P64658 SAPP AnnRep'06 24/07 - Southern African Power Pool Annual Report 2006.pdf · Southern...
Transcript of P64658 SAPP AnnRep'06 24/07 - Southern African Power Pool Annual Report 2006.pdf · Southern...
1
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Contents
Vision and Objectives ........................................................................................................................................................................................................................... 2
Organogram and Members ............................................................................................................................................................................................................... 3
About SAPP ....................................................................................................................................................................................................................................................... 4
Highlights of SAPP Activities ........................................................................................................................................................................................................... 5
SAPP Executive Committee ................................................................................................................................................................................................................ 7
Executive Committee Chairman’s Report .............................................................................................................................................................................. 8
Management Sub-Committee Report ........................................................................................................................................................................................ 12
Operating Sub-Committee Report ................................................................................................................................................................................................ 14
Planning Sub-Committee Report 2005/6 ................................................................................................................................................................................ 18
Environmental Sub-Committee Report ................................................................................................................................................................................... 21
SAPP Co-ordination Centre Report ............................................................................................................................................................................................. 23
Statistics 2005/6 ............................................................................................................................................................................................................................................ 27
Report of the Independent Auditors ........................................................................................................................................................................................... 31
Statement of Accounting Policies ................................................................................................................................................................................................. 32
Income Statement ........................................................................................................................................................................................................................................ 33
Balance Sheet .................................................................................................................................................................................................................................................. 34
Cash Flow Statement ................................................................................................................................................................................................................................ 35
Notes to the Financial Statements ................................................................................................................................................................................................ 36
2
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Vision and Objectives
Vision
The Southern African Power Pool will:
• Facilitate the development of a competitive electricity market in the SADC region.
• Give the end user a choice of electricity supplier.
• Ensure that the southern African region is the region of choice for investment by energy intensive users.
• Ensure sustainable energy developments through sound economic, environmental and social practices.
Objectives
The Southern African Power Pool aims to:
• Provide a forum for the development of a world class, robust, safe, efficient, reliable and stable
interconnected electrical system in the southern African region.
• Co-ordinate and enforce common regional standards of Quality of Supply; measurement and monitoring
of systems performance.
• Harmonise relationships between member utilities.
• Facilitate the development of regional expertise through training programmes and research.
• Increase power accessibility in rural communities.
• Implement strategies in support of sustainable development priorities.
3
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Organogram and Members
SAPP Membership
Full Name of Utility Status Abbreviation Country
Botswana Power Corporation OP BPC Botswana
Electricidade de Mocambique OP EDM Mozambique
Electricity Supply Corporation of Malawi NP ESCOM Malawi
Empresa Nacional de Electricidade NP ENE Angola
ESKOM OP Eskom South Africa
Lesotho Electricity Corporation OP LEC Lesotho
NAMPOWER OP NamPower Namibia
Societe Nationale d’Electricite OP SNEL DRC
Swaziland Electricity Board OP SEB Swaziland
Tanzania Electricity Supply Company Ltd NP TANESCO Tanzania
ZESCO Limited OP ZESCO Zambia
Zimbabwe Electricity Supply Authority OP ZESA Zimbabwe
OP = Operating Member NP = Non-Operating Member
4
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
• SAPP was created in August 1995 at the SADC
summit held in Kempton Park, South Africa, when
member governments of SADC (excluding
Mauritius) signed an Inter-Governmental
Memorandum of Understanding for the formation
of an electricity power pool in the region under
the name of the Southern African Power Pool.
• SAPP is governed by four agreements: the Inter-
Governmental Memorandum of Understanding
which enabled the establishment of SAPP; the
Inter-Utility Memorandum of Understanding,
which established SAPP’s basic management and
operating principles; the Agreement Between
Operating Members which established the specific
About SAPP
rules of operation and pricing; and the Operating
Guidelines, which provide standards and operating
guidelines.
• SAPP has twelve member countries represented
by their respective electric power utilities
organised through SADC.
• SAPP has three working committees: the Operating
Sub-Committee, the Planning Sub-Committee and
the Environmental Sub-Committee under a
Management Committee which in turn reports to
the Executive Committee.
• SAPP coordinate the planning and operation of
the electric power system among member utilities.
• SAPP provide a forum for regional solutions to
electric energy problems.
• SAPP has established and is operating the Short-
Term Energy Market.
5
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
The year under review had seen considerable progress
in the following areas:
• Finding a solution to the diminishing generation
surplus capacity that the SADC region is currently
experiencing. The expansion of the SAPP priority
generation and transmission infrastructure
projects is associated with the proposed solution
together with the review of the SAPP Pool Plan of
2001.
• Continuation of SAPP restructuring and
documentation review following the restructuring
of the SADC Secretariat and within SAPP member
countries.
• Continuation of the development of a competitive
electricity market for the SADC region and also
the associated development of long-term
transmission pricing policy, implementation
procedures and ancillary services market, and
• Implementation of the SAPP telecommunications
project that is aimed at linking the three control
areas; Eskom (South Africa), ZESA (Zimbabwe)
and ZESCO (Zambia) via a VSAT link in the short-
term and fibre optic in the long-term.
• Launch of the Westcor Office in Botswana; and
Training and capacity building of SAPP Members
and exposure to new changes in technology and
practices.
1. Diminishing Generation Surplus Capacity
The Southern African Power Pool (SAPP) in
collaboration with the Regional Electricity
Regulators Association (RERA) hosted the
Regional Electricity Investment Conference
(REIC) in Windhoek, Namibia, from 19-21
September 2005. The meetings coincided with
the SAPP 10th anniversary celebrations. The aim
of the conference was to:
• Provide a platform for investors both from
the private and public sectors and to share
ideas and discuss the challenges facing the
SADC Electricity Supply Industry.
• Facilitate financing and investment in the
SADC short-term and long-term generation
and transmission projects.
• Identify the financial needs of each SADC
member state in both generation and
transmission infrastructure and encourage
the sharing of strategic financial and
investment information.
• Identify potential investors in the SADC
electricity sector and formulate a regional
approach to investment in the electricity
sector and discuss ways of removing red tape
to investment in the electricity sector in the
region.
The conference attracted more than 250 delegates
from 32 countries. A total of 36 papers were
presented at the conference covering a wide range
of areas. On the last day of the conference, 21
September 2005, the SAPP Executive Committee
held a consultative meeting with financiers,
investors and cooperating partners to map a way
forward and to consider recommendation and
outcome from the conference.
2. Restructuring of the Southern African Power Pool
At a meeting of the SADC Council of Ministers
Committee that took place in Gaborone,
Botswana, on 23 February 2006, the Ministers
responsible for energy in the SADC region
signed the Revised SAPP Inter-Governmental
Memorandum of Understanding. The signing
of the Revised SAPP Inter-Governmental
Memorandum of Understanding was facilitated
by the following: the restructuring of the SADC
Secretariat that lead to the changes in the
reporting structure for the SAPP; electricity
sector reforms in SADC Member Countries that
have led to the introduction of Electricity
Regulators in many SADC countries; and the
need to include other participants in the SAPP
other than the national power utilities such as
Independent Power Producers and the
expansion of the SAPP membership. The SAPP
is now working to revise the remaining base
documents: Inter-Utility MOU, Agreement
Between Operating Members and Operating
Guidelines. It is hoped that these would be
completed during 2006.
Highlights of SAPP Activities
6
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
3. Competitive Market Development
The development of the SAPP competitive
electricity market accelerated during 2006
following a formal approval of the project by the
SAPP Executive Committee. On 21 November
2005 and at a special meeting of the SAPP
Executive Committee held in Johannesburg,
South Africa, the Executive Committee agreed
to the Management Committee’s proposal to
continue with the development and
implementation of the SAPP competitive
electricity market for the SADC region. The
Norwegian Government is funding the project.
In May 2005, the SAPP engaged Power Planning
Associates of the UK for consulting services for
the Development of long-term Transmission
Pricing Policy, Implementation Procedures and
Ancillary Services Market Development for the
Southern African Power Pool. Sida (Sweden) is
financing the project and a budget of SEK
9,800,000 (nine million eight hundred thousand
Swedish Kronor) has been made available over a
period of approximately two years from May
2005.
4. Implementation of the SAPP VSAT Project
In September of 2001, a World Bank sponsored
telecommunications study was completed. The
study recommended a VSAT solution in the
short-term and a fibre-network in the medium to
long-term. The implementation of the short-term
solution, VSAT network, started in August 2005.
The Contractor moved on site and installed the
dish at the ZESA control centre in Zimbabwe
including all the necessary communications
equipment and at the Coordination Centre.
Thereafter, the contractor moved to Lusaka,
Zambia, in November 2005 and installed the
equipment at ZESCO control centre. The
remaining work is the installation of similar
equipment in South Africa at the Eskom control
centre and the initialisation of the VSAT system.
5. Other Achievements
Training and capacity building of SAPP Members
and exposure to new changes in technology and
practices. A one-week training on the use of the
PSSE Software was conducted for SAPP members
between 24-28 April 2006. A total of 15 delegates
registered for the training that was sponsored by
the Norwegian Government.
WESTCOR (Pty) Ltd, formed under the auspices
of SAPP to develop the Western Power Corridor
was officially launched in Gaborone on 7
September 2005. The signing of the Shareholders
Agreement ceremony preceded the launch.
