Overview ofOverview of Standard 189.1Standard 189.1...
Transcript of Overview ofOverview of Standard 189.1Standard 189.1...
Overview ofOverview ofOverview of Overview of Standard 189.1Standard 189.1--2011 for 2011 for
HighHigh--Performance, Performance, Green BuildingsGreen BuildingsGreen BuildingsGreen Buildings
Tom Lawrence Ph D P E LEEDTom Lawrence Ph D P E LEED APAPTom Lawrence, Ph.D. P.E., LEEDTom Lawrence, Ph.D. P.E., [email protected] [email protected]
ASHRAE is a Registered Provider with The American Institute of ASHRAE is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on Architects Continuing Education Systems. Credit earned on
completion of this program will be reported to CES Records for AIA completion of this program will be reported to CES Records for AIA p p g pp p g pmembers. Certificates of Completion for nonmembers. Certificates of Completion for non‐‐AIA members are AIA members are
available on request.available on request.
This program is registered with the AIA/CES for continuing This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that professional education. As such, it does not include content that
may be deemed or construed to be an approval or endorsement by may be deemed or construed to be an approval or endorsement by th AIA f t i l f t ti th dth AIA f t i l f t ti th dthe AIA of any material of construction or any method or manner the AIA of any material of construction or any method or manner
of handling, using, distributing, or dealing in any material or of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentationservices will be addressed at the conclusion of this presentationservices will be addressed at the conclusion of this presentationservices will be addressed at the conclusion of this presentation..
This course has been approved for 1 LU/HSW by AIA and the course number is LAWRENCE01. The course material also qualifies for Health, Safety, and Welfarematerial also qualifies for Health, Safety, and Welfare
Program (HSW) credit
The GBCI CMP mark indicates that this course will be monitored by GBCI to ensure
Approved for:
1that it upholds the quality, relevance, and rigor necessary to contribute to ongoing learning in knowledge areas relevant to LEED professionals
1General CE hours
relevant to LEED professionals.
Overview of Standard 189.1-2011 for High-Performance, 0g ,Green Buildings
Tom Lawrenceby
0LEED-specific hours
GBCI cannot guarantee that course sessions will be delivered to you as submitted to GBCI. However, any course found to be in violation of the standards of the program or otherwisethe standards of the program, or otherwise contrary to the mission of GBCI, shall be removed. Your course evaluations will help us uphold these standards. Please complete them as requested by GBCI or the education provider. pApproval date:
Course ID: 0090010505
09/17/2013
Course Description:
S S d d 89 20 fASHRAE Standard 189.1-2011 for High Performance Green Buildings
ASHRAE, in conjunction with the U.S. Green Building Council and the Illumination Engineers Society, has developed a new standard for High Performancedeveloped a new standard for High Performance, Green Buildings (Standard 189.1-2011). The Standard provides the minimum requirements for a hi h f b ildi d d l dhigh-performance green building, and was developed with the intent to provide a balance of environmental factors involved with designing, building, and g g, g,planning for the operation of buildings. This session provides a detailed look at the standard, the background on its development and what is foreseenbackground on its development and what is foreseen for its application and ultimate adoption.
Learning ObjectivesLearning Objectives
1.1. Recognize the importance of developing a Recognize the importance of developing a codecode--intended standard for design of highintended standard for design of high--codecode intended standard for design of highintended standard for design of highperformance green buildings performance green buildings
2.2. Differentiate Standard 189.1 from green Differentiate Standard 189.1 from green ggbuilding rating systems (e.g., LEED, Green building rating systems (e.g., LEED, Green Globes) Globes)
3.3. Identify the key concepts contained in Standard Identify the key concepts contained in Standard 189.1 within each of the main topical areas of 189.1 within each of the main topical areas of it t IEQ d t i lit t IEQ d t i lsites, water, energy, IEQ and materials sites, water, energy, IEQ and materials
4.4. Identify the two compliance path options Identify the two compliance path options (Prescriptive and Performance) and their(Prescriptive and Performance) and their(Prescriptive and Performance) and their (Prescriptive and Performance) and their associated provisions in Standard 189.1. associated provisions in Standard 189.1.
66
77
Introduction and greetings from the Introduction and greetings from the University of GeorgiaUniversity of Georgia
Green Buildings Overview, Green Buildings Overview, Standard 189 Standard 189 -- 88
Green building related speaking events
t id U S i l doutside U.S. mainland
High Performance Green Buildings and related topics are becoming a big focus around the globe
Copyright MaterialsCopyright Materials
Copyright Copyright 2013 by Tom Lawrence and the 2013 by Tom Lawrence and the American Society of Heating, Refrigerating and American Society of Heating, Refrigerating and y g g gy g g gAirAir--Conditioning Engineers (ASHRAE). All rights Conditioning Engineers (ASHRAE). All rights reserved.reserved.
No part of this presentation may be reproduced No part of this presentation may be reproduced without written permission, nor may any part of without written permission, nor may any part of this presentation be reproduced, stored in a this presentation be reproduced, stored in a retrieval system or transmitted in any form or byretrieval system or transmitted in any form or byretrieval system or transmitted in any form or by retrieval system or transmitted in any form or by any means (electronic, photocopying, recording any means (electronic, photocopying, recording or other) without written permission.or other) without written permission.or other) without written permission.or other) without written permission.
