P2 Blackfriars Bridge SIP

download P2 Blackfriars Bridge SIP

of 32

Transcript of P2 Blackfriars Bridge SIP

  • 8/3/2019 P2 Blackfriars Bridge SIP

    1/32

    Introd

    uction

    Introd

    uction

    Thames Tunnel

    Blackfriars BridgeForeshore

    Currently, untreated sewage regularly overows into the River Thames from Londons Victorian sewerage systemvia combined sewer overows (CSOs). The proposed Thames Tunnel would intercept these overows through theuse of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. Thesewage ow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reduction

    in untreated sewage entering the River Thames would bring long-term benets for the environment and users ofthe River Thames. In order to deliver the project we need a number of sites along the route and this documentidenties our current preferred sites at Blackfriars Bridge Foreshore.

    Siteinformationpaper

    1

    Key facts

    Local authority: City of London

    CSO name: Fleet MainCSO spill volume in an average year: 520,000m (equivalent to approximately

    208 Olympic swimming pools)

    Site type: CSO site

    Duration of main construction works: Approximately ve years.

  • 8/3/2019 P2 Blackfriars Bridge SIP

    2/32

    Blackfriars Bridge Foreshore

    2

    The location of the site is shown in Figure 1A. The site

    extends into the River Thames, directly under and to thewest of Blackfriars Bridge. Part of the site extends north

    onto the Victoria Embankment (A3211), along which the

    Thames Path is located. To the north and across Victoria

    Embankment (A3211) is a mix of offices and hotels. The

    President ship is moored beyond Blackfriars Millennium

    Pier to the west. The site is within the Whitefriars

    Conservation Area.

    The permanent site area would include the structuresassociated with the Blackfriars Millennium Pier, which

    would be removed and permanently reinstated to the

    east of the railway bridge on Pauls Walk, as illustrated on

    Figure 1A.

    This site information paper sets out our proposals at

    Blackfriars Bridge Foreshore. We have also produced

    project information papers, which cover overarching

    topics relating to the project. Where we consider that aproject information paper is particularly relevant, we have

    highlighted this in a related documents box. At the end

    of this site information paper is a list of other documents,

    which may be of interest and a glossary of terms.

    We are proposing to reclaim an area of the River Thames,

    adjacent to Blackfriars Bridge for this construction workand to accommodate permanent structures required

    to operate the main tunnel. The site would be used to

    intercept the existing local CSO, known as the Fleet Main

    CSO, and connect to the northern Low Level Sewer No.1 to

    divert flows to the main tunnel.

    These works, along with our works at Victoria

    Embankment Foreshore and Chelsea Embankment

    Foreshore mean that we do not need additional sitesto intercept the following CSOs along the northern

    embankment: Smith Street, Queen Street, Church Street,

    Grosvenor Ditch, Kings Scholars Pond, Western Pumping

    Station, Northumberland Street, Savoy Street, Norfolk

    Street and Essex Street.

    Section 1: Introduction and site information

    Related documents:

    Build

  • 8/3/2019 P2 Blackfriars Bridge SIP

    3/32

    Introduction

    3

    Figure 1A: Blackfriars Bridge Foreshore location plan

    N

    Low LevelSewer No.1

    Fleet Main CSO

    Inner TempleGarden

    Temple Place

    Blackfriars

    Rail Bridge

    BlackfriarsStation

    Blackfriars

    Bridge

    Blackfriars

    Millennium Pier

    VictoriaEmbankment

    SOUTHWARKLAMBETH

    CITY OF LONDON

    Local authority boundary

    Draft limit of land to beacquired or used

    Proposed tunnelroute centreline

    Existing sewer

    Existing CSO

    Tem

    ple

    Avenue

  • 8/3/2019 P2 Blackfriars Bridge SIP

    4/32

    Blackfriars Bridge Foreshore

    4

    How we chose this site

    What we proposed at phase one consultationThrough our site selection process, we identified

    Blackfriars Bridge Foreshore to intercept the Fleet Main

    CSO and connect the northern Low Level Sewer No.1

    to the main tunnel. At phase one consultation, which

    was held between September 2010 and January 2011,

    Blackfriars Bridge Foreshore was presented as our

    preferred site. We assessed other sites but none made it

    through to the shortlist stage of the site selection process.

