Overview of SDPP Acquisition Process
Transcript of Overview of SDPP Acquisition Process
Seriti Commission
Overview of SDPP Acquisition Process
D Griesel
1
Seriti Commission
Contents • Armscor Overview
• Standard Armscor Policy and Practice Documentation
• SDPP Procurement – Deviations from Standard Policies
• SDPP Initiation Process
• Final Offer Solicitation
• SOFCOM
• Project Teams
• Offer Evaluation, Consolidation and Recommendation Process
• Contract Negotiation and Contract Authorization
• Summary of ADPP Acquisition Process
• Armscor Internal Audits
• Conclusion
2
Seriti Commission
Armscor Overview • Armscor established in terms of section 2 of Armaments Development and
Production Act 57 of 1968 – applied during SDPP Acquisitions
• 1968 Act repealed in 2003 – superseded by Act 51 of 2003.
• Section 2 of 1968 Act -
– established Armscor as a body corporate capable of suing and being sued
in its corporate name; and
– “of performing, subject to the provisions of this Act, all such acts as are
necessary for or incidental to the carrying out of its objects, the exercise of
its powers and the performance of its functions”
• Section 3 of Act – Armscor’s objectives were “to meet as effectively and
economically as may be feasible the armaments requirements of the Republic,
as determined by the Minister, including armaments required for export”
3
Seriti Commission
Structure Of Ministry Of Defence
4
Department of Defence Dept Mil Vet
Seriti Commission
Armscor Overview
• Armscor had the power to enter into any contract or perform any act,
whether in the Republic or elsewhere, which may be necessary for or
incidental or conducive to the attainment of any of its objects or which is
calculated directly or indirectly to enhance the value of the services which
it may render in respect of any of the activities contemplated in the 1968
Act or which the Minister of Defence may from time to time determine.
• Section 5 of 1968 Act - the affairs of Armscor were to be managed and
controlled by a board of directors.
• This is still the position under the 2003 Act.
5
Seriti Commission
Standard Armscor Acquisition Process
• In terms of 1968 Act – Armscor appointed as Defence Materiel Acquisition
Tender Board
– Authorization of contracts and decisions regarding preferred bidders –
had to be made by Armscor Board (Tender Board)
• In terms of standard tendering and contracting processes – Armscor is
responsible for all phases of tendering and contracting process.
6
Seriti Commission
STANDARD ARMSCOR POLICY/PRACTICE DOCUMENTATION
7
Seriti Commission
Tender Solicitation and Contracting
• KP 021 - Standard practice for the request of proposals, quotations,
submissions and orders
• Describes handling of RFO’s and submissions for contract authorization.
8
Seriti Commission
Standard Tender Solicitation and Evaluation Process
9
Tender Evaluation and Contracting Process
Tender Solicitation Process Receive DOD Requirement
(URS)
Verify Requirement
Compile WBS & SOW
Compile Value System & RFO
Approve Value System & RFO
Solicit Offers from Suppliers
Evaluate Offers
Compile Eval Report
Approval to Negotiate
Finalize Negotiations
Authorize Order
Place and Admin Order
User Requirement
Review
Process Ass + Line + User
Project team/ Consolidator/ Proc Assuror
Process Assuror’s
Report Tender Board Tender Board
Seriti Commission
Armscor Roles and Responsibilities in Tendering and Contracting Process
10
Receive DOD Requirement (URS)
Prepare RFP & Value System
Evaluate Offers & make Recommendation by means of submission
Issue Order
- Forward complete RFP to offerors - Advertise on Tender bulletin
Receive offers on closing date
Distribute Committee Submissions
Verify correctness of Submission and adherence to procedures
-Minutes decisions -Countersign approved orders -Advertise on bulletin
PROCUREMENT SECRETARIAT AUTHORIZATION COMMITTEE (TENDER BOARD)
ACQUISITION DEPARTMENT
Tender Board (Authorization Committee) considers submission and makes decision
Seriti Commission
Information and Offer Solicitation in Acquisition Process
11
t
PRELIMINARY DESIGN
PRELIMINARY DEVELOPMENT
DETAIL DESIGN
DETAIL DEVELOPMENT QUALIFICATION
ROC SR (URS)
DP AP CR ST PSR DOD PROJECT
MILESTONE DOCUMENTS
ARMSCOR BASELINES
RBL FBL ABL PBL MBL IOBL OBL
CONCEPT PHASE
TECHNOLOGY ACQUISITION
DEFINITION PHASE DESIGN DEVELOPMENT
PHASE
INDUSTRIALI-SATION PHASE
PRODUCTION PHASE
COMMISSIONING PHASE
XDM ADM EDM PPM PM MODELS
RFI RFO
INDUSTRY
TENDER BOARD
CONTRACT
Information and Offer Solicitation
Seriti Commission
• Standard practice for the selection of contractual sources – set out in
A-Proc-097. Established the practice that could –
– best meet Armscor’s need as described in the relevant RFP and
– ensure the source selection process for the impartial, equitable and
comprehensive evaluation of each offeror’s proposal and minimize the
cost of the selection process.
