ white tiles in common areas, maximum use of natural light, provision of STP & reuse of treated sewage etc.
18. Energy Requirement, Source and Conservation
Power supply Maximum demand: 5000 KVA Connected load:
Source: DGVCL Energy saving measures: Use of LED lights for common areas,
solar lights for landscape lighting, reflective/ white tiles on terrace floor, maximum use of natural light etc
DG Sets No. and capacity of the DG sets: 5 x 125 KVA Fuel & its quantity: Low Sulphur High speed Diesel (HSD) & quantity 55 L/h in each.
19. Fire and Life Safety Measures
Fire extinguishers at each floor, hose reel at each floor, wet riser opening at each floor, yard hydrant, automatic sprinkler system in basement, manually operated electric fire alarm system, automatic fire detection & alarm system, underground static fire water storage tanks of 150 KL x 3 nos. capacity, 3 nos. of terrace tank of 15 KL capacity, one electric & one diesel pump of capacity 2280 L/min. & one electric pump of capacity 180 L/min. having pressure 3.5 kg/cm2 at terrace level. Nearest fire station: Dumbhal fire station. Distance from the project site: about 2 km. Time required for the fire tender to reach the project site: 5 – 10 minutes.
20. Details on staircase
No. of Floor
Max. Floor Area (m2)
No. of staircase
Width of Staircase (m)
Maximum travel distance to the staircase (m)
2B+G+8 6337.44 05
2.00 22.52
Page 5 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 5 of 76
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 22.00 m No. & dimensions of RWH tank(s) : 6 nos. of RWH tanks;
size: 4m x 3m x 3m size of Bore: 350 mm dia. size of pipe: 150 mm dia.
No. and depth of percolations wells: 6 nos. of percolating wells Details on Pre-treatment facilities: A de-silting chamber will be
provided to de-silt and remove floating material through bar screen.
22. Green area details
Tree covered area (m2) : 427.0 Area covered by shrubs and bushes (m2): -- Lawn covered area (m2): 834.0 Total Green Area (m2): 1,261.0 Green Area % of plot area: 10 % No. of trees and species to be planted: 71 trees of Asopalav,
Coconut palm tree, Neem, Gulmohar etc. will be planted within premises.
23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Capital cost of Rs. 103.30 lacs and recurring cost of Rs. 4.85 lacs has been allocated towards purposes like rain water harvesting & ground water recharge, greenbelt development, environment monitoring & management, waste management etc.
24. Proposed dust control measures.
Water sprinkling, covered shed for cement unloading activity, tarpaulin cover on excavated earth & construction material etc.
25. Use of Eco – friendly building materials.
Use of fly ash bricks & aerated blocks for wall partition, paving blocks for parking areas & walk ways, Portland Pozzolona Cement for RCC structure, plaster & flooring etc.
26. Details on amenities to be provided to construction workers
Drinking water & tap water, sanitation facilities, domestic waste water collection facility, lunch space, first aid box, free medicines, doctor service, PPEs etc.
27. Documents related to land possession
Copy of village form no. 7 & 112 submitted by them shows that the land is in the name of applicant & others.
During the meeting, unit wise details of the proposed STP & dual plumbing system were presented. Highest flood level recorded for the area is 1 m and it is proposed to raise the ground floor up to +1.35 m above the existing ground level which is +0.35 m above the HFL of the area. It is proposed to provide designated open surface parking space and parking space at lower basement level for the vehicles coming for loading / unloading. It was presented that maximum travel distance from the designated place for loading / unloading to any of the lift at ground floor level & at lower basement level will not be more than 40 m. It was presented that MCB & RCB switches will be provided which will be tripped in case of case of fluctuation or higher power load to prevent electric overloading or sparkling and flameproof electrical fittings confirming to ISO & DGMS standards will be provided. It was presented that traffic survey was carried out on 60 m wide Surat-Kadodara road which shows that the Level of Service in existing scenario is excellent “A” which will become very good “B” in the proposed scenario. During the meeting, after detailed discussion it was decided to appraise the project further only after submission of the following:
Page 6 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 6 of 76
1. Copy of permission obtained from the concerned competent authority for the proposed FSI.
2. Exact aerial distance of the project site from a khadi in the vicinity and copy of permission obtained from the concerned competent authority in this regard.
3. Details of mechanical parking to be provided (also including its operation, maintenance, energy consumption, appointing trained personnel’s etc.) in the basement along with the feasibility of providing mechanical parking considering the basement height.
4. Type of activities to be carried out in the proposed commercial units. Undertaking stating that any kind of manufacturing activity shall not be allowed in the commercial units of the proposed project and they will not sold / allot any commercial unit for storage of chemicals, flammable substances, explosives, fire crackers or any other material of hazardous characteristics.
5. Details on ventilation, lighting arrangements and CO sensors to be provided in the basements. Details on provision to be made for natural lighting & ventilation in the proposed commercial units.
6. Details on common amenities like drinking water facility, sanitary blocks, first aid facilities etc. to be provided at each floor.
7. Details & plans showing floor wise emergency evacuation for the proposed project.
8. Copy of N.A permission obtained for the proposed project site or documents showing correspondences made with concerned competent authority in this regard. Consent of other land owners regarding issuance of the environmental clearance in the name of applicant.
2. Residential building construction project by Mr. Sunnybhai Laheri
Block No: 12, O.P. No:12, F.P. No:12, T.P.S. No:52, Ved Dist: Surat.
Screening / scoping
Details of the proposed project as presented before the committee are described below: Sr. No.
Particulars Details
1. Proposal is for New project [SIA/GJ/NCP/59120/2016] 2. Type of Project High Rise Residential Building Construction Project 3. Project / Activity No. [8(a)
or 8(b)] Project / Activity No. 8(a)
4. Name of Project “High Rise Residential Building Construction Project” 5. Name of Developer Sunny R. Laheri 6. Estimated Project Cost
(Rs. in Crores) 50 Crores.
7. Whether construction work initiated at site? If yes, details thereof
No
8. Project Details Land/Plot Area (m2): 8,113.0 FSI area (m2): 32,323.94 Total BUA (m2): 56,026.96
Permissible Proposed FSI Area (m2) 32,614.19 32,323.94 Ground Coverage (m2) 2,312.17 2,129.46 Common Plot Area (m2) 811.30 811.57 Max. building height (m) As per rule 129.08
Page 7 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 7 of 76
9. Building Details No. of Buildings:3 No. of Blocks:3 Scope of buildings/blocks: 2 level basement + hollow plinth + 29
floors. 27th floor terrace covered area common for all these buildings, 28th floor common library, gym, banquet hall, swimming pool, 29th floor indoor games, children play area & home theatre.
No. & size of Residential Units:78 flats. No. & type of Commercial Units : ---
10. No. of expected residents / users
468 person Residential
11. 1Water & waste water details during construction phase
Water requirement (KL/day): 30.0 Source of water: Borewell water Waste water generation quantity (KL/day): 4.2 Mode of disposal: Temporary septic tank & soak pit. Details of reuse of water, if any: Nil
12. 1Water & waste water details during operation phase
Total water requirement (KL/day): 88.0 Fresh water requirement (KL/day): 61.0 Source of water: water supply from SMC Waste water generation quantity (KL/day): 59.0 Mode of disposal: Sewage to be generated will be treated in the
proposed onsite STP. Treated sewage will be used for gardening & flushing purpose within premises and remaining quantity of treated sewage will be discharged into the drainage line of SMC.
In case of STP provision, capacity of STP: Yes 70 KL/day STP Technology: STP with MBBR reactor. Purposes for treated sewage utilization: Gardening and Flushing Quantity of treated sewage to be reused:1.Gardening (KL/day):
3.0, 2. Flushing (KL/day):24.0 Provision of dual plumbing system (Yes/No): yes Quantity and type (treated/untreated) of sewage to be
discharged: Treated sewage will be used for gardening & flushing purpose within premises and remaining quantity of treated sewage will be discharged into the drainage line of SMC.
Mode of disposal: As above. 13. 1Status of water supply
and drainage line Water supply & drainage line of SUDA will be available during operation phase.
14. Solid waste Management Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 319 319 It will be reused for lawn and tree development within premises.
Page 8 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 8 of 76
Other excavated earth
3,194 m3 2,600 m3 will be reused in plinth filling, trench filling & internal road making.
694 m3 will be given to SMC.
Construction debris
5 m3
5 m3
Reused in trench filling.
Steel Scrap 1 MT 1MT Reused in column footing and foundation work.
Discarded packing materials
Cement & Plastic Bags
Cement bag will be partly reuse in curing purpose & partly sale out in open market while plastic bag sale out to the registered recycler or vendor
Operation Phase:
Type of waste
Generation Quantity (Kg/day)
Mode of waste
collection
Mode of Disposal /
Reuse Dry waste 187 Will be
collected into the bins to be provided to each individual unit.
Final disposal through agency appointed by SMC.
Wet waste 295
STP sludge Whatsoever Will be sold to farmers as manure.
Details of segregation if to be done: No Capacity and no. of community bins to be placed within
premises: 39 bins having volume 1.7 m3 Landfill site where waste will be ultimately disposed by local
authority: Final disposal through agency appointed by SMC.
Page 9 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 9 of 76
15. Parking Details Total parking area requirement for the project as per GDCR: 4,848.55 m2.
Parking area requirement for residential units as per GDCR: 4,848.55 m2.
Total number of CPS requirement for the project as per NBC: 78 CPS
Number of CPS requirement for residential units as per NBC: 78 CPS
Total Parking area provided (m2) & No. of CPS:16,163.79.0 m2
& 406 CPS Parking area provided in hollow plinth (m2) & No. of CPS:
1,152.38 m2 & 42 CPS Parking area provided (Basement) (m2) & No. of CPS:
13,327.42 m2 & 416 CPS 16. Traffic Management Width of adjacent public roads: Site is accessible by 30 m wide
side approach road. Number of Entry & Exit provided on approach road/s: One main
entry of 9 m width & two entry/exit for basement. Width of Entry & Exit provided on approach road/s: 9.0 m & 3 m Minimum width of open path all around the buildings for easy
access of fire tender (excluding the width for the plantation): 6 m
Width of all internal roads:9.0 m 17. Green building features
including measures for conservation of water & energy, use of eco-friendly building materials, etc.
Use of autoclaved aerated blocks & RMC, aerated type water taps, solar based street lights, LED lightings fixtures and low voltage lightings in common areas, maximum use of natural & cross ventilation, energy saving electrical appliances, maintaining on-off schedule of common, landscape & street lights, provision of STP & reuse of treated sewage.
18. 1Energy requirement, source and conservation
Power supply- Maximum demand 1500 KVA Source: DGVCL
% of saving with calculation: 25% saving by using CFL, star rated energy efficient electronic appliances & solar lights.
DG Set: 3 D.G. Set (Each of 50 KVA) Fuel & it quantity: HSD-50 lit/hour
19. 1Fire and Life Safety Measures
2-CO2 type (4.5 Kg) & 2 DCP type (5 Kg) fire extinguishers on
each floor, 2 DCP type fire extinguishers of 50 Kg near electric panel, fire alarm with manual call points & sounder’s on each floor, risers/down comers, automatic sprinkler system in basements, lighting arrester with proper earthing, display of evacuation path on each floor, fire hydrants, hose reel, 3 nos. of underground fire water storage tanks each of 75 KL capacity, overhead tank of 25 KL capacity on each building etc.
Page 10 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 10 of 76
20. Details on staircase Type & no. of buildings
No. of floors
Floor area (m2)
No. of staircase
Width of the staircase
Travel distance (m)
Height (m)
A,B & C 2B+H.P.+29
386.21 1 2.0 28 129.08
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 25 feet in monsoon 55 feet in summer
No. & dimensions of RWH tank(s): No. and depth of percolations wells: 3 nos. Details on Pre-treatment facilities: Not Applicable
22. Green area details Tree covered area (m2): 540.0 . Area covered by shrubs and bushes (m2): --- Lawn covered area (m2): 811.57 Total Green Area (m2): 1,351.57 Green Area % of plot area: 16 % No. of trees to be planted: 60 trees of local species like Neem,
Ashoka etc. will be planted within premises. 23. Dust control measures Spraying of water, peripheral barricading, covered shed for
cement loading area, covering the excavated earth with tarpaulin sheet etc.
24. Budgetary allocation for Environmental Management Plan(Rs. in lacs)
We will allocate fund of rupees 3 lacs for rain water harvesting & tree plantation on both side of TP road.
25. Details of eco-friendly building materials
Fly ash bricks, aerated blocks, fly ash paving blocks, maximum use of RMC, lead free paints etc.
26. Facilities to construction workers
Sanitation & drinking water facilities, welfare facilities as per Gujarat Building & Other Construction Workers Rules.
27. Documents related to land possession
Copy of village form no. 7/12 & N.A order submitted by them shows that the land for residential use is in the name of land owners and land owners have entered into development agreement with the Project Proponent.
Details of STP were presented & discussed during the meeting. It was observed that the project site is at a distance of 160 m from river Tapi. After detailed discussion on various aspects regarding the project, it was decided to appraise the project further only after submission of the following:
1. Authentic documents showing ownership of the land by the project proponent.
2. Copy of permission obtained from the concerned competent authority for the proposed FSI.
3. Structural stability certificate for the proposed high rise buildings of 29 stories also considering the factors like capacity of swimming pool & overhead water storage tanks, vicinity of the river & ground water level, seismic zone of the area etc.
4. Revised water balance details also considering the water requirement for swimming pool.
5. Details on solar energy utilization for the proposed project and how much of the total energy requirement for the project will be compensated/reduced by the proposed energy conservation measures.
Page 11 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 11 of 76
6. Detailed Environment Management Plan with respect to various environmental attributes- Air, Noise, Solid wastes including Hazardous Wastes, land, water including sewage treatment & reuse etc. of the project both during construction and operation phase and strategy for its implementation with financial outlay.
7. Details on provision to be made for refuge area as per the requirement of NBC norms and GDCR.
3. Krish R.S No. 384/2, F.P No.57/2, T.P.S.No. 37, Thaltej, Ahmedabad
Screening/scoping & appraisal.
Details of the proposed project as presented before the committee are described below:
Sr. No.
Particulars Details
1. Proposal is for New Project [SIA/GJ/NCP/58843/2016] 2. Type of Project Residential Project 3. Project / Activity
No.[8(a) or 8(b)]8 (a)
4. Name of the project
Krish
5. Name of Developer
Dreamland Infratech Pvt. Ltd
6. Estimated Project Cost (Rs. In Crores)
@ 48 Crore
7. Whether construction work has been initiated at site? If yes, details thereof
Construction work has not yet been started.
8. Project Details Land / Plot Area (m2): 5,467.0 FSI area (m2):21,858.20 Total BUA (m2):37,406.36
Permissible Proposed FSI Area (m2) --- 21,858.20 Ground Coverage (m2) --- 1,903.65 Common Plot Area (m2) 546.7 552.16 Max. building height (m) 45 45
9. Building Details No. of Buildings:3 No. of Blocks:3 Scope of buildings/blocks: 2 level basement + hollow plinth + 14 floors. No.& size of Residential Units: Total 160 flats. No. & type of Commercial Units : --- Details of amenities if any: No
10. No. of expected residents / users
378 occupants and 100 visitors
Page 12 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 12 of 76
11. Water & waste water details during construction phase
Water requirement (KL/day): 18.75 Source of water: Water supply from Ahmedabad Municipal Corporation
(AMC) Waste water generation quantity (KL/day): 3.0 Mode of disposal: Into septic tank & soak pit Details of reuse of water, if any: No
12. Water & waste water details during operation phase
Fresh water requirement (KL/day):128 Source of water: Water supply from AMC Waste water generation quantity (KL/day):113 Mode of disposal: Into drainage line of AMC.
13. Status of water supply and drainage line
Available at site
14. Solid waste Management
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste & wet waste
320 Into the bins to be provided for individual units.
The waste will be regularly emptied by AMC through designated contractor
Wet waste 142.08 Green Bins Municipal bins
Details of segregation if to be done: yes Capacity and no. of community bins to be placed within premises: 80 L
and 20 number of community bins to be placed in common areas. Landfill site where waste will be ultimately disposed by local authority:
Nearby municipal solid waste collection / dumping site of AMC. 15. Parking Details Total number of CPS requirement for the project as per NBC :160
Number of CPS requirement for residential units as per NBC: 160 Total Parking area provided (m2) & No. of CPS: 10,545.31 m2 & 337
CPS Parking area provided in basement (m2) & No. of CPS:8,641.66 m2 &
270 CPS Parking area provided in hollow plinth (m2) & No. of CPS:1,903.65 m2 &
67 CPS 16. Traffic
Management Width of adjacent public roads:18 m wide road Number of Entry & Exit provided on approach road/s: Two entry/exit will
be provided. Width of Entry & Exit provided on approach road/s: 7.5 m. Minimum width of open path all around the buildings for easy access of
fire tender (excluding the width for the plantation): 5.0 m Width of all internal roads: 7.5 m & 9.05 m.
17. Details of Green Building measures proposed.
Fly ash paver blocks for pavements/walkways, most of the carpentry structures will be made up of processed engineering wood/ particle board instead of wood, aluminum window frame & marble door frame instead of wood, use of PVC electrical boards & RMC, maximum use of cement
Page 13 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 13 of 76
concrete containing 25 % fly ash etc. 18. Energy
Requirement, Source and Conservation
Power supply: Maximum demand: 1200 KVA Connected load: Source: Torrent Power Limited
DG Sets: No. and capacity of the DG sets:1 x 30 KVA Fuel & its quantity: HSD, 12 litre/hr
19. Fire and Life Safety Measures
During Construction Phase: Personal Protective Equipments like earplugs, dust masks, safety shoes, helmets, hand gloves etc. for all workers, training to use welding shields and follow safer practices, first aid facilities for the workers, use of electrical fittings/equipments meeting with the relevant IS standards, “H” frame scaffolds & ladders made of mild steel, completely concealed copper wiring.
20. Details on staircase Type & no. of buildings
No. of floors Floor area m2
No. of staircase
Width of the staircase (m)
Travel distance (m)
2 blds. 2B+H.P+14 455.04 1 2.0 <30 1 bld. 2B+H.P+14 653.60 1 2.0 <30
21. Rain Water Harvesting (RWH)
No. and depth of percolations wells : 2 nos. Details on Pre-treatment facilities: oil and grease removal and filter.
22. Green area details
Tree covered area (m2) :250.0 Area covered by shrubs and bushes (m2):included in lawn covered area. Lawn covered area (m2):302.16 Total Green Area (m2):552.16 Green Area % of plot area: 10% No. of trees and species to be planted: 80-90 trees of local species like
Neem, Acacia, Gulmohar, Peltoforum, Amaltas within premises. 23. Dust control
measures Temporary windshield/barriers, regular water sprinkling, tarpaulin sheet covers on the material during transportation, maximum use of Ready Mix Concrete (RMC), uniform piling of sand and proper storage to avoid dusting etc.
24.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Allocation of Rs.200 lacs has been made for EMP & EMS.
25. Details of eco friendly building materials
Fly ash bricks, aerated blocks, fly ash paving blocks, maximum use of RMC, lead free paints etc.
26. Details of amenities to be provided to construction workers.
Adequate sanitation facilities, drinking water facility, domestic waste collection facility, Personnel Protective Equipments (PPEs) for the construction workers, first aid facility, compliance of the Construction Worker Cess Act etc.
Page 14 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 14 of 76
27. Documents related to land possession
Copy of village form no. 7 submitted by them shows that the land is in the name of Dreamland Infratech Pvt. Ltd.
During the meeting, it was presented that the number of units to come up in project were 160 as per the online application made by them which has now changed to 164. They have also submitted revised Form – I & IA and revised project plan in this regard. The committee found that the project site is falling in the Transit Oriented Zone (TOZ) as well as in residential zone 2 (R2) as per the zoning certificate obtained from Ahmedabad Municipal Corporation. The projects falling in the TOZ can utilize maximum FSI up to 4.0. It was also noticed that though the NA permission for commercial use has been obtained in the past by the original land owner but as per the zoning certificate, the project site is falling in the residential zone 2 (R2) where the residential activity is permissible activity. After detailed discussion, it was decided to consider the project only after submission of the following:
1. Details with respect to proposed use / disposal of excavated soil. Plan for management, use and disposal of construction debris including excavated materials during the construction phase. Details of top soil management plan during construction phase.
