Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the...

100
Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Transcript of Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the...

Page 1: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Brian Parsons

February 19, 2013

Overview of the 2012 AASHTO Bike

Guide

Page 2: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

•2009 MUTCD – FHWA •Public Right-of-Way Accessibility Guidelines (PROWAG) •2010 Highway Capacity Manual

Relationship to other manuals

Page 3: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• NCHRP - National Academy of Sciences

• Scoping Study: 2004-2006

• Preparation of the content of the 4th Edition: 2007-2009

• Final edits/State DOT balloting process: 2010-2012

How the Guide was developed

Page 4: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

How the AASHTO Bike Guide is used

•State DOTs

Some adopt the Guide

Some use it to create their own versions

•Local Jurisdictions Use AASHTO’s version

Use the State’s version, or

Develop own version

Page 5: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Guide expanded from 75 pages to over 200 pages

• 3 chapters to 7 chapters

• Sold 1200 copies in the first month

Release of the guide – June 2012

Page 6: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Chapters

• Chapter 1: Introduction

• Chapter 2: Bicycle Planning

• Chapter 3: Bicycle Operation and Safety

• Chapter 4: Design of On-Road Facilities

• Chapter 5: Design of Shared Use Paths

• Chapter 6: Bicycle Parking Facilities

• Chapter 7: Maintenance and Operations

Page 7: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Chapters

• Chapter 1: Introduction

• Chapter 2: Bicycle Planning

• Chapter 3: Bicycle Operation and Safety

• Chapter 4: Design of On-Road Facilities

• Chapter 5: Design of Shared Use Paths

• Chapter 6: Bicycle Parking Facilities

• Chapter 7: Maintenance and Operations

Page 8: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Guidance on how to choose bikeway type

• Affirms lane diets and road diets

• Expanded bike lane guidance

Major changes in 2012 Guide

Page 9: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Expanded signal guidance

• Expanded shared use path guidance (including paths adjacent to roads)

Major changes in 2012 Guide

Page 10: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• No differentiation of what type of bikeway was appropriate given roadway characteristics

Choosing bikeway type – 1999 Guide

Page 11: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Detailed guidance on facility selection

• Support for bike lanes and shared use paths where volumes and speeds are higher

• Warnings against using wide outside lane as a standard treatment for high volume roads

Choosing bikeway type – 2012 Guide

Page 12: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

•Permission to narrow lane widths to create bike lanes

•10’ and 11’ wide travel lanes are acceptable

Roadway retrofit

Page 13: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Provides guidelines for road diets

Road diets

Page 14: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Nuanced guidance on widths (4 to 7 feet)

• Measures to reduce crashes with car doors

• Bike lanes adjacent to back-in angle parking

• Bike lanes at roundabouts

• Buffered bike lanes

• Green bike lanes, etc.

Bike lanes

Page 15: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Old Guide – weak

New Guide – strong

Detailed guidance on all aspects of signal design

Signal design

Page 16: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Shared use paths

• Extensive intersection design guidance

Major change: paths next to roads are not forbidden, provides guidance on how to design them

Page 17: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• AASHTO covers design comprehensively

• AASHTO covers paths + on-road bikeways

• AASHTO covers many – but not all innovations

• NACTO is a source of information for solutions that are currently being tested

AASHTO vs. NACTO Guides: either/or?

Page 18: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Bike lanes

• Cycle track design

– One-way protected cycle tracks

– Raised cycle tracks

– Two-way cycle tracks

What is in the NACTO Guide?

Page 19: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Bike boxes and other intersection designs (including non-standard)

• Colored pavement material guidance

• Bicycle boulevards

What is in the NACTO Guide?

Page 20: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

NACTO Illustrations of bikeway types

Page 21: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Planning for bicycles

• Bicyclist operating characteristics

• Geometric design values and details

• Shared use path design

• Bridges

• General road compatibility with bicycles

• Bike parking

• Maintenance

What is NOT in the NACTO Guide?