• A-Proc -097 - contains amongst others, the roles and responsibilities of
evaluators and process assurers, guidelines with respect to the
determination of evaluation criteria and generation of an RFO and
subsequent evaluation of the received offers.
12
Selection of Contractual Sources
Seriti Commission
Acquisition Policy • KB 1000 - Armscor Policy: Acquisition and Weapon System Management
Support dated 1 May 1995
– describes the policy for the management of military acquisition
programmes that deal with the acquisition of product systems and
products
– describes the technical baselines to be approved by Armscor
• completely aligned with the DOD Acquisition Policy, VB1000
– describes the composition of Baseline Review Boards who have the
responsibility to approve each identified baseline and to authorise
projects to continue to the next phase.
13
Seriti Commission
DOD/ Armscor Levels 5&6 Process Alignment
14
ROC SR
DP AP CR ST PSR (URS)
RBL FBL ABL PBL MBL OBL
CONCEPT PHASE
DEFINITION
PHASE
DESIGN DEVELOPMENT
PHASE
INDUSTRIALI-
SATION PHASE
PRODUCTION
PHASE
COMMISSIONING PHASE
Prelim Study
Funct Study
Proj Study
Syst Study
Level 6
(DOD)
Level 5
(Armscor)
Acquisition Study
Industrialization Phase
Production Phase
Commissioning Phase
Concept Phase
Definition Phase
Design Development
Phase
Industrialization Phase
Production Phase
Commissioning Phase
Assessing the need
Defining the solution
Contracting the right Contractor and managing the contract
Product Support
Baselines (Technical)
Project Milestones (Governance)
Seriti Commission
• KP 019 – Delegations
– Described decision-making powers and delegations within Armscor
– Armscor Board of Directors being the Tender Board, has the sole authority
that can authorise preferred bidders and also authorise contracts to be placed
on identified preferred bidders.
15
Delegation of Decision Making Powers
Seriti Commission
Management of Acquisition process • VB1000 – General policy for the management of Category 1 Matériel
Acquisition Process, Issue 2, dated 20 April 1994 (Joint Armscor/DOD
Policy).
• Describes the approach to be followed by members of the Defence Family
in the acquisition of weapons systems.
• Contains amongst others -
– the mandates and roles of Armscor and the SADF in the acquisition
process,
– policy to be applied with regard to the management of the acquisition
process of armaments, i.e. Category 1 matériel though all the phases
of the process.
16
Seriti Commission
SDPP PROCUREMENT –
DEVIATIONS FROM STANDARD POLICIES
17
Seriti Commission
SDPP – Deviations from Standard Policies
• A-Proc-097 : Practice for the selection of contractual sources
– guidelines were used in the development of value systems and RFO’s
– deviations in respect of the responsibilities of the Armscor Program
Manager and Project teams.
• The practice dictates that the process would be led by Armscor
and only provides for participation by the DOD on evaluation
panels.
• In the SDPP process, some of the value systems and evaluation
reports were finally approved and signed off by the DOD and not
by Armscor.
18
Seriti Commission
SDPP – Deviations from Standard Policies
• KP 019 – Delegations
– the Armscor Board of Directors being the Tender Board, has is the sole
authority that can authorise preferred bidders and also authorise
contracts to be placed on identified preferred bidders.
– In the case of the SDPP’s the preferred bidders were recommended to
AASB, AAC, Minister’s Committee - eventually authorised by Cabinet
– subsequent contract placement was also authorised by Cabinet,
19
Seriti Commission
SDPP – Deviations from Standard Policies
• VB 1000 - General policy for the management of Category 1 Matériel Acquisition Process
– did not reflect the organisational structures that were formed post 1994 as an output of the MODAC1 process, namely AACB, AASB and AAC
• VB1000 Structure – PKK (PCC), VBR (DCB),VBK (DPC)
– the only 2 non-negotiable milestone documents of the project are the Staff Target and the Acquisition Plan
• Approved AP’s did not exist for all projects
• mandatory AP in the SADF (DOD) environment did not constitute a hold point that from a policy perspective prevented Armscor to authorize a contract.