Dignitaries attended the ceremony from Namibia,
Angola, South Africa, Botswana, the Democratic
Republic of Congo (DRC), the SADC Secretariat
and Chief Executive Officers of the five
participating utilities, SNEL of Democratic
Republic of Congo, ENE of Angola, NamPower
of Namibia, Botswana Power Corporation of
Botswana and Eskom of South Africa. At a
WESTCOR (Pty) Ltd meeting held in Gaborone,
Botswana on 23 February 2006, the Steering
Committee of WESTCOR approved the
appointment of Mr Jean T Lokala, as the Chief
Operating Officer of WESTCOR with effect from
1 May 2006. Mr Jean T Lokala was working for
SNEL, the national power utility in the DRC.
Highlights of SAPP Activities
7
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Dr Sydney GataZESA
SAPP Executive Committee
April 2005 to March 2006
Mr John KaluziBPC
Mr Manuel CuambeEDM
Mr Kandi PondamboESCOM
Mr Edward NelumbaENE
Mr Thulani GcabasheEskom
Mr Cosmas GutuLEC
Dr Leake Hangala NamPower
Mr Vika di PanzuSNEL
Mr Pius GumbiSEB
Mr A J Van Der MerweManaging Director, TANESCO
Mr Rodnie P SisalaZESCO
8
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Opportunities for sustainable development in the
Southern African power sector”.
The Honourable Minister of Mines and Energy
of Namibia, Honourable Erkki Nghimtina, gave a
welcome speech. The Right Honourable Prime
Minister of Namibia, Hon. Nahas Angula, gave
the opening keynote address and officially
opened the conference.
The REIC conference attracted more than 250
delegates from 32 countries. A total of 36 papers
were presented at the conference covering the
following areas: investment climate in the power
sector in SADC; overview of the SAPP; overview
of the regional electricity regulatory developments;
selected power generation projects; financing of
power projects; the new partnership for African
development (NEPAD); coal, gas and hydro
technologies; renewable energy; information and
communications technology; and private sector
participation in the SADC power sector.
There were three panel discussions covering
topics such as how can SADC governments attract
investments into the power sector; are regulatory
policies encouraging and attracting investments
in the SADC region and how to access finance
for power projects in southern Africa.
Executive Committee Chairman’s Report
The Southern African Power Pool (SAPP) is faced with
the challenge of a diminishing generation surplus
capacity. In order to reverse the trend, the SAPP
hosted the second regional electricity investment
conference in Namibia as a way of attracting
investments into the SADC power sector. The first
investment conference was held in Zimbabwe in
September 2001. The second conference was a follow
up to the first one and was well attended.
The second challenge the SAPP is faced with is the
embracement of cost reflective tariffs and the
adoption of regulatory principles that would enhance
the tariffs. The tariffs in most southern African
countries are some of the lowest in the world and
have remained so for a while making it difficult to
sustain the operations of the grid.
1. Regional Electricity Investment Conference
(REIC)
The coming years are crucial to the reliability and
security of supply in the Southern African
Development Community (SADC) region in that
the SAPP had years before predicted that the
SADC region would run out of generation surplus
capacity around the year 2007 if no new
investments in generation and transmission
infrastructure were done.
As a way of attracting investments into the SADC
power sector, the SAPP in collaboration with the
Regional Electricity Regulators Association (RERA)
hosted the Regional Electricity Investment
Conference (REIC) in Windhoek, Namibia, from
19-21 September 2005.
The REIC conference focused on investment in
electricity sector in SADC region. The theme of
the conference was “Emerging Investment
Mr Manuel Cuambe
Executive Committee Chairperson
(Left to Right)
The Honourable Minister Hon. Erkki Nghimtina,
Minister of Mines and Energy of Namibia, and
Right Honourable, Hon. Nahas Angula,
Prime Minister of Namibia.
9
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Executive Committee Chairman’s Report (Continued)
Listing, which is expected to act as a project
investment guideline to Investors, the Public
and the Private Sector. The SAPP Priority
projects have been agreed as follows:
• Rehabilitation projects: These projects
are currently in progress and most of
them are under construction and would
be completed before the end of 2007.
Once completed, they would add about
3,200MW of power to the SAPP grid at
an estimated cost of US$1,4 billion.
• Short-term generation projects: The
short-term generation projects are
expected to be completed in 2010.
Feasibility studies and environmental
impact assessments on the projects have
been completed. Some of the projects
have secured funding and others have
not. Once completed, the short-term
generation projects will add about
4,200MW to the SAPP grid at an
estimated cost of US$3,8 billion.
• Transmission projects: These aim to
interconnect the three non-operating
members of the SAPP (Angola, Malawi
and Tanzania) to the SAPP grid. The
transmission projects also aim to relieve
congestion on the SAPP grid and to
evacuate power from the generating
stations to the load centres.
• Medium to long-term generation
projects: These are meant to supply
power to the SADC region in the
medium to long-term. Notable among
them is the Western Power Corridor
Project, Westcor, which is expected to
move 3,500-4,000MW of power from
Inga-3 in the DRC to southern Africa and
to pick up 6,500MW of generation at
Kwanza River in Angola.
(ii) Marketing of SAPP Priority Projects
The SAPP via the NEPAD initiative is
working with the Ministers responsible for
Various conference activities were sponsored by
the following companies: SAPP, Electricity Control
Board of Namibia, RERA, Shell, New Era, NamDeb,
NamCor, emCON, Alstom, Coal Investment
Corporation, Meepong Investments, NamPower,
BP, NBC, Bank of Windhoek, SAHA International,
Standard Bank, Republikein, Eskom, Citigroup, De
Deers and Telecom Namibia.
Amongst the financiers, investors and cooperating
partners that were represented at the conference
included the European Commission, World Bank,
Development Bank of Southern Africa, INFRACO,
Barclays Bank, African Development Bank,
Citigroup, Bank of Tokyo-Mitsubishi, European
Investment Bank, YTL Malaysia and GE of the
USA.
On the last day of the conference, 21 September
2005, the SAPP Executive Committee held a
consultative meeting with financiers, investors
and cooperating partners to map a way forward
and to consider the recommendations and
outcome from the conference.
Following the REIC conference, the SAPP being
a regional organisation responsible for the supply
of power to the SADC region had put in place the
following measures to avert an impending power
crisis:
(i) Implementation of Priority Projects
The SAPP has formulated a Priority Project
Dr Vicente Veloso (left) with some of the delegates who
attended the conference.
10
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
energy in the SADC region to market the
priority projects and attract funding for
the short and long-term generation and
transmission projects. The REIC conference
was aimed at marketing the SAPP priority
projects and attract investors into the SADC
power sector.
(iii) Energy Regulation and Tariffs
The Ministers responsible for energy in the
SADC region pledged to address regulation
and implement cost reflective tariffs and
adopt regulatory principles that would
enhance those tariffs. Political support from
the SADC governments is essential for cost
reflective tariffs to be implemented.
2. Tenth Anniversary Celebrations
On 21 September 2005, the SAPP celebrated the
10th anniversary that coincided with the REIC
conference. Over 200 delegates attended the
celebrations. High profile dignitaries who
attended the conference included the Chief
Justice of Namibia, the Minister of Mines and
Energy of Namibia, the Ministers responsible for
energy of Angola, Swaziland and Zimbabwe.
Speakers at this function included the Permanent
Secretary in the Ministry of Mines and Energy of
Namibia, the SAPP Executive Committee
Chairperson, the SADC Deputy Executive
Secretary and the Minister of Mines and Energy
of Namibia.
3. Acknowledgements
I would like to acknowledge the contributions
made to SAPP by the following former members
of the SAPP Executive Committee:
• Dr Vicente Veloso, the former Chairman of
EDM and the also the former Chairperson of
the SAPP Executive Committee from April
2005 to October 2005. Dr Veloso is no longer
with EDM but is now working for the Ministry
of Foreign Affairs of Mozambique.
• Dr Leake Hangala, the former Managing
Director of NamPower and also the former
Chairperson of the SAPP Executive Committee
from April 2003 to April 2005. Dr Hangala is
no longer with NamPower but is now in the
Private Sector.
4. Tribute
I would like to pay tribute to the late Managing
Director of LEC, Mr Simon Mhaville, who passed
away on 20 December 2005. At the time of his death,
Mr Simon Mhaville was the Vice Chairperson of
the SAPP Executive Committee. He died of a heart
attack in Tanzania whilst on holiday and was buried
in Tanzania on 22 December 2005. May his soul
rest in peace.
5. New Executive Committee Members
The following members joined the SAPP Executive
Committee during the year under review.
Executive Committee Chairman’s Report
Dr Vicente Veloso
Dr Leake Hangala
NamPower
The late, Mr Simon L Mhaville,
former Managing Director of LEC
11
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Mr Adriaan Jacobus Van Der Merwe
Managing Director, TANESCO
• The Board of LEC appointed Mr Cosmas
Gutu, Managing Director of LEC, with effect
from 1 January 2006.
• The Board of Directors of TANESCO
appointed Mr Adriaan Jacobus Van Der
Merwe as Managing Director of TANESCO
with effect from 1 January 2006. Mr Adriaan
Jacobus Van Der Merwe is a graduate engineer
from University of Stellenbosch, and also
holds MCom degree from University of
Free State. He is a registeredMProfessional
Engineer with ESCA and has various awards
to his credit.MAdriaan has also participated
in many career and professional committees.