Page 22: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Bike boxes

• Bicycle signal heads

• Does not use the term cycle track

• Warns against putting bike lane between parking lane and curb

Issues NOT addressed by AASHTO Guide

Page 23: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Example: Two-Way Cycle track 15th Street

Washington, DC

Page 24: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

One way cycle track 9th Avenue

New York City

Page 25: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Questions?

Page 26: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

• Brian Parsons

• Louisiana Pedestrian/Bicycle Coordinator

• (225) 379-1954

[email protected]

Page 27: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Local Public Agency Programs

Partnering to Improve the Quality of Life for Louisianans

Page 28: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Agenda

• Actions for Partnering to Improve the Quality of Life for Louisianans – The Manual

– Training

– The Agreement

Page 29: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

How it started

• Nationally, FHWA reviews found significant issues with LPA administered projects across the country

• Process review on the LA Urban System Program by FHWA, April 2010, identified several LPA risk areas

Page 30: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

What is an LPA?

A Local Public Agency (LPA) includes:

• Parish Government

• City Government

• Municipal Government

• Airport Authorities

***all of the above are also referred to as “Entity” in legal agreements

Page 31: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Where to go for help?

The Local Public Agency (LPA) Manual and Appendix http://www.dotd.la.gov/administration/lpa/

Page 32: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

LPA Manual Highlights

• Put together in 2011 by DOTD & FHWA as a tool to assist LPAs to fulfill the requirements of implementing a transportation project

• One stop shopping for all information on programs and projects that LPAs can apply for

• Will be updated for MAP-21

Page 33: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Sections of the LPA Manual

• DOTD’s Project Delivery Process and Flowchart

• FHWA Programs & Fact Sheet links

• How projects in each of the programs are selected and programmed

• Specific Program Information

• Frequently Asked Questions

Page 34: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Sections of the LPA Manual Appendix

• Acronyms/Abbreviations & Definitions

• Financial – Audit & accountability, billings/payments

• Planning – Statewide, regionally significant

• Engineering – Agreements, number system, process for

large projects, design, survey & right-of-way, utility relocation, preservation projects, traffic management plan (TMP), pavement & geotechnical

Page 35: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Sections of the LPA Manual Appendix

(cont.)

• Construction – Construction engineering & inspection

(CEI), close-out procedures

• Miscellaneous – Web information, permits, Americans

with Disabilities Act (ADA)

Page 36: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Training

Page 37: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Core Training Partnership

• Core Team

–DOTD

– FHWA

– LTAP

Nick Verret, Marie Walsh, Mary Stringfellow, Ann Wills

LTAP FHWA DOTD

Page 38: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Identified “At Risk” Areas

• Core Training

– Federal Funding

– Not understanding the Entity-State Agreement

– Responsible Charge not implemented

– Local Public Agency Manual

– Reporting

• Technical Training

– Modules

Page 39: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Development of Training

• Preparation

– Researched other states

– Attended the MS training Jan 24, 2012

• Qualification Core Training Presentation & Materials Creation

• Marketing

• Qualification Core Training Pilot – August 21, 2012

Page 40: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Target Audience

The Qualifications Core Training is required for any Local Public Agency (LPA) project sponsor and for every consultant working on LPA projects receiving federal or state funding through DOTD

Page 41: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Qualification Core Training Classes

• 9 sessions taught around the state – Fall 2012

• 6 hour sessions (9 AM – 3 PM)

• Cost - Free

• 5 PDHs offered for engineers

• Over 300 people trained

Page 42: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

NEXT SESSION April 11, 2013

DOTD HQ Auditorium

Sign-up on DOTD’s website

Qualification Core Training Classes

Page 43: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide
Page 44: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

https://www.ltrc.lsu.edu/ltap/fr/lpa_core_training.html

Page 45: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Additional Training Modules

• Purpose – To provide detailed technical assistance

• Topics – Planning, Preconstruction, Construction Contract Administration

• Core Team: DOTD, FHWA, LTAP, LTRC

Page 46: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Future LPA Training Modules

• Planning - Stage 0 – Feasibility & application completion, complete streets policy

• Preconstruction - Project management, environmental (NEPA), consultant expectations/selection, engineering, complete streets policy, acquiring right-of-way/real estate, Title VI – civil rights compliance (ADA, etc.), utility conflicts and relocations

Page 47: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Future Modules (cont.)