• The importance of the AP to Armscor was that it authorized the financial ceiling for issuing a FA to Armscor, without which Armscor would normally not be in a position to consider authorization of a contract on a preferred bidder.
20
Seriti Commission
SDPP – Deviations from Standard Policies
• DOD Policy Directive No 4/147: MOD Policy for Dealing With International
Defence Equipment Offers in the MOD (8 Aug 1997)
– Aim - To provide MOD policy guidelines and management procedures
for dealing with foreign initiated, international government to
government defence equipment offers relating to armament
acquisition for the SANDF, that are to be integrated with an
interdepartmental co-ordinating and decision making structure.
– Applicable to Armscor
21
Seriti Commission
DOD Policy Directive No 4/147
• Acquisition Strategy to incorporate the following:
– The equipment offers are to address approved MOD requirements.
– The MOD requirements statement are to at least have been
progressed to a functional baseline or beyond.
– The individual equipment elements of an offer are to be
comprehensive enough to be evaluated against the corresponding
functional baseline.
– The individual elements are to be able to be evaluated against
competitive offers via application of the same value systems that are
developed for MOD functional requirements.
– Auditability of all decisions is to be ensured
22
Seriti Commission
DOD Policy Directive No 4/147
• MOD Management of Assessment of Offers –
– “Prior to translating an offer into separate, standard armament
acquisition projects, an assessment procedure incorporating the
following iterative, multi-tier approach is to be followed :”
• First Order : Appointment by MOD of a workgroup to undertake
strategic implications of the offer.
– First order value system incorporating military evaluation of
supplier government
– Recommendations regarding political, interdepartmental and
intradepartmental involvement are to emanate from the MOD
evaluation.
23
Seriti Commission
DOD Policy Directive No 4/147
• Second Order
– Implementation of recommendations via representative MOD
evaluation team to develop second order value system.
– Recommendations regarding project teams and project
management requirements to bridge the gap between
elements of the offer and separate, standard acquisition
Projects, are to accompany the second order value system
• Third Order
– Project teams must develop third order value systems for the
individual elements of the offer iaw the second order value
system.
24
Seriti Commission
Impact of Policy Directive 4/147
• Policy Directive 4/147 only relevant to International Defence Equipment Offers
• Numerous Non-SDPP acquisition programmes were being managed by
Armscor in parallel with the SDPP’s
• Policy Directive did not amend any of the standard policies/Practices that
guided other acquisition programmes
• Examples of other acquisition programmes managed concurrent with SDPP’s
– Astra Trainer Aircraft
– C130 upgrade
– Rooivalk Combat Support Helicopter
25
Seriti Commission
SDPP INITIATION PROCESS
26
Seriti Commission
Period Prior to SDPP
• Prior to the approval of the SDPP acquisition, Armscor was in the process of or procuring various product systems on behalf of the DoD.
• before these processes could be completed, the individual procurement processes were suspended at various stages in 1997.
• decided by DoD that the individual procurement processes which had been initiated by Armscor on behalf of the DoD prior to 1997 would be superseded by the package approach reflected in the SDPP.
– LUH – RFI had been issued
– Corvette – Process initiated in 1992 – Progressed to RFO – Cabinet Review.
– AFT – RFO issued in May 1995. Supplementary RFO developed but not issued
– Submarines – Staff Target in August 1996 for replacement of Daphne Subs
27
Seriti Commission
SDPP Initiation
• Seven programmes that constituted the SDPP – emanated from the draft
Defence Review
– Identified 14 required equipment types
– 7 equipment types were deemed to require foreign participation
– Remaining 7 types of such a nature that they could be
developed/manufactured by local South African industry
• Programmes for equipment acquisition which had been previously
initiated as individual requirements but which formed part of the 7 types
identified to require foreign participation, were stopped as individual
projects and were subsequently incorporated into the SDPP process.
28
Seriti Commission
SDPP Initiation
• The initiation of the SDPP acquisition process can be traced back to June 1997 - The international government-to-government defence equipment offers were dealt with by the DoD and Armscor in accordance with DoD Policy Directive No 4/147 approved by the Council of Defence on 08 August 1997.
• A formal process was initiated whereby RFIs for 7 cardinal equipment types were issued by Armscor to the embassies of 9 countries on 23 September 1997
• under the signature of Mr R.F. Haywood in his capacity as Executive Chairman of Armscor.