• The Board of EDM officially appointed Mr
Manuel Joao Cuambe as the new Chief
Executive Officer of EDM with effect from 8
November 2005. Mr Cuambe also became the
Chairperson of the SAPP Executive
Committee, taking over from Dr Vicente
Veloso who left EDM. Mr CuambeMjoined
EDM 17 years ago, having played an
outstanding role in the development of EDM’s
national grid. At SAPP level, Mr Cuambe
participated as active member of the SAPP
Planning Sub-Committee and Management
Committee from 1995 to 1999.
Executive Committee Chairman’s Report (Continued)
Mr Cosmas Gutu
Managing Director of LEC
Mr Manuel Cuambe
Chairperson, SAPP Executive Committee
Honourable Minister of Energy of Mozambique,
Hon Salvador Namburete, speaking during the
official opening ceremony of the
20th SAPP Executive Committee Meeting, 26 April 2006.
(Left to Right): Mr Cosmas Gutu, Managing Director of
LEC and Vice Chairperson of the Executive Committee;
Mr Manuel Cuambe, Chairman of EDM and Chairperson
of the Executive Committee; and Dr Lawrence Musaba,
Coordination Centre Manager.
12
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Management Sub-Committee Report
The SAPP is undergoing a restructuring process and
the Management Committee is the one responsible
for revising the SAPP documents and aligning them
to suit the new environment. During the period under
review, the Inter-Governmental MOU was completed
and circulated to all members for approval. The
Management Committee also started the reviewing
of the Inter-Utility MOU, Agreement Between
Operating Members and Operating Guidelines. The
Management Committee is also the link between
SAPP and other stakeholders.
1. SAPP Documentation Review
The meeting of the SADC Council of Ministers
took place in Gaborone, Botswana, on 23 February
2006. In the evening of the same day, the
Ministers responsible for energy in the SADC
region signed the Revised SAPP Inter-
Governmental Memorandum of Understanding.
The signing of the Revised SAPP Inter-
Governmental Memorandum of Understanding
was facilitated by the restructuring of the SADC
Secretariat that lead to the changes in the
reporting structure for the SAPP; electricity sector
reforms in SADC Member Countries that have
led to the introduction of Electricity Regulators
in many SADC countries; and the need to include
other participants in the SAPP other than the
national power utilities such as Independent
Power Producers, and the expansion of the SAPP
membership.
2. SAPP Priority Projects
On 22 September 2005, a special SAPP Executive
Committee meeting was held in Namibia to map
a way forward in the marketing and sourcing of
funds for the SAPP priority generation and
transmission projects. It was during the meeting
that the SAPP Executive Committee agreed to
develop prioritisation and selection criteria that
could be used to prioritise the projects in the
SAPP. The Executive Committee also agreed that
the final list of the SAPP priority projects could
be promoted by SAPP for funding.
The task of developing the criteria and using it to
select priority projects in the SAPP was given to
the Management Committee and the Management
Committee went ahead and developed the criteria
that was later approved by the Executive
Committee.
Mr Augusto De Sousa Fernando
Management Committee
Chairperson
(Left to Right): Retired Lt. General Mike Nyambuya,
Honourable Minister of Energy and Power Development of
Zimbabwe and Mrs Lindiwe Hendricks, Honourable
Minister of Energy and Minerals of South Africa, signing
the Revised Inter-Governmental MOU, at a ceremony in
Botswana on 23 February 2006.
(Left to Right): Minister of Mines and Energy of Namibia,
Hon. Erkki Nghimtina, and the Swaziland Minister of
Energy and Natural Resources Hon. Mfomfo Nkambule,
signing the Revised Inter-Governmental MOU.
13
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Management Sub-Committee Report (Continued)
3. Cooperation with other power pools
The 37th General Assembly of the Union of
Producers, Transporters, and Distributors of
Electric Power in Africa (UPDEA) took place in
Lusaka, Zambia, from 24-25 November 2005. The
Honourable Vice President of Zambia, Mr
Lupando Mwape, officially opened the assembly
and the exhibitions.
In the framework of NEPAD, UPDEA has set itself
the goal of being a development-oriented
institution to serve the African Power Sector. The
purpose of UPDEA extends to participation in the
development of the power sector in conjunction
with regional, continental and international
players. Its vision is to be the primary catalyst in
the realization of access to electricity of all the
peoples of Africa.
The five power pools operating in Africa signed a
cooperation framework under which the parties
agreed to cooperate and share information. The
purpose of signing the cooperation framework was
to record an understanding between the parties
on their working relationship and technical
cooperation. The cooperation framework does not
make any legally binding or otherwise enforceable
commitments on behalf of any of the parties. The
parties that signed the cooperation framework
included:
• Central African Power Pool, CAPP
• COMELEC of North Africa
• East African Power Pool, EAPP
• Southern African Power Pool, SAPP, and
• West African Power Pool, WAPP.
The parties agreed to co-operate in the following
areas:
• Harmonization of policies concerning sub-
regional power interconnections,
• Harmonization of master-plans and pro-
grammes between sub-regional power pools,
• Promotion of an integrated electricity plan
that can lead to electricity market in Africa
as a region,
• Exchange of experiences in regional co-
operation, codes of practice, electricity
pricing methodologies and wheeling charges,
and
• Exchanges of information and know-how.
4. Acknowledgements
I wish to acknowledge the support that I received
from Members of the SAPP Management
Committee during the year without whom
nothing would have been achieved.
May I take this opportunity and congratulate
Messrs Mr Lovemore Chilimanzi and Mr Mbuso
Gwafila, who were elected to the positions of
Chairpersons of the Operating and Planning Sub-
Committee’s respectively. Also congratulations to
Mr Vusimuzi Simelane, the newly elected Chair-
person of the Environmental Sub-Committee.
Special thanks also goes to the SAPP Coordination
Centre for the work the centre is doing in
coordinating the activities of the SAPP.
Mr Augusto de Sousa Fernando
Management Committee Chairperson
The Honourable Vice President of Zambia,
Mr Lupando Mwape (front row in a cream/white suit)
poses with UPDEA Executive Members.
14
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Operating Sub-Committee Report
Mr L Chilimanzi took over from Ms Erica Johnson as
Chairperson of the OSC from September 2005.
1. The Short-Term Energy Market (STEM)
STEM reached its 5th year of operation in April
2006. The demand has been rising every year
from 766-GWh in 2001 to 4,222-GWh in 2004.
The supply side for the first four years has been
around 2,500-GWh. The energy traded was on the
rise in the first two years and then declined
steadily in the last two years. It reached a high of
842-GWh of energy traded in 2002 and dropped
to 178-GWh in 2005. Figure-1 shows a detailed
comparison.
The total sales in monetary value have been
increasing every year. The highest sale was
recorded in 2004 when total sales amounted to
USD4,4 million. The year 2005 saw a decline in
sales due to reduced energy trade. This was
mainly due to few members participating in the
STEM. HCB of Mozambique and ZESCO of
Zambia did not participate in the STEM as the
two utilities embarked on major power generation
rehabilitation and maintenance works in their
respective countries.
The STEM has also seen prices firming up since
inception. The highest average price of 1,24 USc/
kWh was recorded in 2005. This is characteristic
of the increasing demand and declining supply
as highlighted above.
2. Bilateral Market
Energy trading via bilateral contracts picked up
from around 16-TWh in 2004 to 19-TWh in 2005.
In general, the region is experiencing an increase
in bilateral energy trading amongst SAPP
members. However, there was a reduction in in
2004 due to major power rehabilitation and
maintenance work in Mozambique and Zambia.
Mr Lovemore Chilimanzi
Operating Sub-Committee
Chairperson
Figure 2: Energy Trade versus monetary value Summary
from year beginning 2001 to 2005.
Figure 1: Energy Trade Summary
from year beginning 2001 to 2005.Figure 3: STEM Energy Prices (2001-2005).
15
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Operating Sub-Committee Report (Continued)
3. SAPP Telecommunications Project
Minimum telecommunications requirements for
SAPP are embodied in the SAPP Operating
Guidelines of August 1996. In September of 2001,
a World Bank sponsored telecommunications
study was completed. The study recommended
a VSAT solution in the short-term and a fibre-
network in the medium to long-term. The
implementation of the three terminal short-term
VSAT solution started in August 2005. The
Contractor moved on site and installed the dish
at the ZESA control centre in Zimbabwe
including all the necessary communications
equipment at ZESA control centre and at the
Coordination Centre. Thereafter, the contractor
moved to Lusaka, Zambia, in November 2005 and
installed the equipment at ZESCO control centre.
The remaining work is the installation of similar
equipment at the Eskom control centre in South
Africa and the initialisation of the system. There
is a delay in the installation of the system in South
Africa due to licensing problems.
On 16 November 2005, Telecommunication
experts from Eskom (South Africa) and ZESA
(Zimbabwe) met at the Coordination Centre in
Zimbabwe to discuss VSAT integration with the
existing SAPP infrastructure and particularly
detail how the SCADA and trading information
will pass from the Energy Management System
(EMS) to the SAPP Server and vice versa to enable
operational personnel to receive useable
information. The experts also agreed that the
required information would be made available
in phases and that individual members would
cater for integration expenses such as software
level upgrades or Interface Hardware (Cards or
Modules) as required by the member utility
infrastructure.
4. Working Group Reports
4.1 Traders and Operators Forum
SAPP continued to support the Traders and
Operators forum. The second Traders and
Operators Forum meeting took place in
Gaborone, Botswana, from 28-29 November
2005. The Forum discussed many trading
issues which were referred to the OSC for
resolution.