• Construction Contract Administration

– Construction Engineering and Inspection (CEI) Including Site Manager, final audit (Form 2059, As Built Plans), construction signing, CEI consultant selection

– Material Testing

– Civil rights compliance (Disadvantage Business Enterprise (DBE), subcontracting, etc.)

Page 48: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Tentative Dates

• Planning – Late Spring/Early Summer 2013

• Preconstruction – Late Summer/Early Fall 2013

• Construction Contract Administration – Late Spring/Early Summer 2013

Page 49: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Entity-State Agreement

Page 50: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Entity-State Agreement

• A written/signed agreement between the State and the Sponsoring Entity (an LPA) identifying the responsibilities of each entity – LEGALLY BINDING

• Every project must have an agreement signed by both parties before a project can move forward

• An agreement must be executed prior to a reimbursable stage of a project

• The agreement identifies the funding provisions for a project

Page 51: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Agreement – Basic Information

• Project Number

• Project Title

• Parish & District where project will be constructed

• Sponsoring entity’s legal name and Federal Identification Number

• A detailed project description & scope of work

• Amount or percentage of federal funding eligible to be used for the project & matching funds required

• Responsible Charge

• Design, Right of Way, Utilities

• Project Contract Letting

• Construction plus Construction Engineering & Inspection

• Cost Reimbursements

• Project Record Keeping

• Civil Rights

• Maintenance Responsibilities

• Public Liability

Page 52: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

“New & Improved” Agreement

• DOTD has revised the Entity/State agreement template to make it clearer and simpler to understand

Page 53: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Funding

An Entity can decide to pay for the work done in each phase of the project all on their own, or ask for federal/state funds to reimburse the cost of this work, but this decision must be documented in this agreement

Page 54: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Funding Phase Local Match

Percentage

Federal Percentage

Conceptual Plans and Environmental Decision

20%

80%

Preconstruction Engineering 20% 80%

Right-of-Way Acquisition and Relocation

100% N/A

Utility Relocation 100% N/A

Construction Engineering & Inspection

20%

80%

Construction 20% 80%

Page 55: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Funding Commitment - MPO Area

• Amounts are limited by the TIP

• Any changes must be coordinated by the Entity with the MPO

Page 56: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Funding Commitment Letter Phase Local Match

Percentage

Federal Percentage

Total

Conceptual Plans and Environmental Decision

N/A N/A N/A

Preconstruction Engineering

20% -$3,750.00

80% -$15,000.00 100% - $ 18,750

Right-of-Way Acquisition and Relocation

N/A N/A N/A

Utility Relocation N/A N/A N/A

Construction Engineering & Inspection

20% - $3000

80% - $12,000

100% - $15,000

Construction 20% - $25,000 80% -$100,000 100% - $125,000

Total $31,750.00 $127,000 $158,750.00

Page 57: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Funding Commitment Letter Non-MPO

• The Project Manager will revise the commitment letter accordingly

• Amounts may be limited by the Program

• Any changes must be coordinated by the Entity with the Program Manager

Page 58: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Cost Disbursements

• The cost reimbursement process that DOTD will use is Disbursement – this disburses to the Entity monthly the correct federal ratio of the approved project costs (i.e. pre-construction engineering services, right-of-way acquisitions, utility adjustments and/or the costs of construction)

• Upon receipt of each disbursement requested, Entity is required to tender payment for the invoiced cost to the vendor

Page 59: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Disbursement vs. Reimbursement

• OLD - Reimbursement

– LPA pays contractor

– LPA submits cancelled check

– LPA reimbursed for agreed percentage by DOTD

• NEW - Disbursement

– LPA submits copy of invoice to DOTD

– DOTD sends LPA appropriate percentage

– LPA pays contractor

– LPA provides proof of payment to contractor within 60 days to DOTD

Page 60: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

What are FHWA funds

• FHWA funds are called Federal-aid funds

• They are cost reimbursable funds – can be provided to an LPA by the FHWA through DOTD

• All FHWA funding program are reimbursement programs – NOT Grant programs.