2. Provision of two staircases to open at ground level from the highest point of building [with access from each floor], in each building having floor area more than 500 m2 on each floor.
3. Details on provision of ventilation, lighting arrangements, CO sensors & their functioning etc. in basement.
4. Details of fire fighting system including location of fire water tanks & capacity, separate power
system for fire fighting, automatic sprinkler system, fire detection system with alarms & automatic
fire extinguishers, location of fire lift and fire retardant staircases, details of qualified and trained
fire personnel & their job specifications, distance from nearest fire station & time required to reach
the proposed site etc.
4. Building construction project by Bhanushri Realities.
Survey No: 644, O.P.No/F.P.No:101, TPS No:09 (Uvarasad-Sargasan-Tarapur-Vavol-V.H), At Uvarasad, Dist: Gandhinagar
Screening/ scoping & appraisal.
Details of the proposed project as presented before the committee are described below:
Sr. No.
Particulars Details
1. Proposal is for New Project [SIA/GJ/NCP/59176/2016] 2. Type of Project Residential Project 3. Project / Activity
No. [8(a) or 8(b)] 8(a)
4. Name of the project
"Bhanushri Realities"
5. Name of Developer
Bhanushri Realities
6. Estimated Project Cost (Rs. In Crores)
3500 Lakhs
7. Whether construction work has been initiated at site? If yes, details
No
Page 15 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 15 of 76
thereof 8. Project Details Land / Plot Area (m2) : 13,254.0
Net plot area (m2): 8,615.0 FSI area (m2):19,369.32 Total BUA (m2): 31,624.61
Permissible Proposed FSI Area (m2) 19,383.75 19,369.32 Ground Coverage (m2) --- 3,241.16 Common Plot Area (m2) 861.5 1,008.27 Max. building height (m) -- 24.40
9. Building Details No. of Buildings: 6 Nos. No. of Blocks: 6 Nos. Scope of buildings/blocks: Basement + H.P.+7 Floors No.& size of Residential Units: 152 flats Details of amenities if any:
10. No. of expected residents / users
1000 users with floating population
11. Water & waste water details during construction phase
Water requirement (KL/day):30.0 Source of water: Water supply from Gandhinagar Urban
Development Authority (GUDA) Waste water generation quantity (KL/day): 4.5 Mode of disposal: Into septic tank & soak pit system. Details of reuse of water, if any:
12. Water & waste water details during operation phase
Fresh water requirement (KL/day): 192.0 Source of water: Water supply from GUDA. Waste water generation quantity (KL/day): 167.0 Mode of disposal: Into drainage line of GUDA.
13. Status of water supply and drainage line
Water supply & drainage lines of GUDA area available in the area.
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 1,200 1,200 Green Belt Development
Other excavated earth
14,106 7,052 Internal roads & other paved areas, back filling etc. Remaining will be used for outside road development.
Construction debris
670 670 Back filling & internal road development
Steel scrap 3.10 MT -- Sold to venders Discarded packing materials
325 150 Sold to venders
Page 16 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 16 of 76
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 182 Will be collected into bins
Final disposal through waste collection system of GUDA.
Wet waste 121
Details of segregation if to be done: No Capacity and no. of community bins to be placed within premises:80
Lit capacity & 34 bins. 15. Parking Details Total parking area requirement for the project as per GDCR:3,873.86
m2 Parking area requirement for residential units as per GDCR: 3,873.86
m2 Total number of CPS requirement for the project as per NBC:152
CPS Number of CPS requirement for residential units as per NBC: 152
CPS Total Parking area provided (m2) & No. of CPS: 9,541.53 m2 & 313
CPS Parking area provided in basement (m2) & No. of CPS: 6,300.37 m2 &
197CPS Parking area provided in hollow plinth (m2) & No. of CPS: 3,241.16
m2 & 116 CPS 16. Traffic
Management Width of adjacent public roads: 18.0 m. Number of Entry & Exit provided on approach road/s: 2 entry/exit will
be provided. Width of Entry & Exit provided on approach road/s: 7.50 m. Minimum width of open path all around the buildings for easy access
of fire tender (excluding the width forthe plantation): 3.5 m. Width of all internal roads: 7.50 m.
17. Details of Green Building measures proposed.
Use of energy efficient electrical appliances, maximum use of natural light & ventilation through architectural design, rain water harvesting through ground water recharge, roof top thermal insulation, LED lighting fixtures in the common areas, use of solar energy in external lighting etc.
18. Energy Requirement, Source and Conservation
Power supply: Maximum demand: 1.2MW Connected load: 1.7MW Source: Torrent Power Limited.
Energy saving by Non-conventional Methods: Use of energy efficient electrical appliances, maximum use of natural light & ventilation through architectural design, rain water harvesting through ground water recharge, roof top thermal insulation, LED lighting fixtures in the common areas, use of solar energy in external lighting etc.
DG Sets: No. and capacity of the DG sets: 2 x 120 KVA
Page 17 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 17 of 76
Fuel & its quantity: 30 Lit. / hr. of HSD 19. Fire and Life
Safety Measures Two underground water storage tanks of 100 KL, overhead water tank of 20 KL, fire extinguishers, hose reel, wet riser, manually operated electric fire alarm system.
20. Details on staircase Type & no. of buildings
No. of floors Floor area (m2)
No. of staircase
Width of the staircase (m)
Travel distance (m)
A, B, D & F B+H.P+7 434.49 1 1.50 17.5 C & E B+H.P+7 604.53 1 1.50 25.0
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 150 Ft. No. & dimensions of RWH tank(s) : No. and depth of percolations wells: 02 Nos. Details on Pre-treatment facilities : Desilting & filter chamber.
22. Green area details
Tree covered area (m2) :200 Lawn covered area (m2): 808.0 Total Green Area (m2):1,008.0 m2 Green Area % of plot area:10.00 % No. of trees and species to be planted:200 Nos.
23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Rs. 12 Lacs will be used for the proposed EMP.
24. Proposed dust control measures during the construction phase
Temporary windshield barriers, regular water sprinkling, tarpaulin sheet covers on the material during the transportation, uniform piling of sand and proper storage to avoid dusting.
25. Eco friendly building material usage details.
Use of fly ash paver blocks for pavements/walkways, most of the carpentry structures will be made up of processed engineering wood/ particle board instead of wood, PVC electrical boards, maximum use of Portland Pozzolona Cement (PPC),
26. Details on amenities to be provided to construction workers.
Sanitation facilities, drinking water, municipal solid waste collection facility, first aid facilities.
27. Documents related to land possession.
Copy of village form no. 7& 12 submitted shows that the land for residential use is in the name of land owners and submitted a copy of registered sale deed between the land owners & the project proponent.
During the meeting, the project proponent was suggested to provide two staircases in the buildings having floor area more than 500 m2 on each floor. After detailed discussion, it was decided to consider the project only after submission of the following:
1. Plans showing the Provision of two nos. of staircases in the buildings having floor area more than 500 m2 on each floor as per requirement of the NBC norms.
Page 18 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 18 of 76
5. Building construction project by M/s Shiv Developers
Block No. 261, F.P.No.121, O.P.No. 121, T.P.S.No. 24 ( Mota- Varachha), Surat.
Screening/scoping & appraisal.
Details of the proposed project as presented before the committee are described below:
Sr. No.
Particulars Details
1. Proposal is for New Project [SIA/GJ/NCP/59194/2016] 2. Type of Project Residential & Commercial 3. Project / Activity
No. [8(a) or 8(b)] 8(a)
4. Name of the project
Residential & commercial building construction project by M/s Shiv Developers.
5. Name of Developer
Shiv Developers
6. Estimated Project Cost (Rs. In Crores)
30 Crore
7. Whether construction work has been initiated at site? If yes, details thereof
No.
8. Project Details Land / Plot Area (m2): 10,323.0 FSI area (m2): 20,044.02 Total BUA (m2): 30,753.85
Permissible Proposed FSI Area (m2) 23,071.47 20,044.02 Ground Coverage (m2) 4,490.07 4,391.24 Common Plot Area (m2) 1,032.30 1,035.21 Max. building height (m) -- 15.10 m
9. Building Details No. of Buildings: 08 Nos. No. of Blocks: 15 Nos. Scope of buildings/blocks: Basement + Ground floor (shops & parking)
+ 5 floors No. & size of Residential Units: 294 Nos. (68- 2 BHK & 3 BHK -226) No. & type of Commercial Units: 47 Nos. of Shops Details of amenities if any: -
10. No. of expected residents / users
1323 nos. residential users
11. Water & waste water details during construction phase
Water requirement (KL/day): 15.95 Source of water: Water supply from Surat Municipal Corporation (SMC) Waste water generation quantity (KL/day): 1.15 Mode of disposal: disposal through onsite septic tank and soak pit Details of reuse of water, if any: washing water of construction
equipments will be reused for curing. 12. Water & waste
water details during operation
Fresh water requirement (KL/day): 187.0 Source of water: Water supply from SMC Waste water generation quantity (KL/day): 146.0
Page 19 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 19 of 76
phase Mode of disposal: Disposal through SMC underground sewer line. 13. Status of water
supply and drainage line
Water supply & drainage line of SMC are available in the area.
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 15,974 15,974 Excavated surplus earth and construction debris will be refilled at low lying areas in the project premises and top soil will be used for development of greenbelt.
Other excavated earth
Construction debris
24 24
Steel scrap 3.8 MT 3.04 MT Will be sold to recycler
Discarded packing materials
1 MT -- Will be sold to vendors.
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 794 Kg Will be collected in the bins to be provided to each unit.
Final disposal through SMC. Wet waste
Details of segregation if to be done: The solid wastes generated will be segregated into biodegradable and non-biodegradable wastes and collected in separate bins.
Capacity and no. of community bins to be placed within premises: 140 liter each; 15 nos. of bins;
Landfill site where waste will be ultimately disposed by local authority: M.S.W will be finally transported to the disposal site at Khajod.
15. Parking Details Total parking area requirement for the project as per GDCR: 3,624.31 m2
Parking area requirement for residential units as per GDCR: 3,297.14 m2
Parking area requirement for Commercial units as per GDCR: 327.17 m2.
Total number of CPS requirement for the project as per NBC: 316 nos. Number of CPS requirement for residential units as per NBC: 294 nos. Number of CPS requirement for commercial units as per NBC:22 nos. Total Parking area provided (m2) & No. of CPS: 10,258.04 m2, 346 nos. Parking area provided in basement (m2) & No. of CPS: 5,856.35 m2,
Page 20 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 20 of 76
183 nos Parking area provided in hollow plinth (m2) & No. of CPS: 3,642.22 m2,
130 nos. Parking area provided as open surface (m2) & No. of CPS: 759.47 m2,
33 nos. 16. Traffic
Management Width of adjacent public roads: 18 m wide road Number of Entry & Exit provided on approach road/s: 2 entry/exit will be
provided. Width of Entry & Exit provided on approach road/s: 7.5 m Minimum width of open path all around the buildings for easy access of
fire tender (excluding the width for the plantation): 3 m Width of all internal roads:6 m, 7.5 m
17. Details of Green Building measures proposed.
Maximum utilization of natural light, LED lighting fixtures in common areas, use of solar energy in landscape lighting, rain water harvesting & ground water recharge etc.
18. Energy Requirement, Source and Conservation
Power supply Maximum demand: 1500 KW Connected load: --
Source: D.G.V.C.L Energy saving measures: Maximum utilization of natural light, CFL &
LED lighting fixtures in common areas, use of solar energy in landscape lighting etc.
DG Sets: not proposed. 19. Fire and Life
Safety Measures Fire extinguishers & hose reel at each floor, terrace water tank of 25 KL
on each building block etc. Nearest fire station: Kosad fire station.
Distance from the project site: about 4 km. 20. Details on staircase
Name of Building
Type & no. of buildings
No. of floors
Floor area (m2)
No. of staircase
Width of the staircase(m)
Travel distance (m)
A1 to A6
Joint G + 5 526.74 02 1.20 <30
B1 Joint G + 5 454.61 02 1.20 <30
B2 Single G + 5 362.56 01 1.20 <30
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 80-100 ft No. & dimensions of RWH tank(s) : No. and depth of percolations wells : 3 nos. Details on Pre-treatment facilities : Gravity filter, MOC: PE
22. Green area details
Tree covered area (m2) : 401.77 Area covered by shrubs and bushes (m2): inclusive in lawn area Lawn covered area (m2): 517 Total Green Area (m2): 918.77 Green Area % of plot area: 8.9 % No. of trees and species to be planted: 135 nos. of trees like Asopalav,
Gulamhor, Palm, Ficus, Badam, Neem etc.
Page 21 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 21 of 76
23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Sr. No.
Description Capital Cost (Rs. In
Lacs) 1 Landscaping 7 Lacs 2 Groundwater Recharge Structure 7 Lacs 3 Solar Energy Utilization 5 lacs 4 Energy Efficient Lighting 2 lacs 5 Solid Waste Management 4 lacs 6 Monitoring of Air, Water, Noise & Soil 0.75 lacs
Total 25.75 Lacs
24. Proposed dust control measures during the construction phase
Vertical curtails, water sprinkling, covering the building materials with the tarpaulin sheet etc.
25. Eco friendly building material usage details.
Fly ash based bricks, Ready Mix Concrete, A.C.C Blocks will be used.
26. Amenities for the construction workers.
Sanitation facility, drinking water & tap water, soak pit for domestic waste water collection, first aid box, free medicine, doctor service, PPEs etc.
27. Documents related to land possession.
Copy of Village form no 7 submitted by them shows that the land for residential use is in the name of M/s shiv developers.
During the meeting, it was presented that no construction activity has been started for the proposed project. It was found that the parking area proposed in the hollow plinth is actually not available as per the project plan submitted by them. Further the project proponent was suggested to increase the parking area for the project. After detailed discussion, it was decided to consider the project only after submission of the following:
1. Explore the possibility of increasing the parking area provision for the project. Revised parking area provision details based on the actual parking area available in hollow plinth and proposed increase in parking space.
2. Details of the D.G. sets including fuel, quantity, stack height, location as well as the acoustic measures proposed to abate noise pollution.
6. Building Construction project by Mr. K. P. Patel
Block . No.185, F.P.No. 60, O.P.No.60, T.P.S.No.- 35 (Kumbhariya-Saroli-Saniya Hemand-Devadh), Ta - Choryasi, Dist. - Surat.
Screening/scoping.
Details of the proposed project as presented before the committee are described below:
Sr. No.
Particulars Details
1. Proposal is for New Project [SIA/GJ/NCP/59195/2016] 2. Type of Project Commercial 3. Project / Activity
No. [8(a) or 8(b)] 8(a)
4. Name of the project
K. P. Patel
5. Name of Mr. K. P. Patel
Page 22 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 22 of 76
Developer 6. Estimated
Project Cost (Rs. In Crores)
35 Crore
7. Whether construction work has been initiated at site? If yes, details thereof
No
8. Project Details Land / Plot Area (m2): 9,098 FSI area (m2): 36,218.49 Total BUA (m2): 54,812.23
Permissible Proposed FSI Area (m2) 36,392.0 36,218.49 Ground Coverage (m2) 4,549.0 4,366.73 Common Plot Area (m2) 909.80 910.60 Max. building height (m) - 44.52
9. Building Details No. of Buildings: 1 Nos. No. of Blocks: 1Nos. Scope of buildings/blocks: 2 level basement + ground floor +8 floors No. of residential units:--- No. of commercial units: 329 Shops
10. No. of expected residents / users
1316 nos. Commercial Users
11. Water & waste water details during construction phase
Water requirement (KL/day): 10.3 Source of water: Water supply from Surat Urban Development
Authority (S.U.D.A.) Waste water generation quantity (KL/day): 1.20 Mode of disposal: Onsite sanitation facilities (septic tank/ soak Pit) will
be provided during the construction phase. 12. Water & waste
water details during operation phase
Total water requirement (KL/day): 56.0 Fresh water requirement (KL/day): 35.0 Source of water: Water supply from Surat Urban Development
Authority (SUDA) Waste water generation quantity (KL/day):48.0 Mode of disposal: Sewage to be generated will be treated in the
proposed onsite STP. Treated sewage will be reused for gardening & flushing purpose within premises and remaining will be discharged into the underground drainage line of SUDA.
In case of STP provision, capacity of STP: Yes, 50 KL/day STP Technology: MBBR based Biological Treatment Purposes for treated water utilization: Gardening & flushing. Quantity of treated water to be reused:
1.Gardening (KL/day):1.0 2. Flushing (KL/day): 20.0
Provision of dual plumbing system (Yes/No): yes
Page 23 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 23 of 76
Quantity and type (treated/untreated)of sewage to be discharged: Sewage to be generated will be treated in the proposed onsite STP. Treated sewage will be reused for gardening & flushing purpose within premises and remaining will be discharged into the underground drainage line of SUDA.
Mode of disposal: As above. 13. Status of water
supply and drainage line
Water supply & drainage line of SUDA are available in the area.
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 97,169 97,169 Excavated surplus earth and construction debris will be refilled at low lying areas in the project premises and top soil will be used for development of greenbelt.
Other excavated earth
Construction debris
85 85
Steel scrap 7.6 MT 7.04 MT Will be sold to scrap vendor
Discarded packing materials
1 MT -- Will be sold to vendors.
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 394 Kg Into separate bins to be provided for dry & wet waste
Collection & final disposal through SUDA.
Wet waste
STP Sludge 15 Kg/Week Dewatering will be done through Sludge Drying Bed.
Dry sludge will be used as manure in gardening.
Details of segregation if to be done: The solid wastes generated will be segregated into biodegradable and non-biodegradable wastes and collected in separate bins.
Capacity and no. of community bins to be placed within premises: 140 liter each; 10 nos. of bins;
Landfill site where waste will be ultimately disposed by local authority:
Page 24 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 24 of 76
Final disposal at Khajod disposal site 15. Parking Details Total parking area requirement for the project as per GDCR: 18,109.25
m2 Parking area requirement for commercial units as per GDCR:
18,109.25 m2 Total number of CPS requirement for the project as per NBC: 724 nos. Number of CPS requirement for commercial units as per NBC: 724
nos. Total Parking area provided (m2) & No. of CPS: 18,757.59 m2, 608 nos. Parking area provided in basement (m2) & No. of CPS: 13,162.50 m2,
411 nos. Parking area provided as open surface (m2) & No. of CPS: 1,867.37
m2, 81 nos. Parking area provided (at any other place-specify) (m2) & No. of CPS:
Mechanical – 3,727.72 m2, 116 nos. 16. Traffic
Management Width of adjacent public roads: 24.0 & 9.0 m wide road Number of Entry & Exit provided on approach road/s: 2 nos. Width of Entry & Exit provided on approach road/s: 9 m & 6 m Minimum width of open path all around the buildings for easy access of
fire tender (excluding the width for the plantation): 5 m Width of all internal roads: 6 m & 9 m
17. Details of Green Building measures proposed.
Maximum utilization of natural light, LED lighting fixtures in common areas, use of solar energy in external lighting, rain water harvesting & ground water recharge, provision of STP & reuse of treated sewage etc.
18. Energy Requirement, Source and Conservation
Power supply Maximum demand: 2000 KVA Connected load: --
Source: D.G.V.C.L Energy saving measures: Maximum utilization of natural light, CFL &
LED lighting fixtures in common areas, use of solar energy in external lighting, aerated block [Cement + Fly Ash + Air mixture will be used to reduce heat stress inside building etc.
DG Sets: No. and capacity of the DG sets: 1 x 250 KVA
Fuel & its quantity: Diesel, 12 Lit./hr. 19. Fire and Life
Safety Measures Fire extinguisher, hose reel, wet riser, automatic sprinkler system in basement, manually operated electric fire alarm system, underground water tank of 300 KL capacity, terrace tank of 75 KL capacity etc.
