P922 (81H-L) Test Report Rev 1
-
Upload
samiahmedmansour -
Category
Documents
-
view
218 -
download
0
description
Transcript of P922 (81H-L) Test Report Rev 1
1
Gulf Cooperation Council
Interconnection Authority
GCCIATRANSMISSION & DISTRIBUTION
Engineer
GCC Interconnection Project - Phase I
P922Site Acceptance Test Report
MiCOM P922
81H/LBay Ref:Substation:
SUMMARYREVISION
PAGES01
1PURPOSE OF TESTS2X
2REFERENCE DOCUMENT2X
3SCOPE2X
4RELAY TERMINLOGY 3X
5TEST EQUIPMENT3X
6PRE-REQUISTES3X
7PROCEDURES4X
8RECORD TEST SHEET6X
8.1 RELAY INFORMATION
8.2 VT DATA:
8.3 PRODUCT CHECKS
8.4 MEASURMENT VALUE TEST:
8.5 OVER FREQUENCY PROTECTION
8.6 UNDER FREQUENCY PROTECTION
8.7 BINARY INPUT TEST :
8.8 BINARY OUTPUT TEST:
8.9 FIXED LED INDICATIONS TEST:
8.10 LED INDICATIONS TEST:
8.11 FINAL CHECK
1 PURPOSE OF TESTSThe purpose of the tests is to check the full functionality of the protection relay.This procedure does not intend to check that all alarms and trips are correctly sent to the DCS or SCADA level. This part is already developed into dedicated DCS or SCADA Commissioning procedures.This procedure does not intend to check all tripping matrix and PSL logic tests, this, when applicable, is described into a separate document, dedicated to the specific substation and feeder type.
2 REFERENCE DOCUMENTSDOCUMENTDOCUMENT REFERENCEVERSION/ DATEREMARKS
Protection Line Diagram
Schematic Drawing
Service Manual
Operation Manual
Protection Relay Coordination Principles
Relay setting Calculation
LED Display Configuration
3 SCOPE
Substation Name :-
Diameter:
Bay :
Panel Number :
Relay Denomination in Scheme
Scheme to be Checked Relay Functionality Test.
4 TERMINOLOGYCode ( ANSI) Terminology
81H/LOver/Under Frequency Relay
5 TEST EQUIPMENT USED
Sl NoDescriptionMakeEquipment
Sl No.Calibration dateCalibration due date
1.Secondary Injection Kit
2.Multimeter
3.LaptopNA
Setting software
Type : MICOM S1 Studio
Version : 2.14
6 PRE - REQUISITES
PRE-REQUISITESREMARKS
All Safety Condition Are Ok
All Competent Personnel Available For The Test
Ac & Dc Supply Availability And Security
PPE Safety Available.
All Other Relevant Safety Instructions Been Followed
Coordination With Other Parties ( GIS, Transformer, Etc..)
7 TEST PROCEDURESThe following procedures are written for demonstrating the main protection functions of the P922 relay using an Omicron test set or similar. The tests do not test the boundaries of all available function characteristics. They do test that the function is operating at a point on one chosen characteristic. This document is to be referred to when performing commissioning tests in association with the commissioning section of the service manual.
NOTE :
All the Test are performed in the Test Switch.
Omicron CMC156 Test Equipment or Any Equivalent To Be Used..
7.1 Testing Over/Under Frequency function
Note : stage (f1>) or (f1) (overfrequency), then configure it at (81) or (f1) or (tf1) check:
1. If time delay (tf1>) is short, gradually increase the frequency from the nominal frequency fn to the value of the stage (f1>): tripping should occur for a frequency in the range [(f1>) 10mHz, (f1>) + 10mHz].
2. If time delay (tf1>) is long, adjust the frequency to [(f1>) 50mHz] and check that tripping does not occur. Increase the frequency to 1.2x(f1>) and check that tripping occurs.
3. Gradually reduce the frequency and measure the value of the drop-off stage (f1>): the function must reset for a frequency less than or equal to [(f1>) 50mHz].
Stage (f1