MS

Page 61: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

The Flow of Federal Funding

• Federal Transportation Funds

• Administered by FHWA – Authorization of Funds

• To State DOTs

• DOTD is responsible for ensuring that ALL Federal and State laws and regulations are followed

• DOTD is always the direct recipient of FHWA funds – facilitate funding to sub-recipients

• To Sub-recipients using federal funds (Local Public Agencies (LPA))

• Answer to DOTD for ensuring that ALL Federal and State laws and regulations are followed

Page 62: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Federal-aid Funds

• Federal Law requires states to be fiscally responsible for all sub-recipients’ (LPA’s) proper expenditure of federal funds

• The LPA sponsored projects must be compliant with all applicable federal and state requirements

• Non-compliance can result in partial or complete withdrawal of federal participation and funding in the project

Page 63: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Moving Ahead for Progress in the 21st Century - MAP 21

• New 2 Year National Transportation Law

• Provides States With More Flexibility

• Consolidation of Programs

– 6 Core Program Structure

• Combined many small programs into the core programs

• Requires Performance Measures and Greater Accountability

Page 64: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide
Page 65: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Programs Affecting LPAs

Page 66: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

FHWA MAP 21 Website

http://www.fhwa.dot.gov/map21/

Page 67: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

MAP 21 Fact Sheets

Fact Sheets on:

• Highway Safety Improvement Program (HSIP)

• Metropolitan Planning

• Railway-Highway Crossings

• Surface Transportation Program (STP)

• Transportation Alternatives Program (TAP)

• Tribal Transportation Program

Page 68: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Stages of a Transportation Project

• Stage 0 – Feasibility/Planning

• Stage 1 – Environmental

• Stage 2 – Funding

• Stage 3 – Preconstruction (Design, R/W, Utilities)

• Stage 4 – Letting (Bidding)

• Stage 5 – Construction

• Stage 6 – Maintenance

Page 69: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

AW

Page 70: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

What Can Federal Funds Be Used For Within the LPA Programs?

• Transportation Planning

• Preliminary Engineering (pre-construction) – Design, Right of Way Acquisition, Utility Relocation

• Construction

• Construction Engineering and Inspection

***Matching Funds from the LPA are usually required for all of the above & LPA owns the contracts for these types of projects**

Page 71: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

State Funding

DOTD Transportation Trust Funds (TTF) can only be spent on State owned roads. The only exception is the Off-System Bridge Replacement Program which was amended by law

Page 72: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Funding Decisions Need to be Made for All Project Stages

• If 100% Local Funds are used for Preliminary Engineering (Pre Construction):

– Entity performs work in-house

– Entity selects their own consultant to help with work (if needed)

• If Federal Funds are used for Preliminary Engineering (with Local and/or State match)

– DOTD advertises and selects a consultant for the LPA

• DOTD HQ advertises (lets) all federally funded Construction projects for the LPA

Page 73: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Why Does DOTD have to Select Consultants for Design and

Advertise Construction Projects if an LPA is signing both these

contracts???? DOTD’s procedures for both of these activities have

been previously approved by FHWA as meeting all Federal requirements – DOTD facilitates the projects for LPAs to use Federal funds (with the Entity/State Agreement)

Page 74: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

The Brooks Act – USC 40 Ch 11

The federal Brooks Act requires agencies to promote open competition by advertising, ranking, selecting, and negotiating contracts based on demonstrated competence and qualifications for the type of engineering and design services being procured, and at a fair and reasonable price.