20. Details on staircase Name of Building
No. of floors
Floor area
No. of staircase
Width of the staircase(m)
Travel distance (m)
A 2B+G + 8 3,867.85 02 2.00 <30
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 50-100 ft No. and depth of percolations wells : 3 nos., 40 m Details on Pre-treatment facilities : Gravity filter, MOC: PE
22. Green area details
Tree covered area (m2) : 341.63
Page 25 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 25 of 76
Area covered by shrubs and bushes (m2): inclusive in lawn area Lawn covered area (m2): 568.97
Total Green Area (m2): 910.60
Green Area % of plot area: 3.75 % No. of trees and species to be planted: 115 nos. of trees like
Asopalav, Gulamhor, Palm, Ficus, Badam, Neem tree etc. 23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Sr. No.
Description Capital Cost (Rs. In
Lacs) 1 Landscaping 12 Lacs 2 Groundwater Recharge Structure 7 Lacs 3 Solar Energy Utilization 4 lacs 4 Energy Efficient Lighting 2 lacs 5 Solid Waste Management 2 lacs 6 Monitoring of Air, Water, Noise & Soil 0.75 lacs 7 Sewage Treatment Plant 10 Lacs
Total 37.75 Lacs
24. Proposed dust control measures during the construction phase
Vertical curtails, water sprinkling, covering the building materials with the tarpaulin sheet etc.
25. Eco friendly building material usage details.
Fly ash based bricks, Ready Mix Concrete, A.C.C Blocks will be used.
26. Amenities for the construction workers.
Sanitation facility, drinking water & tap water, soak pit for domestic waste water collection, first aid box, free medicine, doctor service, PPEs etc.
27. Documents related to land possession.
Copy of village form no. 7 submitted by them shows that the land for residential use is in the name of applicant.
During the meeting, it was presented that earlier environmental clearance was granted for residential project at this site. Further it was clarified that they have not started any kind of construction activity for the project even as per the Environmental Clearance obtained earlier. During the discussion, the project proponent stated that they now want to change the scope & planning of the project from completely residential to completely commercial building construction project and hence they want to surrender the earlier Environmental Clearance. In such a case the committee decided to consider the application for the proposed project as a fresh application and asked the project proponent to surrender their Environmental Clearance No.SEIAA/GUJ/EC/8(a)/170/2013 dated 05/07/2013 to SEIAA Gujarat & request them for cancellation of the EC. After detailed discussion it was decided to appraise the project further only after submission of the following:
1. Revised details with increased parking area provision for the project along with the parking plans & back up calculations.
2. Copy of permission obtained from the concerned competent authority for the proposed FSI.
3. Plans showing provision of staircases, the floor area & maximum travel distance of the staircase from the farthest corner of the floor and distance between the two consecutive staircases.
4. Minimum fire water requirement for the proposed project based on the fire study.
5. A notarized undertaking stating that any kind of manufacturing activity will not be allowed in the
Page 26 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 26 of 76
commercial units of the proposed project and any commercial unit will not be sold / allotted for storage of chemicals, flammable substances, explosives, fire crackers or any other material of hazardous characteristics.
6. Perspective view of the building(s) to be constructed along with the materials used such as fibers, glass, etc. on the facades or external walls and the impacts thereof on the nearby buildings / residents due to heat island effect and emissions from the air conditioning systems.
7. Details of mechanical parking to be provided (also including its operation, maintenance, energy consumption, appointing trained personnel’s etc.) in the basement along with the feasibility of providing mechanical parking considering the basement height.
8. Details on provision of ventilation, lighting arrangements, CO sensors & their functioning etc. in basement.
9. Details on common amenities like drinking water facility, sanitary blocks, first aid facilities etc. to be provided at each floor.
10. Details on solar energy utilization for the proposed project.
11. Status of surrendering & cancellation of the earlier environmental clearance No.SEIAA/GUJ/EC/ 8(a)/170/2013 dated 05/07/2013.
7. Building construction project by M/s Shiv Infra Space
F.P.No.31, T.P.S.No.34, Jagatpur, Ahmedabad.
Screening/scoping & appraisal.
Details of the proposed project as presented before the committee are described below:
Sr. No. Particulars Details 1. Proposal is for New Project [SIA/GJ/NCP/59200/2016] 2. Type of Project Residential & commercial building construction project
3. Project / Activity No. [8(a) or 8(b)]
8 (a)
4. Name of the project
Residential & commercial building construction project
5. Name of Developer
Shiv Infra Space
6. Estimated Project Cost (Rs. In Crores)
Rs. 65 Crore
7. Whether construction work has been initiated at site? If yes, details thereof
No
Page 27 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 27 of 76
8. Project Details Land / Plot Area (m2): 12,495 FSI area (m2): 33,579.30 Total BUA (m2): 52,126.48
Permissible Proposed FSI Area, (m2) --- 33,579.30 Ground Coverage, (m2) --- 3,720.04 Common Plot Area, (m2) 1,249.50 1,251.60 Max. building height, (m) - 46.53
9. Building Details No. of Buildings: 9 No. of Blocks: 9 Scope of buildings/blocks: 5 buildings – basement + ground floor
(parking & shops) + 12 floors. 4 buildings – basement + hollow plinth+ 12 floors.
No. of Residential units: 416 No. commercial units: 47
10. No. of expected residents / users
2221 persons
11. Water & waste water details during construction phase
Water requirement (KL/day): 39 Source of water: Local water tankers Waste water generation quantity (KL/day): 3 Mode of disposal: Septic tank to soak pit Details of reuse of water, if any: No
12. Water & waste water details during operation phase
Total water requirement (KL/day): 286.0 Fresh water requirement (KL/day): 191.0 Source of water: water supply from AMC Waste water generation quantity (KL/day): 223.0 Mode of disposal: Sewage to be generated will be treated in the
proposed onsite STP. Treated sewage will be used for gardening & flushing purpose within premises and remaining quantity of treated sewage will be discharged into the drainage line of AMC.
In case of STP provision, capacity of STP: Yes 230.0 KL/day STP Technology: STP with MBR. Purposes for treated water utilization: Gardening and Flushing Quantity of treated water to be reused:1.Gardening (KL/day):5.0, 2.
Flushing (KL/day): 90.0 Provision of dual plumbing system (Yes/No): yes Quantity and type (treated/untreated) of sewage to be discharged:
Treated sewage will be used for gardening & flushing purpose within premises and remaining quantity of treated sewage will be discharged into the drainage line of AMC.
Mode of disposal: As above. 13. Status of water
supply and drainage line
Water supply & drainage line of AMC will be available during operation phase of the project.
14. Solid waste Management
Construction Phase: Description Generation
(kg/day) Quantity to be reused (kg/day)
Mode of Disposal / Reuse
Page 28 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 28 of 76
Top Soil 6.0 100 % reuse For garden development
Other excavated earth
22.0 50 % reuse for back filling & plinth filling.
Remaining quantity will be send to the nearest collection point of AMC
Construction debris
85.0 30% reuse for pavement & internal road sub base.
Remaining quantity will be send to the nearest collection point of AMC
Steel scrap 8.0 30% will be reused
Remaining will be sold to recyclers or vendors.
Discarded packing materials
1.5 - Will be sold to vendors.
Total Solid Waste - 50 workers x 500 gm/person/day = 25 kg/day
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste -Papers, cartons, thermocol, plastic, polythene bags, glasses etc.
Wet waste -Waste vegetable and food
1500
Organic waste and In organic waste will be collected in different buckets.
The recyclable waste will be sold to recyclers. The non recyclable solid waste will be transferred to the nearest collection point of AMC
Details of segregation if to be done: collection of organic and inorganic waste will be in different buckets and it will be subsequently collected by AMC
Capacity and no. of community bins to be placed: No of Bins: 50; Volume of Bins: 80 lit. each for residential units and 4 bins of 80 lit. capacity for commercial units.
Landfill site where waste will be ultimately disposed by local authority: At the nearby MSW collection point of AMC.
15. Parking Details Total parking area requirement for the project as per GDCR: 7,150.82 m2.
Total parking area requirement for residential units as per GDCR: 6,478.29 m2
Total parking area requirement for the commercial units as per GDCR: 672.53 m2
Total number of CPS requirement for the project as per NBC: 470
Page 29 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 29 of 76
Total number of CPS requirement for residential units as per NBC : 416
Total number of CPS requirement for the commercial units as per NBC: 54
Total Parking area provided (m2) & No. of CPS: 13,502.19 m2 & 464 CPS
Parking area provided in basement (m2) & No. of CPS: 9,103.72 m2 & 284 CPS.
Parking area provided in hollow plinth (m2) & No. of CPS: 1,301.47 m2 & 46 CPS.
Parking area provided as open surface parking (m2) & No. of CPS: 3,097.0 m2 & 134 CPS.
16. Traffic Management
Width of adjacent public roads: 30 m & 12 m wide TPS Road Number of Entry & Exit provided on approach road/s: 2 gates will be
provided. Width of Entry & Exit provided on approach road/s: 7.5 m Minimum width of open path all around the buildings for easy
access of fire tender (excluding the width for the plantation): 5 m Width of all internal roads: 7.5 m
17. Details of Green Building measures proposed.
The transformers and motors will be provided having minimum efficiency of 85%. Use of LED or solar lights in the common area. Use of light colors for walls & ceiling to reduce the light absorption and minimize the cooling requirement. Rain water harvesting through ground water recharge.
18. Energy Requirement, Source and Conservation
Power supply: Maximum demand: 750 KW Connected load: -
Source: Torrent Power Limited Energy saving measures: The transformers and motors will be
provided having minimum efficiency of 85%. Use of LED or solar lights in the common area. Use of light colors for walls & ceiling to reduce the light absorption and minimize the cooling requirement. Rain water harvesting through ground water recharge.
DG Set: 1 × 65 KVA Fuel & it quantity: HSD-50 lit/day
19. Fire and Life Safety Measures
Fire extinguishers will be providing on each floor.
20. Details on staircase Type & no. of buildings
No. of floors
Floor area (m2)
No. of staircase
Width of the staircase(m)
Max. Travel distance (m)
A + H + I B+G+12 1,098.75 3 2.52 <20 B,C,D,E & F B+G+12 263.59 1 2.52 <20
G B+G+12 366.37 1 2.52 <20
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 35 m below ground level No. and depth of percolations wells: 4 nos. Details on Pre-treatment facilities : No
22. Green area details
Tree covered area (m2) : 750 Area covered by shrubs and bushes (m2): --- Lawn covered area (m2): 501 Total Green Area (m2): 1,251.0
Page 30 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 30 of 76
Green Area % of plot area: 10 % No. of trees and species to be planted: 188 trees of local species.
23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Total Rs. 23 lacs for MSW management, sewage disposal, greenbelt development, rain water harvesting & ground water recharge etc.
24. Proposed dust control measures during the construction phase
Water spraying, PUC compulsion for vehicles, covered shed for cement loading activity, covering all the loose material with tarpaulin during stacking & transportation etc.
25. Eco friendly building material usage details.
Use of Ready Mix Concrete (RMC)
26. Details of basic amenities to be provided to construction workers.
Drinking water, sanitary facility, free of cost doctor service, all the required personal protective equipments etc.
27. Documents related to land possession
Copy of village form no. 7 submitted shows that the land for residential & commercial use is in the name of M/s Shiv Infra Space.
Details of STP were presented & discussed during the meeting. After detailed deliberation, it was decided to consider the project only after submission of the following:
1. Copy of permission obtained or authentic supporting documents showing the availability of the proposed FSI to the project.
2. Revised details with increased parking area provision for the project with parking plans & back up calculation.
3. Details of first aid / fire fighting and other emergency services to be provided during construction phase and operation phase including the training to be provided to the residential staff of the project as first aid providers, fire fighters etc.
4. Details on solar energy utilization for the proposed project and calculation showing how much of the total energy requirement for the project will be compensated / met by the proposed energy conservation measures.
5. Detailed Environment Management Plan with respect to various environmental attributes- Air, Noise, Solid wastes including Hazardous Wastes, land, water including sewage treatment & reuse etc. of the project both during construction and operation phase and strategy for its implementation with financial outlay.
8. Samirbhai M. Kalariya – Residential project
S.No.11/1/P/1, T.P.S.No.16, O.P.No.16, F.P.No.16, Village: Raiya, Dist: Rajkot.
Appraisal
The project was earlier taken up in the meeting of SEAC held on 25/05/2016. During the meeting held on 25/05/2016, the project proponent was suggested to provide STP and to use solar energy at the extent possible. After detailed discussion, it was decided to appraise the project only after submission
Page 31 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 31 of 76
of the following:
1. Proposal for providing STP for the project and details of Sewage Treatment Plant with its capacity, size of each unit, retention time and its location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation phase. STP sludge management plan. Design details of dual plumbing system to be provided for reuse of treated sewage within premises.
2. Revised details on water requirement and sewage generation for the project considering reuse of treated sewage for gardening & flushing. Design drawing of dual plumbing system.
3. Details on solar energy utilization for the proposed project.
4. Source of availability of water supply, drainage connection & municipal solid waste collection facility to the proposed project and permission or letter of intent from concerned competent authority in this regard.
5. Details of main approach road to the proposed project site or T.P.scheme map showing the availability of the approach road to the proposed project site.
6. Copy of permission obtained from Airports Authority of India for the proposed building height.
7. Details of soil excavation / filling required for the project along with its quantification based on backup calculations. Details with respect to proposed use / disposal of excavated soil. Plan for management, use and disposal of construction debris including excavated materials during the construction phase. Details of top soil management plan during construction phase.
Project proponent submitted the above mentioned details to this office on 15/09/2016.
The project proponent along with their expert/consultant attended the meeting. During the meeting, the project was appraised based on the details submitted as well as facts presented before the committee.
It was presented that STP of 175 KL/day capacity will be installed for treatment of sewage to be generated during the operation phase. Treated sewage will be used for gardening (8 KL/day) & flushing (49 KL/day) purpose within premises and remaining quantity of treated sewage will be discharged into the drainage line of Rajkot Municipal Corporation. Due to reuse of treated sewage, fresh water requirement will be reduced to 124 KL/day. It is proposed to install solar panels to run street lights on solar power. It was mentioned that the project site is covered in the limits of Rajkot Municipal Corporation and hence the water supply & drainage lines, which are already available in the area, will be available to the project during the operation phase. Copy of T.P. Scheme map showing the project location & main 12 m wide approach road to the project site has been submitted. They have submitted a copy of permission obtained from Airports Authority of India for permissible top elevation of 179.41 m above mean sea level i.e 57.4 m above the ground level. Top soil (1300 m3) to be generated will be completely used for gardening & tree plantation purpose within premises. Excavated earth (4,610 m3) will be completely used for back filling & plot levelling.
Salient features of the project are as under: Sr.No.
Particulars Details
1. Proposal is for New Project [SIA/GJ/NCP/53091/2016] 2. Type of Project Residential project 3. Project/Activity No.
[8(a) or 8(b)] 8 (a)
4. Name of the project Residential scheme to be developed by Mr. Samirbhai M Kalaria
Page 32 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 32 of 76
5. Name of Developer Samirbhai M Kalaria 6. Estimated Project
Cost (Rs. In Crores)
95 crore
7. Whether construction work has been initiated at site? If yes, details thereof.
Construction work has not started.
8. Project Details Land /Plot Area (m2): 16,884.0 FSI area (m2):37,967.77 Total BUA (m2):47,952.71
Permissible Proposed
FSI Area (m2) --- 37,967.77 Ground Coverage (m2) 4,558.20 3,950.59 Common Plot Area (m2) 1,690.0 1,690.0 Max. building height (m) --- 39.4
9. Building Details No. of Buildings:7 No. of Blocks: 7 Scope of buildings/blocks: Basement + hollow plinth + 13 floors. No.& size of Residential Units:336 flats No. & type of Commercial Units: NA
10. No. of expected residents / users
Resi.-1350 users including floating population
11. Water & waste water details during construction phase
Water requirement (KL/day):30.0 Source of water: Water supply from Rajkot Municipal
Corporation (RMC). Waste water generation quantity (KL/day):4.5 Mode of disposal: Into septic tank & soak pit. Details of reuse of water, if any:N.A.
12. Water & waste water details during operation phase
Total water requirement (KL/day):181.0
Fresh water requirement (KL/day): 124.0
Source of water: Water supply from Rajkot Municipal Corporation (RMC).
Waste water generation quantity (KL/day): 163.0
Mode of disposal: Sewage to be generated will be treated in the proposed onsite STP. Treated sewage will be reused for gardening & flushing purposes within premises and only remaining quantity of treated sewage will be discharged into the drainage line of Rajkot Municipal Corporation (RMC).
In case of STP provision, capacity of STP: 175.0 KL/day
Purposes for treated sewage utilization: Flushing & Gardening
Quantity of treated water to be reused:1.Gardening(KL/day): 8.0, 2. Flushing (KL/day): 49.0
Provision of dual plumbing system (Yes/No): Yes
Quantity and type (treated/untreated) of water to be
Page 33 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 33 of 76
discharged: Sewage to be generated will be treated in the proposed onsite STP. Treated sewage will be reused for gardening & flushing purposes within premises and only remaining quantity of treated sewage will be discharged into the drainage line of Rajkot Municipal Corporation (RMC).
Mode of disposal: as above. 13. Status of water
supply and drainage line
Water supply & drainage line will be provided by RMC.
14. Solid waste Management
Construction phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top soil 1,300 1,300 Will be completely used for gardening & tree plantation.
Other excavated earth
4,610
4,610
Will be used for back filling & plot levelling.
Construction debris
1,150 1,150 Will be used for back filling & plot levelling.
Steel scrap
Whatsoever Whatsoever Will be sold to vendors.
Discarded packing materials
Whatsoever Whatsoever Will be sold to vendors.
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste
collection
Mode of Disposal /Reuse
Dry waste 404 Into bins to be provided within premises.
Through agency appointed by RMC.
Wet waste 268 Into bins to be provided within premises.
Through agency appointed by RMC.
Details of segregation if to be done: No Capacity and no. of community bins to be placed within
premises: Total 42 bins with 80 lit capacity will be provided for all the residential blocks.
Landfill site where waste will be ultimately disposed by local authority: at the nearest MSW dumping / landfill site of RMC.
15. Parking Details Total parking area requirement for the project as per GDCR: 7,593.55 m2.
Parking area requirement for residential units as per GDCR:
Page 34 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 34 of 76
7,593.55 m2. Total number of CPS requirement for the project as per
NBC:336 CPS Number of CPS requirement for residential units as per NBC:
336 CPS Total Parking area provided (m2) & No. of CPS: 10,539.34 m2 &
408 CPS. Parking area provided in hollow plinth (m2) & No. of CPS:
4,012.87 m2 & 143 CPS. Parking area provided as open surface (m2) & No. of CPS:
5,056.13 m2 & 219 CPS. Parking area provided (Basement) (m2) & No. of CPS: 1,470.64
m2 & 46 CPS. 16. Traffic Management Width of adjacent public roads: Site is accessible by 12 m wide
approach road. Number of Entry & Exit provided on approach road/s: 2 gates
will be provided. Width of Entry & Exit provided on approach road/s:12 m & 7.5 m Minimum width of open path all around the buildings for easy
access of fire tender (excluding the width for the plantation): 8 m Width of all internal roads:12 m & 7.5 m
17. Details of Green Building measures proposed.
Fly ash/PPC will be used in concrete, paving blocks and any cement applications. Lead free paint & enamels will be used for painting wooden and metal surfaces. Provision of CFL/LED lights & solar panels to run street lights.
18. Energy Requirement, Source and Conservation
Power supply: Paschim Gujarat Vij Company Ltd. Maximum demand: 728 KW Connected load: 728 KW
Source: Paschim Gujarat Vij Company Ltd. Energy saving measures: Use of energy efficient electrical
appliances, maximum use of natural light through proper building orientation etc.
% of saving with calculations:Small units & we have not calculated
Compliance of the ECBC guidelines (Yes / No),if yes, compliance in tabular form:Small units & we have not calculated
DG Sets:2 x 120 KVA No. and capacity of the DG sets:2 x 120 KVA Fuel & its quantity:HSD-30 lit/hr.for each
19. Fire and Life Safety Measures
Dedicated underground & terrace water tanks for fire fighting, fire extinguishers, fire alarms, hose reels, external hydrants & wet risers, automatic sprinkler system in basement, pumping arrangement system-riser with pressure pump, first aid box, displaying of important telephone numbers etc.
