Pacific Team
description
Transcript of Pacific Team
Pacific Team For tomorrow may rain, so I’ll follow the sun.
A E C P a c i f i c T e a m 2006
Ajaya MallaUW Madison
Jeremy Tillman
StanfordKatie Walker
Stanford
Magnus Hellsten
KTH
Joannie Rios
UPR
Josh Odelson
Stanford
Construction Managers
ArchitectStructural Engineers
Owner
Erik Kneer
A E C P a c i f i c T e a m 2006
A E C P a c i f i c T e a m 2006
Team Vision
A E C P a c i f i c T e a m 2006
Team ProcessOwner
Construction Managers
ArchitectsEngineers
Solution
O
A
E
C
A E C P a c i f i c T e a m 2006
Site Information Project Details:
• University Building • Use: - Engineering School for Innovative Design
• Location: - San Francisco State University
• Construction in 2015
• $6.5 million Donation
N
A E C P a c i f i c T e a m 2006
Site Location
NEXT TO LAKE MERCED
NNN
A E C P a c i f i c T e a m 2006
Site Climate Information Mild Local Climate
Average Temp: - Mid- 40 deg
Precipitation: - 23 in rain/year
A E C P a c i f i c T e a m 2006
Site Conditions • 18 degree Slope
Hazards:
• Earthquakes – Zone 4 ~ 1-2 miles away from San Andreas Fault• Landslides• Liquefaction
Lake Merced
BLVD.MAP OF
LIQUIFACTION & LANDSLIDE POTENITIAL
SITE SLOPE
N
A E C P a c i f i c T e a m 2006
Site Master Plan
• Reflection Pond
• Bridge Building Entrance • Running/walking path to Lake - Platforms - Ramps - Stairs • Swale
• Natural Vegetation
N
A E C P a c i f i c T e a m 2006
Innovative Financing
University Foundation•$6.5 million to use•Meet current needs
Build Parking Garage•Alleviates university parking problems•Parking fees back Revenue Bonds•Return rate of 6%
$8,415,000
A E C P a c i f i c T e a m 2006
Schedule
Labs FinishedApril 30, 2016
Project Finish July 12, 2016
Site
Foundation
Interior Framing
Roof
MEP/Interior Finishes
A E C P a c i f i c T e a m 2006
Site Access
SITE
Street improvement for South access
Re-route runningpath
BUS STOPS
N
A E C P a c i f i c T e a m 2006
Site Layout
Material StorageSite officesSecurityWater/ElectricityWCParkingWaste containerEquipmentRecyle areaWorkshopWheel wash
N
A E C P a c i f i c T e a m 2006
Slope Stability Solutions Control:
1. Ground water pressure
- Horizontal Drains
2. Storm-water run-off
- Swales3. Slope erosion
- Re-vegetation- Gabions
SWALE
GABIONS
CROSS-SECTION
A E C P a c i f i c T e a m 2006
17 Base Isolators
19
’-4
”
19
’-4
”
1
9’-
4”
1
9’-
2”
1
9’-
2”
1
9’-
2”
19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”
Foundation Options:
1. Base Isolation2. Foundation
On-Grade
Trade Off Analysis:
Base IsolationDesign RequirementsCost of Structure = $2,155,000
SAVE $580,000
Foundation On-GradeDesign RequirementsCost of Structure = $1,575,000
REQUIRES:
1. Higher Building Design Forces
- Larger Structural Members
- Ductile Connections
58’-0”
REQUIRES:
1. Second Basement
2. Flexible Utility Connections
58’-0”
N
A E C P a c i f i c T e a m 2006
Foundation Solution Design:
• 12” Diameter Bored Pile• Concrete Grade Beams • 4” Concrete Slab On- Grade• Display Graphic for pile design
PILE CAP DETAIL
12 in
~ 40 ft
4 in
Pile Comparison:
• Bored - Cost = $9100/pile
• Driven - Cost = $6300/pile
A E C P a c i f i c T e a m 2006
Basement Floor Instructional Lab
Computer Lab
Seminar Rooms
Auditorium
Restroom
Storage
Balcony
116’-0”
116’-0”
N
A E C P a c i f i c T e a m 2006
Basement• MEP Room
19
’-4
”
19
’-4
”
1
9’-
4”
1
9’-
2”
1
9’-
2”
1
9’-
2”
19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”
• Gravity System:
- Steel Columns and Beams - Retaining Walls
• Lateral System:
Moment Frame - Column: HSS 16x16 - Beam: W12x120
Shear Wall - Concrete - 12” wide
Shear Wall Core - Concrete - 12” wide
1
9’-
4”
19
’-4
”
1
9’-
4”
1
9’-
2”
1
9’-
2”
1
9’-
2”
19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”
N
A E C P a c i f i c T e a m 2006
First Floor Small Classrooms
Large Classrooms
Administration
Storage
Restrooms
125’-0”
125’-0”
N
A E C P a c i f i c T e a m 2006
First Floor
Wall Truss:
• Span Auditorium
• Transfer Load
• Architectural requirement1
9’-
4”
19
’-4
”
1
9’-
4”
19
’-2
”
1
9’-
2”
19
’-2
”19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”
N
A E C P a c i f i c T e a m 2006
Wall Truss - Connection
Connection Detail:
• Gusset Plate• Pin Connection
19’-2”
12’-6”
58’-0”
A E C P a c i f i c T e a m 2006
Wall Truss: Load Path
58’-0”
A E C P a c i f i c T e a m 2006
Second FloorStudent offices
Faculty offices
Faculty Lounge
Restrooms
128’-0”
128’-0”
N
A E C P a c i f i c T e a m 2006
Special Features:
1. Link Bridge2. Lateral System3. Core-wall Interface
Second Floor
13
’-6
1
9’-
4”
1
9’-
4”
1
9’-
4”
1
9’-
2”
1
9’-
2”
1
9’-
2”
19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2” 13’-6
N
A E C P a c i f i c T e a m 2006
Moment Frame Connection
Moment Frame •Double Moment Connection•Biaxial Bending•Use of HSS square tubular section•Pre-North Ridge approved connection
Full Penetration WeldShear
Tab
Bolt
A E C P a c i f i c T e a m 2006
Second Floor
Link Bridge:
• Provides Diaphragm Action• Transfers Lateral Load to Shear Core• Shear Tab Connection to Girder
A E C P a c i f i c T e a m 2006
Lateral System Load Path
Moment Frame
Link Bridge
Shear Wall Core
Load Transfer Girder
N
A E C P a c i f i c T e a m 2006
Roof
128’-0”
128’-0”
Corrugated Metal
Glass
Solar Panels
Louvers
N
A E C P a c i f i c T e a m 2006
Building Section
Interior Spaces
Open Space
Outside Space
128’-0”
A E C P a c i f i c T e a m 2006
HVAC - Evolution
MECHANICAL SYSTEM
HYBRID SYSTEM
Supply
Return
A E C P a c i f i c T e a m 2006
Roof Evolution
A E C P a c i f i c T e a m 2006
Roof Evolution
A E C P a c i f i c T e a m 2006
Roof Structural Evolution
58 ft
30 ft
Efficient Load Path
Shallow Depth
A E C P a c i f i c T e a m 2006
ELLIPTICAL ROOF
(END TRUSS)
Roof Structural Evolution
ARCH TRUSS (WITH COLUMNS)
ELLIPTICAL TRUSS (VARIABLE DEPTH)
A E C P a c i f i c T e a m 2006
Trade Off Analysis
Arch Beam(Option-1)
Curved Truss(Option-2) Comparison
Architecture
Shallow structure Column free spaceSmaller section
Open space highly desired (Option-2)
Structure Efficient Lateral load resisting mechanism
Deep truss required for stiffness
Arch is more efficient
Costing Weight – 20 kip/TrussMore bending More handling
Weight – 21.5 kip/TrussMore welding
Negligible difference
A E C P a c i f i c T e a m 2006
Final Structural Design Key Structure
TOP CHORD (8.625 x 0.5 HSS)BOTTOM CHORD (8.625 x 0.375 HSS)DIAGONALS(7.5 x 0.375 HSS)GIRDER(W6x9 @ 6ft c/c)
58 ft
27 ft
3 ft
5.5 ft
Material Specification
Hollow SectionsASTM A500
Rolled open sectionASTM 529 (Gr 50 Steel)
Bolts & FastenersASTM A490
N
A E C P a c i f i c T e a m 2006
Load Carrying Mechanism
Gravity Load
(Dead / Live)
58 ft
30 ft
97 ft
Dead Load – 35 psf
Live Load - 20 psf
DL – 2.2 in. (L/331)
LL – 0.97 in. (L/725)
------------------------
(DL+LL)= 3.1 in.(L/225)
A E C P a c i f i c T e a m 2006
Load Carrying Mechanism
Lateral Load
(Seismic / Wind)
Wind – 20psf
Seismic – 20% DL
30 ft
58 ft
97 ft
Lateral Drift (max)
1.5 in ( H / 240)
A E C P a c i f i c T e a m 2006
Transverse Direction Bracing Lateral Load: - 0.5” Dia. Bracing rod.