The Forum also discussed operational issues
that included the monitoring of system
reserves, frequency control, time error
correction, coordination of information
under abnormal conditions and adherence
to the SAPP Operating Guidelines.
In addition, participants were trained on the
use of the Internet based trading system that
was implemented at the SAPP Coordination
Centre during the year.
Figure 4: Bilateral Trading (2002-2005).
Installed VSAT dish at the ZESA control centre
in Harare, Zimbabwe.
16
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Operating Sub-Committee Report
4.2 Markets Development
The Norwegian Government is funding the
development of a competitive electricity
market for the SADC region.
Nord Pool ASA (NP) of Norway won the
tender for the supply, installation and
implementation of the SAPP Trading
Platform in February 2005 after a competitive
tender. The tender award was approved by
the SAPP Executive Committee in November
2005. Contract negotiations between SAPP
and NP then started. Final contract
negotiations took place in Harare from 18-
19 January 2006 culminating in the two
parties signing two agreements stated below.
• SAPP-NP Delivery Contract, 19 Jan 2006.
• SAPP-NP Support Contract, 19 Jan 2006.
Queries on specifications for the SAPP Day
Ahead market were agreed and finalized by
SAPP and Nord Pool at the OSC meeting in
Tanzania on 1 March 2006. Points discussed
were relating to the treatment of bilateral
contracts, block bids; value added tax, fees
and the level of security that will be required
by SAPP from participants. The two parties
confirmed that the trading platform will be
delivered in November 2006 and market
trials would be expected to start after
January 2007. The creation of a balancing
mechanism for handling imbalances
consistent with the proposed SAPP market
platform is now under consideration.
5. System Operations
5.1 SAPP Transfer Limits
The SAPP Study Group finalised the transfer
limit studies. The report was finalised and
the applicable transfer limits were distributed
to the Planning and Operating Sub
Committees for consideration.
5.2 Treatment of Losses
Part of the terms of reference for the
consultant appointed for the Sida funded
project on the development of transmission
pricing policy, implementation procedures
and ancillary services market, is to address
treatment of losses arising from trans-
national wheeling. The work is in progress
but in the meantime, the OSC has agreed
that members would continue to settle
losses in kind and financially.
5.3 Transmission Wheeling Path
The three Control Areas in the SAPP
(Eskom, ZESA and ZESCO) submit and
exchange their trading schedules in advance
before the day of trade. However, it has been
observed that in many cases, the declared
schedules are exceeded. This is a violation
of the SAPP Operating Guidelines (OG) as
the changes need to be agreed in advance.
In 2005, a lot of instances for exceeding
schedules were observed by the wheeling
members and the incidences were reported
to the SAPP Coordination Centre. The SAPP-
OG do not cover the issue of unscheduled
wheeling. The OSC has a challenge to come
up with guidelines when the declared
schedules are exceeded.
At an operational meeting held in Harare
on 15 August 2005, the importance of
adhering to the operational discipline
stipulated in the SAPP-OG was stressed.
Improvements are yet to be realised.
5.4 Inadvertent Energy Management
The three Control Areas have finalised their
inadvertent energy figures from 2004 up to
December 2005. The agreed figures have
been reconciled and were made available
to the SAPP Coordination Centre on 31
March 2006. Among the three control areas,
agreements have been reached for the
payback of the energy.
5.5 Emergency energy rates
The OSC mandated the SAPP Coordination
Centre to negotiate emergency energy rates
for all members with the three control areas
17
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Operating Sub-Committee Report (Continued)
(Eskom, ZESA and ZESCO) and to thereafter
make a recommendation. The intention was
that the new rates would take effect from
15 June 2006.
5.6 Maintenance Schedules
SAPP Members submitted their maintenance
schedules to the SAPP Coordination Centre
for the coming year that starts on 1 April 2006
for reconciliation and publication.
5.7 System Disturbances
In the period under review, over 20 system
disturbances occurred on the SAPP network.
The 16 major disturbances are summarised
in the Table above. Most of the disturbances
that occurred in Botswana were attributed
to line faults on the Phokoje-Matimba line
within Botswana and resulted in a total
blackout on 3 November 2005. The
disturbances in Zambia were known and
were mostly due to the act of God. The
disturbances in the DRC could have been
prevented if regular checkups on the tower
lines and maintenance were done to avoid
further collapse of the towers.
Mr Lovemore Chilimanzi
Operating Sub-Committee Chairperson
Table 1: Table indicating the SAPP major System faults in 2005
No. Member Country Major Disturbances Main Cause of Disturbance
1 BPC, Botswana 2 Line faults on the Phokoje-Matimba line
in Botswana.
2 EDM, Mozambique 2 Transformer tap-changer fault and broken
junction of a line conductor.
3 Eskom, South Africa 4 Problem with transformer, fault on reactor and
fire under transmission line.
4 SNEL, DRC 3 Collapse of towers and broken conductors.
5 ZESCO, Zambia 5 Landslides due to heavy rains and thunderstorms.
Total 16
18
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Planning Sub-Committee Report 2005/6
1. Introduction
The Planning Sub Committee is pivotal to the
provision of reliable information regarding the
power supply situation in the SADC region. It is
this proactive approach that issue of the
diminishing generation surplus capacity is
actively being addressed. Generation projects are
being tracked to assess their status and progress
to meet their target commissioning dates. In the
year under review various projects were
commissioned. Most countries experienced a
positive demand growth with Botswana,
Mozambique, Namibia and Malawi recording the
highest demand growth of 7,96%, 7,1% 6,51%
and 6,5% respectively. Negative growth was
recorded in South Africa and Zimbabwe with –
2,2% and – 0,1% respectively.
Mr. Mbuso Gwafila of BPC was nominated to be
the Planning Sub Committee Chairperson taking
over from Mrs Angela Dava of EdM. The Planning
Sub-Committee thanked Mrs Dava for her
excellent leadership for the past two years
2. Diminishing Generation Surplus Capacity
It is the objective of SAPP to have a robust
generation capacity plan with adequate reserve
margins to cater for forced outages and load
forecast error. The annual demand is increased
by 3 percent. Different projects were identified
in the following classes:
• Rehabilitation Projects
• Short term generation projects
• Long term generation projects
• Transmission interconnector projects aimed
at interconnecting the SAPP non-operating
members namely Angola, Malawi and
Tanzania.
• Transmission projects, which relieve
congestion within the major wheeling
countries that would increase trade.
Graph 1 below highlights the demand and supply
situation when the rehabilitation and short-term
projects are commissioned. It can be noted that
the capacity shortfall can be contained if all
planned projects are commissioned.
A 150 MW unit was returned to service in
December 2005 at Kariba North hydro power
station in Zambia. Construction work started at
the Tedzani I and II hydro power plant
rehabilitation programme. 40 MW would be
available to Malawi when the rehabilitation is
completed in June 2007.
It remains a challenge for SAPP to meet the ever-
increasing demand to ensure security of supply.
3. Transmission Pricing and Ancillary Services
Market Development
SAPP secured funding from Sida for the
development of a long-term transmission pricing
policy, implementation procedures and ancillary
services market development. In May 2005,
Power Planning Associates of the UK was
awarded the contract to carry out the study. The
methodology for determining transmission
pricing was agreed to be a nodal pricing approach.
Transmission loss factors across the SAPP
network were also determined.
On the ancillary services market development,
three broad categories of services were agreed
upon and are to be evaluated further as follows:
• Reactive Power and Voltage Control
• Frequency Control Services
• Instantaneous reserves
• 10 – minute reserves
• Regulating Reserves
• Black Start Capability
The high-level market design principles and
criteria have been developed. A methodology for
charging and remunerating services is to be
agreed upon. The costing components for each
service were developed. The ancillary services
market is expected to be operational in 2007.
Mr Mbuso Gwafila
of BPC (Botswana)
Planning Sub-Committee
Chairperson
19
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Planning Sub-Committee Report 2005/6 (Continued)
4. SAPP Pool Plan Review
In December 2005, the World Bank informed
SAPP that the Bank had approved funding to
SAPP for the review of the SAPP Pool Plan
through an Africa Region Energy Sector
Management Assistance Program (ESMAP)
facility. Tenders were floated and six companies
were short-listed and the World Bank was still
reviewing the tenders by the time of writing this
report. The Pool Plan would be a regional
integrated generation and transmission plan
highlighting the benefits of optimizing the
generation resources. The studies would start in
July 2006.
5. Transmission Interconnector Projects
5.1 WESTCOR
The Project Office for the WESTCOR Project
was set up in Gaborone, Botswana. The
Chief Operating Officer was also appointed.
Feasibility studies for the transfer of 3500
MW from Inga in DRC to Botswana, Namibia
and South Africa using the HVDC technology
would be done. Options for connecting the
Cunene hydro power plants in Angola would
be investigated.
5.2 DRC – Zambia
SNEL, Copper Belt Energy Corporation and
ZESCO carried out detailed studies to
evaluate the maximum transfer limit on the
existing DRC – Zambia 220 kV line. It was
concluded that the line could carry a
maximum of 310 MW.
ZESCO of Zambia has finished the con-
struction of a 330 kV line from Luano to
Solwezi in Zambia where a large copper
mine was opened.
With the construction of a 330kV line the
transfer capability of the DRC-Zambia
interconnector would increase from the
present 260MW to over 800MW. The
transmission line that will run from Solwezi
in Zambia to Kolwezi in the DRC would be
approximately 200 km.
