Pacific Team

49
Pacific Team For tomorrow may rain, so I’ll follow the sun.

description

For tomorrow may rain, so I’ll follow the sun. Pacific Team. Ajaya Malla UW Madison. Structural Engineers. Architect. Jeremy Tillman Stanford. Katie Walker Stanford. Joannie Rios UPR. Construction Managers. Owner. Erik Kneer. Josh Odelson Stanford. Magnus Hellsten KTH. - PowerPoint PPT Presentation

Transcript of Pacific Team

Page 1: Pacific Team

Pacific Team For tomorrow may rain, so I’ll follow the sun.

Page 2: Pacific Team

A E C P a c i f i c T e a m 2006

Ajaya MallaUW Madison

Jeremy Tillman

StanfordKatie Walker

Stanford

Magnus Hellsten

KTH

Joannie Rios

UPR

Josh Odelson

Stanford

Construction Managers

ArchitectStructural Engineers

Owner

Erik Kneer

Page 3: Pacific Team

A E C P a c i f i c T e a m 2006

Page 4: Pacific Team

A E C P a c i f i c T e a m 2006

Team Vision

Page 5: Pacific Team

A E C P a c i f i c T e a m 2006

Team ProcessOwner

Construction Managers

ArchitectsEngineers

Solution

O

A

E

C

Page 6: Pacific Team

A E C P a c i f i c T e a m 2006

Site Information Project Details:

• University Building • Use: - Engineering School for Innovative Design

• Location: - San Francisco State University

• Construction in 2015

• $6.5 million Donation

N

Page 7: Pacific Team

A E C P a c i f i c T e a m 2006

Site Location

NEXT TO LAKE MERCED

NNN

Page 8: Pacific Team

A E C P a c i f i c T e a m 2006

Site Climate Information Mild Local Climate

Average Temp: - Mid- 40 deg

Precipitation: - 23 in rain/year

Page 9: Pacific Team

A E C P a c i f i c T e a m 2006

Site Conditions • 18 degree Slope

Hazards:

• Earthquakes – Zone 4 ~ 1-2 miles away from San Andreas Fault• Landslides• Liquefaction

Lake Merced

BLVD.MAP OF

LIQUIFACTION & LANDSLIDE POTENITIAL

SITE SLOPE

N

Page 10: Pacific Team

A E C P a c i f i c T e a m 2006

Site Master Plan

• Reflection Pond

• Bridge Building Entrance • Running/walking path to Lake - Platforms - Ramps - Stairs • Swale

• Natural Vegetation

N

Page 11: Pacific Team

A E C P a c i f i c T e a m 2006

Innovative Financing

University Foundation•$6.5 million to use•Meet current needs

Build Parking Garage•Alleviates university parking problems•Parking fees back Revenue Bonds•Return rate of 6%

$8,415,000

Page 12: Pacific Team

A E C P a c i f i c T e a m 2006

Schedule

Labs FinishedApril 30, 2016

Project Finish July 12, 2016

Site

Foundation

Interior Framing

Roof

MEP/Interior Finishes

Page 13: Pacific Team

A E C P a c i f i c T e a m 2006

Site Access

SITE

Street improvement for South access

Re-route runningpath

BUS STOPS

N

Page 14: Pacific Team

A E C P a c i f i c T e a m 2006

Site Layout

Material StorageSite officesSecurityWater/ElectricityWCParkingWaste containerEquipmentRecyle areaWorkshopWheel wash

N

Page 15: Pacific Team

A E C P a c i f i c T e a m 2006

Slope Stability Solutions Control:

1. Ground water pressure

- Horizontal Drains

2. Storm-water run-off

- Swales3. Slope erosion

- Re-vegetation- Gabions

SWALE

GABIONS

CROSS-SECTION

Page 16: Pacific Team

A E C P a c i f i c T e a m 2006

17 Base Isolators

19

’-4

19

’-4

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

Foundation Options:

1. Base Isolation2. Foundation

On-Grade

Trade Off Analysis:

Base IsolationDesign RequirementsCost of Structure = $2,155,000

SAVE $580,000

Foundation On-GradeDesign RequirementsCost of Structure = $1,575,000

REQUIRES:

1. Higher Building Design Forces

- Larger Structural Members

- Ductile Connections

58’-0”

REQUIRES:

1. Second Basement

2. Flexible Utility Connections

58’-0”

N

Page 17: Pacific Team

A E C P a c i f i c T e a m 2006

Foundation Solution Design:

• 12” Diameter Bored Pile• Concrete Grade Beams • 4” Concrete Slab On- Grade• Display Graphic for pile design