CONNECTION DETAIL
12.5 k
A E C P a c i f i c T e a m 2006
Roof Connections - Conceptual TRUSS BASE
CONNECTION
-CONNECTS TO WIDE
FLANGE COLUMN
-PIN-TYPE DETAIL
3 ft
5.5 ft
A E C P a c i f i c T e a m 2006
Truss Construction (temporary) PREFABRICATED
C-CLAMP
BOLTS
SLOTTED ANGLE WELDED TO COLUMN
ADJUSTABLE COLUMN WITH ANGLED CUT
End Truss with Temporary Supports
A E C P a c i f i c T e a m 2006
2nd Floor Beam Completion
End Truss with Temporary Supports
Roof Construction
Center Truss Installation
TRUSS CHORD SPLICE (Detail
Below)
8.625 x 0.375” HSS
8.625 x 0.375” HSS
0.5” Round End Capping Plate
3/8” Single “V” Butt-Weld
TRUSS CHORD – SPLICE DETAIL
A E C P a c i f i c T e a m 2006
Roof ConnectionsDiagonal Truss Connection
8.625 x 0.5 HSS
(Diagonal truss chord)
0.5” thk capping plate
8.625 x 0.375 HSS (Parallel Truss chord)
3 nos. ½ in. dia (A490 bolts)
4”
0.75” thk end plate Welded to HSS
A E C P a c i f i c T e a m 2006
4D Construction
A E C P a c i f i c T e a m 2006
Cost Comparison
Winter Concept
SUBSTRUCTURE1%
EXTERIOR CLOSURE22%
FOUNDATION7%SITEWORK
6%
EQUIPMENT0%
ELECTRICAL13%
ROOFING & WATERPROOFING
2%
CONVEYING SYSTEM
1% INTERIOR CONSTRUCTION
12%
SUPERSTRUCTURE17%
MECHANICAL19%
Spring Concept
EXTERIOR CLOSURE18%
SUBSTRUCTURE2%
FOUNDATION3%SITEWORK
6%
EQUIPMENT0%
ELECTRICAL16%
ROOFING & WATERPROOFING
2%
CONVEYING SYSTEM
1%
INTERIOR CONSTRUCTION
13%
SUPERSTRUCTURE24%
MECHANICAL15%
Cost Changes
•Superstructure + Increased Truss Steel
• Exterior Closure – Changed from glass to corrugated metal
• Mechanical costs + Under-estimated cost Natural ventilation
•Foundation – Overdesigned piles
• Overall building cost Lowered by $515,000
Finish July 12, 2016
$8,630,000
$8,115,000
$SSU Global Teamwork Center DATED 2/10/2005
ARCHITECT: Joannie Rios
TECHNOLOGY CONCEPT - COLUMNS Building Gross Square Footage 30,000 GSF
Item Description Quantity Unit Unit Price Sub Total Cost/Sf Comments
00 DEMOLITION N/A N/A Building Demolition n/a
01 FOUNDATION $277,250 $9.24
Concrete Piers 23 EA 11,000.00$ 253,000.00$ 8.43$ Piles, 200kip load
Pile Caps 5 CY 250.00$ 1,250.00$ 0.04$ Grade Beams 92 CY 250.00$ 23,000.00$ 0.77$ Structural Excavation Caps/ Grade Beams 110 CY 20.00$ 2,200.00$ 0.07$
02 SUBSTRUCTURE $110,600 $3.69Mass Excavation 1,490 CY 20.00$ 29,800.00$ 0.99$
Retaining Wall 2,600 SF 25.00$ 65,000.00$ 2.17$ 13' high wall,
pumpedSlab on Grade 9,600 SF 4.75$ 45,600.00$ 1.52$ 4" reinforced
03 SUPERSTRUCTURE $1,713,150 $57.11Structural Steel - Standard 235 TONS 4,000.00$ 940,000.00$ 31.33$ Structural Steel - Curved 107 TONS 4,500.00$ 481,500.00$ 16.05$ Concrete Fill over Metal Deck 24,100 SF 4.50$ 108,450.00$ 3.62$ Metal Deck 24,100 SF 2.00$ 48,200.00$ 1.61$ Fireproofing 300 TONS 200.00$ 60,000.00$ 2.00$ Misc. Steel & Metal Stair 1 LS 75,000.00$ 75,000.00$ 2.50$
04 EXTERIOR CLOSURE $1,477,000 $49.23Curved Curtainwall 20,100 SF 70.00$ 1,407,000.00$ 46.90$ Flat End Windows 1,000 SF 45.00$ 45,000.00$ 1.50$ Louvers 1,000 SF 25.00$ 25,000.00$ 0.83$