LA State Law procurement requirements for professional services do NOT meet the Brooks Act

Page 75: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

LPA vs. FHWA funding – LPA signs & owns all contracts

Stage of a Project LPA Paying 100% Federal $$ will Reimburse costs

Conceptual Plans and Environmental Decision

LPA can do work or

pick consultant

DOTD process used for

consultant selection

Preconstruction Engineering

LPA can do work or

pick consultant

DOTD process used for

consultant selection

Right-of-Way Acquisition and Relocation

LPA purchases –

must follow fed.

procedures

LPA purchases – must

follow Federal procedures

Utility Relocation LPA handles LPA handles – must follow

DOTD procedures Construction Engineering & Inspection

LPA can do work or

pick consultant

DOTD process used for

consultant selection

Construction N/A DOTD process used for

project - award to low bid

contractor

Page 76: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

“Responsible Charge” On Your Projects (See Handout)

If an LPA accepts Federal-aid funds - Federal Regulation 23 CFR 635.105 – LPA must provide a full time employee of the LPA to be in “responsible charge” of a stages of a project.

– Not required to be engineer

– Required even if a consultant is retained by LPA to act as the Entity’s engineer

– Not a full time job, but must be full time on the Entity’s staff

– Does not have to be the same person in design as in construction

Page 77: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Responsible Charge’s Key Role

Acts as the primary point of contact for the Entity with the DOTD Project Manager / District Project Coordinator

- Attends all key project related meetings IF THE PERSON IN RESPONSIBLE CHARGE IS NOT IN ATTENDANCE, THE MEETING WILL BE CANCELLED

- Is involved in and/or knowledgeable of key project decisions

Page 78: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Responsible Charge

Page 79: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

This is YOUR project. It is YOUR

responsibility to keep it moving!

Page 80: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

“Responsible Charge”

• Federal Regulation 23 CFR 635.105 – LPA must provide a full time employee of the LPA to be in “responsible charge” of a project. – Not required to be an engineer

– Required even if a consultant is retained by the LPA to act as the LPA’s engineer

– Not a full time job, but must be full time on the LPA’s staff

– Does not have to be the same person in design as in construction

Page 81: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

“Responsible Charge”

• Not a new rule

• New enforcement by DOTD and FHWA

• New article in the Entity-State Agreement

• Must submit quarterly or monthly reporting forms (frequency will depend on the project’s program)

More information can be found at:

http://www.dotd.la.gov/administration/lpa/forms.aspx

Page 82: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Responsible Charge Form

Page 83: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Reporting Form

Page 84: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Reporting Form

Page 85: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Key Role • Acts as the primary point of contact for the LPA with

the DOTD Project Manager and the District Project Coordinator

– Is involved with and/or knowledgeable of key decisions

– Attends all key project related meetings • Any decision making meeting – Project Manager will identify required

meetings (i.e. Kickoff, Plan-in-Hand Inspection)

IF THE PERSON IN RESPONSIBLE CHARGE IS NOT IN ATTENDANCE, THE MEETING WILL BE CANCELLED.

Page 86: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Key Duties for

LPA Responsible Charge and LDOTD

See Handout

Page 87: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Working with DOTD

Page 88: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Conceptual

LPA

• Develops the Stage 0 Report/Program Application

• Processes the Entity-State Agreement

• Completes and submits the updated reporting form to the DOTD Project Manager with a copy to the District Administrator & the MPO (if applicable)

DOTD

• Reviews & approves the Stage 0 Report/Program Application

• Determines the type of required environmental document

• Prepares the Entity-State Agreement

Page 89: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering

LPA

• Submits the scope of services & man-hours

• Executes the contract

• Provides the schedule & budget

• Reviews, approves & transmits invoices to the DOTD

• Monitors the contract time & grants any extensions / suspensions

DOTD

• Reviews the scope & man-hours

• Prepares & advertises the contract

• Selects the consultant with input from the LPA (depending on the program)