5.3 Mozambique – Malawi
HCB of Mozambique and ESCOM of Malawi
finalized the negotiations on the Power
Purchase Agreement.
This would lead to the construction of a 219
kilometer 220 kV transmission line from
Tete in Mozambique to Phombeya in
Malawi, construction and extension of
related substations in the two countries. The
estimated construction period is 24 months.
Bankable documents were prepared and
finalized.
5.4 Zambia – Tanzania – Kenya
• A grant of approximately USD 1,2
million was secured from World Bank,
ADB and DBSA for the feasibility
studies
• Scoping Studies on the Tanzania side
were completed for the EIA
• ZESCO completed studies on the
Zambian side. Negotiations with a
transactions advisor who is a
Consortium comprising of Technical,
financial and legal specialists are to be
undertaken.
• Discussions are underway with Kenyan
government who are interested in taking
part in the project.
5.5 Zambia – Namibia
60% of projects works were completed on
the Zambian side including substation
works at Victoria Falls. For the 3,5 km stretch
of the AC line on the Namibian side, the
Zambian Contractor was assigned to carry
out the works. The EIA was completed on
the Namibian side. The commissioning date
was shifted from May 2006 to June 2006.
The project would enable Namibia to have
an alternative route for power imports.
5.6 Luano – Solwezi - Lumwana 330 kV line
The second phase of the 65 km Luano-
Solwezi- Lumwana 330 kV line in Zambia
is aimed at supplying a new copper mine at
20
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Lumwana. The Power Purchase Agreement
was already signed and the project would
be commissioned in December 2007. With
the Kolwezi - Solwezi 330 kV line complete
the transfer capacity would be increased
from the DRC to Zambia.
6. Technical Issues
SAPP Transfer Limit Studies
A special Study Group was set up to determine
the transfer limits in the SAPP interconnected
system. Transmission Congestion has been noted
on some points in the system especially the
transmission bottlenecks within the ZESA system
in Zimbabwe, which geographically lies on the
centre of SAPP. This bottleneck is hindering the
electricity trade between the northern and
southern countries. Special projects were
identified to relieve the congestion.
Counter trade in some hours is assisting to relieve
congestion.
Transmission Wheeling Charges
SAPP successfully implemented the full rate for
the wheeling charges on 1 January 2006. The rates
were being increased every six months starting 1
January 2003.
7. Coordination Meeting of Power Pools
SAPP has been active in different forums. A
Coordination meeting of Power Pools was held
in Addis Ababa, Ethiopia. It was attended by
representatives from Southern, Central, Western
and Eastern African Power Pools. The Union of
Electric and Distributors of Electricity (UPDEA)
arranged the meeting.
Mr Mbuso Gwafila
Planning Sub Committee Chairperson
Planning Sub-Committee Report 2005/6
21
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
1. Introduction.
The year 2005/6 witnessed a lot of achievements
in SAPP’s vision of ensuring sustainable energy
developments through sound economic,
environmental and social practices.
2. Evaluation of Environmental Impacts of SAPP
Projects.
2.1 WESTCOR
Activities for this project are proceeding
according to plan. A Chief Operations
Officer has been appointed. Environmental
studies are to be done with the aid of
satellite images (remote sensing techniques)
and the ESC will be involved at all stages.
2.2 DRC – Zambia Inter-connector
The survey works and the way leave
acquisition have been completed.
Compensation and relocations issues are
being worked out in both countries.
Environmental Management Plans for both
the line and sub-station have been
completed and will be part of the
implementation contracts
2.3 Zambia – Tanzania – Kenya Inter-
connector
Environmental Scoping has been done and
the report is ready for review by authorising
agencies. The Environmental Impact
Assessment is to commence as soon as the
Environmental Scoping report is approved.
2.4 Mozambique – Malawi Inter-connector
Compensation evaluation is currently in
progress in Malawi. Route pegging has been
completed. Environmental Impact
Assessment has not yet been done.
Environmental Sub-Committee Report
Mr Vusumuzi F Simelane
Environmental Sub-Committee
Chairperson
2.5 Zambia – Namibia Inter-connector
Environmental Impact Assessment as well
as Environmental Management plans have
been done for the project. Consultants are
yet to undertake an in-depth study on birds
at sensitive river crossings. Environmental
monitoring of the implementation of the
project is being done.
2.6 Lower Kafue – Gorge Power Station
– 750 MW
The EIA is yet to be submitted to the
authorising agency. A site selection study
has been completed and detailed design
works are to commence.
2.7 Open Cycle Gas Turbines at Atlantis and
Mossel Bay (SA) – 1000MW
Construction works at both sites com-
menced on 17 and 24 January 2006
respectively. Actions have been taken to
ensure compliance of conditions of approval.
2.8 Matimba Coal Fired Power Station (SA)
The scoping report for Matimba B EIA has
been issued to the authorities and the public
for review. It is anticipated that final EIA
will be submitted to authorities in May 2006
for the issuance of the Record of Decision.
2.9 Morupule Coal Fired Power Station
(Botswana) – 400MW
The scoping report for the project has been
approved and the Terms of Reference for the
EIA are being finalised.
22
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
3. Working Groups
3.1 Environmental Impact Assessment (EIA)
Guidelines for Hydropower Projects
A consultant (Nexant INC), was contracted
to develop EIA Guidelines for Hydropower
projects. The consultant has completed a
draft report, which is scheduled to be
presented to ESC members at a workshop
to be held in South Africa during the month
of June 2006.
3.2 Training
Two Training Sessions were held during the
period under review. Members received
training on Social Impact Assessment and
Triple Bottom Line Reporting and GRI
Guidelines for Sustainability Reporting at
Stellenbosch and Dar Es Salaam
respectively. These sessions are useful as
capacity building initiatives within ESC
members.
3.3 SAPP Position on Climate Change
The Management Committee approved the
ESC document on Climate Change and
agreed to have the document implemented
in SAPP as per ESC proposal.
3.4 Negative Impacts of Climate Change
The Research Project on Emission Factors
(EFs) in the power sector in Southern Africa
has achieved the following results to date:
• Fuel characteristics in four countries
(South Africa, Tanzania, Zambia and
Zimbabwe)
• Plant characteristics of the region
• EFs for each fuel quality considered
• Methodologies for treating flue gas
measurements for coal, diesel and coal
mining methane.
Outstanding Issues on the Research are:
• Developments of a publication for phase
1, 2 and 3 results for peer review and
depositing EFs into IPCC database
• Additional measurements are to be
undertaken in Botswana, Namibia and
Mozambique
3.5 Guidelines on Environmental Management.
The following Environmental Management
Guidelines were approved by the
Management Committee at the MANCO
Meeting Held in Tanzania, on 1st march,
2006. Utilities were urged to use the
guidelines.
i. Guidelines on Management of Oil Spills
ii. Guidelines on Management of Asbestos
iii. Guidelines on Animal Interactions
3.6 Environmental Management Policy
A Draft SAPP Environmental Management
Policy was prepared and circulated to all
utilities for comments and inputs. The
Policy is expected to be finalised during the
next SAPP ESC Meeting to be held in
Zambia in September 2006.
3.7 Pool Plan Review
The ESC made a presentation to the
Management Committee on the role of the
Strategic Impact Assessment to the Pool
Plan. The Management Committee
approved the inclusion of SEA into the
SAPP Pool Plan under Environmental
Scoping Study and at negotiation level with
the selected consultant.
4.0 ESC Coordination
A major milestone was the appointment of the
Environmental Officer at the Coordination Centre
in Harare. The major tasks for the EO is to provide
strategic and operational direction to SAPP on
environmental issues.
Mr Vusumuzi F Simelane
Environmental Sub-Committee Chairperson
Environmental Sub-Committee Report (Continued)
23
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
SAPP Co-ordination Centre Report
Dr Lawrence MusabaCo-ordination Centre Manager
Mr Alison ChikovaActing Chief Engineer
Mrs Joyce MutsauFinance & Admin Officer
Mr Johnson MaviyaEnvironmental Officer
Mr Elisha MutambudziSTEM Finance Officer
Ms Daisy MudangweSTEM Finance Officer
Miss Caroline GanyaniIT Specialist
Mr Simon JarichaMessenger
24
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
1. Introduction
The activities of the SAPP Coordination Centre
are funded by SAPP members through yearly
contributions to the Coordination Centre budget.
The activities of the Coordination Centre in the
past year included, but were not limited to STEM
operations and management, prioritisation of
SAPP projects, organising REIC, system studies,
competitive market development, ancillary
services development and many other activities.
The Coordination Centre successfully imple-
mented the full wheeling rate on 1 January 2006.
Over the past year the Coordination Centre
actively disseminated information on the
activities being undertaken to address the
diminishing generation surplus capacity in SAPP.
The Coordination Centre is focused to meet the
SAPP challenges into the future.
2. Human Resources
The SAPP Coordination Centre appointed Mr
Johnson Maviya to the position of SAPP
Environmental Officer with effect from 1 March
2006. Prior to his appointment, Mr Maviya
worked as a Lecturer at the University of Bindura,
Zimbabwe. He has a Masters degree in
Environmental Policy and Management from the
University of Zimbabwe.