1010
Progress and StatusProgress and Status 3 ½ years of development, with 4 rounds 3 ½ years of development, with 4 rounds
of public reviewof public reviewpp Initial release in January 2010Initial release in January 2010 New edition published Dec 2011New edition published Dec 2011 New edition published Dec. 2011New edition published Dec. 2011
Standard 189.1Standard 189.1--201120112013 d t ith 18 dditi l dd d2013 d t ith 18 dditi l dd d 2013 update with 18 additional addenda2013 update with 18 additional addenda
In continuous maintenanceIn continuous maintenance
ASHRAE ASHRAE Standard 189.1Standard 189.1
Overview of ASHRAE Standard 189.1 for Overview of ASHRAE Standard 189.1 for “High“High--Performance, Green Buildings”Performance, Green Buildings”HighHigh Performance, Green BuildingsPerformance, Green Buildings-- What is it?What is it?
Why was it created?Why was it created?-- Why was it created?Why was it created?-- Highlights Highlights
1212
http://www.ashrae.org/greenstandard
Compare Standard 189.1 to LEEDCompare Standard 189.1 to LEED
Std. 189.1:Std. 189.1:-- Improvement in all Improvement in all
V lV l1313
topical areastopical areas-- Pushes the envelopePushes the envelope
Voluntary vs. Voluntary vs. mandatorymandatory
ASHRAE Standard 189.1ASHRAE Standard 189.1--20112011
An optional compliance path (“Jurisdictional An optional compliance path (“Jurisdictional Compliance Option”) to the InternationalCompliance Option”) to the InternationalCompliance Option ) to the International Compliance Option ) to the International Green Construction Code (IGCC)Green Construction Code (IGCC)
Official description of Standard 189 1 within U S
“… compliance option of the International Green Construction
Official description of Standard 189.1 within U.S.
International Green Construction Code.” Choice of the project team to use IGCC or Std 189.1
1414
Sponsors and Project CommitteeSponsors and Project Committee
Consensus processConsensus process Sponsor and coSponsor and co--sponsors:sponsors: Sponsor and coSponsor and co sponsors:sponsors:
-- ASHRAE (American Society of Heating, ASHRAE (American Society of Heating, Refrigerating and AirRefrigerating and Air--Conditioning Engineers)Conditioning Engineers)Refrigerating and AirRefrigerating and Air Conditioning Engineers)Conditioning Engineers)
-- USGBC (U.S. Green Building Council)USGBC (U.S. Green Building Council)-- IES (Illuminating Engineering Society)IES (Illuminating Engineering Society)IES (Illuminating Engineering Society)IES (Illuminating Engineering Society)
Project committee:Project committee:35+ voting members;35+ voting members;35+ voting members;35+ voting members;variety of disciplines, variety of disciplines, industries & organizationsindustries & organizations
1515
industries & organizationsindustries & organizations
Standard 189.1: IntentStandard 189.1: Intent
What Standard 189.1 is:What Standard 189.1 is:d dd d-- a standarda standard
-- applies to all buildings except lowapplies to all buildings except low--rise residential rise residential buildings (same as ASHRAE Std 90.1)buildings (same as ASHRAE Std 90.1)
-- intended for adoption into model building codesintended for adoption into model building codesp gp g
What Standard 189.1 is not:What Standard 189.1 is not:-- notnot a design guidea design guidenotnot a design guidea design guide-- notnot a rating systema rating system
Even if not adopted by your local authorities,Even if not adopted by your local authorities, this Standard is an indication of future industry trends
Standard 189.1: Relation Standard 189.1: Relation totoOtherOther ASHRAE StandardsASHRAE StandardsOther Other ASHRAE StandardsASHRAE Standards
62.1 (current version)90.1 (current version)90.1 (current version) Standard 62.1
Adopt, with modifications
AdoptAdopt, with minor
modifications
Adopt
Standard 55
Adopt
Organization and What it CoversOrganization and What it Covers Similar to other ASHRAE standards and LEEDSimilar to other ASHRAE standards and LEED Similar to other ASHRAE standards and LEED Similar to other ASHRAE standards and LEED
1818
Standard 189.1 Basic StructureStandard 189.1 Basic Structure
x.1: x.1: ScopeScope x 2:x 2: ComplianceCompliance
For Each Section
x.2: x.2: ComplianceCompliance x.3: x.3: Mandatory Mandatory
( i d f ll j t )( i d f ll j t )(required for all projects)(required for all projects) x.4: x.4: Prescriptive Prescriptive pathpath
(simple option, minimal choices, (simple option, minimal choices, very few calculations)very few calculations)
x.5: x.5: Performance Performance pathpath(more sophisticated, flexibility, but (more sophisticated, flexibility, but
1919
( p , y,( p , y,more effort)more effort)
Highlights of Standard 189.1Highlights of Standard 189.1S ti 5S ti 5 SitSitSection 5 Section 5 –– Sites:Sites:
Mandatory provisionsMandatory provisions Allowable sites, where to build; or Allowable sites, where to build; or
where where notnot to allow a buildingto allow a building Other areas that are addressed:Other areas that are addressed:
-- Urban heat islandUrban heat island-- Light “pollution” limitationsLight “pollution” limitations
Prescriptive optionPrescriptive option-- Pervious surface areaPervious surface area-- Greenfield site, maintainingGreenfield site, maintaining
t i i ti tit i i ti ti
2020