Name of the nearest fire station: Ramdevpir sub fire station Distance from the project site: About 3 Km
Time required by the fire tender to reach the project site:5-10
Page 35 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 35 of 76
minutes. 20. Details on staircase:
Type of block
No. of floors
Floor area (m2)
Maximum travel distance (m)
Number of Stair case
Width of Stair case in (m)
4 blds. B+H.P.+13 427.09 <15 1 2.0
3 blds. B+H.P.+13 388.94 <15 1 2.0
21. Rain Water Harvesting (RWH)
Level of the Ground water table:35-40 m BGL No. & dimensions of RWH tank(s):Nil No. and depth of percolations wells:4 nos. of percolating wells. Details on Pre-treatment facilities :--
22. Green area details Tree covered area (m2):1,575.0 Area covered by shrubs and bushes (m2):-- Lawn covered area (m2):115.0 Total Green Area (m2):1,690.0 Green Area % of plot area:10% No. of trees and species to be planted:50
23. Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Allocation of Rs. 14.5 lacs has been proposed for water sprinklers, barricades, waste water & waste management, provision of PPEs etc. during the construction phase. Capital cost of Rs. 26.0 lacs and recurring cost of Rs. 6 lacs has been proposed for installation of energy efficient appliances, green belt development, rain water harvesting & ground water recharge, waste water management, solid waste management etc. during the operation phase.
24. Dust control measures
Water sprinkling, maintaining roads & trees to avoid dust generation etc.
25. Eco friendly building material usage details.
Fly ash & pozzolana cement will be used in concrete, paving blocks and any cement applications. Lead free paint, enamels will be used for painting wooden and metal surfaces.
26. Details of basic amenities to be provided to construction workers.
Adequate sanitation facilities, drinking water, bins for collection of municipal solid waste.
27. Documents related to land possession.
Village form no. 7 & 6 submitted by them show that the N.A land for residential use is in the name of Mr. Samirbhai M. Kalariya & others. Copy of deed of association of persons (all the land owners), registered with the Sub-Registrar Rajkot – 4 [Raiya], has been submitted.
During the meeting, after detailed discussion, it was decided to recommend the project to SEIAA Gujarat for granting Environment Clearance subject to the strict compliance of the following project specific conditions as well as the standard conditions finalized during the meeting of SEAC held on 09/09/2015 for building construction projects falling under project activity no. 8(a) as per the schedule of the EIA Notification 2006:
CONSTRUCTION PHASE :
WATER: 1. Fresh water requirement during the construction phase shall be 30.0 KL/day and it shall be met
Page 36 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 36 of 76
through the water supply from Rajkot Municipal Corporation (RMC). No ground water shall be tapped during the construction phase.
2. Sewage generated during the construction phase shall be disposed off through septic tank & soak pit system.
OPERATION PHASE:
WATER: 3. Total water requirement during the operation phase shall be 181.0 KL/day, out of which 124.0
KL/day of fresh water requirement shall be met through the water supply from Rajkot Municipal Corporation (RMC). Remaining water requirement of 57.0 KL/day for flushing and gardening purposes shall be met by reuse of treated sewage from the proposed onsite STP. No ground water shall be tapped during the operation phase. Metering of the water shall be done and its records shall be maintained.
4. The sewage generation during the operation phase shall be 163.0 KL/day, which shall be treated in the proposed sewage treatment plant (STP) of adequate capacity. The STP shall be operated regularly and efficiently so as to achieve the GPCB norms at the STP outlet.
5. Treated sewage conforming to GPCB norms shall be reused within the premises for gardening & flushing purpose at the maximum extent possible. Only remaining quantity of treated sewage shall be discharged into the drainage line of from Rajkot Municipal Corporation (RMC).
6. A proper logbook of STP operation and also showing the quantity of treated sewage reused in flushing, gardening and quantity discharged into the drainage line etc. shall be maintained and furnished to the GPCB from time to time.
7. Dual plumbing system with separate tanks and lines shall be provided for utilization of treated sewage for flushing.
8. No new bore well shall be constructed and existing bore well/s, if any, shall be either sealed or converted into the recharge well.
9. Rain water harvesting from rooftop and paved areas and ground water recharge through 4 nos. of percolation wells shall be carried out as per the details submitted. Before recharging the runoff, pre-treatment must be done to remove suspended matter.
AIR: 10. D. G. sets (2 × 120 KVA) proposed as backup power shall be of enclosed type and confirm to
prescribe standards under EPA rules. Necessary acoustic enclosures shall be provided at diesel generator set to mitigate the impact of noise.
11. The gaseous emissions from the D.G. Sets shall conform to the standards prescribed under EPA Rules as amended from time to time. At no time, the emission levels shall go beyond the stipulated standards.
12. The stack height of the D.G.sets shall be equal to the height needed for the combined capacity of all proposed D.G.sets
SOLID WASTE: 13. The solid waste generated shall be properly collected and segregated at source. The recyclable
material shall be sold to vendors whereas other garbage shall be disposed off properly as per the provisions made by the Rajkot Municipal Corporation (RMC).
SAFETY: 14. All the staircases and lifts shall open out at ground level from the highest point of building [with
access from each floor] for emergency evacuation. Two staircases shall be provided in each building having floor area more than 500 m2 on each floor.
Page 37 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 37 of 76
15. Fire fighting facilities like dedicated underground & terrace water tanks for fire fighting, fire extinguishers, fire alarms, hose reels, external hydrants & wet risers, automatic sprinkler system in basement, pumping arrangement system-riser with pressure pump, first aid box, displaying of important telephone numbers etc. shall be provided as proposed.
16. In basement at least two separate ramps of adequate width and slope shall be provided, located preferably at opposite ends.
17. Provision for adequate air changes per hour in the basement shall be made so as to avoid build up of CO in the area.
18. Car park exhaust system equipped with CO (Carbon Monoxide) sensor shall be provided to ensure operation of exhaust fans as CO concentration levels.
PARKING / TRAFFIC CONGESTION: 19. Minimum parking space of 10,539.34 m2 [1,470.64 m2 in basement + 4,012.87 m2 in hollow plinth
+ 5,056.13 m2 as open surface parking] shall be provided as proposed. ENERGY CONSERVATION: 20. Energy conservation measures viz. provision of CFL/LED lights, solar panels to run street lights,
use of energy efficient electrical appliances, maximum use of natural light through proper building orientation etc. shall be implemented as proposed.
GREEN BELT: 21. Green belt area of 1,690.0 m2 comprising of 1,575.0 m2 tree covered area shall be developed as
proposed. The other open spaces inside the plot shall be suitably landscaped and covered with vegetation of indigenous tree species.
9 SIA/GJ/IND2/17286/2016 M/s: Sigma Laminates Plot no. 3410, GIDC-Chattral, Kalol, Dist.: Gandhinagar
Screening & Scoping
Project / Activity No.: 5(f)
M/s: Sigma Laminates (herein after Project Proponent – PP) has submitted application vide their proposal no. SIA/GJ/IND2/17286/2016 dated 16/09/2016.
Project status: New/Expansion
Project / Activity Details:
This is a new unit proposes the manufacturing of Synthetic organic chemicals as tabulated below: Sr. no.
Name of the Products Quantity (MT/Month)
Existing Proposed Total 1 Laminated Sheets 450 - 450
2 Urea Formaldehyde Resin - 200 200
3 Melamine Formaldehyde Resin - 50 50
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Total plot area is 3228 sq. m. PP has proposed to develop greenbelt in nearby villages as per
requirement. Expected project cost for proposed project is INR. 2 Crores. Water requirement for the
Page 38 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 38 of 76
proposed project will be 22 KL/day (2 KL for Domestic, 22 KL for Industrial Purpose) and it will be met
through GIDC water supply. Industrial waste water generation will be 6.4 KL/day, which will be treated
in proposed Primary treatment plant followed by evaporator to achieve Zero Liquid Discharge.
Domestic waste water (1.8 KL/day) will be disposed off into septic tank/soak pit system. Briquettes to
the tune of 4.5 MT/day shall be used in the Boiler (5 TPH). Multi Cyclone dust collector followed by Bag
filter will be provided as APCM for Boiler. HSD to the tune of 18 ltrs/day shall be used in the stand-by
DG set (100 KVA Capacity). ETP waste (20 MT/Annum) will be disposed off at the Common TSDF site.
Resin waste / edge cutting waste (0.81 MT/Annum) will be disposed off at the CHWIF. Discarded
barrels / containers / bags / liners (9 MT/Annum) will be either reused or returned back to suppliers or
sold only to the authorized vendors after decontamination. Used oil will be sold only to the registered
recyclers.
Observations & Discussions: Technical presentation made during the meeting by project proponent. While discussing about the
waste water management, PP informed that industrial waste water mainly generated from boiler &
washing will be collected & evaporated after primary treatment to achieve zero liquid discharge.
Committee noted that there is no process gas emission from the proposed project.
During meeting Project proponent has requested to consider the project as B2 category project.
Looking to the low pollution potential and location of the proposed site, the request was considered and
the project was categorized as B2 and the additional information was sought for appraisal of the
project.
1. Copy of plot holding Certificate.
2. Demarcation of proposed activities in lay out plan. Exact details about infrastructural facilities,
plant machineries etc. required for the proposed project.
3. Detailed manufacturing process along with chemical reactions and mass balance (including
reuse-recycle, if any) for each product to be manufactured. Details on end use of each product.
Give full name and chemical formula of all the raw materials and products.
4. Copy of permission obtained from concern authority for water supply.
5. Water consumption and consumption of each raw material per MT of each product.
6. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative
analysis of the each waste stream to be generated. A detailed treatability study vis-à-vis the
adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated.
7. Treated effluent management plan during monsoon season when utilization of treated effluent
for gardening & plantation purpose is not feasible. Detailed study report considering Percolation
rate of the land available for gardening & plantation. Ensure that land is suitable for utilization of
treated waste water for plantation & gardening.
8. Technical details of the ETP including size of each unit, retention time etc.
9. Action plan for ‘Zero’ discharge of effluent shall be included. Give qualitative and quantitative
data with feasibility report for reuse of Mother Liquor in process again. Submit an undertaking in
this regard.
10. Plan for management and disposal of waste streams to be generated from spillage, leakages,
occasional reactor washing and exhausted media from Scrubber etc.
11. Explore the possibility of reuse / recycle and other cleaner production options for reduction of
Page 39 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 39 of 76
wastes. Details of methods to be adopted for the water conservation.
12. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air
pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air
pollution control measures for process gas emission measures to achieve the GPCB norms (iv)
Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue
gas emission rate emission from each utility (vii) Air Pollution Control Measures proposed to
each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its
quantification and proposed measures to control it.
13. Details on management of the hazardous wastes to be generated from the project stating detail
of storage area for each type of waste, its handling, its utilization and disposal etc. How the
manual handling of the hazardous wastes will be minimized. Explore the possibilities for co-
processing of the Hazardous waste/Solid waste prior to disposal into TSDF/CHWIF.
Methodology of de-contamination and disposal of discarded containers and its record keeping.
14. Membership of Common Environmental Infrastructure including TSDF, Common Hazardous
Waste Incineration Facility (CHWIF) along with an assessment to accommodate the additional
quantity of wastes to be generated.
15. Complete Management plan for By-products/spent acid to be generated, (if any) from the
project including their quantity, quality, characteristics, end use etc. along with the name and
address of end consumers to whom the by-product will be sold. Copies of agreement / MoU /
letter of intent from them, showing their willingness to purchase said by-products/spent acids
from the proposed project.
16. Name and quantity of each type of solvents to be used for proposed production. Details of
solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of
reusing the recovered solvents etc. for each type of solvent. Leak detection and repairing
programme (LDAR)for VOC
17. Data on air emissions, wastewater generation and solid / hazardous waste generation and
management for the existing plant should also be incorporated. (Comparative data in tabular
format).
18. Details of measures proposed for the noise pollution abatement and its monitoring.
19. A detailed EMP including the protection and mitigation measures for impact on human health
and environment as well as detailed monitoring plan and environmental management cell
proposed for implementation and monitoring of EMP. The EMP should also include the concept
of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural
resource conservation. Total capital cost and recurring cost/annum earmarked for environment
pollution control measures.
20. Occupational health impacts on the workers and mitigation measures proposed to avoid the
human health hazards along with the personal protective equipment (PPE) to be provided to the
workers. Provision of industrial hygienist and monitoring of the occupational injury to workers as
well as impact on the workers. Plan for periodic medical check up of the workers exposed.
Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.
21. Details of hazardous characteristics and toxicity of raw materials and products to be handled
Page 40 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 40 of 76
and the control measures proposed to ensure safety and avoid the human health impact. MSDS
of all the products and raw materials to be used. Permission from PESO, Nagpur for storage of
solvents, other toxic chemicals, if any.
22. Details of quantity of each hazardous chemical to be stored, material of construction of major
hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture,
Storage & Import of Hazardous Chemicals (MSIHC) Rules of major hazardous chemicals.
23. Details of the separate isolated storage area for flammable chemicals. Details of flame proof
electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control
plan for flammable substances and processes showing hydrant pipeline network, provision of
DG Sets, fire pumps, jockey pump, toxic gas detectors etc.
24. Risk assessment including prediction of the worst-case scenario and maximum credible
accident scenarios should be carried out. The worst-case scenario should take into account the
maximum inventory of storage at site at any point of time. The risk contours should be plotted
on the map clearly showing which of the facilities and surrounding units would be affected in
case of an accident taking place. Based on the same, proposed safeguard measures including
On-Site / Off-Site Emergency Plan should be provided.
25. Details of fire fighting system including provision for flame detectors, temperature actuated heat
detectors with alarms, automatic sprinkler system, location of fire water tanks & capacity,
separate power system for fire fighting, details of qualified and trained fire personnel & their job
specifications, nearest fire station & time required to reach the proposed site. Submit line
diagram of the fire hydrant network.
26. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,
manufacturing utility staff for safety related measures.
27. Detailed five year greenbelt development program including annual budget, types & number of
trees to be planted, area under green belt development [with map], budgetary outlay; along with
commitment of the management to carry out the tree plantation activities outside the premises
at appropriate places in the nearby areas and elsewhere.
28. A tabular chart with index for point-wise compliance of above.
The project shall be appraised after satisfactory submission of the aforesaid additional details
10 SIA/GJ/IND2/17334/2016 M/s: Bliss Industries Plot No. 824/29 & 30, GIDC-Jhagadia, Dist.: Bharuch.
Screening & Scoping
Project / Activity No.: 5(f)
M/s: Bliss Industries (herein after Project Proponent – PP) has submitted application vide their proposal no. SIA/GJ/IND2/17334/2016 dated 20/09/2015.
Project status: New
Project / Activity Details:
This is a new unit proposes the manufacturing of Synthetic organic chemicals as tabulated below:
Sr. No.
Name of the Products Capacity
(TPM)
Page 41 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 41 of 76
1. Meta Dinitro Benzene 50.00
2. Meta Phenyline Diamine 35.00
3. Meta Uriedo Aniline 39.00
4. 5-Chloro-8-Quinolinol 30.00
5. 5-Chloro-2-Hydroxy Aniline or 3-Chloro-4-Hydroxy Aniline
51.00
6. 2,5-Dichloro Nitro Benzene or 2,3-Dichloro Nitro Benzene
90.00
7. Isatoic Anhydride 20.00
8. Methyl Anthranilate or Butyl Anthranilate or Ethyl Anthranilate
125.00
9. 5-Chloro-2-Hydroxy Nitro Benzene or 3-Chloro-4-Hydroxy Nitro Benzene
20.00
10. 3-Nitro Acetophenone 51.00
11. 3-Amino Acetophenone 30.00
12. 3-Hydroxy Acetophenone 15.00
13. 3-Amino-4-Hydroxy Nitro Benzene 30.00
Total 586.00
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006. Total plot area is 7886 sq. m & unit has proposed 1694 sq m area for the green belt development/ Tree plantation. Expected project cost is INR. 4.9 Crores.
Source of Water Supply GIDC Water consumption ( 132 KL/day) Industrial: 122
Domestic: 5 Gardening: 5
Waste water generation (KL/day) Industrial: 104.7 Domestic: 4
Treatment facility with capacity (ETP, CETP, MEE, STP etc).
Effluent Treatment Plant Stripper followed by Multiple Effect Evaporator
Mode of Disposal & Final meeting point
Domestic: The domestic wastewater will be discharged into soak pit through septic tank. Industrial: Treated effluent from ETP will be discharged into underground drainage system of NCT.
Reuse/Recycle details (KL/day) -- Details of flue gas emission:
Sr. No.
Stack Attached to Utility
Type of Fuel Height
(m) Dia. (m)
Concn. of Polluants
Air Pollution Control Mesures
Page 42 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 42 of 76
1 Steam Boiler
(1 No. x 2 TPH + 1 No. x 1 TPH)
Agrowaste/ Biofuel &/OR
Coal 30.0 1.50
PM ≤ 150 mg/Nm3
SO2 ≤ 100 ppm
NOx ≤ 50 ppm
Individual Cyclone Separator followed by
common Bag filter
2 Thermic Fluid
Heater (2 Nos. x 4 Lac Kcal/Hr)
Agrowaste/ Biofuel &/OR
Coal 30.0 1.00
Individual Cyclone Separator followed by
common Bag filter
3 DG Set (350
KVA), Stand-by Diesel 7.0 0.15 Adequate stack height
Details of Gaseous Emissions from Process
Product Code
Product Expected Pollutants
Gaseous Pollutant Load
Kg/ batch
Kg/kg TPM
1 Meta Dinitro Benzene SO2 gas 5.0 0.004 0.21
NO2 gas 5.0 0.004 0.21
6 2,5-Dichloro Nitro Benzene &/OR 2,3-Dichloro Nitro Benene
SO2 Gas 5.0 0.004 0.35
NO2 Gas 5.0 0.004 0.35
10 3-Nitro Acetophenone NO2 Gas 25.0 0.015 0.75
12 3-Hydroxy Acetophenone HCl Gas 50.0 0.050 0.75
Details of Process Gas Stack & APCM
Sr. No.
Stack attached to Reactor
Ht. & Dia. (m)
Pollutant Concentration,
mg/Nm3
Air Pollution Control Equipment
1st Stage 2nd Stage
1. Reactor of products- 1, 6 & 10
4 & 0.3 SO2<40 NO2 < 25
Alkali Scrubber (A) <Output to
ETP>
Alkali Scrubber (B) <Output to
ETP>
2. Reactor of product-12 4 & 0.3 HCl < 20
Water Scrubber (C) HCl for
captive consumption
Alkali Scrubber (D) <Output to
ETP>
Hazardous waste management : Sr. no.
Type of wastes Quantity MT/Annum
Mode of Disposal
1 ETP Sludge 150 TSDF 2 Iron Sludge 5429 TSDF or Co-processing 3 Distillation Residue 32 CHWIF or Co-processing 4 Organic Waste 122 CHWIF or Co-processing 5 Spent Carbon 268 CHWIF or Co-processing 6 Sodium Thiosulfate 5100 Actual authorised end-users or
send to Common MEE of ETL. 7 Spent Sulfuric Acid 3151 Actual authorised end-users 8 Discarded Drums/ Bags 10 Decontamination and sold to
authorised recyclers. 9 Spent Oil/ Used Oil 200 To registered re-processors.
Page 43 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 43 of 76
Discussions & Observations: Technical presentation made during the meeting by project proponent. Committee noted that PP has proposed two options for treatment of industrial effluent. Upon asking, PP informed that initially the membership of NCT was not obtained and they have put two options. Now they got membership from NCT for waste water discharge and new pipeline will be commissioning within few months. PP requested to consider their proposal with effluent discharge into GIDC pipeline as ZLD is not viable for proposed project which was agreed to by the Committee. Committee put emphasis on maximum reuse of waste water by segregation of effluent at source and to minimize discharge of waste water. After detailed deliberations on various aspects of the project following TORs were prescribed in addition to the draft TOR proposed, to carry out EIA study covering 10 km radius from the project boundary of the proposed site :
1. Copy of plot holding certificate obtained from GIDC Jaghadia.
2. Present land use pattern of the study area shall be given based on satellite imagery.
3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all
round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders
without reversing back. Mark the same in the plant layout.