    What we are proposing at phase two consultationWe have considered the comments from phase one

    consultation, feedback from ongoing engagement and

    new information; and undertaken further technical work.

    We still consider that Blackfriars Bridge Foreshore should

    be our preferred site because Blackfriars Bridge Foreshoreis the only location where we can both intercept the Fleet

    Main CSO and connect the northern Low Level Sewer No.1

    to the main tunnel.

    Related documents:

    Q&A Consultation

    Site selection

  • 8/3/2019 P2 Blackfriars Bridge SIP

    5/32

    Construction

    Construction

    5

    Section 2: Construction

    Construction activitiesConstruction activities are required to intercept the CSO

    and connect the northern Low Level Sewer No.1 to the

    main tunnel. We would construct an interception chamber

    to intercept the CSO. A connection culvert would link the

    interception chamber to a drop shaft (approximately

    53m deep), through which flows would drop into the

    main tunnel. We would also construct an overflow weir

    chamber which would allow flows to be transferred from

    the northern Low Level Sewer No.1 down the same

    drop shaft.

    Main tunnel

    Drop shaft

    Valve chamber

    Existingoverfow to

    River ThamesInterception

    chamber

    Existing overfow sewerExisting LowLevel Sewer No.1

    Overfow weir chamber

    Figure 2A: Illustration showing typical elements of below ground infrastructure

    As the construction works would take place within the

    foreshore of the River Thames, permanent structures

    extending into the foreshore are required. Figure 2A

    illustrates the below ground infrastructure proposed.

    These activities would take place within the area

    indicated by the red line in Figure 1A, in four main phases,

    lasting approximately five years in total. The main

    construction activities associated with these phases are

    set out in Table 2.1.

  • 8/3/2019 P2 Blackfriars Bridge SIP

    6/32

    Blackfriars Bridge Foreshore

    6

    Advance works

    Phase 1

    Site setup

    Figure reference Figure 2C Figure 2C

    Typical working hours Varies Standard

    Mainconstructionactivities

    Utilities connected

    Utilities diverted or protected

    Pier relocated

    Site cleared

    Temporary works in the River Thames constructed

    Site facilities and access set up

    Drop shaft excavated and built

    Above and below ground structures constructed

    Mechanical and electrical equipment installed

    Temporary works in the River Thames removed

    Site restored and landscaped

    Temporary site facilities removed

    Table 2.1: Main activities during construction phases

    Our typical working hours are expected to be:

    Standard: 8am-6pm weekdays, 8am-1pm Saturday*

    Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays

    Continuous: 24 hours a day, seven days a week**

    Varies: Working hours for advanced works will depend on the nature of the works and will be

    agreed with the local authority

    * Standard working hours would also include, subject to agreement with the local authority:

    a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.

    equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.

    ** The main activities taking place 24 hours a day are below ground or within an enclosure.

  • 8/3/2019 P2 Blackfriars Bridge SIP

    7/32

    Construction

    7

    Phase 2

    Drop shaft

    construction

    Phase 3

    Construction of

    other structures

    Phase 4

    Completion of works

    and site restoration

    Figure 2D Figure 2E

    Standard with

    occasional extended

    standard

    Standard Standard

    Related documents:

    Build

    Managing construction

  • 8/3/2019 P2 Blackfriars Bridge SIP

    8/32

    Blackfriars Bridge Foreshore

    8

    Site layout and construction phasesFigures 2C, 2D and 2E show how the site might be laid

    out during the construction phases, which are set outin Table 2.1 and Figure 2B. These layouts have been

    informed by the size of the infrastructure proposed,

    the construction methods required and the location

    of neighbouring buildings and structures. They have

    also been developed to minimise effects on the local

    community and environment. Particular factors at this site

    that have influenced the layout are as follows:

    Since our phase one consultation we have increasedthe drop shaft in size from approximately 20m to 24m

    in internal diameter as a result of further physical

    modelling of the shaft.