PILE CAP DETAIL

12 in

~ 40 ft

4 in

Pile Comparison:

• Bored - Cost = $9100/pile

• Driven - Cost = $6300/pile

Page 18: Pacific Team

A E C P a c i f i c T e a m 2006

Basement Floor Instructional Lab

Computer Lab

Seminar Rooms

Auditorium

Restroom

Storage

Balcony

116’-0”

116’-0”

N

Page 19: Pacific Team

A E C P a c i f i c T e a m 2006

Basement• MEP Room

19

’-4

19

’-4

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

• Gravity System:

- Steel Columns and Beams - Retaining Walls

• Lateral System:

Moment Frame - Column: HSS 16x16 - Beam: W12x120

Shear Wall - Concrete - 12” wide

Shear Wall Core - Concrete - 12” wide

1

9’-

4”

19

’-4

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

N

Page 20: Pacific Team

A E C P a c i f i c T e a m 2006

First Floor Small Classrooms

Large Classrooms

Administration

Storage

Restrooms

125’-0”

125’-0”

N

Page 21: Pacific Team

A E C P a c i f i c T e a m 2006

First Floor

Wall Truss:

• Span Auditorium

• Transfer Load

• Architectural requirement1

9’-

4”

19

’-4

1

9’-

4”

19

’-2

1

9’-

2”

19

’-2

”19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

N

Page 22: Pacific Team

A E C P a c i f i c T e a m 2006

Wall Truss - Connection

Connection Detail:

• Gusset Plate• Pin Connection

19’-2”

12’-6”

58’-0”

Page 23: Pacific Team

A E C P a c i f i c T e a m 2006

Wall Truss: Load Path

58’-0”

Page 24: Pacific Team

A E C P a c i f i c T e a m 2006

Second FloorStudent offices

Faculty offices

Faculty Lounge

Restrooms

128’-0”

128’-0”

N

Page 25: Pacific Team

A E C P a c i f i c T e a m 2006

Special Features:

1. Link Bridge2. Lateral System3. Core-wall Interface

Second Floor

13

’-6

1

9’-

4”

1

9’-

4”

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2” 13’-6

N

Page 26: Pacific Team

A E C P a c i f i c T e a m 2006

Moment Frame Connection

Moment Frame •Double Moment Connection•Biaxial Bending•Use of HSS square tubular section•Pre-North Ridge approved connection

Full Penetration WeldShear

Tab

Bolt

Page 27: Pacific Team

A E C P a c i f i c T e a m 2006

Second Floor

Link Bridge:

• Provides Diaphragm Action• Transfers Lateral Load to Shear Core• Shear Tab Connection to Girder

Page 28: Pacific Team

A E C P a c i f i c T e a m 2006

Lateral System Load Path

Moment Frame

Link Bridge

Shear Wall Core

Load Transfer Girder

N

Page 29: Pacific Team

A E C P a c i f i c T e a m 2006

Roof

128’-0”

128’-0”

Corrugated Metal

Glass

Solar Panels

Louvers

N

Page 30: Pacific Team

A E C P a c i f i c T e a m 2006

Building Section

Interior Spaces

Open Space

Outside Space

128’-0”

Page 31: Pacific Team

A E C P a c i f i c T e a m 2006

HVAC - Evolution

MECHANICAL SYSTEM

HYBRID SYSTEM

Supply

Return

Page 32: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Evolution

Page 33: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Evolution

Page 34: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Structural Evolution

58 ft

30 ft

Efficient Load Path

Shallow Depth

Page 35: Pacific Team

A E C P a c i f i c T e a m 2006

ELLIPTICAL ROOF

(END TRUSS)

Roof Structural Evolution

ARCH TRUSS (WITH COLUMNS)

ELLIPTICAL TRUSS (VARIABLE DEPTH)

Page 36: Pacific Team

A E C P a c i f i c T e a m 2006

Trade Off Analysis

Arch Beam(Option-1)

Curved Truss(Option-2) Comparison

Architecture

Shallow structure Column free spaceSmaller section

Open space highly desired (Option-2)

Structure Efficient Lateral load resisting mechanism

Deep truss required for stiffness

Arch is more efficient

Costing Weight – 20 kip/TrussMore bending More handling

Weight – 21.5 kip/TrussMore welding

Negligible difference

Page 37: Pacific Team

A E C P a c i f i c T e a m 2006

Final Structural Design Key Structure

TOP CHORD (8.625 x 0.5 HSS)BOTTOM CHORD (8.625 x 0.375 HSS)DIAGONALS(7.5 x 0.375 HSS)GIRDER(W6x9 @ 6ft c/c)