05 ROOFING & WATERPROOFING $120,000 $4.00Waterproofing 30,000 SF 1.00$ 30,000.00$ 1.00$ Flashing & Sheet Metal 30,000 SF 2.00$ 60,000.00$ 2.00$ Sealants and Caulking 30,000 SF 1.00$ 30,000.00$ 1.00$
06 INTERIOR CONSTRUCTION $954,000 $31.80Doors, Frames & Hardware 70 EA 1,500.00$ 105,000.00$ 3.50$ Wall, Floor, Ceiling Finishes 30,000 SF 25.00$ 750,000.00$ 25.00$ Atrium 1 EA 50,000.00$ 50,000.00$ 1.67$ Building Insulation 30,000 SF 0.50$ 15,000.00$ 0.50$ Miscellaneous Specialties 1 LS 15,000.00$ 15,000.00$ 0.50$ Toilet and Bath Accessories 9 EA 1,000.00$ 9,000.00$ 0.30$ Main Entrance Doors 1 ea 10,000.00$ 10,000.00$ 0.33$
07 CONVEYING SYSTEM $100,000 $3.33Elevators 1 EA 100,000.00$ 100,000.00$ 3.33$
08 MECHANICAL $1,206,000 $40.20Fire Protection 30,000 SF 2.50$ 75,000.00$ 2.50$ Plumbing 18 FIX 4,500.00$ 81,000.00$ 2.70$ HVAC 30,000 SF 35.00$ 1,050,000.00$ 35.00$
09 ELECTRICAL $1,050,000 $35.00Electrical 30,000 SF 35.00$ 1,050,000.00$ 35.00$
11 EQUIPMENT $15,000 $0.50Trash Chute and Compactor 1 LS 15,000.00$ 15,000.00$ 0.50$
12 SITEWORK $420,000 $14.00
Site Preparation 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Concrete 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Improvements, AC Paving 1 Allow 100,000.00$ 100,000.00$ 3.33$ Landscape & Irrigation 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Utilities 1 Alllow 100,000.00$ 100,000.00$ 3.33$ Gabions, horizontal drains 1 Alllow 50,000.00$ 50,000.00$ 1.67$ Pedestrain Trail Alteration 1 Allow 20,000.00$ 20,000.00$ 0.67$ INDIRECT COST 7,055,000.00$ $7,023,000 $220.10 General Conditions 15% $1,058,250 $1,058,250 $35.28Fee 5% $352,750 $352,750 $11.76Contingency 5% $352,750 $352,750 $11.76TOTAL COST $8,818,750 $8,786,750 $292.89
A E C P a c i f i c T e a m 2006
LEED - SustainabilityLEED-NC Version 2.2 Registered Project Checklist
Yes ? No
7 2 6 Sustainable Sites 14 Points
Prereq 1 Construction Activity Pollution Prevention Required
Credit 1 Site Selection 1
Credit 2 Development Density & Community Connectivity 1
Credit 3 Brownfield Redevelopment 1
Credit 4.1 Alternative Transportation, Public Transportation Access 1
Credit 4.2 Alternative Transportation, Bicycle Storage & Changing Rooms 1
Credit 4.3 Alternative Transportation, Low-Emitting and Fuel-Efficient Vehicles 1
Credit 4.4 Alternative Transportation, Parking Capacity 1
Credit 5.1 Site Development, Protect of Restore Habitat 1
Credit 5.2 Site Development, Maximize Open Space 1
Credit 6.1 Stormwater Design, Quantity Control 1
Credit 6.2 Stormwater Design, Quality Control 1
Credit 7.1 Heat Island Effect, Non-Roof 1
Credit 7.2 Heat Island Effect, Roof 1
Credit 8 Light Pollution Reduction 1
Yes ? No
4 1 Water Efficiency 5 Points
Credit 1.1 Water Efficient Landscaping, Reduce by 50% 1
Credit 1.2 Water Efficient Landscaping, No Potable Use or No Irrigation 1
Credit 2 Innovative Wastewater Technologies 1
Credit 3.1 Water Use Reduction, 20% Reduction 1
Credit 3.2 Water Use Reduction, 30% Reduction 1
Yes ? No