4. Technical details of the plant/s along with details on best available technologies (BAT),
proposed technology and reasons for selecting the same.
5. Details of manufacturing process / operations of each product along with chemical reactions,
mass balance, consumption of raw materials etc. Details on strategy for the implementation of
cleaner production activities.
6. Chemical name of each proposed product to be manufactured. Details on end use of each
product.
7. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative
and quantitative analysis of the each waste stream from the processes.
8. Assessment of source of the water supply with adequacy of the same to meet with the
requirements for the project. Permission obtained from the GIDC for supply of raw water.
Undertaking stating that no bore well shall be dug within the premises.
9. Explore the possibility of reuse / recycle and other cleaner production options for reduction of
wastes. Details of methods to be adopted for the water conservation.
10. Qualitative and quantitative analysis of waste water to be generated from the manufacturing
process of each product to be manufactured along with mass balance.
11. Segregation of waste streams and details on specific treatment and disposal of each stream
including action plan for maximum recycle of treated waste water and minimum discharge.
12. Action plan for reuse of waste streams like spent sulphuric acid, Sodium Thiosulfate etc. within
premises to convert into valuable products instead of sending outside to actual end-users.
13. Details of ETP including dimensions of each unit along with schematic flow diagram. Inlet,
transitional and treated effluent qualities with specific efficiency of each treatment unit in
reduction in respect of all concerned/regulated environmental parameters. Inlet effluent quality
should be based on worst case scenario considering production of most polluting products that
can be manufactured in the plant concurrently.
14. Copy of permission letter with quantity from the concern authority of drainage network (for NCT
pipeline) regarding confirmation for spare capacity available to take additional effluent drainage
Page 44 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 44 of 76
pipeline.
15. Proposal to provide and maintain separate electric meter, operational logbook for effluent
treatment systems, online meters for monitoring of flow, pH, TOC/COD, etc. of effluent
discharge.
16. Application wise break-up of effluent quantity to be recycled / reused in various applications like
sprinkling for dust control and green belt development etc. In case of land application, details on
availability of sufficient open land for utilizing effluent for plantation / gardening. How it will be
ensured that treated effluent won't flow outside the premises linked with storm water during high
rainy days.
17. Economical and technical viability of the effluent treatment system.
18. Undertaking stating that a separate electric meter will be provided for the ETP.
19. Characteristics of the combined effluent and treated water to be sent to Common pipeline with
reference to the GPCB discharge norms.
20. Application wise break-up of effluent quantity to be recycled / reused in various applications like
sprinkling for dust control and green belt development etc. In case of land application, details on
availability of sufficient open land for utilizing effluent for plantation / gardening. How it will be
ensured that treated effluent won't flow outside the premises linked with storm water during high
rainy days.
21. Plans for management, collection and disposal of waste streams to be generated from spillage,
leakages, vessel washing, used container washing etc. Measures proposed for preventing
effluent discharge during unforeseen circumstances.
22. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly
wind speed and direction and rainfall should be incorporated.
23. Anticipated environmental impacts due to the proposed project/production may be evaluated for
significance and based on corresponding likely impacts VECs (Valued Environmental
Components) may be identified. Baseline studies may be conducted within the study area of 10
km for all the concerned/identified VECs and likely impacts will have to be assessed for their
magnitude in order to identify mitigation measures.
24. One complete season base line ambient air quality data (except monsoon) to be given along
with the dates of monitoring. The parameters to be covered shall be in accordance with the
revised National Ambient Air Quality Standards as well as project specific parameters.
Locations of the monitoring stations should be so decided so as to take into consideration the
pre-dominant downwind direction, population zone and sensitive receptors. There should be at
least one monitoring station in the upwind direction. There should be at least one monitoring
station in the pre dominant downwind direction at a location where maximum ground level
concentration is likely to occur.
25. Modeling indicating the likely impact on ambient air quality due to proposed activities. The
details of model used and input parameters used for modeling should be provided. The air
quality contours may be shown on location map clearly indicating the location of sensitive
receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should
also be indicated on the map. Impact due to vehicular movement shall also be included into the
Page 45 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 45 of 76
prediction using suitable model. Results of Air dispersion modeling should be superimposed on
satellite Image / geographical area map.
26. Base line status of the noise environment, impact of noise on present environment due to the
project and proposed measures for noise reduction including engineering controls.
27. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air
pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air
pollution control measures for process gas emission measures to achieve the GPCB norms (iv)
Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue
gas emission rate emission from each utility (vii) Air Pollution Control Measures proposed to
each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its
quantification and proposed measures to control it (ix) Details on tail gas treatment.
28. Action plan for odour control to be submitted.
29. Details on management of the hazardous wastes to be generated from the project stating detail
of storage area for each type of waste, its handling, its utilization and disposal etc. How the
manual handling of the hazardous wastes will be minimized. Methodology of de-contamination
and disposal of discarded containers and its record keeping.
30. Membership of Common Environmental Infrastructure including the TSDF / Common
Incineration Facility, Common effluent discharge pipeline etc.
31. Complete management plan for By-products/Spent acids to be generated, along with the name
and address of end consumers to whom the by-product/s will be sold. Copies of agreement /
MoU / letter of intent from them, showing their willingness to purchase said by-products/Spent
acids from the proposed project.
32. Sound management for Spent Sulphuric acid, Spent HCl, effluent generated from scrubbing
system etc.
33. Undertaking regarding in-house treatment of Aluminium Chloride solution and no disposal
outside premises in any case.
34. Name and quantity of each type of solvents to be used for proposed production. Details of
solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of
reusing the recovered solvents etc. for each type of solvent.
35. A detailed EMP including the protection and mitigation measures for impact on human health
and environment as well as detailed monitoring plan and environmental management cell
proposed for implementation and monitoring of EMP. The EMP should also include the concept
of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural
resource conservation. Total capital cost and recurring cost/annum earmarked for environment
pollution control measures.
36. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.
37. Occupational health impacts on the workers and mitigation measures proposed to avoid the
human health hazards along with the personal protective equipment to be provided. Provision of
industrial hygienist and monitoring of the occupational injury to workers as well as impact on the
workers. Plan for periodic medical checkup of the workers exposed. Details of work place
ambient air quality monitoring plan as per Gujarat Factories Rules.
Page 46 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 46 of 76
38. Details on volatile organic compounds (VOCs) from the plant operations and occupational
safety and health protection measures.
39. Risk assessment including prediction of the worst-case scenario and maximum credible
accident scenarios should be carried out. The worst-case scenario should take into account the
maximum inventory of storage at site at any point of time. The risk contours should be plotted
on the plant layout map clearly showing which of the facilities would be affected in case of an
accident taking place. Based on the same, proposed safeguard measures including On-Site /
Off-Site Emergency Plan should be provided.
40. MSDS of all the products and raw materials.
41. Details of hazardous characteristics and toxicity of raw materials and products to be handled
and the control measures proposed to ensure safety and avoid the human health impacts. This
shall include the details of Antidotes also.
42. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of
Construction of major hazardous chemical storage tanks, dyke details, threshold storage
quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules
of major hazardous chemicals, size of the biggest storage tank to be provided for each raw
material & product etc. How the manual handling of the hazardous chemicals will be minimized?
43. Details of the separate isolated storage area for flammable chemicals. Details of flame proof
electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control
plan for flammable substances and processes showing hydrant pipeline network, provision of
DG Sets, fire pumps, jockey pump, toxic gas detectors etc.
44. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,
manufacturing utility staff for safety related measures.
45. Detailed five year greenbelt development program including annual budget, types & number of
trees to be planted, area under green belt development [with map], budgetary outlay; along with
commitment of the management to carry out the tree plantation activities outside the premises
at appropriate places in the nearby areas and elsewhere.
46. Detailed socio-economic development measures including community welfare program most
useful in the project area for the overall improvement of the environment. Submit a detailed plan
for social corporate responsibilities, with appropriate budgetary provisions for the next five years
and activities proposed to be carried out; specific to the current demographic status of the area.
47. (a) Does the company have a well laid down Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA report. (b). Does the Environment Policy prescribe
for standard operating process / procedures to bring into focus any infringement / deviation /
violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.
48. What is the hierarchical system or administrative order of the company to deal with the
environmental issues and for ensuring compliance with the EC conditions. Details of this
system may be given.
49. Does the company have a system of reporting of non compliances / violations of environmental
norms to the Board of Directors of the company and / or shareholders or stakeholders at large?
This reporting mechanism should be detailed in the EIA Report.
Page 47 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 47 of 76
50. Phase wise project implementation schedule with bar chart and time frame, in terms of site
development, infrastructure provision, EMS implementation etc.
51. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should
be incorporated in the EIA Report.
52. A tabular chart with index for point-wise compliance of above TORs.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be considered as
generic TORs for preparation of the EIA report in addition to all the relevant information as per the
generic structure of EIA given in Appendix III in the EIA Notification, 2006. The project shall be
appraised on receipt of the final EIA report.
Validity of ToR: The ToRs prescribed for the project will be valid for a period of three years for submission of EIA &
EMP report accordingly, ToR will lapse after 23/10/2019.
The period of validity could be extended for a maximum period of one year provided an application
is made by the applicant to the Regulatory Authority, at least three months before the expiry of
valid period together with an updated Form-I, based on proper justification and also
recommendation of the SEAC.
11 SIA/GJ/IND2/17333/2016 M/s: Kandla LPG import terminal, Indian Oil Corporation Limited (IOCL), K.K. Road, Kandla, Dist. Kutchh
Screening & Scoping
Project / Activity No.: 6(b)
M/s: Kandla LPG import terminal (herein after Project Proponent – PP) has submitted application vide their proposal no. SIA/GJ/IND2/17333/2016 dated 21/09/2016.
Project status: Expansion
Project / Activity Details:
This is an existing unit engaged in storage and bottling of LPG Sr. no.
Product Existing Proposed Total
1 Propane* 15000 MT In 1 no. of cryogenic tank
15000 MT In 1 no. of cryogenic tank
30000 MT
2 Butane* 15000 MT In 1 no. of cryogenic tank
15000 MT In 1 no. of cryogenic tank
30000 MT
3 LPG / Propane**
300MT in 2X150MT Mounded bullets
1200MT in 2X600MT each in Phase I 1200MT in 2X600MT each in Phase II
2700 MT
The project falls under Category B of project activity 6(b) as per the schedule of EIA Notification 2006.
Total plot area is 671078 sq. m & unit has provided 153742 sq m area for the green belt
development/Tree plantation. Proposed project is within the existing land. Expected project cost is INR.
671 Crores. Gujarat Pollution Control Board Gandhinagar has issued Consent & Authorisation vide
Consent Order No. AWH 56516 vide letter reference PC/CCA-KUTCH-33/GPCB ID 17880/159992,
Page 48 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 48 of 76
dated 18.09.2013 for receiving, storage & distribution of petroleum product i.e LPG which is valid up to
20.05.2018.
Sr. No.
Description
Water Consumption (KL/Day)
Waste Water Generation (KL/Day)
Existing Proposed Total Existing Proposed Total
I Domestic 20.0 20.0 40.0 1.5 2.5 4.0
II Industrial process I/c boiler feed
70.0 70.0 140.0 40.0 40.0 80.0
Total 90.0 90.0 180.0 41.5 42.5 84.0
Fresh water will be met through Narmada water supply. Domestic waste water (4 KL/day) will be
disposed off into septic tank/soak pit system. Flue gas emission from existing DG sets and existing
Fire hydrant pumps. Fuel consumption will be 250 Lit/day (existing) +250 Lit/day (proposed) for boiler
and 160Lit/Hr (existing) for DG set as backup + 160Lit/Hr Proposed. No process gas emission. Used
oil will be sold only to the registered recyclers. Other hazardous wastes and Solid wastes will be
handled as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules
2016
Observations & Discussions: Technical presentation during the meeting included details of project including its need, demand-
supply gap, location map, site plan, water consumption, waste water generation, air emission details,
DG set requirement, proposed quantity of the LPG, Butane and propane, power requirement, details of
hazardous waste etc. While asking about CRZ applicability for the proposed expansion, PP informed
that their activity falls outside the CRZ area. However, PP could not furnished authenticated documents
regarding non-applicability of CRZ Notification 2011. Committee noted that the proposed project is to
expansion in receiving Propane, Butane & LPG through ocean tankers and dispatches the blended
product as LPG to different parts of the country through pipeline. Proposed additional storage facilities
will be within the existing LPG import terminal land. However, new pipeline from Jetty to plant or
modification in the existing pipeline will be carried out. After deliberation on various aspects, following
additional TOR was prescribed for the EIA study covering 5 km radius of the project boundary.
1. Land use pattern for the study area.
2. CRZ clearance from the competent authority.
3. Copy of Notified Port area mentioning proposed unit is located in the notified port area.
4. Details of breather valves to be provided on the storage tanks.
5. Permission from PESO-Nagpur for design of layout, pipelines, instrumentation etc.
6. Submit details of Mutual Aid Plan with other neighbouring units in the area keeping in view the
hazardous nature of operations.
7. Details of hazardous characteristics and toxicity of raw materials and products to be handled
and the control measures proposed to ensure safety and avoid the human health impact.
8. Details of quantity of each hazardous chemical to be stored, material of construction of major
hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture,
Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals.
Page 49 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 49 of 76
9. Details of hazardous processes and their engineering controls.
10. Details of possibility of occupational health hazard from the proposed activities and proposed
measures to prevent it.
11. Detailed mass balance and water balance (including reuse-recycle with source details if any)
along with stream wise waste water generation quantity & quality as well as their disposal &
treatment plan.
12. Details of ETP including dimensions of each unit along with schematic flow diagram. Inlet,
transitional and treated effluent qualities with specific efficiency of each treatment unit in
reduction in respect of all concerned/regulated environmental parameters. Mode of disposal
and its impact on environment.
13. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly
wind speed and direction and rainfall should be incorporated.
14. Anticipated environmental impacts due to the proposed project/production may be evaluated for
significance and based on corresponding likely impacts VECs (Valued Environmental
Components) may be identified. Baseline studies may be conducted within the study area of 5
km for all the concerned/identified VECs and likely impacts will have to be assessed for their
magnitude in order to identify mitigation measures.
15. One complete season base line ambient air quality data (except monsoon) to be given along
with the dates of monitoring. The parameters to be covered shall be in accordance with the
revised National Ambient Air Quality Standards as well as project specific parameters (SO2,
NOx, PM10, PM2.5, VOC, Methane, CO2 etc.). The locations of the monitoring stations should
be so decided so as to take into consideration the pre-dominant downwind direction, population
zone and sensitive receptors. There should be at least one monitoring station in the upwind
direction. There should be at least one monitoring station in the pre dominant downwind
direction at a location where maximum ground level concentration is likely to occur.
16. Impact of the project on the AAQ of the area. Details of the model used and the input the
parameters used for modeling should be provided. The air quality contours may be plotted on a
location map showing the location of project site, habitation, sensitive receptors, if any. The
wind roses should also be shown on this map.
17. Details on noise levels at sensitive/commercial receptors.
18. Specific details of (i) Process emission from each unit process as well as emission from the
storage tanks with its quantification, (ii) Air pollution Control Measures proposed with technical
specifications (iii) Adequacy of the air pollution control measures to achieve the GPCB Norms
(iv) Details of the utilities required (v) Flue gas emission rate emission from the utilities along
with stack height calculation (v) Air Pollution Control Measures proposed for the utilities along
with its adequacy (vi) Sources of fugitive emission from the unit along with its quantification and
proposed measures to control it.
19. Measures proposed to be taken for the work area ambient air quality monitoring as per Gujarat
Factories Rules.
20. Details of relocation of trees planned from the plot if any and detailed greenbelt development
program including annual budget, types & number of trees to be planted, area under green belt
Page 50 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 50 of 76
development [with map]; along with commitment of the management to carry out the tree
plantation activities outside the premises at appropriate places in the nearby area and
elsewhere.
21. A detailed EMP including the protection and mitigation measures for impacts on human health
and environment as well as detailed environmental monitoring plan with respect to various
parameters, environmental management cell proposed for implementation & monitoring of EMP
as well as person responsible for the same. This shall include the details of antidotes also.
22. Detailed risk assessment report including the identification of the most hazardous activity, its
sub activity, prediction of the worst-case scenario and maximum credible accident scenario,
catastrophic failure along with damage distances and preparedness plan to combat such
situation and risk mitigation measures. Vulnerable zone demarcation. Detailed fire control plan
for flammable substances and processes. Environment Management Plan and On-Site / Off-
Site emergency plan including mock drills for the proposed plant.
23. Details of management of the solid waste and hazardous wastes to be generated from the
project stating detail of storage area for each type of waste, its handling and its disposal. How
the manual handling of the hazardous wastes shall be minimized.
24. Details of decontamination process of mercaptan container and its associated environment
management plan.
25. To explore the use of renewable energy to the maximum extent possible.
26. Detailed cleaner production measures to reduce w/w qty, reuse / recycle option if possible in the
proposed project & commitment of the management on futuristic development / implementation
for the same. Also provide details for the use of lead free paints for storage tanks/LPG bottles in
the proposed project.
27. Specific safety details / precautionary measures proposed for VOC’s in the plant / storage area /
warehouse/ including ventilation aligned in the natural wind direction.
28. HAZOP study.
29. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as
impact on the workers.
30. A tabular chart for the issues raised and addressed during public hearing/consultation and
commitment of the project proponent on the same should be provided. An action plan to
address the issues raised during public hearing and the necessary allocation of funds for the
same should be provided.
31. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure
notices etc. served by the GPCB to the existing unit in last five years and actions taken then
after for prevention of pollution.
32. Copies of Environmental Clearances obtained for the existing plant, its point wise compliance
report.
33. Environmental audit reports for last 3 years and compliance of its
recommendations/Suggestions. (Include latest audit report and its compliance.)
34. Copy of Consent to Operate (CC&A) obtained along with point wise compliance status of all the
conditions stipulated therein.
Page 51 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 51 of 76
35. Being an expansion project, compliance of MoEF circulars vide No: J-11011/618/2010-IAII(I)
dated 30/05/2012 and J-11013/41/2006-IA-II(I) dated 20/10/2009
36. Copies of XGN generated Inspection reports with analysis reports of the water/Air/Hazardous
samples collected by GPCB (Last 2 years). Copies of instructions issued by GPCB in last 2
years and point wise compliance thereof.
37. Details of disaster management plan / emergency management systems during operational
phase of the project should also include scenario of natural catastrophe like earth quake, floods
in addition to other disasters. The plan should include the details of (i) Emergency evacuation
(ii) Emergency lighting system (iii) details of power back up system in the case of emergency
(iv) fire fighting arrangements (v) first aid arrangement (vi) Training and Mock drill
(vii)Emergency announcement or public address system (viii)Signage’s including fluorescent
pathways/ exit marker signs (ix)Location of emergency pathways and glow light signs. (x)
Emergency response procedures.
38. Details of first aid, fire fighting system and other emergency services to be provided during
operation phase including the training to be provided to the staff of the project as first aid facility
providers, fire fighters etc. Tie up with emergency services like local fire station, emergency van
etc. to be made during the operational phase.
39. Details of automatic fire detection and fire fighting system at project site including provision for
flame detectors, temperature actuated heat detectors, location of fire water tanks & capacity
based on fire study, separate power system for fire fighting, automatic sprinkler system, fire
detection system with alarms & automatic fire extinguishers, details of qualified and trained fire
personnel & their job specifications, nearest fire station & time required to reach the proposed
site. Submit line diagram of the fire hydrant line passing through the plant premises. Fire control
plan for flammable substances and processes based on the flammable area classification.
40. Undertaking stating that sufficient peripheral open passage shall be kept for accessibility of fire
tender/ emergency vehicles around the premises.
41. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary
provisions.
42. The project shall be appraised on satisfactory submission of the above mentioned details.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for Isolated Storages and Handling of Hazardous Chemicals shall
be considered as generic TORs for preparation of the EIA report in addition to all the relevant
information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The
draft EIA report shall be submitted to the Gujarat Pollution Control Board for conducting the public
consultation process as per the provisions of the EIA Notification, 2006. The project shall be appraised
on receipt of the final EIA report.