or restoring existing native or restoring existing native plants (20% of site)plants (20% of site)
Section 6 Section 6 –– Water Use EfficiencyWater Use Efficiency
Mandatory ProvisionsMandatory Provisions Site water useSite water use Site water useSite water use Building water useBuilding water use HVAC Systems, equipmentHVAC Systems, equipment Water consumptionWater consumptionpp
managementmanagement
2121
Section 6 Section 6 –– Water Use EfficiencyWater Use EfficiencyMandatory ProvisionsMandatory Provisions Site water useSite water use: :
Landscape design: Landscape design: biobio--diverse and diverse and adapted plantings for 60% of landscapeadapted plantings for 60% of landscapeIrrigation design: Irrigation design: hydrozoninghydrozoningControls: Controls: smart irrigation controllers smart irrigation controllers
2222
Section 6 Section 6 –– Water Use EfficiencyWater Use Efficiency
Mandatory ProvisionsMandatory Provisions Building water useBuilding water use:: Building water useBuilding water use: :
((§§6.3.2.1) 6.3.2.1) plumbing fixtures & fittings per plumbing fixtures & fittings per U S EPAU S EPA WaterSenseWaterSense or ASME Standardsor ASME StandardsU.S. EPA U.S. EPA WaterSenseWaterSense or ASME Standards, or ASME Standards, with specific limit on flow amount or ratewith specific limit on flow amount or rate((§§6 3 2 2)6 3 2 2) appliances per U S EPAappliances per U S EPA((§§6.3.2.2) 6.3.2.2) appliances per U.S. EPA appliances per U.S. EPA EnergyStarEnergyStar, with water use factor for , with water use factor for dwelling unit or public accessdwelling unit or public accessdwelling unit or public accessdwelling unit or public access
2323
Section 6 Section 6 –– Water Use EfficiencyWater Use EfficiencyMandatory Provisions (Mandatory Provisions (contcont.).) HVAC Systems (HVAC Systems (§§6.3.2.3)6.3.2.3)::
-- Subsystem metering above thresholdsSubsystem metering above thresholds-- Efficient drift eliminators (0 002%Efficient drift eliminators (0 002%Efficient drift eliminators (0.002% Efficient drift eliminators (0.002%
counterflowcounterflow, 0.005% cross, 0.005% cross--flow)flow)Condensate collection from units >19 kWCondensate collection from units >19 kW-- Condensate collection from units >19 kW Condensate collection from units >19 kW (65,000 Btu/h) in areas with mean (65,000 Btu/h) in areas with mean coincident wet bulb >72coincident wet bulb >72F (22F (22C)C)coincident wet bulb >72coincident wet bulb >72F (22F (22C)C)
Georgia: ~12.6 gal/cfm Outdoor airAnnual condensate collection
2424
Georgia: ~12.6 gal/cfm Outdoor air or about 100 liters water/(l/s)
Condensate CollectionCondensate Collection
How Would You Comply with This?How Would You Comply with This?
How Would You Use the Water?How Would You Use the Water?
How to Calculate Estimated Water How to Calculate Estimated Water Collected?Collected?Collected?Collected?
Issues associated with collection andIssues associated with collection andIssues associated with collection and Issues associated with collection and reuse of condensate …reuse of condensate …
2525
Section 6 Section 6 –– Water Use EfficiencyWater Use Efficiency
Prescriptive OptionPrescriptive Option Building Water Use (Building Water Use (§§6.4.2)6.4.2)::g (g (§§ ))
-- Cooling tower cycles of concentrationCooling tower cycles of concentration-- Commercial food serviceCommercial food serviceCommercial food serviceCommercial food service
Use high efficiency equipment (Energy Star Use high efficiency equipment (Energy Star or equivalent)or equivalent)or equivalent)or equivalent)
Air cooled ice machines onlyAir cooled ice machines only-- Other requirements for medical andOther requirements for medical andOther requirements for medical and Other requirements for medical and
laboratory facilitieslaboratory facilities-- Water featuresWater features
2626
Water features Water features
ff
Section 6 Section 6 –– Water Use EfficiencyWater Use EfficiencyPerformance OptionPerformance Option Site water use reductionSite water use reduction: :
Potable water for irrigation Potable water for irrigation <35% of landscape water demand<35% of landscape water demand
Building useBuilding use::Building useBuilding use: :
Proposed use < [mandatory + prescriptive]Proposed use < [mandatory + prescriptive]Proposed use < [mandatory + prescriptive]Proposed use < [mandatory + prescriptive]
2727
Energy Energy –– Section 7Section 7
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Energy Energy –– General Highlights: General Highlights: gygy g gg g Original goal 30% lower than Standard Original goal 30% lower than Standard
90.190.1--20072007 INCLUDING PROCESSINCLUDING PROCESS90.190.1 2007 2007 INCLUDING PROCESSINCLUDING PROCESS Appendix G from Standard 90.1 is Appendix G from Standard 90.1 is
incorporated as aincorporated as a Normative AppendixNormative Appendixincorporated as a incorporated as a Normative AppendixNormative Appendix Other areas increase stringency beyond Other areas increase stringency beyond
Standard 90 1Standard 90 1Standard 90.1Standard 90.1
2929
ASHRAE Energy GoalsASHRAE Energy Goals
ASHRAE goal to have netASHRAE goal to have net--zero energy and zero energy and carbon by 2030carbon by 2030carbon by 2030carbon by 2030