    Part of the site would be constructed on piles to

    minimise the effects on river ecology compared to other

    construction options.

    The layout of the site has been designed to reduce

    effects on the navigation of the River Thames.

    The connection to the northern Low Level Sewer No.1

    has moved to beneath the existing Blackfriars Bridge

    ramp to minimise the effects on existing utilities

    running within the Victoria Embankment (A3211).

    P1 P3

    P2 P4

    Year 1 Year 2 Year 3 Year 4 Year 5

    Advance

    works

    The site layouts are indicative only, and the contractor

    may arrange the site in a different way, depending onthe chosen construction methods, provided that any

    environmental effects are appropriately managed, and

    that the main construction activities are undertake within

    the red line shown in Figure 1A.

    Figure 2B: Construction timeline showing approximate duration of works in phases (P)

  • 8/3/2019 P2 Blackfriars Bridge SIP

    9/32

    Construction

    9

    Jack up bargeservicing pilingoperations

    Working area for pierrelocation (advance

    works only)

    NSOUTHWARK

    CITY OF LONDON

    LAMBETH

    Diversion rejoins

    Thames Path atTemple Place

    Possible locationof President duringconstruction

    Existing mooringfor President

    Barge

    Figure 2C: Illustrative advance works and phase 1 construction plan

    Maximum extent ofconstruction site foradvance works and phase 1

    Site hoarding/traffic barrier

    Cofferdam

    Local authority boundary

    Site support/welfare

    Traffic lane coned off for site access

    Site access

    Existing Thames Path

    Thames Path diversion

    BlackfriarsBridge

    BlackfriarsRail Bridge

    BlackfriarsStationVictoria Embankment

  • 8/3/2019 P2 Blackfriars Bridge SIP

    10/32

    Blackfriars Bridge Foreshore

    10

    Figure 2D: Illustrative phase 2 construction plan

    Option for contractorto transport materialsusing barges

    Piling rig Cranes

    Drop shaft

    N

    Maximum extent ofconstruction site for phase 2

    Site hoarding/traffic barrier

    Cofferdam

    Local authority boundary

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    SOUTHWARK

    CITY OF LONDON

    LAMBETH

    Diversion rejoins

    Thames Path atTemple Place

    Possible locationof President duringconstruction

    Traffic lane coned offfor site access

    Site access

    Existing Thames Path

    Thames Path diversion

    BlackfriarsStation

    BlackfriarsBridge

    BlackfriarsRail Bridge

  • 8/3/2019 P2 Blackfriars Bridge SIP

    11/32

    Construction

    11

    Figure 2E: Illustrative phase 3 construction plan

    Option for contractorto transport materialsusing barges

    Cranes

    CraneDrop shaft

    N

    Maximum extent ofconstruction site for phase 3

    Site hoarding/traffic barrier

    Cofferdam

    Local authority boundary

    Site support/welfare

    Maintenance workshop and storage

    Internal site road

    Site access

    Existing Thames Path

    Thames Path diversion

    CITY OF LONDON

    SOUTHWARKLAMBETH

    Possible locationof President duringconstruction

    BlackfriarsStation

    BlackfriarsBridge

    BlackfriarsRail Bridge

    Diversion rejoins

    Thames Path atTemple Place

  • 8/3/2019 P2 Blackfriars Bridge SIP

    12/32

    Blackfriars Bridge Foreshore

    12

    Additional works and activitiesThe main construction activities at this site are set out in

    Table 2.1. We would also need to undertake additionalworks and activities, some of which may be located

    outside of the area indicated by the red line in Figure 1A.