Validity of ToR: The ToRs prescribed for the project will be valid for a period of three years for submission of EIA &
EMP report accordingly, ToR will lapse after 23/10/2019.
The period of validity could be extended for a maximum period of one year provided an application
is made by the applicant to the Regulatory Authority, at least three months before the expiry of
Page 52 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 52 of 76
valid period together with an updated Form-I, based on proper justification and also
recommendation of the SEAC.
12 SIA/GJ/IND2/17266/2016 M/s: Rageshwari Textiles Pvt. Ltd. Plot.no. 272/C & D, B+F, Pandesara-GIDC, Dist.: Surat.
Screening & Scoping
Project / Activity No.: 5(f)
M/s: Rageshwari Textiles Pvt. Ltd. (herein after Project Proponent – PP) has submitted application vide their proposal no. SIA/GJ/IND2/17266/2016 dated 22/09/2015.
Project status: New
Project / Activity Details:
This is a new unit proposes the manufacturing of Synthetic organic chemicals as tabulated below:
Sr. no.
Name of the Products Quantity MT/Month
1. Copper Phthalocyanine Blue 200 2. Pigment Phthalocyanine Aplha Blue 55 3. Pigment Phthalocynine Beta Blue 145 4. Ammonium Sulphate (By-Product) 207
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Total plot area is 4483.05 sq. m & unit has proposed 1427.80 sq m area for the green belt
development/Tree plantation. Expected project cost is INR. 568 Crores. Water requirement for the
proposed project will be 98 KL/day. Industrial waste water generation will be 68.6 KL/day, which will be
treated in proposed treatment plant followed by MEE and treated waste water will be reused to achieve
Zero Liquid Discharge. Domestic waste water (7.5 KL/day) will be disposed off into septic tank/soak pit
system.
Discussions/Observations: Technical presentation made during the meeting by project proponent. Committee discussed about the
technology of the process, treatability of waste water, process emission & its control etc. Committee
noted that the Pandesara GIDC is now surrounded by residential pockets of Surat city and the
proposed products are highly polluted with respect to Air, Water and Hazardous. Looking to the product
profile, while concerning about the problems of treatability of concentrated effluent & its disposal issues
being faced in present scenario, Committee was of view that such products having high pollution
potential should not be allowed in GIDC – Pandesara which is a part of Surat city. Further Committee
asked to remove products having high pollution potential and to submit revised proposal with Pigment
Phthalocynine Beta Blue, which was agreed to by the project proponent. Considering the above facts, it
was unanimously decided to consider the project for TOR/Scoping only after satisfactory submission of
the following: (1) Revised proposal with sound environmental management system including Complete
Zero Liquid Discharge.
13 SIA/GJ/IND2/17114/2016 M/s: Bharuch Enviro Infrastructure Limited P.No.911/C, Jhagadia Industrial Estate, Dist: Bharuch
Screening & Scoping
Project / Activity No.: 7(d)
Page 53 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 53 of 76
M/s: Bharuch Enviro Infrastructure Limited – BEIL (herein after Project Proponent – PP) has submitted application vide their proposal no. SIA/GJ/IND2/17114/2016 dated 28/09/2016.
Project status: New
Project / Activity Details:
M/s.: Bharuch Enviro Infrastructure Limited (BEIL) has proposed to establish a TSDF site at plot no.
911/C within the Jhagadia Industrial estate, Dist.: Bharuch. PP has acquired 87226.31 sq. m land for
the development of Common Hazardous Waste Treatment, Storage and Disposal Facility (TSDF site).
The proposed activity falls under Category B of project activity 7(d) as per the EIA Notification 2006.
Total area proposed for greenbelt/tree plantation is 17445.26 sq. m. Total area for land filling cell will be
39080 sq. m and total capacity of the site will be 10 Lacs MT. Total no.s of Cell will be 06 (Six). It is
reported that no ecosensitive zone (National Park, Wildlife sanctuary, biosphere reserve, wild life
sanctuary is located within 10 km distance. Nearest residential area of village Taladara is @ 0.75 km
from the proposed project site. Expected project cost is Rs. 77.65 Cr. Water requirement for operation
phase will be 350 KLPD. From which 30 KLD for the domestic use and balancing will be used for the
green belt & gardening. Leachate generation: (KL/day): for initial Two years leachate generation will be
10 KL / Day and in following 3rd and 4th Years leachate generation quantity will increase to 20 KL /
Day. Leachate will be sent to MEE plant at BEIL, Ankleshwar. There will be no discharge of waste
water within or outside premises. Domestic wastewater (10KL/day) will be disposed off in Septic
Tank/Soak Pit. Unit has proposed two DG sets (125 KVA each) as stand by facility. HSD (3 KL/Month)
will be used as a fuel for DG sets. Hazardous waste suitable for landfill and if generator has obtained
authorization under the Hazardous and Other Wastes (Management and Transboundary Movement)
Rules 2016, waste will be weighed, sampled and then sent inside TSDF cell for unloading. Quick test
will be carried out of each consignment of waste and Only if the sample passes through quick tests, it
will be allowed to enter the disposal site. Compaction and levelling will be carried out regularly.
Manifest system as per CPCB guideline will be followed. Transportation of Hazardous Solid Waste
from Generation Site to TSDF will be carried out through authorized transporter with dedicated vehicles
with online tracking system (GPS) and covered from top having the name plate with details of
company’s name, address, phone no., etc. The TSDF will have Leachate collection wells. Leachate will
be pumped from Leachate wells by pipeline and will be sent to Common MEE of M/s: BEIL,
Ankleshwar for treatment and disposal. Hazardous wastes/solid wastes to be generated from their own
activities will be handled as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Discussions/Observations:
Technical presentation made during the meeting by project proponent. During meeting, the project
proponent presented that they have started baseline environmental monitoring from November 2016
and requested to allow them to use the same for the preparation of the EIA report which was agreed to
by the committee. The project proponent was further asked to follow all the relevant guidelines of MoEF
and CPCB for setting up and operation of the hazardous waste landfill sites. After deliberation on
various issues, following additional TORs were prescribed for the EIA study to be carried out for
proposed TSDF project :
Page 54 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 54 of 76
1. The study area shall be up to a distance of 10 Km for air quality, soil, surface and ground water
quality from the boundary of the proposed project site.
2. Location of TSDF, township and nearest villages with distances from the facility to be
demarcated on a toposheet.
3. Importance and benefits of the project.
4. Present land use pattern of the study area shall be given based on recent satellite imagery as
well as field investigation clearly indicating, residential area, industries, vegetation (agricultural
land, irrigated, un-irrigated, un-cultivable land-as per the revenue records, forest land- as per
the records) grazing and waste land.
5. Comparison of alternate sites considered and the reasons for selecting the proposed site.
Conformity of the site with the prescribed guidelines in terms of habitation, river, highways,
railways, etc.
6. Justification for selecting particular capacity of the TSDF.
7. Point wise compliance of guidelines published by MoEF & CPCB for sitting and designing of the
proposed TSDF.
8. Land requirement for the facility including its break up for various purposes, its availability and
optimization.
9. Details of proposed layout clearly demarcating peripheral open path for unobstructed movement
of fire tender as well as various activities such as security, weighbridge, laboratory facility,
temporary hazardous waste storage areas, stabilization units, landfill, vehicle tyre wash areas,
leachate collection pits / wells and others such as admin building, canteen, worker’s room,
health centers, vehicle cleaning areas/ maintenance areas, greenbelt, internal roads, etc.
10. Details of temporary storage facility for storage of hazardous waste at project site.
11. Water requirement for the project and permission from the concern authority.
12. Details on proposed recovery and recycling options, if any.
13. Details of pre-treatment facility of hazardous waste at TSDF.
14. List of waste to be handled and their source along with mode of transportation.
15. Details on hazardous waste inventorisation, segregation at source for compatibility with
transportation system and subsequent treatment.
16. Details on compliance program to the manifestation corresponding to waste transportation from
source to TSDF – adequate number of trucks, authorized dealers if any, features of the
vehicles, trained manpower, health and safety measures, identification of transportation routes
by avoiding vulnerable installations, frequency of truck movements, etc.
17. Details on proposed protocol for waste acceptance (verifying the waste quantity through weigh
bridge, frequency of calibration of weighing machine, system for sampling, testing parameters,
analysis methods, time lags, criteria for identifying the wastes which require stabilization prior to
the landfill, no. of people, qualifications, manifestation systems, etc.)
18. Details of the laboratory facilities and statement on adequacy including proposals for
accreditation, etc.
19. Process description along with major equipments and machineries, process flow sheet
(quantative) from waste material to disposal to be provided.
Page 55 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 55 of 76
20. Design details of hazardous waste storage facilities (capacities, protocol for storing the
segregated hazardous waste, compliance to the statutory requirements and proposed safety
precautions).
21. Details on proposed protocol for establishing the requirement of stabilization for various types of
hazardous waste.
22. Details of stabilization process (step by step procedure, proposed structures, equipments,
operations, general list of chemicals/material use, handling, personal protective equipments,
occupational health and safety measurers, emergency preparedness, etc.
23. Details of the secured landfill (design, construction, operational and post closure maintenance)
including waste volume, landfill capacity, phase-wise landfill capacity development and
utilization plan, groundwater table, slope stability, compaction levels, liners, waste layers,
capping arrangement, gas collection, leachate collection, equipments, stability considerations,
trouble shooting mechanism, peizometric wells, health and safety measures, etc.
24. Specification of liners (for bottom & sides) and coveres to be used for the proposed landfill site.
25. Details on landfill gas collection / venting system and its management.
26. Details of leachate collection system – leachate generation rates, leachate collection network
within the landfill, external collection tanks (if any), treatment and disposal options (recirculation,
evaporation, treatment, discharge, etc.), overflow control measures during flood/heavy rains,
etc.
27. Details on landfill closure and its post closure monitoring plan including leachate, landfill gas,
etc.
28. Possibilities of seepage & soil contamination and mitigation measure proposed to prevent the
same.
29. Details of ETP including dimensions of each unit along with schematic flow diagram. Inlet,
transitional and treated effluent qualities with specific efficiency of each treatment unit in
reduction in respect of all concerned/regulated environmental parameters. Inlet effluent quality
should be based on worst case scenario considering production of most polluting products that
can be manufactured in the plant concurrently.
30. Membership certificate of common facilities like MEE, CHWIF etc. (Whichever is applicable).
31. Action plan for complete “Zero Liquid Discharge” (ZLD) system for proposed project.
32. Details of the existing access road(s)/walkways to the development site and its layout.
33. Details of vehicular traffic management within and outside the project area during waste
transportation.
34. Proposed financial model, creation of fund for future liabilities till 30 years of post closure
including monitoring, etc.
35. Specific details of (i) Details of the utilities required, (v) Types & quantity of fuel to be used in
each of the utilities, (vi) Flue gas emission rate from each utility along with stack height, (vii) Air
Pollution Control Measures proposed along with its adequacy, (viii) List the sources of fugitive
emission from the unit along with its quantification and proposed measures to control it.
36. Specific details of fugitive emission from the proposed TSDF project and proposed measures to
control it along with measures proposed to monitor VOC within work area.
Page 56 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 56 of 76
37. Details of management of the hazardous wastes to be generated from the project stating detail
of storage area for each type of waste, its handling, its utilization and disposal etc. How the
manual handling of the hazardous wastes will be minimized.
38. Survey and topography details of the project area with appropriate contour interval.
39. Details of site topography along with the contour plan of the project area. Details of change in
topography of the area due to the project. Details of the management of the run off / rainwater
flowing through the existing natural drain / nallah / streams within the project site if any. Impacts
on the surface hydrology pattern due to the proposed project. Details of measures proposed to
ensure that natural drainage of the site will not be disturbed obstructed / disturbed and
measures proposed to protect existing natural drain / nallah / streams within the project site.
40. Detailed plan to manage surface runoff in monsoon season. Measures proposed to avoid
contamination of surface runoff from the TSDF in monsoon season. How it will be ensured that
contaminated runoff won't flow outside the premises during rainy days.
41. Baseline data to be collected from the study area w.r.t. different components of environment viz.
air, noise, water, land, biology and socio-economics.
42. Soil map up to 5 feet prepared by concerned Government Authority.
43. Details on geological and hydro-geological features of the project area such as type of soil,
nature of soils, soil quality, soil properties including compressive strength, soil bearing capacity,
consolidation, etc.
44. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly
wind speed and direction and rainfall should be incorporated.
45. Anticipated environmental impacts due to the proposed project/production may be evaluated for
significance and based on corresponding likely impacts VECs (Valued Environmental
Components) may be identified. Baseline studies may be conducted within the study area of 10
km for all the concerned/identified VECs and likely impacts will have to be assessed for their
magnitude in order to identify mitigation measures.
46. One complete season base line ambient air quality data (except monsoon) to be given along
with the dates of monitoring. The parameters to be covered shall be in accordance with the
revised National Ambient Air Quality Standards as well as project specific parameters (SO2,
NOx, PM10, PM2.5, VOC, Methane, CO2 etc.). The locations of the monitoring stations should
be so decided so as to take into consideration the pre-dominant downwind direction, population
zone and sensitive receptors. There should be at least one monitoring station in the upwind
direction. There should be at least one monitoring station in the pre dominant downwind
direction at a location where maximum ground level concentration is likely to occur.
47. Impact of the project on the AAQ of the area. Details of the model used and the input the
parameters used for modeling should be provided. The air quality contours may be plotted on a
location map showing the location of project site, habitation, sensitive receptors, if any. The
wind roses should also be shown on this map.
48. Details on noise levels at sensitive/commercial receptors.
49. Impact of the TSDF installation on the environment including the local hydrology, soil condition,
floral and faunal bio-diversity of the region and the mitigation measures proposed.
Page 57 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 57 of 76
50. Details of flora and fauna duly authenticated should be provided. In case of any scheduled
fauna, conservation plan should be provided.
51. Demography details of all the villages falling within the study area.
52. While identifying the likely impacts, also include the following for analysis of significance and
required mitigation measures:
impacts due to hazardous waste carrying trucks movement impacts due to leachate on surface water, soil and groundwater impacts due to air pollution including landfill gas impacts due to odour pollution impacts due to noise impacts due to fugitive emissions impact on health of workers due to proposed activities
53. Proposed odour control measures.
54. Detailed five year greenbelt development program including types & number of trees to be
planted, width of plantation, area under green belt development [with map], budgetary outlay;
along with commitment of the management to carry out the tree plantation activities outside the
premises at appropriate places in the nearby areas and elsewhere.
55. Details of existing trees to be protected / preserved / transplanted / removed. Permission of
concerned authority for cutting the trees within the premises. Time bound action plan for
compensatory tree plantation including details like number and type of trees to planted, area of
tree plantation, budgetary allocation for the same etc. should also be submitted.
56. Details of top soil management plan during construction phase. If the topsoil is proposed to be
preserved, the details relating to the quantity of topsoil stored, demarcated area on plan where
it is stored along with preservation & reutilization plan is to be given.
57. Monitoring of pollutants at receiving environment for all the appropriate notified parameters
Air quality, groundwater, surface water, leachate, gas quality, etc. during operational phase of the project
Leachate within the landfill and after treatment Groundwater quality around the landfill Surface water quality Gas quality within landfill (VOCs, H2S, etc.) Air quality above landfill
58. Details on monitoring of qualitative parameters – air quality, groundwater, surface water,
leachate, gas quality, etc. – location, frequency, parameters, etc. for all the appropriate notified
parameters for monitoring after landfill closure
Leachate quality after treatment and at receiving environment Groundwater quality around the capped landfill Surface water quality Air quality above landfill and at gas vents
59. Details of in-house monitoring capabilities and the recognized agencies if proposed for
conducting monitoring.
60. Occupational health impacts on the workers and mitigation measures proposed to avoid the
human health hazards along with the personal protective equipment to be provided to the
Page 58 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 58 of 76
workers. Plan for pre-employment and periodical medical checkup of the workers.
61. Details on landfill closure and its post closure monitoring plan including leachate, landfill gas
etc.
62. Details of the proposed overall safety and health protection measures during the project design,
construction and operation phases.
63. Details on surface/storm water management.
64. Risk assessment including prediction of the worst-case scenario and maximum credible
accident scenario. The worst-case scenario should take into account the maximum inventory of
storage at site at any point in time. The risk contours should be plotted on the plant layout map
clearly showing which of the activities would be affected in case of an accident taking place.
Measures to guard against fire hazards including details of fire detection and control system
and fire control plan showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey
pump, toxic gas detectors etc.
65. Details of the emergency preparedness plan and on-site & off-site emergency management
plan and disaster management plan.
66. Details of disaster management plan during operation phase of the project should include also
scenario of natural catastrophe like earth quake, cyclone and floods in addition to other
disasters. The plan should include the details of (i) Emergency lighting plan (ii) details of power
back up system in the case of emergency (iii) fire fighting arrangements (iv) first aid
arrangement (v) Training and Mock drill (vi) Emergency announcement system (vii) Signages
(viii) location of emergency stair cases and pathways etc.
67. Details of seismic zone of the project site and design aspects required to be adhered to as per
National standards.
68. Proposal for socio-economic development activities including community welfare program most
useful in the project area for the overall improvement of the environment. Submit a detailed plan
for social corporate responsibilities, with appropriate budgetary provisions for the next five years
and activities proposed to be carried out; specific to the current demographic status of the area.
69. Detailed EMP including the protection and mitigation measures for impact on human health and
environment as well as detailed monitoring plan and environmental management cell proposed
for implementation and monitoring of EMP. The EMP should also include the concept of waste-
minimisation, recycle/reuse/recover techniques, energy conservation, and natural resource
conservation. Total capital cost and recurring cost/annum earmarked for environment pollution
control measures.
70. Plan for reuse / recycling of gypsum sludge and iron sludge along with the agreement letters of
endusers.
71. (a) Does the company have a well laid down Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA report.(b). Does the Environment Policy prescribe
for standard operating process / procedures to bring into focus any infringement / deviation /
violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.
72. What is the hierarchical system or administrative order of the company to deal with the
environmental issues and for ensuring compliance with the EC conditions. Details of this
Page 59 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 59 of 76
system may be given.
73. Does the company have a system of reporting of non compliances / violations of environmental
norms to the Board of Directors of the company and / or shareholders or stakeholders at large?
This reporting mechanism should be detailed in the EIA Report.
74. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should
be incorporated in the EIA Report.
75. A tabular chart with index for point-wise compliance of above TORs.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for “CHWTSDF” shall be considered as generic TORs for
preparation of the EIA report in addition to all the relevant information as per the generic structure of
EIA given in Appendix III in the EIA Notification, 2006. The project shall be appraised on receipt of the
final EIA report.
Validity of ToR: The ToRs prescribed for the project will be valid for a period of three years for submission of EIA &
EMP report accordingly, ToR will lapse after 23/10/2019.
The period of validity could be extended for a maximum period of one year provided an application
is made by the applicant to the Regulatory Authority, at least three months before the expiry of
valid period together with an updated Form-I, based on proper justification and also
recommendation of the SEAC.
14 SIA/GJ/IND/17426/2016 M/s: Zydus Infrastructure Pvt. Ltd. Survey no. 467, Village Bavla, Ta. Sanand, Dist. Ahmedabad.
Appraisal
Project / Activity No.: 7(h)
M/s: Zydus Infrastructure Pvt Ltd (herein after Project Proponent – PP) has submitted application vide their online proposal no. SIA/GJ/MIS/5152/2015 dated 16/12/2015.