58 ft

27 ft

3 ft

5.5 ft

Material Specification

Hollow SectionsASTM A500

Rolled open sectionASTM 529 (Gr 50 Steel)

Bolts & FastenersASTM A490

N

Page 38: Pacific Team

A E C P a c i f i c T e a m 2006

Load Carrying Mechanism

Gravity Load

(Dead / Live)

58 ft

30 ft

97 ft

Dead Load – 35 psf

Live Load - 20 psf

DL – 2.2 in. (L/331)

LL – 0.97 in. (L/725)

------------------------

(DL+LL)= 3.1 in.(L/225)

Page 39: Pacific Team

A E C P a c i f i c T e a m 2006

Load Carrying Mechanism

Lateral Load

(Seismic / Wind)

Wind – 20psf

Seismic – 20% DL

30 ft

58 ft

97 ft

Lateral Drift (max)

1.5 in ( H / 240)

Page 40: Pacific Team

A E C P a c i f i c T e a m 2006

Transverse Direction Bracing Lateral Load: - 0.5” Dia. Bracing rod.

CONNECTION DETAIL

12.5 k

Page 41: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Connections - Conceptual TRUSS BASE

CONNECTION

-CONNECTS TO WIDE

FLANGE COLUMN

-PIN-TYPE DETAIL

3 ft

5.5 ft

Page 42: Pacific Team

A E C P a c i f i c T e a m 2006

Truss Construction (temporary) PREFABRICATED

C-CLAMP

BOLTS

SLOTTED ANGLE WELDED TO COLUMN

ADJUSTABLE COLUMN WITH ANGLED CUT

End Truss with Temporary Supports

Page 43: Pacific Team

A E C P a c i f i c T e a m 2006

2nd Floor Beam Completion

End Truss with Temporary Supports

Roof Construction

Center Truss Installation

TRUSS CHORD SPLICE (Detail

Below)

8.625 x 0.375” HSS

8.625 x 0.375” HSS

0.5” Round End Capping Plate

3/8” Single “V” Butt-Weld

TRUSS CHORD – SPLICE DETAIL

Page 44: Pacific Team

A E C P a c i f i c T e a m 2006

Roof ConnectionsDiagonal Truss Connection

8.625 x 0.5 HSS

(Diagonal truss chord)

0.5” thk capping plate

8.625 x 0.375 HSS (Parallel Truss chord)

3 nos. ½ in. dia (A490 bolts)

4”

0.75” thk end plate Welded to HSS

Page 45: Pacific Team

A E C P a c i f i c T e a m 2006

4D Construction

Page 46: Pacific Team

A E C P a c i f i c T e a m 2006

Cost Comparison

Winter Concept

SUBSTRUCTURE1%

EXTERIOR CLOSURE22%

FOUNDATION7%SITEWORK

6%

EQUIPMENT0%

ELECTRICAL13%

ROOFING & WATERPROOFING

2%

CONVEYING SYSTEM

1% INTERIOR CONSTRUCTION

12%

SUPERSTRUCTURE17%

MECHANICAL19%

Spring Concept

EXTERIOR CLOSURE18%

SUBSTRUCTURE2%

FOUNDATION3%SITEWORK

6%

EQUIPMENT0%

ELECTRICAL16%

ROOFING & WATERPROOFING

2%

CONVEYING SYSTEM

1%

INTERIOR CONSTRUCTION

13%

SUPERSTRUCTURE24%

MECHANICAL15%

Cost Changes

•Superstructure + Increased Truss Steel

• Exterior Closure – Changed from glass to corrugated metal

• Mechanical costs + Under-estimated cost Natural ventilation

•Foundation – Overdesigned piles

• Overall building cost Lowered by $515,000

Finish July 12, 2016

$8,630,000

$8,115,000

$SSU Global Teamwork Center DATED 2/10/2005

ARCHITECT: Joannie Rios

TECHNOLOGY CONCEPT - COLUMNS Building Gross Square Footage 30,000 GSF

Item Description Quantity Unit Unit Price Sub Total Cost/Sf Comments

00 DEMOLITION N/A N/A Building Demolition n/a

01 FOUNDATION $277,250 $9.24

Concrete Piers 23 EA 11,000.00$ 253,000.00$ 8.43$ Piles, 200kip load

Pile Caps 5 CY 250.00$ 1,250.00$ 0.04$ Grade Beams 92 CY 250.00$ 23,000.00$ 0.77$ Structural Excavation Caps/ Grade Beams 110 CY 20.00$ 2,200.00$ 0.07$