• Prepares the contract

• Processes & pays invoices

(If federal funds are being used for engineering)

Page 90: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering

LPA and/or Design Consultant

• Prepares the environmental document

• Obtains all required permits (environmental & railroad)

• Coordinates the utility clearances/certification documentation

DOTD

• Processes & obtains federal approval of the environmental document

• Ensures permits & utility clearances are obtained

Page 91: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering

LPA and/or Design Consultant • Completes the predesign form

• Attends the predesign meeting**

• Prepares & reviews preliminary & final plan submittals (including cost estimates)

• Sends the plans to & works with the utility companies

• LPA distributes plans internally

• Attends the Plan-in-Hand field Inspection**

**Responsible Charge must attend

DOTD • Schedules & chairs predesign

meeting*

• Reviews preliminary & final plans (including cost estimates)

• Distributes plans internally to DOTD & FHWA for review

• Schedules & chairs the Plan-in-Hand Field Inspection*

*Consultant performs this in

LRSP & SRTS as per

Agreement

Page 92: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering

LPA and/or Design Consultant

• Reviews plans to ensure all comments have been addressed

• Completes Non-Standard pay item request (if applicable)

• Completes design exception/design waiver request (if applicable)

DOTD

• Distributes the notes from field inspection & reviews

• Processes Non-Standard pay item request (if applicable)

• Processes design exception/design waiver request (if applicable)

Page 93: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering

LPA

• Transmits the stamped, signed & dated final plans, the cost estimate, & calculations to the DOTD

DOTD

• Prepares the submittal for letting

• Advertises & receives the bids

• Reviews the bids with the LPA & the MPO (if applicable)

Page 94: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering

LPA

• Reviews the bids for anomalies

• Formally responds to the DOTD request for concurrence

• Awards, signs & returns the contract timely

DOTD

• Awards the bid

• Prepares the contract for execution by the LPA & the contractor

Page 95: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Engineering (R/W) (if required)

LPA and/or Design Consultant

• Prepares the preliminary right-of-way maps

• Attends the Joint Plan Review Meeting (Responsible

Charge must attend)

• Prepares the final right-of-way maps

• Acquires the right-of-way

DOTD

• Schedules & chairs the Joint Plan Review Meeting

• Audits the right-of-way acquisition files to ensure all parcels were acquired following all state & federal guidelines

Page 96: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Working with DOTD

Page 97: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Construction

LPA and/or CEI Consultant

• Records the contract in the Clerk of Court’s office

• Schedules the Preconstruction meeting

• Attends all meetings when a decision is needed (Responsible Charge must attend)

• Ensures the project is constructed in accordance with plans & specs

DOTD District Project Coordinator

• Attends the Preconstruction meeting

• Attends all meetings when a decision is needed

• Verifies that the project is constructed in accordance with the plans and specifications

Page 98: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Construction

LPA and/or CEI Consultant

• Reviews & recommends approval of change orders (Responsible Charge must be involved)

• Ensures work zone safety

• Ensures the contractor’s monthly estimate documentation is provided to the DOTD

• Pays the contractor’s monthly partial estimates (Responsible Charge)

• Prepares/submits the Cost Disbursement Certification to DOTD (Responsible Charge)

DOTD

• Disburses monies to the LPA

• Reviews & approves change orders

• Verifies that the work zone safety requirements are being implemented on the project

Page 99: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Construction

LPA and/or CEI Consultant

• Attends the final inspection (Responsible Charge must attend)

• Records the Final Acceptance in Clerk of Court’s office

• Ensures the Final Estimate & required documentation is transmitted to DOTD timely

DOTD District Project Coordinator

• Attends the final inspection

• Audits the final estimate

Page 100: Overview of the 2012 AASHTO Bike Guide of LPA... · Brian Parsons February 19, 2013 Overview of the 2012 AASHTO Bike Guide

Questions?