Project status: Existing
Project / Activity Details:
M/s. Zydus Infrastructure Pvt. Ltd. (ZIPL) is having Common Effluent Treatment Plant (CETP) and is
engaged in the treatment of waste water collected from the member units of Special Economic Zone
(SEZ). ZIPL has proposed for expansion of existing CETP from 0.8 MLD to 3 MLD, located at Survey
No. 467, “Pharmez” Special Economic Zone, Sarkhej-Bavla Road, NH-8 A, Village Matoda, Taluka
Sanand, District Ahmedabad, Gujarat. Member units are only High Tech Pharmaceutical (Formulation)
Manufacturing units. At present unit has obtained CCA from Gujarat Pollution Control Board for 0.8
MLD capacity. Existing total land area is 17,919.26 sq. m. including 5,936.58 sq. m of green belt/tree
plantation area. No additional land is needed to acquire for the proposed expansion project. Proposed
expansion activity will be carried out in open area available within the premises i.e. 315.54 sq. m. Cost
of the proposed expansion facility would be approx Rs. 20 Crores. As the proposal is for expansion of
CETP, which is an environmental infrastructure. The total estimated expenditure of Rs. 20 Crores is for
pollution control measures. Recurring cost per annum would be approximately Rs. 8 Crores. Fresh
water requirement will be increased from 70 KL/day to 158 KL/day (for Domestic 15 KL/day,
Gardening/ Green belt – 50 KL/day and for Industrial – 93 KL/day. Total 85 KL/day waste water will be
Page 60 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 60 of 76
generated from the facility which will be treated along with member units' effluent in proposed
expansion CETP with capacity of 3 MLD. Total effluent will be subjected to treatment in proposed
treatment facilities comprises of primary, secondary, MBR process, RO and MEE (7500 Kg/hr.)
treatment. Treated water will be reused in utilities and send to member units for reuse. Total domestic
waste water 12 KLD will be disposed off through soak pit/well.
Waste water from the member units will be collected through tankers. Raw effluent is subjected to the
primary physic-chemical treatment followed by biological treatment in MBR unit. Treated waste water
will be sent to RO system. RO permeate will be reused and RO reject will be sent for MEE. At present
unit has provided CETP with primary, secondary, MBR process & MEE. Unit has proposed to install
additional CETP units like equalization tank, neutralization tank, clarifloculator, fine screen platform, pre
air basin, MBR Basin etc. Unit has provided one steam Boiler (3 TPH) for MEE. FO/HSD/LDO (300
Lit./Hr.) will be used as a fuel for Boiler. Unit will install DG sets (320 KVA x 3 no.s) in addition to
existing DG set (720 KVA). FO/HSD/LDO ( Total 250 lit./hr.) will be used as a fuel for all DG sets. No
process gaseous emission is envisaged. Hazardous waste generated from the proposed CETP project
will be ETP sludge (15 MT/Month), MEE/Decanter sludge (114 MT/Month) and used oil (0.2 MT
/Month). CETP sludge and MEE salt will be sent to TSDF site. CETP is having valid membership for
the TSDF of NECL, Nandesari and they have also obtained membership of upcoming facility M/s:
Ecocare infrastructure Pvt. Ltd., Dasada, Surendranagar.
CETP daily performance is monitored by fully equipped laboratory as well as continuous up-gradation and optimization of the plant with R & D of the treatment process. The laboratory consist various instruments for the analysis of various parameters for the effluent at stages. The facility is having data center for the interpretational analysis of data from SCADA as well as manual observations. CETP daily performance is monitored by fully equipped laboratory. Records of monitoring are maintained. Effluent is being collected through tankers and the same will be followed in proposed scenario. ZIPL is having own tanker facility for collection of effluent from member units in SEZ. In existing, 05 tankers of 20 KL capacity After expansion, 15 nos. of tankers of 20 KL capacity 02 nos. of tankers will be kept as standby for emergency purpose. Daily collection of effluent from member units, route and trips of tankers are scheduled as per booked quantity. Tracking and monitoring is being done on every tanker trip. Member unit is having their own treatment scheme for up to acceptable effluent characteristic. ZIPL ensures to receive effluent from member unit well within prescribed inlet norms. Manifests are maintained for each tankers being sent to members units. Tanker no. and driver details Out time and in time of tanker from ZIPL Name of the member unit Acknowledgment from member units ZIPL continuously monitors their tankers of transport and ensures manifests completely fills up for each of the member units. Inspection visits are periodically conducted to member units to ensure that unit is sending all treated effluent to CETP and do not discharging anywhere else. ZIPL ensures that the effluent is being collected by CETP as per prescribed inlet design standard. Dedicated tankers to be used for transporting effluent from various member units to CETP inlets and monitored continuously. Flow meter is installed, at the inlet of CETP at equalization tank which measures the flow of effluents received from member units, and outlet of the CETP for final reusable effluent. Effluent sample from each tanker received within the premises of ZIPL is analyzed for the important parameters before emptying into the equalization tank. Not in any case highly acidic/alkaline effluents, very high TDS effluents are taken in to equalization tanks of CETP. The tankers are made to wait till the parameters are analyzed if parameters are not satisfied, tanker is not permitted to empty into equalization tank.
Page 61 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 61 of 76
Final quality of the treated effluent is completely reusable and regular demand from member units for the water is made facility complete Zero Liquid Discharge for any time. Random cross checking of production and effluent generation details of member units to make sure entire effluent transfer to CETP for treatment. Proposed design inlet norms of CETP Sr. no. Parameter CETP Inlet Norms 1 pH 6 to 8 2 Temperature - 3 Colour - 4 Suspended Solids 300 mg/l 5 Oil and Grease 5 mg/l 6 BOD 1500 mg/l 7 COD 3000 mg/l 8 Total Dissolved Solids <2500 mg/l
Member units will send their effluent which complies with abovementioned inlet norms. Discussions/Observations: Technical presentation made during the meeting by project proponent. During the appraisal, issues raised during the public consultation were discussed. While discussing about the treatment and reuse of waste water, Committee emphasised on drip irrigation system for utilization of treated waste water in green belt development. The project proponent presented that they have already started baseline environmental monitoring from 1st January 2016 and requested to allow them to use the same for the preparation of the EIA report which was agreed to by the committee. After detailed discussion on each and every aspect of the project, following TOR were prescribed to include them in the EIA report to be prepared for the study area covering 5 km radius from the boundary of the project site. Committee noted that the treated waste water will be completely recycled and there will be no discharge of waste water. Committee emphasized on the conveyance system of the raw effluent and treated effluent and CETP performance. Project proponent assured that the wastewater quantity being received through member unit and the recycled water quantity to be distributed to member units needs to be monitored through SCADA based system as well as manual observations. Committee found that EIA report covering compliance of ToR submitted by project proponent was found satisfactory. After detailed discussion, it was decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance. 15 SIA/GJ/IND2/17412/2015 M/s: Dorf Ketal Chemicals India Pvt. Ltd.
P.No.Z-108, Dahej SEZ,(Part-2), Vagra, Bharuch
Appraisal
Project / Activity no.: 5(f) & 6(b)
M/s: Dorf ketal Chemicals (I) Pvt. Ltd. (herein after Project Proponent – PP) has submitted application vide their online proposal no. SIA/GJ/IND2/17412/2015 dated 28/09/2016 regarding grant of Environmental Clearance..
Project proponent has submitted EIA Report prepared by M/s: Eco-Care Solutions, Vadodara based on the TOR prescribed to the project in SEAC meeting dated 16/07/2015.
Project status: New Project / Activity Details: This is a new unit proposes the manufacturing of Synthetic Organic Chemicals and isolated storage & handling of hazardous chemicals as tabulated below: Sr. no.
Name of the Products
Trade Name Chemical Name Production Capacity MT/ Annum
1. Lubricity Additive SR 2008 Fatty acid in aromatic
Page 62 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 62 of 76
solvent 16000 SR 2010 Fatty Acid Ester
2.
Antioxidants UOP-5
Alkylated Phenylenediamine
2000
Dorf-410C Alkylated Phenylenediamine
DA 2516 Alkylated Phenylenediamine
Px3811 Alkylated PANA 3.
Antifoulants
DA 2313 Quinnone Methide and sebacate ester of 4 Hydroxy Tempo in Aromatic Solvent
6500 DA 2316
DA 2326 DA 2338 DA 2339
SR1289 Reaction adduct of PIB and P2S5 in Aromatic Solvent
SR1336
Reaction adduct of PIB, P2S5 and Pentaerythritol in Aromatic Solvent
SR1390
Reaction adduct of PIB, P2S5 and Pentaerythritol in Aromatic Solvent
SR1347
Reaction adduct of PIB, P2S5 and Pentaerythritol in Aromatic Solvent
SR1393
Reaction adduct of PIB, P2S5 and Pentaerythritol in Aromatic Solvent
SR1385
Reaction adduct of PIB, P2S5 and Pentaerythritol in Aromatic Solvent
SR1303
Reaction adduct of PIB, P2S5 and Pentaerythritol in Aromatic Solvent
SR1392 Reaction adduct of PIB, P2S5 and Pentaerythritol
Polyflo 130 Amine-Epihydrochlorin Polymer in Aromatic Solvent
SR1226 Reaction adduct of PIB, P2S5 and Pentaerythritol
F22S Mixture of Fatty Alcohol Acrylates
SR1648 Mixture of Fatty Alcohol Acrylates
Page 63 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 63 of 76
Px4005 Aminified Polyisobutylene Succinic Anhydride
Px4006 Borated Aminfied PIBSA
Px3812 Ester of PIBSA Px3824 PIBSA Derivative
Px3872 Borated Glycerolmono Oleate
Px3871 Mixed Penanol/Tridecanol Borate Ester
4.
Demulsifies
SR1123 Alkylphenol ethoxylates in Aromatic Solvent
5000
SR1125 Alkylphenol ethoxylates in Aromatic Solvent
SR1153 Alkylphenol ethoxylates in Aromatic Solvent
SR1167 Alkylphenol ethoxylates in Aromatic Solvent
SR1192 Alkylphenol ethoxylates in Aromatic Solvent
SR1106 Alkylphenol ethoxylates in Aromatic Solvent
Px3843 EO/PO Block CoPolymer and TricresylPhosphate
Px3841 Alkyl Acrylate Polymer 5.
Plastic Additives UOP-225/
N-N disecbutyl - diamino diphenyl methane
1200
PX3805/Unilink 4200
N-N disecbutyl - diamino diphenyl methane
Clearlink 1000 N-N disecbutyl - diamino dicyclohexyl methane
Clearlink 1080 Alkylated IPDA Clearlink 3000 Alkylated Alkyl PACHm
6.
Antistatic Additives
SR1795 Polysulfone and Amine-Epihydrochlorin Polymer in Solvent
1800
1714ND Polysulfone in Aromatic Solvent
7.
H2S Scavenger
SR1982 Metal-Alkoxide Salt in Alcohol Base
500
SR1954 Alkyl Triazine 8.
Coke Inhibitors
SR1311 Metal Salt in Aromatic Base
10000
SR1358 Metal Salt in Aromatci Base
9.
Cold filter plug point
SR1649 Alkyl-vinylacetate Polymer in Aromatic Solvent
5000
Page 64 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 64 of 76
SR1650 SR1651
10.
Octane Boosters
PX3402 Ferrous Organometallic Salt
5000
SR1200 Imidazoline in Aromatic Solvent
11.
Corrosion inhibitors
Dorf 5123 Organic Amine in aqueous Base
2000
DA2215 Imidazoline in Aromatic Solvent
SR1206 Imidazoline D5 Mixed Imidazolines FGDU1012 Mixed Imidazolines
SR1253 Mixed Amines in aqueous base
SR1202 Imidazoline in Aromatic Solvent
SR1224 Mixed Imidazolines
DA2606 Blend of imidazoline and Amine
YSDA2606 Blend of imidazoline and Amine
YSDA2606 Blend of imidazoline and Amine
Unicor C Imidazoline in Aromatic Solvent
Unicor J Dimmer Fatty Acid in Aromatic Solvent
Dorf 1440
Reaction product of Di-N-Alkyl Amine with Aldehyde in Alcohol Base
AW50
Reaction product of alkyldiamine and Aldehyde in aromatic base
Px3844 Mixture of Amine Phosphates
Px3846 Mixed aminified ALkylPhosphates
Px3866
1H-Benzotriazole, methyl-, reaction products with Butyl vinyl ether
Px3865 metal saltsof DDSA of amino acetic acid in glycerine
Px3861
Imide/amide/imidazoline reaction products of fatty and dodecenyl succinic acids with tertiarty amines
Px3864 Imide/amide/imidazoline reaction products of
Page 65 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 65 of 76
fatty and dodecenyl succinic acids with tertiary amines
Px3851 N-Tallow-1,3-diaminopropane dioleate salt
Px3845 Mixed Alkyl Phosphate Esters
Px3862 Blend of DDSA and Tollytriazole
Px3863 Fatty Acid Tollytriazole
Px3847 2,5-dimercapto-1,3,4-thiadiazole + Mixed Amines Blend
Total Manufacturing Capacity (MT / Annum)
55000 MT/Annum
Unit has also proposed Storage Terminal for handling and storage of Ethylene Oxide (Class A) – 32
m3.
The project falls under Category B of project activity 5(f) and 6(b) as per the schedule of EIA
Notification 2006. Total plot area is 86565.06 sq. m & unit has proposed 25040 sq. m. area for the
green belt development/Tree plantation. Expected project cost is Rs. 111.55 Crores. Total water
consumption for proposed project will be 345 KL/day (20 KL for Domestic, 150 KL for Gardening, 159
KL for Process, Boiler & Cooling and 16 KL for Scrubbers,) which will be sourced from GIDC water
supply. Industrial waste water generation will be 118.7 KL/day( 9 KL from Process, 5.3 KL from
Cooling, 56.4 KL from Boiler, 32 KL from RO reject and 16 KL from scrubber) which will be treated in
proposed Primary, Secondary & Tertiary treatment plant and treated waste water will be discharged
into GIDC drainage line for Sea disposal. 16 KLD domestic waste water will be treated in the in house
STP & will be used for Horticulture & Green belt development within premises.
It is proposed to install two steam boilers having 10 TPH capacity (one working & one stand-by), two
TFH (15 Lac Kcal/hr each) and one DG set (500 KVA). Coal (1.7 MT/hr) or FO (760 Kg/hr) for steam
boiler, FO/LDO (170 Kg/hr for each) for TFH and HSD (125 ltrs/hr) is proposed as fuel. Multi cyclone
separator and bag filter will be provided as APCM for steam Boilers. Unit has proposed to provide
scrubbing system for control of process emissions like VOC, H2S and Ethylene Oxide. Hazardous
waste generated from the manufacturing activity will be ETP sludge (40 MT/Year), Residue / Process
waste (300 MT/Year), Discarded containers/Bags/Liners (500 MT/Year) and used oil (10 MT /Year).
NaHS (1200 MT/Annum) and Spent solvent (1200 MT/Annum) generated will be sent to actual
authorised reprocessors.
Observations/Discussion:
Technical presentation made during the meeting by project proponent. The baseline environmental
quality has been assessed for various components of the environment viz. air, noise, water, biological
and socioeconomic The baseline environmental study has been conducted for the study area of 10 km
radial distance from project site for the period December 2015 to February 2016. Ambient Air Quality
monitoring was carried out for PM10, PM2.5, SO2, NOx, HCl and NH3 at five locations, including the
project site. Values conform to the prescribed standards for Ambient Air Quality. The incremental
Page 66 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 66 of 76
Ground Level Concentration (GLC) has been computed using ISCST – 3 model. The resultant
concentrations are within the NAAQS. Committee noted that PP has not considered VOC for baseline
study. While reviewing the EIA report, Committee observed that PP has submitted Risk assessment
report and disaster management plan. However, details regarding hazardous waste management,
APCM details, spent solvent management, permission for effluent disposal etc. are not properly
addressed. After deliberation on various aspects, the Committee sought following additional information
for further consideration of the proposal:
1. Compliance of TOR no. 27 & 28 with respect to project specific parameters like VOC.
2. Submit the schematic diagram of all APCM with technical details. Complete mass balance of
scrubbing media with qualitative analysis (Characteristics) and mode of disposal.
3. Permission letter from competent authority with effluent discharge quantity – 345 KL/day.
4. Compliance of ToR no. 7 . Give Chemical reactions of all the products & mass balance.
5. Compliance of ToR no. 11 regarding Reuse/ Recycle of waste water.
6. Compliance of ToR no. 39 regarding Solvent / spent solvent management. Explore the
possibilities for in-house distillation for spent acid generated from the proposed project.
7. Compliance of ToR no. 33 regarding Hazardous waste management. Give source of hazardous
waste, quantity of hazardous waste in MT/Annum, specific mode of disposal etc. as per the
Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.
Following proposal was also considered for ToR amendment and screening & scoping based on their submission. 16 SIA/GJ/IND2/16809/2016 M/s: NOCIL Limited
Plot No. 12/A/1 & 13/B/1, Dahej Industrial Estate, Tal. Vagra, Dist. Bharuch, Gujarat
ToR Amendment
This project was issued TOR in the 282th meeting of SEAC dated 25/02/2016 and was communicated
to project proponent vide letter no.SIA/GJ/IND2/9547/9547/846 dated 21/04/2016.
Project proponent has requested vide online proposal no. SIA/GJ/IND2/16809/2016 dated 22/07/2016
for amendment in TOR. PP has submitted Revised Form-1 and relevant details. The case was
considered for amendment in ToR.
During meeting, Committee noted that project proponent has decided to change product list by addition
of new products namely 2 MercaptoBenzothiazole (MBT), 1, 6- Dichloro hexane (1,6-DCH),
Hexamethylene-1,6-bis(thiosulfate), disodium salt dihydrate (Pilcure DHTS) and
Tetramethylthiuramdisulphide (TMTD) Pilcure TMT. Thus total production after expansion will be 8050
MT/Month in place of 7775 MT/Month.
Committee noted that there is a minor change in flue gas & process gas emission details. Based on the
information furnished by the project proponent in revised Form-1 and PFR, Committee unanimously
decided for the amendment sought and now project/activity details shall be read as under:
Project / Activity Details:
This is an existing unit engaged in Synthetic Organic Chemicals and now proposed for expansion as
tabulated below:
Page 67 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 67 of 76
Sr. No.
Name of Product Existing Capacity (MT/Month)
Additional Capacity
(MT/Month)
Total after Proposed Expansion (MT/Month)
A. Rubber Chemical & Rubber Chemicals Intermediates
1 4 Amino Diphenyl Amine (4 ADPA) 1700 800 2500
2 Sodium MercaptoBenzothiazole (NaMBT) 350 650 1000
3 2 MercaptoBenzothiazole (MBT) 100 0 100
4 1, 6- Dichloro hexane (1,6-DCH) 0 100 100
B. Finished Products
1 N-1,3 Dimethylbutyl-N-Phenyl-P-Phenylenediamines Pilflex-13 & Similar Derivatives
1000 2000 3000
2 Dibenzothizyl Disulfide (Pilcure MBTS) 100 0 100
3 N Cyclohexyl -2-Benzothiazyl Sulfonamides (Pilcure CBS/DCBS/NS)
250 550 800
4 Tetra Methyl Ammonium Hydroxide -100% 0 75 75
5 Hexamethylene-1,6-bis(thiosulfate), disodium salt dihydrate (Pilcure DHTS)
0 175 175
6 Tetramethylthiuramdisulphide (TMTD) Pilcure TMT
0 200 200
Total 3500 4550 8050
1 Captive Power Plant 2 MW 2 MW 4 MW
LIST OF BY-PRODUCT
Sr. No.
Name of Product Existing Capacity (MT/Month)
Additional Capacity
(MT/Month)
Total after Proposed Expansion (MT/Month)
1 Sodium Hypo Chlorite (100% Basis) -- 35 35
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Plot area is approx. 206910 sq. m. Unit has proposed 62073 sq. m area for green belt/tree plantation.
Estimated cost of proposed expansion is Rs. 255 Crores.