02 SUBSTRUCTURE $110,600 $3.69Mass Excavation 1,490 CY 20.00$ 29,800.00$ 0.99$

Retaining Wall 2,600 SF 25.00$ 65,000.00$ 2.17$ 13' high wall,

pumpedSlab on Grade 9,600 SF 4.75$ 45,600.00$ 1.52$ 4" reinforced

03 SUPERSTRUCTURE $1,713,150 $57.11Structural Steel - Standard 235 TONS 4,000.00$ 940,000.00$ 31.33$ Structural Steel - Curved 107 TONS 4,500.00$ 481,500.00$ 16.05$ Concrete Fill over Metal Deck 24,100 SF 4.50$ 108,450.00$ 3.62$ Metal Deck 24,100 SF 2.00$ 48,200.00$ 1.61$ Fireproofing 300 TONS 200.00$ 60,000.00$ 2.00$ Misc. Steel & Metal Stair 1 LS 75,000.00$ 75,000.00$ 2.50$

04 EXTERIOR CLOSURE $1,477,000 $49.23Curved Curtainwall 20,100 SF 70.00$ 1,407,000.00$ 46.90$ Flat End Windows 1,000 SF 45.00$ 45,000.00$ 1.50$ Louvers 1,000 SF 25.00$ 25,000.00$ 0.83$

05 ROOFING & WATERPROOFING $120,000 $4.00Waterproofing 30,000 SF 1.00$ 30,000.00$ 1.00$ Flashing & Sheet Metal 30,000 SF 2.00$ 60,000.00$ 2.00$ Sealants and Caulking 30,000 SF 1.00$ 30,000.00$ 1.00$

06 INTERIOR CONSTRUCTION $954,000 $31.80Doors, Frames & Hardware 70 EA 1,500.00$ 105,000.00$ 3.50$ Wall, Floor, Ceiling Finishes 30,000 SF 25.00$ 750,000.00$ 25.00$ Atrium 1 EA 50,000.00$ 50,000.00$ 1.67$ Building Insulation 30,000 SF 0.50$ 15,000.00$ 0.50$ Miscellaneous Specialties 1 LS 15,000.00$ 15,000.00$ 0.50$ Toilet and Bath Accessories 9 EA 1,000.00$ 9,000.00$ 0.30$ Main Entrance Doors 1 ea 10,000.00$ 10,000.00$ 0.33$

07 CONVEYING SYSTEM $100,000 $3.33Elevators 1 EA 100,000.00$ 100,000.00$ 3.33$

08 MECHANICAL $1,206,000 $40.20Fire Protection 30,000 SF 2.50$ 75,000.00$ 2.50$ Plumbing 18 FIX 4,500.00$ 81,000.00$ 2.70$ HVAC 30,000 SF 35.00$ 1,050,000.00$ 35.00$

09 ELECTRICAL $1,050,000 $35.00Electrical 30,000 SF 35.00$ 1,050,000.00$ 35.00$

11 EQUIPMENT $15,000 $0.50Trash Chute and Compactor 1 LS 15,000.00$ 15,000.00$ 0.50$

12 SITEWORK $420,000 $14.00

Site Preparation 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Concrete 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Improvements, AC Paving 1 Allow 100,000.00$ 100,000.00$ 3.33$ Landscape & Irrigation 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Utilities 1 Alllow 100,000.00$ 100,000.00$ 3.33$ Gabions, horizontal drains 1 Alllow 50,000.00$ 50,000.00$ 1.67$ Pedestrain Trail Alteration 1 Allow 20,000.00$ 20,000.00$ 0.67$ INDIRECT COST 7,055,000.00$ $7,023,000 $220.10 General Conditions 15% $1,058,250 $1,058,250 $35.28Fee 5% $352,750 $352,750 $11.76Contingency 5% $352,750 $352,750 $11.76TOTAL COST $8,818,750 $8,786,750 $292.89

Page 47: Pacific Team

A E C P a c i f i c T e a m 2006

LEED - SustainabilityLEED-NC Version 2.2 Registered Project Checklist

Yes ? No

7 2 6 Sustainable Sites 14 Points

Prereq 1 Construction Activity Pollution Prevention Required

Credit 1 Site Selection 1

Credit 2 Development Density & Community Connectivity 1

Credit 3 Brownfield Redevelopment 1

Credit 4.1 Alternative Transportation, Public Transportation Access 1

Credit 4.2 Alternative Transportation, Bicycle Storage & Changing Rooms 1

Credit 4.3 Alternative Transportation, Low-Emitting and Fuel-Efficient Vehicles 1