    The anticipated additional works and activities are set

    out in Table 2.2.

    When Type of works What we would do

    Required for

    construction

    phase

    Installation of equipment to monitorenvironmental matters such as noise,

    vibration and dust.

    The locations of monitoring equipment would be agreedwith the local authority and relevant landowners.

    Protection works to third party structures

    (such as buildings, bridges and tunnels).

    We would undertake studies to identify any effects our

    construction work may have on third party structures.

    The studies may recommend particular construction

    methods or, in very limited instances, protection works.

    If protection works are required to the existing sewer,

    we would access the sewer network through existingmanholes.

    Temporary connection to utilities (such as

    water, sewer, phone and electricity supply).

    We expect to connect to utilities in Victoria

    Embankment (A3211).

    Traffic management works.

    These would need to extend beyond our site and could

    include relocating kerb lines, repainting road lines and

    modifying traffic signals.

    Dredging.

    There is a possibility that as the detailed design isdeveloped we may need to undertake dredging to allow

    barges to get to and from our site and for the relocated

    Millennium Pier.

    Protection of the river.We may need to carry out works to strengthen the river

    bed to avoid scour.

    Required for

    operational

    phase

    Permanent connection to utilities (such as

    water, phone and electricity supply) for the

    operational tunnel.

    We expect to connect to utilities in Victoria

    Embankment (A3211).

    Table 2.2: Additional works and activities

  • 8/3/2019 P2 Blackfriars Bridge SIP

    13/32

    Construction

    13

    Construction transport and accessWe propose to use barges to bring in and take away the

    material used to fill the cofferdam. Each barge wouldremove approximately 55 lorries from the road. Using

    barges at this site would reduce the number of lorry visits

    to/from this site by approximately 45% (saving 14,500

    lorry visits over the construction period of approximately

    five years). Table 2.3 sets out the anticipated average

    daily number of lorries and barges visiting (ie travelling to

    and from) the site during the peak months of each phase,

    based on moving cofferdam fill material by barge.

    During phases 1 and 2 of construction, construction

    traffic would access the site travelling across Blackfriars

    Bridge and turning left into the site through a new

    entrance from the westbound ramp leading down from

    Blackfriars Bridge. Traffic leaving the site would turn left

    from a second new entrance then merge onto Victoria

    Embankment (A3211) and continue westbound.

    During construction phase 3, the westbound ramp fromBlackfriars Bridge would be closed. Construction traffic

    would access the site by turning left from the Blackfriars

    underpass, and would leave the site by the same route

    as for the other construction phases. Beyond this,

    construction traffic would use the major road network to

    get to and from its final destination. Site access points

    are shown on Figures 2C, 2D and 2E.

    During construction phase 3, general traffic that would

    normally use the westbound ramp from Blackfriars Bridgewould be diverted as shown in Figure 2F.

    We would need to suspend some coach parking bays on

    the westbound ramp from Blackfriars Bridge and some

    loading bays on Victoria Embankment (A3211) during

    construction.

    The Thames Path runs through our construction site. We

    would create a temporary diversion for the duration of

    our works, as shown in Figures 2C, 2D and 2E. Based on

    our current design we do not anticipate that any other

    footpath or bus stop relocations would be required.

    Phase 1Site setup

    Phase 2Drop shaft

    construction

    Phase 3Construction ofother structures

    Phase 4Completion ofworks and site

    restoration

    Average daily lorry visits 21 lorries 35 lorries 29 lorries 6 lorries

    Average daily barge visits 2 barges none none 3 barges

    Table 2.3: Average daily lorry and barge visits during the peak months

    Related documents:

    Transport

  • 8/3/2019 P2 Blackfriars Bridge SIP

    14/32

    Blackfriars Bridge Foreshore

    14

    Figure 2F: Proposed diversion for westbound ramp from Blackfriars Bridge

    SOUTHWARKLAMBETH

    CITY OF LONDONWESTMINSTER

    N

    Diversion route

    Local authority

    boundary

    WestminsterBridge

    WaterlooBridge

    BlackfriarsBridge

    BlackfriarsRail Bridge London

    BridgeMillenium

    Bridge

    Golden JubileeFootbridges

    Hungerford

    Bridge

  • 8/3/2019 P2 Blackfriars Bridge SIP

    15/32

    Construction

    15

    Related documents:

    Environment

    Managing construction

    Transport

    Management of construction worksOur construction works would be managed in accordance

    with an agreed Code of construction practice (CoCP).For phase two consultation, we have produced a draft

    CoCP Part A: General requirements, informed by CoCPsfrom other major construction projects in London and

    consultation with the local authorities. Through the

    environmental impact assessment process, scheme-

    wide principles to address potential effects on the local

    environment have been identified and integrated into

    the design. The CoCP Part A sets out scheme-wide control

    measures that would be used to minimise potentialeffects during the construction process.

    Table 2.4 sets out what we consider to be the key issues

    for this site during construction, and how we are currently

    proposing to address them.

    Bl kf i B id F h

  • 8/3/2019 P2 Blackfriars Bridge SIP

    16/32

    Blackfriars Bridge Foreshore

    16

    Table 2.4: Key issues relating to construction

    Issue Our response

    Construction activities would

    require the temporary relocation

    of the President ship and

    the permanent relocation of

    Blackfriars Millennium Pier.

    The President ship would be temporarily moved west to the formerChrysanthemum Pier moorings. Blackfriars Millennium Pier would be relocated to

    the east of Blackfriars Bridge.

    Possible effect of construction

    vehicles on the volume of traffic

    on Victoria Embankment (A3211).

    We have sought to minimise disruption to the local road network through our

    site layout, design and phasing of our construction works. We would manage

    the effects of road transport through our traffic management plans, which will

    seek to limit the number of vehicle movements and hours of operation, identify

    the most suitable site access points and any necessary highway management

    arrangements. As already set out, we also propose to use barges to bring in and

    take away the material used to fill the cofferdam, which would reduce the number

    of lorry movements from this site by approximately 45% over the construction

    period.

    Temporary diversion of the

    Thames Path.

    The Thames Path would be temporarily diverted via a safe alternative route along

    the northern footpath to Victoria Embankment (A3211), and back to the Thames

    Path via steps and a temporary lift to the east of Blackfriars Bridge.

    Possible effect of foreshore

    construction activities on river

    navigation and river users.

    We have undertaken modelling to test the effect that the structure has on the flow

    of the river. The modelling has shown the proposed structure to be satisfactory

    and the Port of London Authority and other key stakeholders are satisfied the

    permanent works have a minimum effect on river navigation. A full navigational

    risk assessment will be undertaken for the temporary and permanent works.

    Possible effect of noise and

    vibration from construction

    activities on neighbouring areas.

    The contractor would be required to implement noise and vibration control

    measures at the worksite, which will be set out in the CoCP.

    Possible effects on local air

    quality and dust nuisance in

    neighbouring areas.

    Preliminary findings indicate that while there is the potential for dust nuisance

    effects, there are unlikely to be any significant local air quality effects at any of

    the sites. The contractor would put in place air and dust control measures at the

    worksite, which will be set out in the CoCP.

  • 8/3/2019 P2 Blackfriars Bridge SIP

    17/32

    Future

    use

    Future use

    17

    Section 3: Future use

    This section describes the site after the completion of the

    construction work, ie when the main tunnel is in use the

    operational phase.

    Design

    Since our phase one consultation we have progressed

    the design for the permanent use and appearance of

    the structures at Blackfriars Bridge Foreshore. The design

    of the permanent proposals follows our scheme-wideprinciples and takes into account comments made and

    ongoing engagement with the City of London and other

    technical consultees.