Page 68 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 68 of 76
Details of water balance is tabulated as below:
Water Consumption Waste water generation Existing Additional Total Existing Additional Total Industrial 2550 KL/Day
(Process & Washing:1400 KL/Day, Boiler:800 KL/Day, Cooling:300 KL/Day, DM Water: NIL & Others:50 KL/Day)
(Process & Washing:350 KL/Day, Boiler: -300 KL/Day, Cooling: NIL)
2550 KL/Day (Process: 1700 KL/Day, Washing: 50 KL/Day, Boiler: 500 KL/Day & Cooling: 300 KL/Day)
1720 KL/Day (Process & Washing: 1550 KL/Day, Boiler: 20 KL/Day, Cooling: 50 KL/Day, DM Water: 50 KL/Day & Others: 50 KL/Day)
(Process & Washing: 100 KL/Day, Boiler: NIL, Cooling: NIL)
1720 KL/Day (Process: 1600 KL/Day, Washing: 50 KL/Day, Boiler: 20 KL/Day & Cooling: 50 KL/Day)
Domestic & Gardening
Domestic: 100 KL/Day & Gardening: 50 KL/Day
Domestic: 100 KL/Day & Gardening: 50 KL/Day
Domestic: 50 KL/Day
Domestic: 80 KL/Day
Total 2700 KL/Day 2700 KL/Day 1770 KL/Day
1800 KL/Day
Fresh water requirement after proposed expansion will be 2700 KL/day which will be supplied by the
GIDC. Industrial wastewater generation after the expansion will be 1720 KL/day which will be treated
in proposed ETP consisting of primary, secondary and tertiary treatment units. Finally treated will be
discharged into GIDC drainage. Unit has proposed ETP having Primary, Secondary & Tertiary
Treatment Facility Industrial effluent (1720 KL/Day) will be treated in ETP having Primary, Secondary &
Tertiary Treatment and treated effluent will be subjected to GIDC sewer for deep sea disposal.
Domestic waste water (80 KL/day) will be treated in STP or added in secondary treatment unit of ETP.
Flue gas & process gas emission details for existing as well as proposed expansion will be as under:
Flue gas emission details Stack attached to (Mention
Existing or Proposed) APCM Fuel consumption
Existing 1 Steam Boiler-I ESP Coal: 140 TPD/ NG:
75 TPD 2 D.G. Set -- HSD: 250 Liter/Hr 3 Hot Air Generator-I Multicyclone Separator FO: 5 TPD 4 CPP -- Coal: 2 MW Total Proposed 1 Steam Boiler-I & II ESP with Scrubber Coal: 280 TPD/ NG:
75 TPD
Page 69 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 69 of 76
2 D.G. Set -- HSD: 250 Liter/Hr 3 Hot Air Generator-I, II & III Multicyclone Separator HSD: 5 TPD 4 CPP -- Coal: 4 MW
Process gas emission details Vent attached to (Mention
Existing and Proposed) APCM Type of gaseous
emission Existing 1 Process vent-Thios Reactor Dust Collector PM-150 mg/Nm3 2 Process vent-NaMBT Plant Caustic Scrubber H2S-45 mg/Nm3
Mercaptans-0.5 ppm CS2-180 mg/Nm3
3 Process vent-Thiazole Caustic Scrubber HCl-20 mg/Nm3 Cl2-9 mg/Nm3
4 Process vent-(PX 13) Steam Snuffing H2 5 Process vent-Electrolysis cell Caustic Scrubber Cl2-9 mg/Nm3 Total Proposed 1 Process vent-Thios Reactor Dust Collector PM-150 mg/Nm3 2 Process vent-NaMBT Plant Caustic Scrubber H2S-45 mg/Nm3
Mercaptans-0.5 ppm CS2-180 mg/Nm3
3 Process vent-Thiazole Caustic Scrubber HCl-20 mg/Nm3 Cl2-9 mg/Nm3
4 Process vent-(PX 13) Steam Snuffing Residual H2 5 Process vent-Electrolysis cell Caustic Scrubber Cl2-9 mg/Nm3 6 Process vent Caustic Scrubber HCl-20 mg/Nm3
Cl2-9 mg/Nm3 SO2-40 mg/Nm3
Hazardous waste to be generated are tabulated as below:
Sr. No.
Waste Details
Waste Category
Quantity MT/Month
Mode of Disposal
Existing Proposed Total After Proposed Expansion
1. ETP Sludge 34.3 5 20 25 Collection, Storage, Transportation and Disposal at Nearest TSDF
2. Process waste (Organic Matter)
20.3 34 100 134 Collection, Storage, Transportation and Disposal at Nearest Common Incineration site or co-processing in Cement Industry
3. Used Oil 5.1 1.5 -- 1.5 Collection, Storage,
Page 70 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 70 of 76
Transportation And Selling to authorized recyclers.
4. Discarded liners /Drums
33.3 1667 Nos/Month
42 Nos/Month
1733 Nos/Month
60 Nos/Month
3400 Nos/Month
102 Nos/Month
Collection, Storage, Transportation And Selling to authorized recyclers after decontamination.
5. Distillation Residue
36.4 25.0
25.0
50.0
Collection, Storage, Transportation and sell to Cement Industry for Co-processing or Disposal at Common Incineration Site
6. Other waste(Aesbestos containing)
32.1 0.3 0.2 0.5 Collection, Storage, Transportation and Disposal at Nearest TSDF
7. Spent Carbon
-- -- 1.5 1.5 Collection, Storage, Transportation and co-processing in cement industries or Disposal at Nearest TSDF
Fly ash (450 MT/Month) will be sold out to Brick manufacturers.
The project shall be appraised on receipt of the final EIA report based on the TOR issued vide letter no.
SIA/GJ/IND2/9547/9547/846 dated 21/04/2016 and the following additional ToR.
1. Being an expansion project, compliance of MoEF circulars vide No: J-11011/618/2010-IAII(I) dated 30/05/2012 and J-11013/41/2006-IA-II(I) dated 20/10/2009
2. Copies of XGN generated Inspection reports with analysis reports of the water/Air/Hazardous samples collected by GPCB (Last 2 years). Copies of instructions issued by GPCB in last 2 years and point wise compliance thereof.
The project shall be appraised on receipt of the final EIA report.
Validity of ToR: The ToRs prescribed for the project will be valid for a period of three years for submission of
EIA & EMP report accordingly, ToR will lapse after 24/02/2019.
The period of validity could be extended for a maximum period of one year provided an
application is made by the applicant to the Regulatory Authority, at least three months before
the expiry of valid period together with an updated Form-I, based on proper justification and
also recommendation of the SEAC.
17 SIA/GJ/IND2/17080/2013 M/s: Styrolution India Pvt. Ltd., Plot no. 4, GIDC-Dahej, Ta: Vagra, Dist: Bharuch.
ToR amendment
This project was issued TOR in the 203rd meeting of SEAC dated 14/08/2014 and was communicated
to project proponent vide letter no. EIA-10-2013-3466-E-2598 dated 15/09/2014.
Project proponent has requested vide their letter no. NIL dated 06/10/2016 for amendment in TOR. PP
has submitted Revised Form-1 and relevant details. The case was considered for amendment in ToR.
Earlier, this project was accorded ToR with Public Hearing as per the Ministry’s O.M. dated 16/05/2014 as provided under para7(i) III.Stage(3)(i)(b) of EIA Notification, 2006. Now, PP has requested that
Page 71 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 71 of 76
Public hearing is not applicable to their expansion project as the proposed expansion is within the existing premises in Dahej-I GIDC which is notified industrial estate. PP has submitted a copy of gazette notification of Dahej-I which was published on July 21, 1995. As per the MoEF&CC’s O.M. dated 10/12/2014, the exemption from the public consultation, as provided under para 7(i) III. Stage (3) (i) (b) of EIA Notification, 2006 is available to the projects or activities or units located within the Industrial Estates or Parks, which were notified prior to 14.09.2006, i.e. the EIA Notification, 2006 coming in to force.
Committee also took notice of one of the ToR issued by MoEF&CC in case of M/s: Anvitha Life Care, plot no. 6, industrial park, Attivaram village, Ozili Mandal, SPSR Nellore district, Andhra Pradesh vide no. J-11011/177/2014-IA II (I) dated January, 2015 which states that “The project may be exempted from public hearing as per Ministry”s O.M. dated 10/12/2014 subject to submission of authenticated documents showing industrial estate has been established by the state prior to 2006 or has been obtained EC after 2006.”
In view of the above, It was unanimously decided to exempt the aforesaid project namely M/: Styrolution India Pvt. Ltd. from carrying out public consultation as per the said O.M. dated 10/12/2014, to cancel the ToR no. 46 and to replace the last paragraph of the ToR issued vide this office letter dated 15/09/2014. Hence, last para shall be read as under: The above mentioned project specific TORs/additional TORs and the model TORs available in the MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be considered as generic TORs for preparation of the EIA report in addition to all the relevant information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report. Validity of ToR:
The ToRs prescribed for the project will be valid for a period of three years for submission of
EIA & EMP report accordingly, ToR will lapse after 13/08/2017.
The period of validity could be extended for a maximum period of one year provided an
application is made by the applicant to the Regulatory Authority, at least three months before
the expiry of valid period together with an updated Form-I, based on proper justification and
also recommendation of the SEAC.
18. SIA/GJ/IND/10911/2016 M/s: Sun Cement, Survey. No. 701/6 paiky 2, Vill. Dabhoda, Ta: Kheralu, Dist.: Mehsana
Screening & Scoping
Project / Activity No.: 3(b)
Project status: New
Chronology of EC Process:
M/s: Sun Cement (herein after Project Proponent – PP) has submitted application vide their
proposal no. SIA/GJ/IND/10911/2016 dated 05/04/2016.
Earlier this case was considered in the SEAC meeting dated 07/05/2016.
During the meeting, PP requested for B2 category as per the OM dated 24/12/2013. Committee
took note of the OM no.J-13012/12/2013-IA-II (I) dated 24/12/2013. Upon asking about the
transportation of the raw materials & products, PP could not reply satisfactorily. Committee was
of the view that, PP should submit the complete details about availability of railway for
transportation of raw materials as well as finished products and undertaking in this regard
Page 72 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 72 of 76
covering requirement as per OM dated 24/12/2013 for consideration of project as B2 project.
Considering the above facts, it was unanimously decided to consider the project for
TOR/Scoping only after submission of the following: (1) Revised complete proposal with
Revised Form-1 & relevant details through online web portal.
PP has submitted revised proposal with revised form-1 and PFR vide their letter on 24/10/2016.
Project status: New Project / Activity Details:
Sr. no. Name of Product Capacity
1 Cement 3000 MT/Month
The project falls under Category B of project activity 3(b) as per the schedule of EIA Notification 2006. Total plot area is 9713 sq. m. Unit has proposed 3000 sq. m area for green belt. Expected project cost is Rs. 1.32 Crores. Main raw materials to be used are Clinker, Slax, Fly ash, Marine Gypsum & Carbon black. Total water consumption for proposed project will be 11 KL/day. There will be no generation of industrial waste water from the proposed project. Domestic waste water (0.8 KL/day) will be disposed off into Soak pit system. There is no flue gas emission from the proposed activity. There will be no generation of hazardous waste from the manufacturing activity. Observations/Discussion: During the meeting, revised proposal was considered by the Committee. Committee noted that the
transportation of raw materials and products will be carried out through railway. Distance between
Taranga hill railway station and Sun cement is @ 500 meters. Rail connectivity of Taranga hill railway
station is through meter gauge line. Converting of meter gauge into broad gauge line is going on this
railway track. Letter in this regard is submitted by PP. As soon as broad gauge line will be completed,
they will transport raw materials directly to the plant. Considering this, the project was categorized as
B2 as per OM issued MoEF vide no. J-13012/12/2013-IA-II(I) dated 24th December, 2013. After
detailed deliberations the Committee sought following additional information for further consideration of
the proposal:
1. Land possession documents.
2. Project site specific details such as distance of the project site from the nearest (1) Village (2)
Water Body : Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway (4) State
Highway (5) Railway line (6) Heritage site (7) Marine National Park/National Park / Wild Life
Sanctuary / Reserve Forest.
3. Compliance of OM issued MoEF vide no. J-13012/12/2013-IA-II(I) dated 24th December, 2013
regarding condition of transportation of raw materials and products through Railway. Legal
undertaking in this regard shall be submitted.
4. Water balance diagram. Status of permission from the concern authority for water supply.
5. Detailed report for storm water drainage, management & disposal, measures proposed to avoid
contamination of the storm water as well as restricting the contaminated storm water not
allowing it to flow out of the premises.
6. Details of all possible sources of air pollution including the process emission as well as fugitive
emission along with the mitigation measures and the technical specifications of the proposed air
pollution control equipment [designed by credible institutes like NPC, LDCE and other such
institutes of repute] proposed to control the air pollution and the capability of the management to
Page 73 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 73 of 76
maintain and run the same during the operational phase of the project in the form of an
undertaking.
7. Detailed cleaner production measures to reduce emissions if possible in the proposed project &
commitment of the management on futuristic development / implementation for the same.
8. Details of all possible sources of noise pollution, its magnitude and mitigation measures
proposed to control it.
9. Occupational health impacts on the workers and its mitigation measures. Detailed safety
precautions proposed to avoid silica and cement dust hazard along with the personal protective
equipment to be provided to the workers.
10. A detailed cement dust and silica dust monitoring plan including the measurement and control.
Plan for medical examination of the workers exposed. Report for measurement of cement dust
at workers level as per GFR.
11. Type of ventilation proposed in the work area.
12. Details of the safety control measures to be implemented.
13. Source of raw material along with their mode of transport as well as the air pollution mitigation
measures proposed during transportation and handling of the various raw materials.
14. A detailed greenbelt development plan along with the commitment of the management to take
up extensive plantation in phased manner.
15. Details of scheme for surface as well as roof top rain water harvesting and ground water
recharge.
16. Detailed EMP including the protection and mitigation measures for impact on human health and
environment as well as detailed monitoring plan. The EMP should also include the concept of
waste minimization, recycle/reuse/recover techniques, energy conservation, natural resource
conservation, total capital cost and recurring cost/annum earmarked for environment pollution
control measures etc.
17. Undertaking from the project management regarding efficient floor sweeping with vacuum
cleaner device for reducing fugitive dust emission.
18. Undertaking from the project management regarding effective implementation of proposed
EMS.
The project shall be appraised on satisfactory submission of the above.
The additional information received from the project proponents, which was sought during various SEAC meetings for granting Environmental Clearance to the projects. The said submissions by the project proponents were considered by the committee during the meeting and as it was found satisfactory, the committee decided to recommend the following projects for grant of environmental clearance.
1. M/s: Charon Pharma Chem Industries, S. no. 183, At.: Hardesan, Ta.: & Dist.: Mehsana. 2. M/s: Universal Organics, Plot no. 124/9, GIDC-Nandesari, Dist.: Vadodara 3. M/s: Valiant Organics Pvt. Ltd. , Plot no: 2906,752,753, 754,755, GIDC-Sarigam,
Ta.: Umbergam, Dist.: Valsad. 4. M/s.: Swastik Laminates, S. no.. 203/15, B/H. Shaktiman Rotawetar, NH-8 b, Vill. Bhunava, Ta.
Gondal, Dist. Rajkot. 5. M/s: Colosperse Dyes & Intermediates, Plot No:508/1, GIDC Estse, Sachin, Choryasi, Surat.
Page 74 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 74 of 76
6. M/s: Aromatics (India) Pvt. Ltd. Plot No: 334, Phese-2 ,GGDC-GIDC Industrial Estate, Mithi Rohar, Gandhidham, Kutch.
7. M/s: M.D. Inducto Cast Ltd., Plot no:144, Paiki 1&2, Vill: Nesada, Ta: Sihor, Dist: Bhavnagar. 8. M/s: CRL Terminal Pvt. Ltd., Near Oil Jetty, Opp. IFFCO, Old Kandla, Ta.: Gandhidham, Dist.:
Kutch.
Following officers from the Geology and Mining Department attended the meeting:
1. Shri M.B.Shah, Royalty Inspector, Dist: Chota Udepur
Sr. No
District Ordinary Clay Riverbed Sand Total
1 Tapi ‐ 2 2
Above proposals of minor minerals which have been received by the Committee through the project proponent were taken up in the meeting.
1. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. no.
Proposal No.
Project Name
S NO Vill,
Taluka
District
Hectare
Rate of mining
Nearest Habitation
Name of the river
Proposed Use
1 SIA/GJ/MIN/
58308/2016
River Bed Sand Mining Project of Ghanshyambhai Narsinhbhai Patel
115,118 ni Same, Tapi Nadi Patt
Vill:Anturli,Ta:Nijar
Tapi 09-77-00
36,500 MTPM
Anturli:0.80 km
Tapi Construction
During SEAC meeting on 14/09/2016,Project proponent /Geologist /RQP remained absent to represent the above proposal before the committee. Hence, it was decided to defer the above proposal in one of the up coming SEAC meeting. The above proposal was considered and details are as below. Shri Rupesh B Patel remained present to represent above proposal before the committee. He informed that there is no bridge piers / water intake wells / irrigation structures within 500 m distance from boundary of above lease area. He explained that sand excavation will be done up to maximum 3 m depth or water level, whichever is less. Water sprinkling will be done during loading of material. All the transportation vehicles are proposed to be covered to avoid fugitive emission of fine particles. PP informed that setback distance of 10 meter will be maintained from the river bank to prevent bank erosion. PP further mentioned that copy of mining plan under approval, prefeasibility report including mitigation measures to curb pollution and details regarding non applicability of cluster formation for homogeneous minerals validated by the Asst. geologist are submitted.
Page 75 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 75 of 76
In project details, Asst. geologist has validated that there is no instream mining and lease area remains dry except during monsoon seasonThe above proposal was categorized as B2 as per the amended EIA Notification 2016. Considering the anticipated impacts of mining and mitigation measures proposed by the lease holder, committee unanimously decided to recommend the proposal for grant of environmental clearance to SEIAA with stipulation of standard conditions for Sand mining as approved in 232nd SEAC meeting held on 15thApril 2015 with compliance of all the conditions mentioned in Sustainable sand mining management guidelines 2016 of MOEF&CC, New Delhi.
2. RIVER BED SAND MINING PROJECT,DIST: TAPI
Sr. no.
Proposal No.
Project Name
S NO Vill,
Taluka
District
Hectare
Rate of mining
Nearest Habitation
Name of the river
Proposed Use
2 SIA/GJ/MIN/
58307/2016
Smt. Naynaben Pravinbhai Vasava
S NO: 1 to 4 Ni Same, Tapi Nadi Patt
Vill: Anturli,
Ta: Nijar
Tapi 10-00-00
New
37,500 MTPM
Anturli:0.82 km
Tapi Construction
During SEAC meeting on 14/09/2016,Project proponent /Geologist /RQP remained absent to represent the above proposal before the committee. Hence, it was decided to defer the above proposal in one of the up coming SEAC meeting. The above proposal was considered and details are as below. Shri Shanti A Bala remained present to represent above proposal before the committee. He informed that there is no bridge piers / water intake wells / irrigation structures within 500 m distance from boundary of above lease area. He explained that sand excavation will be done up to maximum 3 m depth or water level, whichever is less. Water sprinkling will be done during loading of material. All the transportation vehicles are proposed to be covered to avoid fugitive emission of fine particles. PP informed that setback distance of 10 meter will be maintained from the river bank to prevent bank erosion. PP further mentioned that copy of mining plan under approval, prefeasibility report including mitigation measures to curb pollution and details regarding non applicability of cluster formation for homogeneous minerals validated by the Asst. geologist are submitted.
In project details, Asst. geologist has validated that there is no instream mining and lease area remains dry except during monsoon season The above proposal was categorized as B2 as per the amended EIA Notification 2016.
Considering the anticipated impacts of mining and mitigation measures proposed by the lease holder, committee unanimously decided to recommend the proposal for grant of
Page 76 of 76
311th meeting of SEAC-Gujarat, Dated 24.10.2016 Page 76 of 76
environmental clearance to SEIAA with stipulation of standard conditions for Sand mining as approved in 232nd SEAC meeting held on 15thApril 2015 with compliance of all the conditions mentioned in Sustainable sand mining management guidelines 2016 of MOEF&CC, New Delhi.
ADDITIONAL AGENDA
1. Letter of Shri Bharat S. Dave regarding allotment of quarry permits without Environmental Clearance.
The aforementioned letter was received by this office on 21/10/2016 and it was deliberated in the meeting. After referring to the letter of Shri B.S.Dave, committee unanimously decided to forward the letter of Shri B.S.Dave to office of Geology and Mining,Gandhinagar as it is pertaining to that office.
Meeting ended with thanks to the Chair and the Members.
--------------------------------
Minutes approved by:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Vice Chairman, SEAC.
3. Shri R. J. Shah, Member, SEAC
4. Dr. V. K. Jain, Member, SEAC
5. Dr. Mayuri Pandya, Member, SEAC
6. Shri Rajesh I Shah, Member, SEAC.
7. Shri Natrajan Pratap, Member, SEAC