• All Embassies received RFI’s for all the types of equipment, and were required to distribute the RFI’s to relevant companies in their respective countries.
29
Seriti Commission
Issuing of RFI’s
• RFI’s Issued to 9 countries :
– United Kingdom
– Germany
– France
– Canada
– Italy
– Spain
– Sweden
– Brazil
– Denmark
30
Seriti Commission
Issuing of RFI’s
• The information elicited in the RFIs dealt with aspects such as:
– Functional performance of the offered equipment;
– Industrial Participation considerations relating to South African
Industry involvement; and
– Financing schemes to facilitate the business arrangements.
• On the 31st of October 1997 -
– total of 37 responses to the RFI’s were received from the countries
above, except from Brazil and Denmark who declined to offer.
– Unsolicited responses were received from Russia and the Czech
Republic.
31
Seriti Commission
RFI Evaluation
• Received responses were evaluated against previously approved value
systems in each of the categories of :
– functional performance
– financing
– Industrial Participation
• Subsequent to completion of the offer evaluation process, the CoD
approved a shortlist of 23 products offered by 8 countries, to enter a
subsequent round of “Best and Final Offer” bidding
32
Seriti Commission
Shortlisted Products
• The shortlisted products were arrived at after evaluation of the RFI
responses against the RFI value systems that existed for each product
type.
• Minimum Functionality levels were determined by the respective User
environments.
• The minimum functionality levels were determined on the basis of
minimum functionality that would meet the User’s Requirement to such
an extent that the products would be acceptable for use in the intended
role.
• The shortlisted products were identified on the basis of them all meeting
the minimum functionality requirements.
33
Seriti Commission
Shortlisted Products
EQUIPMENT TYPE
COUNTRY
PRODUCT
Corvettes / Frigates
United Kingdom
Germany
France
Spain
GEC F3000
GFC MEKO 200 / A200
DCN LAFAYETTE
Bazan 590B
Submarines
United Kingdom
Germany
France
Italy
Sweden
Upholder
GSC 209 1400 MOD
DCN Scorpene
Fincanteri S1600
Kockums T192
Advanced Light Fighter Aircraft
(ALFA)
United Kingdom/Sweden
Germany
France
BAE/SAAB Gripen
DASA AT2000
Dassault Mirage 2000
34
Seriti Commission
Shortlisted Products
35
EQUIPMENT TYPE
COUNTRY
PRODUCT
Lead-In Fighter Trainer
(LIFT)
United Kingdom
Czech Republic
Italy
Italy
BAE Hawk 120
AERO VODOCHODY L159
AERMACCHI MB 339FD
AERMACCHI AEM/YAK 130
Main Battle Tank (MBT) United Kingdom
France
VICKERS CHALLENGER 2E
GIAT LECLERC
Maritime Patrol Helicopter (MH)
United Kingdom
France/Germany
GKN Super Lynx
Eurocopter Cougar
Light Utility Helicopter (LUH)
Italy
France/Germany
Canada
Agusta A109
Eurocopter EC635
Textron Bell 427
Seriti Commission
FINAL OFFER SOLICITATION
36
Seriti Commission
Final Offer Solicitation
• During February 1998, the RFO's for the short-listed products in 6
equipment categories (excluding LIFT) were submitted via the Military
Attache’s of the respective countries /suppliers.
• The closing dates for submission of the best and final offers ranged from
11 May to 15 May 1998 for the 6 categories of equipments.
• The RFO for the LIFT lagged behind the initial six equipment types. The
RFO was sent out on 11 May 1998 and responses received back on 15 June
1998.
37
Seriti Commission
Final Offer Solicitation
• The RFO’s for the short-listed equipment types indicated that the final
offers should consist of 4 separate sections, each detailing the following
aspects:
– Functional Performance of equipment and Tender Price for the
specified quantities;
– Economical advantage for South African Industry related to Industrial
Participation programs in the two categories of
• Defence Industrial Participation (DIP) and
• National Industrial Participation Programme (NIP);
– Financial benefits as available from financing arrangements.
38
Seriti Commission
SDPP Third Order Value Systems
• Prior to acceptance of the final offers, detailed value systems, against which
the respective proposals would be evaluated, were lodged with Armscor’s
Procurement Secretariat.
• In terms of paragraph 5.2.3.1 of KP021, Armscor Procurement Secretariat was
responsible for issuing RFOs to prospective offerors; receiving offers from the
offerors; and distributing such offers to the various Integrated Project Teams.