3. Host Country Agreement
On 13 March 2006, the Government of Zimbabwe
and the Southern African Power Pool (SAPP)
signed a Host Country Agreement between the
Government of Zimbabwe and SAPP for the
hosting of the SAPP Coordination Centre in
Harare, Zimbabwe. Signing on behalf of the
Government of Zimbabwe was the Minister of
Energy and Power Development of Zimbabwe,
Retired Lt. General Mike Nyambuya, and on
behalf of SAPP was Dr Lawrence Musaba, the
SAPP Coordination Centre Manager.
Representatives from SADC countries such as
Angola, Botswana, Malawi, Mozambique and
Zambia graced the occasion. Other representatives
included officials from the Royal Norwegian
Embassy in Harare, ZESA Holdings, Zimbabwe
Electricity Regulatory Commission, Ministry of
Foreign Affairs and the Ministry of Energy and
Power Development of Zimbabwe.
The host country agreement would help the SAPP
Coordination Centre:
• To be fully recognized as a SADC Institution
in Zimbabwe,
• Achieve its stated aims, goals and objectives,
• Reduce its operating costs and tax burden on
member states, and
• Receive support and donations from
cooperating partners without difficulties.
4. Conferences and Workshops
4.1 IEEE PES Conference
The IEEE Power Engineering Society in
association with SAPP, the University of
KwaZulu-Natal (UKZN) and the South
African Institute of Electrical Engineers
(SAIEE) hosted the inaugural 2005
conference and exposition in Africa in
Durban, South Africa, from 11–15 July 2005.
The conference consisted of four targeted
panel sessions comprising invited papers
from both local and international experts.
The themes for the sessions were: energy
development without impacting on global
warming; extra long distance economical
bulk power transmission; security and
quality of supply in national and regional
electricity markets; and, experiences in
energy intensive industrial power
consumption at the world’s lowest cost. The
conference was covered by South African
Broadcasting Corporation (SABC) and was
SAPP Co-ordination Centre Report (Continued)
Mr Johnson Maviya
SAPP Environmental Officer
25
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
televised on news hour. Dr Musaba and Mr
Naidoo were both interviewed by SABC.
In the closing plenary, the President of IEEE
Power Engineering Society, Dr Teddy
Puttgen, expressed delight on conference
arrangements and technical discussions and
called for the establishment of an IEEE
Power Engineering Society to be chaired by
Mr Pat Naidoo of Eskom. He also requested
southern Africa to host a second conference
in 2007.
4.2 Cigré Conference
Cigré conference took place in Cape Town,
South Africa, from 24–27 October 2005.
Cigré, the International Council on Large
Electric Systems, was established in 1921
and is a non-profit organization. It consists
of specialist study committees with
membership of experienced engineers from
over 80 countries who provide practical
inputs to identified study and problem
areas. It is a forum for the exchange of
information on experiences and development
in the field of generation, transmission, and
distribution.
The aim of the Cigré Conference held in
South Africa was to provide a platform for
Cigré members and non-members alike to
address the challenges in the Southern
African region, and to network with world
experts in their chosen technical fields. The
SAPP Coordination Centre presented two
papers; one on the development of the
competitive electricity market, and the other
on the development of an ancillary services
market.
4.3 Coordination Meeting of Power Pools in
Africa
A coordination meeting of the power pools
in Africa was held at the African Union
Headquarters in Addis Ababa on 22–24
March 2006 where presentations were made
on the activities of the power pools. Mr
Alison Chikova represented SAPP.
Representatives attended the coordination
workshop from the Central African Power
Pool (CAPP), East African Power Pool (EAPP),
Dr L Musaba represented SAPP at the Cigré Conference.
Mr Alison Chikova
Acting Chief Engineer
(Left to Right): Dr Lawrence Musaba, SAPP Coordination
Centre manager; Dr Teddy Puttgen, President of the
Power Engineering Society of IEEE and Mr Pat Naidoo,
Senior General Manager of Eskom.
SAPP Co-ordination Centre Report (Continued)
26
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Southern African Power Pool (SAPP), West
African Power Pool (WAPP), and the Nile
Basin Initiative. An inauguration meeting of
Ministers responsible for Energy in Africa
followed the workshop.
4.4 Annual Meeting between SAPP, Sida and
the Norwegian Embassy
The Annual General Meeting between SAPP,
Sida and the Norwegian Embassy took place
at the SAPP Coordination Centre in Harare
on 21 April 2006. A detailed presentation
on the power supply situation in SAPP was
done highlighting the initiatives being
undertaken by the SAPP to address the
anticipated 2007 energy shortfall. All the
parties expressed satisfaction at the way the
competitive market development project
and the transmission pricing and ancillary
services market development projects were
progressing.
5. Technical Issues
5.1 Transfer Limits across SAPP
The transfer limits across the SAPP inter-
connectors were updated after a special task
force carried out a detailed analysis of the
steady state and dynamic conditions of the
SAPP interconnected system.
Recommendations were put in place to
alleviate transmission congestion and
improve the transfer limits.
Incremental transmission losses recon-
ciliation due to wheeling transactions was
timeously done during the year under
review including inadvertent energy
reconciliation between the control areas.
5.2 Quality of Supply Data Base
The Quality of Supply Working Group
agreed on a piggy back on Day Ahead Market
(DAM) System. The proposed new scope of
implementation includes the following:
• Installation of a quality of supply data
base service as part of the DAM client
side database system,
• Configure SAPP QOS to load, store and
display the cross-border interconnections,
and
• Design, build and test an integration
adaptor between Eskom QOS data (for
cross border inter-connectors), and the
SAPP QOS database.
Dr Lawrence Musaba
SAPP Coordination Centre Manager
SAPP Co-ordination Centre Report (Continued)
Dr L Musaba represented SAPP at the
26th SAPP Meeting in Dar Es Salaam, Tanzania.
27
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Statistics 2005/6
Graph 1: SAPP Demand Supply Situation.
Table 1: Key Statistics 2004/5
Generation Number ofUTILTY (Peak Demand) Sent Out Customers Energy Sales
MW/Employee GWh/Employee per Employee GWh/Employee
ENE 0.934 0.623 34 0.62
BPC 2.076 0.467 73 1.43
SNEL 1.615 1.101 57 0.81
LEC 2.050 1.016 105 1.01
ESCOM 1.007 0.490 56 0.49
EDM 0.960 0.050 114 0.05
NamPower 5.511 1.863 4 3.77
ESKOM 11.267 7.475 127 7.33
SEB 2.579 0.155 73 1.53
TANESCO 1.093 0.756 113 0.77
ZESCO 3.487 2.329 78 2.31
ZESA 3.485 1.584 94 1.99
28
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Statistics 2005/6 (Continued)
Graph 3: Performance Analysis 2005/6
Graph 2: Number of Customers per Employee 2005/6
Number of
UTILTY Customers
per Employee
ENE 34
BPC 73
SNEL 57
LEC 105
ESCOM 56
EDM 114
NamPower 4
ESKOM 127
SEB 73
TANESCO 113
ZESCO 78
ZESA 94
29
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Graph 4: Peak Demand Growth 2005/6
Statistics 2005/6 (Continued)
Table 2: Utility General Information
April 2005 to March 2006
Trans-
Country Utility Installed Maximum MD Sales Sales Number of Number of Generation Net Net mission Revenue Debtor Rate of Net
Capacity Demand Growth Growth Customers Employees Sent Out Imports Exports System US$ Days Return Income
losses Million USD
MW MW % GWh % GWh GWh GWh % % Million
Angola ENE 745 397 9 1,843 12,7 143,937 4,250 2,649 0 0 25 87,94 82 n/a -18,58
Botswana BPC 132 434 7,96 2583,7 7,5 152,744 2,091 977 2,006.50 0 10,96 121,8 37,79 -2,35 22
DRC SNEL 2,442 1012 2,53 4,656 13 360,329 6,268 6,904 0 1,800.00 6,3 149,2 n/a n/a n/a
Lesotho LEC 72 90 0 354 12 46,173 439 446 8 11 20 25,6 57 -0,9 -0,96
Malawi ESCOM 285 242 6,5 970 4 135,000 2,400 1,177 0 0 19 5,319 110 1 2,218
Mozambique EDM 233 285 7,1 1,308 11,8 338,597 2,969 147,418 1,501 1,496 5 110,9 64 n/a n/a
Namibia NamPower 393 491 6,51 2,976 6,5 3,403 891 1,660 1,703.0 0 8 169 34 0,97 10,4
South Africa ESKOM 42,011 33,461 -2,2 207,921 0,8 3,758,569 29,697 221,985 8,730 13,107 8,9 5,388 22 8,4 592
Swaziland SEB 51 172 1 852,8 2,5 48,500 667 103,5 916,8 0 16 59,7 85 4,5 5,1
Tanzania TANESCO 839 531 4,3 2,549 10,3 550,863 4857 3674 43 0 24 188 92 n/a n/a
Zambia ZESCO 1,732 1,330 2,8 8,457 3,1 297,000 3,814 8,884 0 69 3,6 217,6 207 n/a n/a
Zimbabwe ZESA 1,975 2,066 -0,1 10,480 3,5 559,766 5,928 9,391 2,666 255,5 12,6 29,463 33 -23 -372
30
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Table 3: Annual Maximum Demand – MW
April 2005 to March 2006
Table 4: Annual Generation Sent Out – GWh
April 2005 to March 2006
Statistics 2005/6 (Continued)
HISTORIC FORECAST
YEAR 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Angola 209 326 250 291 330 342 374 397 846 871 898 924 952 981 1010
Botswana 239 256 285 337 362 393 402 434 452 479 507 534 562 591 609
DRC 830 841 895 929 991 994 1012 1012 1,070 1,100 1,138 1,172 1,207 1,244 1281
Lesotho 69 77 85 88 89 90 90 90 115 125 130 136 142 148 152
Malawi 190 185 205 212 236 261 227 242 311 330 350 371 394 414 426
Mozambique 245 214 231 234 250 258 266 285 305 326 349 374 400 428 441
Namibia 292 314 320 335 362 371 393 491 670 681 692 703 713 724 746
South Africa 27,803 27,813 29,188 30,599 31,621 30,154 34,195 33,461 35,100 36,200 37,032 38,144 39,288 40,467 41681