ASHRAE’s Tech Council will suggest EUI ASHRAE’s Tech Council will suggest EUI targets for Standards 189 1 and 90 1targets for Standards 189 1 and 90 1targets for Standards 189.1 and 90.1targets for Standards 189.1 and 90.1
Monitoring of progress based on Monitoring of progress based on t d di d t d lit d di d t d listandardized computer modelingstandardized computer modeling
Goal is to have 189.1 reach Net Energy Goal is to have 189.1 reach Net Energy Use Intensity targets (but not net zero) Use Intensity targets (but not net zero) by 2020by 2020
3030
Standard 90.1-2010, Site EUI
Standard 189.1-2011, Site EUI
52.2 (592)47.7 (541)
Net EUI for Standard 189.1-2011 is44.5 (505), which accounts for on-site
3131
renewable contribution
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Mandatory Requirements:Mandatory Requirements:OnOn site renewable power (site renewable power (§§7 3 2)7 3 2)-- OnOn--site renewable power (site renewable power (§§7.3.2)7.3.2)Provisions for future installation Provisions for future installation annual annual energy productionenergy production ≥≥66 kBtukBtu/ft/ft² (² (20 kWh20 kWh/m/m²)²)energy production energy production ≥≥6 6 kBtukBtu/ft/ft ( (20 kWh20 kWh/m/m ) ) singlesingle--story; story; ≥10≥10 kBtukBtu/ft/ft² ² ((32 kWh32 kWh/m²/m²)) multimulti--storystoryException for areas with low incident solar (4.0 Exception for areas with low incident solar (4.0 kWh/mkWh/m22/day), /day), account for local shadingaccount for local shading
3232
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Mandatory Requirements:Mandatory Requirements:-- OnOn--site renewable power (site renewable power (§§7.3.2)7.3.2)OnOn site renewable power (site renewable power (§§7.3.2)7.3.2)
Provisions for future installation Provisions for future installation annual energy production annual energy production ≥≥6 6 kBtukBtu/ft/ft² (² (20 20 kWhkWh/m/m²) ²) singlesingle--story; story; ≥10≥10 kBtukBtu/ft/ft² ² ((32 kWh32 kWh/m²/m²)) multimulti--storystory
If project complies with higher energy If project complies with higher energy p j p g gyp j p g gyefficiency requirements efficiency requirements (~Energy Star or (~Energy Star or equivalent), lowers equivalent), lowers toto ≥4≥4 kBtukBtu/ft/ft² ² ((13 kWh13 kWh/m/m²) ²) i li l 77 kBkB /f/f ²² ((22 kWh22 kWh// ²² l il isinglesingle--story; story; ≥7≥7 kBtukBtu/ft/ft² ² ((22 kWh22 kWh/m/m²) ²) multimulti--storystory
3333
Approximate f 4 0range of <4.0
kWh/m² per day
3434
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Energy Energy –– Mandatory (Mandatory (contcont.): .): Remote or automatic energyRemote or automatic energy Remote or automatic energy Remote or automatic energy
monitoring (monitoring (§§7.3.3) 7.3.3) criteria based on sizecriteria based on sizecriteria based on sizecriteria based on size-- Energy sources (Table 7.3.3Energy sources (Table 7.3.3--1) 1) -- Key systems (Table 7.3.3Key systems (Table 7.3.3--2)2)
Meters communicate to central recording Meters communicate to central recording ggsystem system
Data storage for minimum 36 monthsData storage for minimum 36 months
3535
Data storage for minimum 36 monthsData storage for minimum 36 monthsException: Residential portions of buildings complying with this Standard
Energy Metering ThresholdsEnergy Metering Thresholds
3636
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (General)Prescriptive Option (General)From DOE StudyFrom DOE Study From DOE Study From DOE Study ––Std. 189.1Std. 189.1--2009 30.2 2009 30.2 lower than Standard 90 1lower than Standard 90 1 20072007lower than Standard 90.1lower than Standard 90.1--20072007(9% due to (9% due to renewablesrenewables) ) Average EUI 50 4Average EUI 50 4 kBtukBtu/ft/ft²²Average EUI = 50.4 Average EUI = 50.4 kBtukBtu/ft/ft²²
Standard 189.1 builds Standard 189.1 builds f d df d dfrom Standard 90.1… from Standard 90.1…
3737
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive OptionPrescriptive Option Prescriptive Option: Renewable EnergyPrescriptive Option: Renewable Energy Prescriptive Option: Renewable EnergyPrescriptive Option: Renewable Energy
-- OnOn--site renewable energy system with site renewable energy system with ≥≥66 kBtkBt /ft²/ft² [20 kWh/ ²[20 kWh/ ² ] i l] i l≥≥6 6 kBtukBtu/ft²/ft²--yr [20 kWh/m²yr [20 kWh/m²--yr] single yr] single story or story or 10 010 0 kBtkBt /ft²/ft² [32 kWh/ ²[32 kWh/ ² ]]10.0 10.0 kBtukBtu/ft²/ft²--yr [32 kWh/m²yr [32 kWh/m²--yr] yr] multiple story, multiple story, based on roof areabased on roof area
3838
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive OptionPrescriptive Option Prescriptive Option: Renewable EnergyPrescriptive Option: Renewable Energy Prescriptive Option: Renewable Energy Prescriptive Option: Renewable Energy
(Continued)(Continued)Exception (meet both of these):Exception (meet both of these):Exception (meet both of these):Exception (meet both of these):-- Low incident solar locations Low incident solar locations
(<(<4 0 kWh/m4 0 kWh/m22/day)/day)(<(<4.0 kWh/m4.0 kWh/m22/day)/day)-- Purchase of green power in terms of Purchase of green power in terms of
“7 kWh/ft²“7 kWh/ft²--yr [75 kWh/m²yr [75 kWh/m²--yr]” annually untilyr]” annually until7 kWh/ft7 kWh/ft yr [75 kWh/myr [75 kWh/m yr] annually until yr] annually until cumulative purchase of 70 kWh/ft²cumulative purchase of 70 kWh/ft²--yr yr [750 kWh/m²[750 kWh/m²--yr]yr]
3939
[ /[ / y ]y ]
P i i O i (B ildi E l )P i i O i (B ildi E l )