Credit 4.4 Alternative Transportation, Parking Capacity 1

Credit 5.1 Site Development, Protect of Restore Habitat 1

Credit 5.2 Site Development, Maximize Open Space 1

Credit 6.1 Stormwater Design, Quantity Control 1

Credit 6.2 Stormwater Design, Quality Control 1

Credit 7.1 Heat Island Effect, Non-Roof 1

Credit 7.2 Heat Island Effect, Roof 1

Credit 8 Light Pollution Reduction 1

Yes ? No

4 1 Water Efficiency 5 Points

Credit 1.1 Water Efficient Landscaping, Reduce by 50% 1

Credit 1.2 Water Efficient Landscaping, No Potable Use or No Irrigation 1

Credit 2 Innovative Wastewater Technologies 1

Credit 3.1 Water Use Reduction, 20% Reduction 1

Credit 3.2 Water Use Reduction, 30% Reduction 1

Yes ? No

5 3 1 Energy & Atmosphere 17 Points

Prereq 1 Fundamental Commissioning of the Building Energy Systems Required

Prereq 2 Minimum Energy Performance Required

Prereq 3 Fundamental Refrigerant Management Required

Credit 1 Optimize Energy Performance 1 to 10

Credit 2 On-Site Renewable Energy 1 to 3

Credit 3 Enhanced Commissioning 1

Credit 4 Enhanced Refrigerant Management 1

Credit 5 Measurement & Verification 1

Credit 6 Green Power 1

continued…

Yes ? No

2 10 1 Materials & Resources 13 Points

Prereq 1 Storage & Collection of Recyclables Required

Credit 1.1 Building Reuse, Maintain 75% of Existing Walls, Floors & Roof 1

Credit 1.2 Building Reuse, Maintain 100% of Existing Walls, Floors & Roof 1

Credit 1.3 Building Reuse, Maintain 50% of Interior Non-Structural Elements 1

Credit 2.1 Construction Waste Management, Divert 50% from Disposal 1

Credit 2.2 Construction Waste Management, Divert 75% from Disposal 1

Credit 3.1 Materials Reuse, 5% 1

Credit 3.2 Materials Reuse,10% 1

Credit 4.1 Recycled Content, 10% (post-consumer + ½ pre-consumer) 1

Credit 4.2 Recycled Content, 20% (post-consumer + ½ pre-consumer) 1

Credit 5.1 Regional Materials, 10% Extracted, Processed & Manufactured Regionally 1

Credit 5.2 Regional Materials, 20% Extracted, Processed & Manufactured Regionally 1

Credit 6 Rapidly Renewable Materials 1

Credit 7 Certified Wood 1

Yes ? No

11 6 Indoor Environmental Quality 15 Points

TechnologySan Francisco State University

Prereq 1 Minimum IAQ Performance RequiredPrereq 2 Environmental Tobacco Smoke (ETS) Control RequiredCredit 1 Outdoor Air Delivery Monitoring 1Credit 2 Increased Ventilation 1Credit 3.1 Construction IAQ Management Plan, During Construction 1Credit 3.2 Construction IAQ Management Plan, Before Occupancy 1Credit 4.1 Low-Emitting Materials, Adhesives & Sealants 1Credit 4.2 Low-Emitting Materials, Paints & Coatings 1Credit 4.3 Low-Emitting Materials, Carpet Systems 1Credit 4.4 Low-Emitting Materials, Composite Wood & Agrifiber Products 1Credit 5 Indoor Chemical & Pollutant Source Control 1Credit 6.1 Controllability of Systems, Lighting 1Credit 6.2 Controllability of Systems, Thermal Comfort 1Credit 7.1 Thermal Comfort, Design 1Credit 7.2 Thermal Comfort, Verification 1Credit 8.1 Daylight & Views, Daylight 75% of Spaces 1Credit 8.2 Daylight & Views, Views for 90% of Spaces 1

Yes ? No

5 Innovation & Design Process 5 Points

Credit 1.1 Innovation in Design: Provide Specific Title 1

Credit 1.2 Innovation in Design: Provide Specific Title 1

Credit 1.3 Innovation in Design: Provide Specific Title 1

Credit 1.4 Innovation in Design: Provide Specific Title 1

Credit 2 LEED® Accredited Professional 1

Yes ? No

29 26 9 Project Totals (pre-certification estimates) 69 Points

Certified 26-32 points Silver 33-38 points Gold 39-51 points Platinum 52-69 points

29 Points

LEED Certification

• Rain water collection

• PV Cells

• Natural ventilation

• Sustainable material

• Sustainable construction

Page 48: Pacific Team

A E C P a c i f i c T e a m 2006

Page 49: Pacific Team

A E C P a c i f i c T e a m 2006