    Our permanent works which are formed within a structure

    extending into the foreshore of the River Thames need to

    incorporate functional elements, which are required for

    the operation of the tunnel. These include:

    Underground structures with ground level access covers

    including: a CSO drop shaft with an internal diameter

    of approximately 24m, connection culverts, interception

    chamber, valve chamber, passive filter chamber and an

    overflow weir chamber to divert flow from the northern

    Low Level Sewer No.1.

    Five main ventilation columns up to 6m high.

    A small diameter ventilation column to the interception

    chamber up to 6m high.

    Maintenance vehicle access.

    Electrical and control kiosks.

    Table 3.1 sets out the site specific issues that haveinfluenced our permanent design proposals and how we

    have addressed them in our proposed design.

    Blackfriars Bridge Foreshore

  • 8/3/2019 P2 Blackfriars Bridge SIP

    18/32

    Blackfriars Bridge Foreshore

    18

    Issue Our response

    Effect on the historic setting of

    the site including views alongthe River Thames towards St

    Pauls Cathedral.

    The form of the proposed structure in the foreshore of the River Thames is

    contemporary and seeks to resolve the level differences created by the Thames Path

    and the Blackfriars Bridge approach ramp.

    The structure is designed to allow unhindered views of the listed buildings located

    along Victoria Embankment (A3211) and views towards St Pauls Cathedral. In

    addition, new views of the River Thames would be offered from the viewing platforms

    created on the new structure.

    The proposed materials would complement those of the Embankment and the listed

    buildings located close to the site while making it clear that we have created a newextension into the River Thames.

    The historic line of trees (London Planes) along the Embankment would be extended

    onto the new structure to help create areas of shade.

    As a result in the change to the ventilation strategy we no longer need a large

    ventilation building on the site as was indicated at phase one consultation.

    Ventilation of the tunnel is still required, and in this location we have designed a

    series of five smaller columns that form a feature on the proposed landscape whilstmeeting our operational requirements to manage the air in the main tunnel.

    Effects on river navigation and

    hydraulics.

    Preliminary modelling has indicated that the proposed design is acceptable in terms

    of river flow. The proposals have been discussed with the Port of London Authority

    and other key stakeholders to develop a layout that has a minimal effect on river

    navigation.

    Effect on the Thames Path.

    The Thames Path would be restored after our works are complete and would be

    central to the proposed new landscaped public area, where people can stop to enjoy

    the River Thames.

    The proposals would enhance the Thames Path which is currently characterised by a

    number of narrow ramps and stairs in this location.

    Our design allows a flat and fairly direct pedestrian route from the western access

    point on Victoria Embankment (A3211) to the eastern access on Pauls Walk beneath

    the road bridge, while offering opportunities to step to the side and ascend ramps or

    stairs to rest, enjoy the views or walk up to Blackfriars Bridge or Blackfriars Station.

    Future use

  • 8/3/2019 P2 Blackfriars Bridge SIP

    19/32

    Future use

    19

    Issue Our response

    Effect on river based business

    and passenger services from

    Blackfriars Millennium Pier.

    It is proposed to permanently relocate Blackfriars Millennium Pier to the east of theBlackfriars Railway Bridge.

    The shape of the structure to intercept the Fleet CSO has been designed to ensure

    that it does not impede the navigational channel of the River Thames in this

    location.

    Following completion of the works the President ship would be restored from its

    temporary location during the construction works to its current mooring to the west

    of the new structure.

    An alternative location onshore would be found for Crown River Cruises, who are

    currently located on Blackfriars Millennium Pier.

    Loss of foreshore habitat andeffects on ecology.

    Our proposals for the permanent layout and design of the site have sought to reduce

    the extent of the permanent works within the river to minimise effects on water

    ecology as far as possible.

    Ecological surveys of the River Thames are being undertaken to identify possibleeffects, and design measures would be incorporated where required.