Highlights for Energy (Section 7)Highlights for Energy (Section 7)Prescriptive Option (Building Envelope)Prescriptive Option (Building Envelope) Comply with Standard 90.1, Section 5 with Comply with Standard 90.1, Section 5 with
difi tidifi timodifications …modifications … Replaces Table 5.5Replaces Table 5.5--1 thru 8 on building envelope 1 thru 8 on building envelope
in 90 1 for example:in 90 1 for example: ((§§7 4 2)7 4 2)in 90.1, for example:in 90.1, for example: ((§§7.4.2)7.4.2)
4040
Climate ZonesClimate Zones
4141
Highlights for Energy (Section 7)Highlights for Energy (Section 7)((§§7 4 2)7 4 2)
Prescriptive Option (Building Envelope)Prescriptive Option (Building Envelope) Example comparisons:Example comparisons:
((§§7.4.2)7.4.2)
Example comparisons:Example comparisons:Example:Example:Climate zone 3Climate zone 3 Std 90 1 Std 189 1Std 90 1 Std 189 1
M t i t SHGCM t i t SHGC
Climate zone 3Climate zone 3 Std 90.1 Std 189.1Std 90.1 Std 189.1Insulation above deck RInsulation above deck R--20 20 RR--2525
R=3 5 R=4 4 (SI) More stringent SHGCMore stringent SHGCBoth 90.1 and 189.1 limit to <40% Both 90.1 and 189.1 limit to <40% window area :window area :
R=3.5 R=4.4 (SI)
window area :window area :Climate zone 5 SHGC ; all orientations Climate zone 5 SHGC ; all orientations Std 90 1: 0 40Std 90 1: 0 40
4242
Std. 90.1: 0.40 Std. 90.1: 0.40 Std. 189.1: Std. 189.1: 0.350.35
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Building Envelope)Prescriptive Option (Building Envelope) Vertical fenestrationVertical fenestration Vertical fenestration Vertical fenestration
<40% gross wall area<40% gross wall area((§§7.4.2.4)7.4.2.4)((§§ ))
4343
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Building Envelope)Prescriptive Option (Building Envelope) Overhang: PF >0.5Overhang: PF >0.5 Overhang: PF >0.5Overhang: PF >0.5
((§§7.4.2.5) 7.4.2.5) Exceptions for Exceptions for pp< 250 hours/yr direct sun,< 250 hours/yr direct sun,dynamic glazing, dynamic glazing,
t t d h dit t d h dior automated shadingor automated shading
W t t & th i t tiW t t & th i t ti
4444
-- West, east & south orientationsWest, east & south orientations-- Climate zones 1Climate zones 1--55
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Building Envelope)Prescriptive Option (Building Envelope) Push toward “smarter” window placement Push toward “smarter” window placement pp
and selection and selection ((§§7.4.2.8)7.4.2.8)
ExceptionExceptionExceptionExceptionBuildings Buildings adjacent to or adjacent to or shaded by shaded by otherother bbuildings, uildings, hill thill t
4545
hills, etc.hills, etc.
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Building Envelope)Prescriptive Option (Building Envelope) Continuous air barrier requirementContinuous air barrier requirement Continuous air barrier requirementContinuous air barrier requirement
((§§7.4.2.9)7.4.2.9) Complies with Normative Appendix B toComplies with Normative Appendix B to
Addendum in process
Complies with Normative Appendix B to Complies with Normative Appendix B to control air leakage in and out control air leakage in and out D t il d t ti d tD t il d t ti d t Detailed on construction documentsDetailed on construction documents
Not required for semiNot required for semi--heated spaces that heated spaces that comply with Std. 90.1 Section 5.4.3.1 comply with Std. 90.1 Section 5.4.3.1 (that defines areas of envelope to be sealed, (that defines areas of envelope to be sealed,
lk dlk d k t dk t d thth t i d)t i d)
4646
caulked, caulked, gasketedgasketed or weatheror weather--stripped) stripped)
§§7.4.3 HVAC7.4.3 HVAC
90.1 (current version)
General Concept:Based on Standard 90.1, but modify to gain improved90.1 (current version) modify to gain improved energy performance over code minimum standards
( )
Adopt, with modifications
code minimum standards
§§7.4.3 HVAC 7.4.3 HVAC –– Equipment EfficiencyEquipment Efficiency
Repeated overviewRepeated overview-- §§7 4 3 17 4 3 1 Minimum equipment efficiencyMinimum equipment efficiency§§7.4.3.1 7.4.3.1 Minimum equipment efficiencyMinimum equipment efficiency
incentives for higher efficient equipmentincentives for higher efficient equipment
Equipment Efficiency Compliance Options
“Code Minimum” EPActBaseline (Standard 90.1)
Higher efficiency
Use equipment with EPActbaseline efficiency levels, and:• Renewable energy system producing 6.0 kBtu/ft² roof area annually
Use higher efficiency of Energy Star requirements and Appendix C, and:• Renewable energy system producing 4.0 kBtu/ft² roof area annually
4848
/ y• Peak electrical load reduction of 10%
/ y• Peak electrical load reduction of 5%
Demand Controlled Ventilation (DCV)Demand Controlled Ventilation (DCV)
Both Standard 189.1 and 90.1 include Both Standard 189.1 and 90.1 include requirements for DCVrequirements for DCV
90.1 (current version)90.1 (current version)
Standard 90 1-2010: 40 people/1000 ft²
Recent 90.1 Addendum bs modified this to 25 people/1000 ft² as well
Addendum ‘ay’ lowers
Standard 90.1-2010: 40 people/1000 ft²(100 m²) and area >500 ft² (50 m²)
Addendum ay lowers threshold values of outdoor airflow from Std 90.1
If with CO2 sensors, install per §7.4.3.2
4949
Note: Type of DCV used is not specified
§§7.4.3 HVAC7.4.3 HVAC