– constitute the “third order” value systems contemplated in the Ministerial
Policy Directive 4/147.
• developed per equipment type.
• based on the requirements of the respective URS’s and were aimed at
evaluating the functionality of the offered equipments.
39
Seriti Commission
SDPP Third Order Value Systems
Guidelines established by Departmental Coordinating Team (SOFCOM) :
• Three elements of each offer (Military Value, IP Value, Financing) will carry
equal weights
• Determined uniform method of calculation of program cost
• The final consolidation of the results of the evaluation of the respective
elements of the offers would be achieved by adding the 3 indices to obtain
a Best Value option, being the bidder obtaining the highest score.
• The recommenced option in each equipment category would thus be the
option achieving the highest Best Value score, where
– Best Value = Military Value Index + Financing Index + IP Index
40
Seriti Commission
Elements of Second Order Value System • Military Value Index - determined from the results of the evaluation by dividing the
technical evaluation outcome by program cost, and then normalising the results to a
value of 100, with the best value option carrying a weight of 100.
• Financing Index - determined from the evaluation of the elements of the offers relating
to financing, by normalising the results to a value of 100, with the best option carrying a
weight of 100.
• Industrial Participation Indices for the elements of the offers relating to proposed
industrial participation projects (DIP and NIP) - determined by normalising the results to
a value of 100 (one hundred), with the best options carrying a weight of 100.
– A consolidated Industrial Participation Index - determined by adding the DIP and
NIP indices, and again normalising the highest scoring option to a value of 100.
41
Seriti Commission
STRATEGIC OFFERS MANAGEMENT COMMITTEE
42
Seriti Commission
Strategic Offers Management Committee
• Seven procurement programmes running simultaneously
– consolidated into 1 procurement package under the aucpices of the
SDPP
– necessary to coordinate and consolidate the acquisition process. For
such purpose the SOFCOM was created.
• SOFCOM – was a coordinating committee
– appointed by the AAC on 7 April 1998
– established with the aim of supporting the Minister of Defence in the
management and execution of the DoD involvement in the SDPP
acquisition.
43
Seriti Commission
Strategic Offers Management Committee
• SOFCOM operated under a formal constitution which spelt out the
functions of the committee
– constituted of senior representatives from Armscor, the Acquisition
Division of the DoD (“DAPD”), Arms of Service (SANDF), DTI and the
DoF.
• SOFCOM functioned under the dual chairmanship of :
– Chief of Acquisitions of the DoD Mr. Shamin (Chippy) Shaikh and
– General Manager: Aero Maritime of Armscor, Mr. Heinrich de Waal
Esterhuyse.
44
Seriti Commission
Strategic Offers Management Committee • SOFCOM membership :
– Chief of Acquisition (Co-Chairperson);
– General Manager: Aero Maritime, Armscor (Co-Chairperson);
– Chief of Finance (DOD);
– General Manager, Combat Systems, Armscor;
– Director Weapon Systems, Acquisition Division;
– Chief of Army Representative;
– Chief of Air Force Representative;
– Chief of Navy Representative;
– Chief of Intelligence Representative;
– Department of Trade and Industry Representative;
– Department of Finance Representative;
– Representative from Acquisition Division (SOFCOM Secretariate);
– Representative from Armscor (SOFCOM Secretariate).
45
Seriti Commission
Strategic Offers Management Committee Members
46
Seriti Commission
Strategic Offers Management Committee
• SOFCOM met approximately once every 2 weeks during the 3 months it
was in existence.
• Most of the time the SOFCOM performed the function of, among other
things, reviewing and monitoring the progress of the evaluations
performed by the different project teams and
• primarily concerned to ensure that there was consistency and alignment
in approach on the part of the 7 project teams,
• especially in light of the fact that the DIP, NIP and Finance project
teams straddled each of the 7 projects.
47
Seriti Commission
Strategic Offers Management Committee
• The constitution of the SOFCOM did not provide for decision-making
authority in respect of any matters that would materially affect the
evaluation as it pertained to the selection of the preferred bidder.
• SOFCOM was entitled to submit recommendations to the CoD.
• The Minister of Defence had approved this deviation from the standard
Armscor procurement procedures through the appropriate structures.
48
Seriti Commission
Strategic Offers Management Committee • SOFCOM continued to formally function as a committee until the recommendation of
the preferred bidders was presented to AASB on 8 July 1998 (albeit that it was not dissolved).
• SOFCOM was responsible for developing the Second Order Evaluation Value System which was eventually to be used for the consolidation of the evaluation results from the respective teams.