    Construction of the tunnel would also deliver river wide improvements to local water

    quality, which would result in positive effects on river ecology, including habitat

    improvements and reduced fish kills.

    Table 3.1: Site specific elements and issues that have influenced our permanent design

    Blackfriars Bridge Foreshore

  • 8/3/2019 P2 Blackfriars Bridge SIP

    20/32

    Blackfriars Bridge Foreshore

    20

    Figure 3A: Photo of the site before the works

    Figures 3A, 3B, 3C and 3D show the current site and

    provide illustrations of our design proposals. Further

    information on the development of our design can be

    found in the Design development report.

    Related documents:

    Design

    Future use

  • 8/3/2019 P2 Blackfriars Bridge SIP

    21/32

    Future use

    21

    Figure 3B: Artists impression of the site after the works are completed

    Blackfriars Bridge Foreshore

  • 8/3/2019 P2 Blackfriars Bridge SIP

    22/32

    Blackfriars Bridge Foreshore

    22

    Figure 3C: Aerial view of the completed works

    Future use

  • 8/3/2019 P2 Blackfriars Bridge SIP

    23/32

    23

    Figure 3D: Layout of site once construction works complete

    President reinstatedin current positionat the end of

    construction period

    Ventilationcolumns

    Provision

    for smallretail kiosk

    Access for

    maintenancevehicles

    Stepped platformand seating area

    Level Thames Path

    over new foreshorestructure

    Raised viewingplatform

    VictoriaEmbankment

    BlackfriarsBridge

    Ramp providesstep free access toviewing platform

    New water featurein paving surfacein the shape of the

    River Thames

    Widened

    pedestrian routeunder bridge

    Stairs from

    BlackfriarsBridge reinstated

    Foreshore structureto extend underbridge deck

    N

    Electrical and control kioskunder vehicle ramp fromBlackfriars Bridge

    New entrance topublic WCs and privatesporting facility

    New FleetCSO outlet

    Refer to detail below

    Millennium pierpermanently relocated

    Blackfriars Bridge Foreshore

  • 8/3/2019 P2 Blackfriars Bridge SIP

    24/32

    Blackfriars Bridge Foreshore

    24

    Operation and maintenanceOnce the tunnel is operational, we would need access

    to the site occasionally for inspection and maintenance

    purposes. We expect to visit the site approximately

    once every three to six months to carry out inspections

    and maintenance of the ventilation and below ground

    equipment. This is likely to involve a visit by staff in a

    small van, and may take several hours.

    Once every ten years, we expect to carry out a major

    internal inspection of the tunnel and underground. This is

    likely to involve a small team of inspection staff, a small

    team of support crew and two mobile cranes to lower

    the team and inspection vehicle into the shaft. This is

    likely to take several weeks, and would require temporary

    fencing around the shaft for safety and security while the

    inspection takes place.

    We may also need to make visits to the site for unplanned

    maintenance or repairs, for example, if there is a blockage

    or equipment failure. This may require the use of mobile

    cranes and vans.

    Permanent vehicular access would be from Victoria

    Embankment (A3211).

    Management of operational effectsWe have undertaken technical work, including stakeholder

    engagement, to assess and identify the key issues

    associated with this site once it is operational. Table

    3.2 summarises these issues and how we are currently

    proposing to address them.

    Future use

  • 8/3/2019 P2 Blackfriars Bridge SIP

    25/32

    25

    Issue Our response

    Possible odour effects during the

    operation of the tunnel.

    Odour effects at this site are expected to be negligible because we have developedanAir management plan to minimise possible odour and air quality effects arisingfrom the operation of the tunnel. The technology we are proposing to use at

    this site includes the use of passive below ground carbon filters that will remove

    possible odour before air leaves the ventilation equipment.

    Disturbance from future

    maintenance access.