Swaziland 145 153 154 159 160 172 171,5 172 185 191 196 202 208 215 221
Tanzania 368 394 426 465 474 506 509 531 654 700 747 786 873 910 937
Zambia 1,126 1,069 1,085 1,087 1,118 1,255 1,294 1,330 1,374 1,399 1,426 1,499 1,529 1,560 1606
Zimbabwe 1,950 2,034 1,986 2,013 2,028 2,007 2,069 2,066 2,208 2,287 2,363 2,446 2,527 2,610 2688
Total
Interconnected 32,699 32,771 34,229 35,781 36,981 35,694 39,893 39,341 41,479 42,788 43,832 45,209 46,576 47,986 49,426
Total SAPP 33,466 33,676 35,110 36,749 38,021 36,803 41,003 40,511 43,290 44,689 45,827 47,290 48,795 50,291 51,800
HISTORIC FORECAST
YEAR 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Angola 1,319 1,516 1,104 1,840 1,866 1,993 2,344 2,649 2,870 3,090 3,320 3,665 3,820 3,935 3,935
Botswana 1,543 1,645 1,880 2,043 2,150 2,282 2699,8 977 2,717 2,880 3,054 3,237 3,431 3,637 3,637
DRC N/A N/A N/A N/A 5,907 6,084 6,904 6,904 6,648 6,848 7,053 7,264 7,482 7,707 7,707
Lesotho 271 267 427 393 378 429 428 446 490 512 528 554 576 600 600
Malawi 1,023 1,087 902 1,091 1,134 1,177 1,177 1,177 1,327 1,380 1,435 1,492 1,552 1,614 1,614
Moxambique 1,076 1,186 1,212 1,257 1,307 1,392 102,2 147,418 158 169 181 193 207 221 237
Nambia 1,881 1,676 1,978 2,016 2136 1,421 1,379 1,660 4,400 4,456 4,512 4,567 4,623 4,679 4,679
South Africa 185,583 188,475 194,601 198,790 207,233 210,112 210,218 221,985 234,555 240,377 251,834 256,013 261,458 267,955 267,955
Swaziland 718 760 820 847 765 991 1005 1000,9 979 1,008 1,039 1,070 1,102 1,135 1,135
Tanzania 2,096 2,240 2,394 2,654 2,708 3,052 3674 3674 3,556 3,782 4,025 4,238 4,820 5,021 5,021
Zambia 7,868 7,656 7,798 8,152 8,308 8,466 8,512 8,884 8,974 9,209 9,373 9,542 9,728 10,224 10,224
Zimbabwe 11,529 12,811 12,090 11,972 8,587 8,799 9,719 9,391 12,937 13,349 13,800 14,295 14,777 15,271 15,779
Total
Interconnected 210,469 214,476 220,806 225,470 236,771 239,976 239,210 251,395 271,857 278,808 291,373 296,735 303,384 311,429 311,953
Total SAPP 214,907 219,319 225,206 231,055 242,479 246,198 246,405 258,895 279,610 287,060 300,153 306,130 313,576 321,999 322,523
31
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Report of the Independent Auditors
TO THE MEMBERS OF SOUTHERN AFRICAN POWER POOL
We have audited the annual financial statements set out on pages 32 to 40 for the year ended 31 March 2006.
Respective responsibilities of the executive committee and auditors
The financial statements are the responsibility of the executive committee of the organisation. Our responsibility
is to express an opinion on these financial statements based on our audit.
Scope
We conducted our audit in accordance with approved International Standards on Auditing. Those standards
require that we plan and perform the audit to obtain reasonable assurance that the financial statements are
free of material misstatement. An audit includes:
• examining, on a test basis, evidence supporting the amounts and disclosures in the financial statements,
• assessing the accounting principles used and significant estimates made by management, and
• evaluating the overall financial statement presentation.
We believe that out audit provides a reasonable basis for our opinion.
Audit opinion
In our opinion, the financial statements, in all material respects, give a true and fair view, of the financial
position of the organisation at 31 March 2006 and of the results of its operations and cash flows for the year
then ended in conformity with International Financial Reporting Standards.
Ernst & Young
Chartered Accountants (Zimbabwe)
HARARE
10 May 2006
32
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Statement of Accounting Policies
The following principal accounting policies have been consistently applied throughout the period:
ACCOUNTING CONVENTION
The financial statements are prepared under the historical cost convention. No procedures are adopted to
reflect the impact on the financial statements of specific price changes or changes in the general level of
prices.
CURRENCY
The financial statements are expressed in United States dollars. Assets and liabilities are translated to the
relevant currencies at the exchange rate ruling on the balance sheet date, income and expenditure items are
translated at the ruling average monthly rates for the period to which they relate. Realised exchange differences
are taken to the income statement in the year in which they arise. Surpluses and deficits on translation are
dealt with in the income statement in the determination of net income.
DEPRECIATION
Fixed assets are depreciated over their expected useful lives on a straight line basis as follows:-
Computer equipment – 3 years
Office equipment – 5 years
Office furniture and fittings – 10 years
The carrying amounts of fixed assets are reviewed at each balance sheet date to assess whether they are
recorded in excess of their receivable amounts and where carrying values exceed this estimated recoverable
amount, assets are written down to their recoverable amount.
SPECIAL FUND
Funds granted for specific purposes are not included in the income and expenditure account, but are accounted
for separately as Special Fund on the balance sheet. They are maintained in a separate bank account and any
interest earned on the unused funds is credited to the Special Fund.
PROVISIONS
Provisions are recognised when the Organisation has a present obligation (legal or constructive) as a result of
a past event, it is probable that an outflow of resources embodying economic benefits will be required to settle
the obligation and a reliable estimate can be made of the amounts of the obligation.
RETIREMENT BENEFIT COSTS
Retirement benefits are provided for the organisation employees through the National Social Security Authority
(NSSA) scheme.
Employer’s contributions to the NSSA scheme are charged to the income statement when due.
REVENUE RECOGNITION
Funds Income
Income received is based on a set budget agreed upon by all members of the organisation and contributions
made by members are based on set percentages and proportions based on electricity usage. The income is
brought to account per issued invoice to each of the member countries.
Interest
Revenue is recognised as the interest accrues.
STATEMENT OF COMPLIANCE
The financial statements of Southern African Power Pool have been prepared in accordance with International
Financial Reporting Standards (IFRS’s).
33
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Notes 2006 2005
US$ US$
INCOME
OPERATING INCOME
Operating members 121 085 69 000
Imported energy 45 407 69 000
Exported energy 45 533 –
Peak demand 30 145 46 000
Thermal rating 30 271 23 000
Host member 30 271 23 000
Short Term Energy Market 31 810 51 482
Non-member participation fees 29 940 30 000
364 462 311 482
OTHER INCOME/EXPENSES
Anniversary celebrations 50 000 –
Special fund – Telecoms Project 15 000 392 409
Sundry income 11 725 6 980
Foreign exchange loss (19 069) (2 013)
Foreign exchange difference on fixed assets 115 –
Interest received 31 436 9 856
Profit on disposal of fixed assets – 237
453 669 718 951
EXPENDITURE
Administration expenses 2 442 549 737 453
(DEFICIT)/SURPLUS FOR THE YEAR
TRANSFERRED TO ACCUMULATED FUND 3 11 120 (18 502)
Income Statement
For the Year Ended 31 March 2006
34
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Notes 2006 2005
US$ US$
FUNDS AND LIABILITIES
FUNDS
Accumulated funds 3 217 691 231 571
Special funds 4
– Norwegian Government Grant – Botswana 4.1 699 445 72 805
– Norwegian Government Grant – Norway 4.2 1 651 155 –
– Sida Grant 4.3 416 143 –
General reserve 100 000 75 000
CURRENT LIABILITIES
Accounts payable 5 68 518 139 470
TOTAL LIABILITIES 3 152 952 518 846
ASSETS
NON-CURRENT ASSETS
Property, plant and equipment 6 20 709 29 213
CURRENT ASSETS
Accounts receivable 7 33 923 148 225
Cash at bank and on hand
– Co-ordination centre funds 331 577 268 603
– Special fund
– Norwegian Government Grant – Botswana 699 445 72 805
– Norwegian Government Grant – Norway 1 651 155 –
– Sida Grant 416 143 –
TOTAL ASSETS 3 152 952 518 846
L Chilimanzi
Co-ordination Centre Board Chairperson
L Musaba
Co-ordination Centre Manager
10 May 2006
Balance Sheet
As at 31 March 2006
35
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
Notes 2006 2005
US$ US$
NET CASH INFLOW FROM OPERATING ACTIVITIES 1 34 104 11 329
RETURNS ON INVESTMENTS
Interest received 31 436 9 856
Interest paid – (319)
INVESTING ACTIVITIES
Capital expenditure (3 029) (4 751)
Disposal of fixed assets 461 237
FINANCING ACTIVITIES
Grants received 3 637 501 –
Grants utilised/remitted (943 561) (470 911)
INCREASE/(DECREASE) IN CASH RESOURCES 2 2 756 912 (454 559)
NOTES TO THE CASH FLOW STATEMENT
1. NET CASH INFLOW/(OUTFLOW) FROM
OPERATING ACTIVITIES
This is arrived at as follows:
Surplus/(deficit) for the year 11 120 (18 502)
Depreciation 11 187 15 758
Interest receivable (31 437) (9 856)
Interest payable – 319
(Increase) in accounts receivable 114 302 (95 261)
Increase in provisions 9 434 41 362
(Decrease)/increase in accounts payable (80 387) 77 746
Profit on sale of fixed assets (115) (237)
34 104 11 329
2. (DECREASE)/INCREASE IN CASH RESOURCES
The (decrease)/increase in cash resources is
represented by a movement in balances, as follows:
At 1 April 2005 341 408 795 967
At 31 March 2006 3 098 320 341 408
2 756 912 (454 559)
Cash Flow Statement
For the Year Ended 31 March 2006
36
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
1. ACTIVITIES
The main object of the organisation is to co-ordinate the planning and development of electricity inter-
connections between members’ respective networks and to expand the Interconnected Power System and
electricity trading in the region.