5 3 1 Energy & Atmosphere 17 Points
Prereq 1 Fundamental Commissioning of the Building Energy Systems Required
Prereq 2 Minimum Energy Performance Required
Prereq 3 Fundamental Refrigerant Management Required
Credit 1 Optimize Energy Performance 1 to 10
Credit 2 On-Site Renewable Energy 1 to 3
Credit 3 Enhanced Commissioning 1
Credit 4 Enhanced Refrigerant Management 1
Credit 5 Measurement & Verification 1
Credit 6 Green Power 1
continued…
Yes ? No
2 10 1 Materials & Resources 13 Points
Prereq 1 Storage & Collection of Recyclables Required
Credit 1.1 Building Reuse, Maintain 75% of Existing Walls, Floors & Roof 1
Credit 1.2 Building Reuse, Maintain 100% of Existing Walls, Floors & Roof 1
Credit 1.3 Building Reuse, Maintain 50% of Interior Non-Structural Elements 1
Credit 2.1 Construction Waste Management, Divert 50% from Disposal 1
Credit 2.2 Construction Waste Management, Divert 75% from Disposal 1
Credit 3.1 Materials Reuse, 5% 1
Credit 3.2 Materials Reuse,10% 1
Credit 4.1 Recycled Content, 10% (post-consumer + ½ pre-consumer) 1
Credit 4.2 Recycled Content, 20% (post-consumer + ½ pre-consumer) 1
Credit 5.1 Regional Materials, 10% Extracted, Processed & Manufactured Regionally 1
Credit 5.2 Regional Materials, 20% Extracted, Processed & Manufactured Regionally 1
Credit 6 Rapidly Renewable Materials 1
Credit 7 Certified Wood 1
Yes ? No
11 6 Indoor Environmental Quality 15 Points
TechnologySan Francisco State University
Prereq 1 Minimum IAQ Performance RequiredPrereq 2 Environmental Tobacco Smoke (ETS) Control RequiredCredit 1 Outdoor Air Delivery Monitoring 1Credit 2 Increased Ventilation 1Credit 3.1 Construction IAQ Management Plan, During Construction 1Credit 3.2 Construction IAQ Management Plan, Before Occupancy 1Credit 4.1 Low-Emitting Materials, Adhesives & Sealants 1Credit 4.2 Low-Emitting Materials, Paints & Coatings 1Credit 4.3 Low-Emitting Materials, Carpet Systems 1Credit 4.4 Low-Emitting Materials, Composite Wood & Agrifiber Products 1Credit 5 Indoor Chemical & Pollutant Source Control 1Credit 6.1 Controllability of Systems, Lighting 1Credit 6.2 Controllability of Systems, Thermal Comfort 1Credit 7.1 Thermal Comfort, Design 1Credit 7.2 Thermal Comfort, Verification 1Credit 8.1 Daylight & Views, Daylight 75% of Spaces 1Credit 8.2 Daylight & Views, Views for 90% of Spaces 1
Yes ? No
5 Innovation & Design Process 5 Points
Credit 1.1 Innovation in Design: Provide Specific Title 1
Credit 1.2 Innovation in Design: Provide Specific Title 1
Credit 1.3 Innovation in Design: Provide Specific Title 1
Credit 1.4 Innovation in Design: Provide Specific Title 1
Credit 2 LEED® Accredited Professional 1
Yes ? No
29 26 9 Project Totals (pre-certification estimates) 69 Points
Certified 26-32 points Silver 33-38 points Gold 39-51 points Platinum 52-69 points
29 Points
LEED Certification
• Rain water collection
• PV Cells
• Natural ventilation
• Sustainable material
• Sustainable construction
A E C P a c i f i c T e a m 2006
A E C P a c i f i c T e a m 2006