§§7.4.3.3 7.4.3.3 Economizer requirement changes from Economizer requirement changes from Standard 90.1Standard 90.1
Standard 90 1-2010 Requirement
-- Rooftop units <5 tons: two stage (first stage economizer, Rooftop units <5 tons: two stage (first stage economizer, d t dd h i l)d t dd h i l)
Standard 90.1-2010 Requirement-Capacity > 54,000 Btu/h (15.8 kW), and same climate zones
second stage adds mechanical)second stage adds mechanical)-- VAV with fixed supply temperature, capable for temperature VAV with fixed supply temperature, capable for temperature
reset by at least 5reset by at least 5º F (3º C) during economizer operationº F (3º C) during economizer operation
5050
-- Exceptions per Standard 90.1, Section 6.5.1 with slight Exceptions per Standard 90.1, Section 6.5.1 with slight modificationsmodifications
§§7.4.3 HVAC7.4.3 HVAC§§7 4 3 47 4 3 4 Z t lZ t l §§7.4.3.4 7.4.3.4 Zone controlsZone controls-- Have adapted Standard 90.1Have adapted Standard 90.1--2010 approach, 2010 approach,
b t t i tib t t i tibut more restrictivebut more restrictive-- General intent is to restrict the amount of air General intent is to restrict the amount of air
that is reheatedthat is reheated recooledrecooled or otheror otherthat is reheated, that is reheated, recooledrecooled, or other , or other simultaneous heating/cooling operations in simultaneous heating/cooling operations in the same zonethe same zonethe same zonethe same zone
-- Exceptions allowed (from Standard 90.1 Exceptions allowed (from Standard 90.1 §§6.5.2.1), 6.5.2.1), §§6 5 ),6 5 ),with modifications with modifications [Exception (a) [Exception (a)
From 90.1-2010
5151
not allowed]not allowed]
§§7.4.3 HVAC7.4.3 HVAC
§§7.4.3.5 7.4.3.5 Fan power limits, Fan power limits, below Standard 90.1below Standard 90.1--20102010below Standard 90.1below Standard 90.1 20102010
- 10%
5252
§§7.4.3 HVAC7.4.3 HVAC
•• §§7.4.3.6 7.4.3.6 Expand energy recovery Expand energy recovery requirements from Standard 90.1requirements from Standard 90.1--20102010qq
• Includes columns for between 10% and 30% outside airIncludes columns for between 10% and 30% outside air
5353
• Includes columns for between 10% and 30% outside airIncludes columns for between 10% and 30% outside air•• Energy recovery effectiveness of Energy recovery effectiveness of 60% 60% (instead of 50% in Standard 90.1)(instead of 50% in Standard 90.1)
§§7.4.3 HVAC7.4.3 HVAC
§§7.4.3.7 7.4.3.7 Kitchen hoods add variable Kitchen hoods add variable speed ≥50% reduction in flow whenspeed ≥50% reduction in flow whenspeed, ≥50% reduction in flow when speed, ≥50% reduction in flow when not needed not needed (significant impact)(significant impact)
§§7.4.3.8 7.4.3.8 Minimum duct insulation Minimum duct insulation increased (Tables Cincreased (Tables C--9 and 10)9 and 10)(( ))
§§7.4.3.12 7.4.3.12 Unoccupied hotel/motel Unoccupied hotel/motel >50 guest rooms>50 guest rooms>50 guest rooms>50 guest rooms-- Lighting, outlets, TV off Lighting, outlets, TV off
HVACHVAC t i tt i t i d/l d bi d/l d b
5454
-- HVAC HVAC setpointsetpoint raised/lowered byraised/lowered by55F (3F (3 C)C)
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Prescriptive Option (contcont.).) §§7 4 57 4 5 PowerPower §§7.4.57.4.5 PowerPower
Peak load reduction:Peak load reduction:Red ce peak capacit of the b ildingRed ce peak capacit of the b ilding-- Reduce peak capacity of the building Reduce peak capacity of the building through demandthrough demand--limiting or load limiting or load shifting measures (10%)shifting measures (10%)shifting measures (10%)shifting measures (10%)
-- Standby generation does not count…Standby generation does not count…
5555The “Energy Star equivalent” exception
Highlights for Energy (Section 7)Highlights for Energy (Section 7)Prescriptive Option (Lighting)Prescriptive Option (Lighting) ((§§7.4.6.1) 7.4.6.1) Interior lighting power Interior lighting power
allowance reduced from Table 9.5.1 allowance reduced from Table 9.5.1 in Standard 90.1in Standard 90.1--20102010
Example for Space-by-Space Method: LPD Factor is
5656
multiplier for 90.1-2010 values
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Lighting)Prescriptive Option (Lighting) ((§§7 4 6 2)7 4 6 2) Occupancy sensor control toOccupancy sensor control to ((§§7.4.6.2) 7.4.6.2) Occupancy sensor control to Occupancy sensor control to
reduce power to <50% for:reduce power to <50% for:Hotel motel hallwaysHotel motel hallways-- Hotel, motel hallwaysHotel, motel hallways
-- Storage stack aislesStorage stack aislesLib t kLib t k-- Library stacksLibrary stacks
Exception: HID lit areas Exception: HID lit areas < 0 8 W/ft< 0 8 W/ft² or 8 W/m²² or 8 W/m²< 0.8 W/ft< 0.8 W/ft² or 8 W/m²² or 8 W/m²
Egress lighting control Egress lighting control ((§§7 4 6 3)7 4 6 3) 0 1 W/ft0 1 W/ft22 (1 W/(1 W/ ²²))
5757
((§§7.4.6.3) 7.4.6.3) < 0.1 W/ft< 0.1 W/ft22 (1 W/m(1 W/m²²) ) Additional allowed if w/ auto shutAdditional allowed if w/ auto shut--off off
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Prescriptive Option (Lighting)Prescriptive Option (Lighting) ((§§7 4 6 4)7 4 6 4) Occupancy sensors:Occupancy sensors: ((§§7.4.6.4) 7.4.6.4) Occupancy sensors:Occupancy sensors:
Manual on, auto off, except following Manual on, auto off, except following where auto on is allowedwhere auto on is allowedwhere auto on is allowedwhere auto on is allowed-- Areas per 7.4.6.2Areas per 7.4.6.2