2006 2005
US$ US$
2. ADMINISTRATION
Cleaning 895 828
Audit fee
– current year annual audit 8 750 8 788
– prior year charge (421) 2 430
– STEM review 6 250 2 944
Advertising and promotions – 438
Bank charges 14 688 14 693
Computer expenses 1 974 3 086
Courier and postage 4 718 6 602
Depreciation 11 187 15 758
Entertainment 70 379
General expenses 659 –
Insurance 1 669 2 477
Interest paid – 319
Legal fees 265 –
Leave pay expenses 6 392 –
Leasing and hiring costs 274 –
Magazines and books 168 50
SAPP Anniversary Celebrations and other costs 51 086 –
Printing and stationery 1 182 2 211
Recruitment and relocation 1 501 656
Rent paid 17 394 12 500
Repairs and maintenance 443 1 198
Salaries and wages 222 660 194 862
Staff expenses 335 292
Staff training 1 648 1 737
Subscriptions 1 678 405
Sundry expenses 2 300 2 387
Telephone and fax 3 679 7 519
Internet 4 565 6 092
Travel and accommodation 46 620 45 223
Withholding tax on interest – 5
Reports and periodicals 16 670 7 446
Telecommunications – VSAT Project – 396 128
Telecommunications – Training 13 250
TOTAL ADMINISTRATION EXPENSES 442 549 737 453
3. ACCUMULATED FUND
At 1 April 2005 231 571 275 073
Surplus/(deficit) for the year 11 120 (18 502)
Transfer to General Reserve (25 000) (25 000)
At 31 March 2006 217 691 231 571
Notes to the Financial Statements
For the Year Ended 31 March 2006
37
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
2006 2005
US$ US$4. SPECIAL FUNDS
4.1 NORWEGIAN GOVERNMENT GRANT – BOTSWANA
Balance as at 1 April 2005 72 805
Advance 934 652
Payments: (314 943)
Nordpool Consulting 04.05.05 (35 302)Nordpool Consulting 17.05.05 (35 303)Nordpool Consulting 29.06.05 (35 303)Norwegian Water Resources 30.06.05 (16 594)Nordpool Consulting 27.07.05 (29 492)Nordpool Consulting 04.08.05 (35 303)Nordpool Consulting 01.09.05 (25 000)Nordpool Consulting 04.10.05 (25 000)Nordpool Consulting 11.10.05 (12 500)Norwegian Water Resources 14.11.05 (11 128)Norwegian Water Resources 18.11.05 (1 196)Nordpool Consulting 11.01.06 (12 500)Nordpool Consulting 24.01.06 (12 500)Nordpool Consulting 13.02.06 (12 500)Norwegian Water Resources 20.02.06 (2 822)Nordpool Consulting 15.03.06 (12 500)
Bank charges (569)Interest received 7 500
Balance as at 31 March 2006 699 445
Balance as at 1 April 2004 543 716
Additional advance 04.10.04 297 937
Payments: (769 612)
Nordpool Consulting 21.04.04 (75 465)Nordpool Consulting 28.05.04 (63 848)Nordpool Consulting 08.06.04 (65 500)Nordpool Consulting 07.07.04 (64 187)Nordpool Consulting 06.08.04 (62 200)Nordpool Consulting 09.09.04 (61 307)Shaw Technologies Incorporation(Planning Software) 29.10.04 (69 250)Nordpool Consulting 04.10.04 (61 307)Nordpool Consulting 22.11.04 (63 228)Nordpool Consulting 20.12.04 (52 007)Nordpool Consulting 04.01.05 (35 303)Nordpool Consulting 07.02.05 (35 303)Nordpool Consulting 02.03.05 (35 303)Nordpool Consulting 24.03.05 (17 069)Norwegian Water Resources 17.11.04 (8 337)
Bank charges (477)Interest received 1 241
Balance as at 31 March 2005 72 805
Notes to the Financial Statements (Continued)
For the Year Ended 31 March 2006
38
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
2006 2006
NOK US$4 SPECIAL FUNDS (continued)
4.2 NORWEGIAN GOVERNMENT GRANT – NORWAY
Balance as at 1 April 2005
Advance 08.12.05 12 000 000 1 791 903
Payments: (1 099 335) (162 469)
Nordpool ASA 14.03.06 (1 098 575) –Bank charges 01.08.06 (200) (31)Bank charges 01.09.06 (80) (13)Bank charges 05.10.05 (80) (12)Bank charges 01.11.05 (80) (12)Bank charges 01.12.05 (80) (12)Bank charges 02.01.06 (80) (12)Bank charges 01.02.06 (80) (12)Bank charges 01.03.06 (80) (12)
Interest charges 31.12.05 (14) (2)
Interest received 31.12.05 5 855 875Rate variance 30.03.06 – 20 848
Balance as at 31 March 2006 10 906 506 1 651 155
The goal of the project funded by the Norwegian Government is to provide least cost, environmentallyfriendly and affordable energy and increase accessibility for rural areas in Southern Africa throughthe development of a competitive electricity market. The project is expected to run until 2007.
2006 2006SEK US$
4.3 Sida GRANT
Balance as at 1 April 2005
Advance 03.06.05 3 999 999 533 860
Additional advance 21.02.06 2 825 347 377 085
Payments: (3 726 734) (497 389)
Power Planning Associates 12.07.05 (66 819) (8 918)Power Planning Associates 04.08.05 (612 168) (81 703)Power Planning Associates 07.09.05 (299 282) (39 944)Power Planning Associates 05.10.05 (238 312) (31 806)Power Planning Associates 16.11.05 (674 937) (90 081)Power Planning Associates 14.12.05 (546 007) (72 873)Power Planning Associates 14.12.05 (634 481) (84 681)Power Planning Associates 02.02.06 (240 602) (32 112)Power Planning Associates 14.03.06 (414 126) (55 271)
Bank charges (5 336) (712)Interest received 24 719 3 299
Balance as at 31 March 2006 3 117 995 416 143
The goal of the project funded by Sida is the development of a long term transmission pricing policy,implementation procedures and ancillary services market development for the Southern African
Power Pool. The project is expected to run until 2007.
Notes to the Financial Statements (Continued)
For the Year Ended 31 March 2006
39
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
2006 2005
US$ US$
5. ACCOUNTS PAYABLE
Provisions 31 649 22 215
United States Agency for International
Development (USAID) 30 872 30 872
Other creditors 5 997 86 383
68 518 139 470
6. PROPERTY, PLANT AND EQUIPMENT
6.1 Summary
Computer equipment
Cost 46 736 45 091
Aggregate depreciation 42 142 36 992
Net book value 4 594 8 099
Office equipment
Cost 20 000 20 000
Aggregate depreciation 19 631 18 245
Net book value 369 1 755
Office furniture and fittings
Cost 35 422 35 422
Aggregate depreciation 19 675 16 063
Net book value 15 747 19 359
Total
Cost 102 158 100 513
Aggregate depreciation 81 449 71 300
Net book value 20 709 29 213
6.2 Movements for the year
Net book value of total property,
plant and equipment at 1 April 2005 29 213 40 220
Capital expenditure – at cost
Computer equipment 3 029 3 866
Office furniture and fittings – 885
3 029 4 751
Depreciation
Computer equipment 6 189 8 182
Office equipment 1 386 3 971
Furniture 3 612 3 605
11 187 15 758
Disposals – at net book value
Computer equipment 346 –
Net book value of total property,
plant and equipment at 31 March 2006 20 709 29 213
Notes to the Financial Statements (Continued)
For the Year Ended 31 March 2006
40
Southern African Power PoolA N N U A L R E P O R T 2 0 0 6
2006 2005
US$ US$
7. ACCOUNTS RECEIVABLE
Trade debtors 18 922 132 164
Prepayments 6 939 14 371
Other debtors 8 062 1 690
33 923 148 225
8. RELATED PARTY TRANSACTIONS
W Balet
Transaction Relation Amount
Sale of computer Ex. Senior Advisor US$ 461,40
Notes to the Financial Statements (Continued)
For the Year Ended 31 March 2006