    Permanent access would be required for maintenance and servicing purposes to

    the shaft and ventilation equipment. Any planned maintenance visits would be

    undertaken during normal working hours and all visits managed to avoid disruption

    to local residents, businesses and users of affected public areas as far as possible.

    Table 3.2: Key issues relating to site operation

    Related documents:

    Odour

  • 8/3/2019 P2 Blackfriars Bridge SIP

    26/32

  • 8/3/2019 P2 Blackfriars Bridge SIP

    27/32

    27

    Phase two public consultation material

    Icon Title Details

    OverflowSets out how Londons sewerage system works and why the capital has an overflow

    problem.

    Route and

    tunnel

    alignment

    Sets out the preferred route of the main tunnel and the reasons for our preference.

    Site selection Sets out the process we followed to find and select our preferred sites.

    Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.

    Further information

  • 8/3/2019 P2 Blackfriars Bridge SIP

    28/32

    28

    Technical reports

    Theme Icon Title Details

    Phase one

    consultation1

    SUMMARY

    Report on phase one

    consultation:

    summary report

    Provides a summary of the comments made at phase one

    consultation and our responses.

    Phase two

    construction

    information

    Code of construction

    practice Part A:

    General requirements

    (CoCP)

    Sets out control measures to be adopted during the project

    construction period.

    Phase two

    environmental

    information

    Air management

    plan

    Outlines the methods which we will use to manage odour

    from the main tunnel at all our preferred sites.

    Preliminary

    environmental

    information report

    (PEIR)

    Contains initial assessments on the environmental effects of

    the Thames Tunnel project based on information collected

    to date. Please refer to volume 21 of the non-technical

    summary and volume 21 of the PEIR for more informationon this site.

    Phase two scheme

    development

    Design development

    report

    Provides a general overview of how the scheme design at

    each site has evolved to date. Please refer to chapter 18 for

    more information on this site.

    2Phase two schemedevelopment report

    Provides an overview of the development of the Thames

    Tunnel project and how each site was chosen. Please refer toAppendix Q for more information on this site.

    Site glossary

  • 8/3/2019 P2 Blackfriars Bridge SIP

    29/32

    29

    g y

    Term Definition

    Carbon filters Filters that remove odours before the air is released from the tunnel.

    CofferdamA wall that is constructed within the river around the outside of the working area and then

    pumped dry. The inside of the cofferdam can then be filled to create a safe working area.

    Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.

    Combined sewer

    overflow (CSO)

    A structure, or series of structures, that allows sewers to overflow into the river when they

    are full as a result of increased rainfall. Without the overflows, the sewers would back up

    and cause flooding in streets or houses.

    Connection tunnel A tunnel connecting a drop shaft to the main tunnel.

    Conservation areaAn area designated by the local authority or English Heritage as having special

    architectural or historical interest.

    Draft limit of land to be

    acquired or used

    The extent of land that we may need to use or acquire, or over which rights may be needed

    to carry out works that are essential to the project.

    Drop shaft

    A vertical circular concrete structure, used to drop flows from the high level of the CSO to

    the low level of the main tunnel. It would also be used to provide access to construct the

    connection tunnels.

    Foreshore Ground uncovered by the river when the tide is low.

    Interception chamberA structure, built on an existing combined sewer, which diverts stormwater overflow into the

    main tunnel.

    Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.

    Operational phase After the completion of the construction work, when the main tunnel is in use.

    Scour Movement of the riverbed materials due to the force of the water.

    Thames Tunnel project

    The Thames Tunnel project comprises a storage and transfer tunnel, from west London to

    Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the

    Thames Tideway.

    Transport for London

    Road Network (TLRN)

    The network of roads managed by Transport for London. These are the major or strategic

    roads, which have high capacity.

  • 8/3/2019 P2 Blackfriars Bridge SIP

    30/32

  • 8/3/2019 P2 Blackfriars Bridge SIP

    31/32

  • 8/3/2019 P2 Blackfriars Bridge SIP

    32/32