P blic co ido s stai ellsP blic co ido s stai ells-- Public corridors, stairwellsPublic corridors, stairwells-- RestroomsRestrooms
E t d l bbiE t d l bbi-- Entrance areas and lobbiesEntrance areas and lobbies
5858
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
§§7.5 7.5 Performance Based Option:Performance Based Option: Demonstrate equivalent performance in Demonstrate equivalent performance in
bothboth energy costenergy cost and and COCO22 equivalentequivalentcompared to using the Prescriptive path compared to using the Prescriptive path for energy, plus relevant portions of for energy, plus relevant portions of Sections 5, 6 and 8 Sections 5, 6 and 8
Proposed Proposed (Mandatory +(Mandatory +Prescriptive Path)Prescriptive Path)
U i N i A di DU i N i A di D
5959
Using Normative Appendix D Using Normative Appendix D “Performance Option for Energy Efficiency”“Performance Option for Energy Efficiency”
Highlights for Energy (Section 7)Highlights for Energy (Section 7)
Performance Based Option:Performance Based Option:§§7.5.47.5.4 Annual Load Factor/Annual Load Factor/
Peak Electric DemandPeak Electric Demand Same or less peak electric demand as if Same or less peak electric demand as if
following the prescriptive pathfollowing the prescriptive pathg p p pg p p p Minimum annual electrical load factor Minimum annual electrical load factor
of 0 25of 0 25of 0.25of 0.25
6060
Section 8Section 8Indoor Environmental QualityIndoor Environmental QualityIndoor Environmental QualityIndoor Environmental Quality
Key ItemsKey Items-- Outdoor airflowOutdoor airflow-- Tobacco smoke controlTobacco smoke control-- Outdoor air monitoringOutdoor air monitoring-- Filtration and air cleaningFiltration and air cleaninggg-- DaylightingDaylighting-- Thermal comfortThermal comfort-- AcousticsAcoustics
6161
Indoor Environmental QualityIndoor Environmental Quality§§8.3.1 IAQ8.3.1 IAQ Using Ventilation Rate Procedure onlyUsing Ventilation Rate Procedure only
§§8.3.1.18.3.1.1 Outdoor air monitoring Outdoor air monitoring
§§8.3.1.28.3.1.2-- Permanently mounted, Permanently mounted,
direct outdoor airflow direct outdoor airflow ±±15% of 15% of minimum outdoor airflow minimum outdoor airflow (Differs from LEED in that CO(Differs from LEED in that CO22 monitoring for densely occupiedmonitoring for densely occupied(Differs from LEED in that CO(Differs from LEED in that CO22 monitoring for densely occupied monitoring for densely occupied spaces not specified)spaces not specified)
-- Exception for constant volume air supply, Exception for constant volume air supply,
6262
damper position feedbackdamper position feedback
Indoor Environmental QualityIndoor Environmental Quality
§§8.3.1.3 Filtration8.3.1.3 Filtration-- (a) Particulates (a) Particulates -- Minimum Minimum MERV 8MERV 8 upstreamupstream
of wetted surfaces or to reduce PMof wetted surfaces or to reduce PM1010, , MERV 13 MERV 13 when designed to reduce PMwhen designed to reduce PM2.52.5
( d f d h d( d f d h d ))(Modifies and strengthens Std. 62.1 (Modifies and strengthens Std. 62.1 §§6.2.1.1)6.2.1.1)
-- (b) Ozone cleaners for outdoor air in building (b) Ozone cleaners for outdoor air in building projects located in high ozone areasprojects located in high ozone areas (O(Oprojects located in high ozone areas. projects located in high ozone areas. (Ozone (Ozone removal efficiency = 40%, per Std. 62.1 removal efficiency = 40%, per Std. 62.1 §§6.2.1.2)6.2.1.2)
-- (c) Filter frames air cleaner racks access(c) Filter frames air cleaner racks access(c) Filter frames, air cleaner racks, access (c) Filter frames, air cleaner racks, access doors sealed to eliminate bypass pathwaysdoors sealed to eliminate bypass pathways
6363
From Std. 62.1-2010
Indoor Environmental QualityIndoor Environmental Quality
§§8.3.1.48.3.1.4E i t l T b S kE i t l T b S kEnvironmental Tobacco Smoke Environmental Tobacco Smoke ControlControl-- No smoking inside, with signageNo smoking inside, with signage-- No smoking within 25 feet (7.5 m) of No smoking within 25 feet (7.5 m) of
d i i kd i i kentrance, outdoor air intakes or entrance, outdoor air intakes or operable windowsoperable windows
6464
Indoor Environmental QualityIndoor Environmental QualityOth M d tOth M d tOther Mandatory: Other Mandatory: Thermal ComfortThermal Comfort
-- Comply with Comply with Std. 55Std. 55Sections 6.1 and 6.2Sections 6.1 and 6.2(D i d(D i d(Design and (Design and Documentation)Documentation)
M t t tM t t t Mat systems at Mat systems at building entrancesbuilding entrances
Envelop acoustical Envelop acoustical design (design (soundsound
6565
transmission rating transmission rating criteria)criteria)
Indoor Environmental QualityIndoor Environmental Quality
Prescriptive OptionPrescriptive Option ((§§8.4)8.4)
D li htiD li hti DaylightingDaylighting
Office space shading (glare)Office space shading (glare)Office space shading (glare)Office space shading (glare)
LowLow--emitting materialsemitting materials
6666
Indoor Environmental QualityIndoor Environmental Quality
Performance Option (Performance Option (§§8.5)8.5): : DaylightingDaylighting simulationsimulation DaylightingDaylighting simulationsimulation-- Office space and classroomsOffice space and classrooms
Minimum illuminance target:Minimum illuminance target:-- Minimum illuminance target: Minimum illuminance target: 300 300 luxlux (30 (30 fcfc) on work surfaces in 75% of ) on work surfaces in 75% of daylight zone, at noon equinoxdaylight zone, at noon equinoxy g , qy g , q
-- Recent addendum added simulation for Recent addendum added simulation for toplighting areastoplighting areas
Direct sun limitation on office Direct sun limitation on office worksurfaceworksurface Direct sunlight on Direct sunlight on worksurfaceworksurface <20% of <20% of
i d h i di d h i d
6767
occupied hours on equinox dayoccupied hours on equinox day((worksurfaceworksurface = 2.4 feet [0.75 m] above floor)= 2.4 feet [0.75 m] above floor)
Building’s Impact on Atmosphere, Building’s Impact on Atmosphere, Materials and Resources (Section 9)Materials and Resources (Section 9)Materials and Resources (Section 9)Materials and Resources (Section 9)Mandatory: Mandatory: Construction waste managementConstruction waste management No CFC based refrigerantsNo CFC based refrigerantsgg
Prescriptive Option: Prescriptive Option: R d d i t t i lR d d i t t i l Reduced impact materialsReduced impact materials(recycled or salvaged,(recycled or salvaged,egionalegional biobasedbiobased))regional, regional, biobasedbiobased))
Performance Option: Performance Option:
6868
Life Cycle AssessmentLife Cycle Assessment
Construction and Operation PlansConstruction and Operation PlansOVERVIEWOVERVIEWOVERVIEWOVERVIEW
All Mandatory Provisions:All Mandatory Provisions: §§10 3 1 Construction10 3 1 Construction §§10.3.1 Construction10.3.1 Construction §§10.3.2 Plans for Operation 10.3.2 Plans for Operation
6969
Construction and Operation PlansConstruction and Operation PlansOVERVIEWOVERVIEW
§§10.3.1 Construction10.3.1 Construction
OVERVIEWOVERVIEW
Building acceptance testingBuilding acceptance testing CommissioningCommissioninggg Erosion and sediment controlErosion and sediment control Indoor air qualityIndoor air quality Indoor air qualityIndoor air quality Moisture controlMoisture control Construction vehiclesConstruction vehicles
7070
Construction Requirements (Construction Requirements (contcont.).)§§10.3.1.2 Building Project 10.3.1.2 Building Project
CommissioningCommissioninggg Full commissioning for Full commissioning for
>500 m² (5,000 ft²)>500 m² (5,000 ft²)>500 m (5,000 ft )>500 m (5,000 ft )-- HVAC, building envelope, lighting, irrigation, HVAC, building envelope, lighting, irrigation,
plumbing, domestic water, renewable energyplumbing, domestic water, renewable energyplumbing, domestic water, renewable energyplumbing, domestic water, renewable energy
Designate Designate CxACxADevelop OPR and Basis of DesignDevelop OPR and Basis of Design
Doing full Cxprocess also
Develop OPR and Basis of DesignDevelop OPR and Basis of Design Design reviews at 50% and ‘final’ Design reviews at 50% and ‘final’
psatisfies the Building Acceptance
7171
construction documentsconstruction documents Test requirements
Addendum in process
Construction Requirements (Construction Requirements (contcont.).)§§10.3.1.4 IAQ Construction Mgmt10.3.1.4 IAQ Construction Mgmt Develop and implement an IAQDevelop and implement an IAQ Develop and implement an IAQ Develop and implement an IAQ
Construction Management Plan, to include:Construction Management Plan, to include:-- Air conveyance materialsAir conveyance materials-- Air conveyance materialsAir conveyance materials-- Permanent HVAC not used during construction, Permanent HVAC not used during construction,
except for startup balancing commissioningexcept for startup balancing commissioningexcept for startup, balancing, commissioningexcept for startup, balancing, commissioning-- FlushFlush--out out oror baseline IAQ monitoringbaseline IAQ monitoring
7272
Construction Requirements (Construction Requirements (contcont.).)IAQ Construction Management IAQ Construction Management PostPost--construction preconstruction pre--occupancyoccupancy PostPost construction, preconstruction, pre occupancy occupancy
1.1. FlushFlush--out: Temp >60out: Temp >60º F (15 C), RH ≤60%º F (15 C), RH ≤60%
2.2. Baseline IAQ Testing for 34 contaminantsBaseline IAQ Testing for 34 contaminants
7373
§§10.3.2 Plans for Operation10.3.2 Plans for Operation
1.1. High Performance Building OperationHigh Performance Building Operation-- Site SustainabilitySite Sustainability-- Water Use EfficiencyWater Use Efficiency-- Energy EfficiencyEnergy Efficiency-- Indoor Environmental QualityIndoor Environmental QualityQ yQ y
2.2. MaintenanceMaintenance33 Service LifeService Life3.3. Service LifeService Life4.4. Transportation ManagementTransportation Management
7474
More InformationMore Information
Information on ASHRAE standards: Information on ASHRAE standards: www.ashrae.orgwww.ashrae.org then followthen followwww.ashrae.orgwww.ashrae.org then follow then follow “Standards”, includes listserv for “Standards”, includes listserv for Standard 189.1Standard 189.1Standard 189.1Standard 189.1
Information on USGBC programs:Information on USGBC programs:bbwww.usgbc.orgwww.usgbc.org
Information on IES programs:Information on IES programs:p gp gwww.iesna.orgwww.iesna.org
Thank you!Thank you!
Comments, questions, concerns, advice …Comments, questions, concerns, advice …
Dr. Tom Lawrence, P.E., LEEDDr. Tom Lawrence, P.E., [email protected]@engr.uga.edu
7676