– The formula that was ultimately adopted was the following:-
BV = MV + IP + FI
– Where:
• BV = Best Value
• MV = Military Value (Military Performance Index/Cost)
• IP = Industrial Value Index
• FI = Financing Index
49
Seriti Commission
PROJECT TEAMS
50
Seriti Commission
SDPP Process – Offer Evaluation
• The received proposals were evaluated by 12 (twelve) project teams, i.e.
– 7 (seven) Program-related teams for the technical appraisal,
comprising members from the respective Arm of Service (SANDF),
Armscor and the Defence Secretariat;
– 1 (one) NIP team for the NIP appraisal, comprising members from DTI;
– 3 (three) DIP teams for the DIP appraisal, comprising members from
Armscor, SANDF and the Defence Secretariat; and
– 1 (one) Financial team for the Financing appraisal, comprising
members from Armscor, Defence Secretariat, SANDF, Department of
Finance and Financial Institutions.
51
Seriti Commission
ALFA Team
52
Seriti Commission
Corvette Team
53
Seriti Commission
LIFT Team
54
Seriti Commission
LUH Team
55
Seriti Commission
MBT Team
56
Seriti Commission
MH Team
57
Seriti Commission
Submarine Team
58
Seriti Commission
Integrated Project Teams
• The IPTs consisting of members from both Armscor and the DoD, were
established for each of the product systems.
• The appointment and responsibilities of the members were in accordance
with VB1000.
• The IPTs were responsible for:
– preparation of the RFI and RFO documentation based on the URS;
– development of the Third Order Value System, in terms of paragraph 15c
of the DoD Policy Directive No 4/147, for individual product systems;
– adjudicating received offers against the approved value system;
– negotiating the technical contents of the contracts; and
– negotiating the Supply Terms.
59
Seriti Commission
OFFER EVALUATION, CONSOLIDATION AND RECOMMENDATION PROCESS
60
Seriti Commission
SDPP Evaluation and Consolidation Process
61
Seriti Commission
Evaluation Results - ALFA
62
Seriti Commission
Evaluation Results - Corvettes
63
Seriti Commission
Evaluation Results - LIFT
64
Seriti Commission
Evaluation Results - LUH
65
Seriti Commission
Evaluation Results - MBT
66
Note : MBT recommended by SOFCOM to AASB, but excluded from final SDPP contracts
Seriti Commission
Evaluation Results - MH
67
Note : MH recommended by SOFCOM to AASB, but excluded from final SDPP contracts
Seriti Commission
Evaluation Results - Submarine
68
PROG FIN COST TOTAL MIL MIL IP MIL + IP FIN BESTOFFEROR/PRODUCT COST (M USD) COST PERF VALUE VALUE INDEX INDEX VALUE
(M USD) (NPV @ 13,5%) INDEX INDEX INDEX
GERMANY 995.9 532.6 1528.5 80.6 100.0 100.0 100.0 100.0 100.0GSC 209 1400 MOD (523.0)
FRANCE 1210.2 728.1 1938.3 85.7 66.0 72.0 69.0 93.0 77.0DCN SCORPENE (615.0)
ITALY 1173.1 574.4 1747.5 100.0 83.0 67.0 75.0 87.0 79.0FINCANTERI S1600 (632.4)
SWEDEN 1280.8 738.7 2019.5 80.9 91.0 69.0 80.0 78.0 79.3KOCKUMS TYPE 192 (676.6)
Seriti Commission
Evaluation and Consolidation Process
• Consolidated evaluation results were presented to the AASB on 8 and 16 July 1998.
• During the presentation by SOFCOM to the AASB on 8 and 16 July 1998, the Chief of Acquisition of the DoD, who was the presenter, introduced a “Non-Costed Option” for the LIFT.
– This “option” was a consolidation of the evaluation results for the LIFT, but excluded cost.
– Implied that the normalized Military Performance Index without having been divided by cost, was added to the normalized Industrial Participation Value and Financing Indices.
– The exclusion of cost in the Military Value, brought about a change in “Best Value” scores and also in the ranking of the offerors
69
Seriti Commission
LIFT Non-Costed Option Results
70
Seriti Commission
Recommendation Process
• SOFCOM recommended result of costed options to AASB on 8 July 1998
• AASB met on 8 and 16 July 1998 - submitted their recommendations to
the AAC.
• AAC submitted their recommendations to the Minister’s Committee
• Minister’s Committee submitted their recommendations to Cabinet.
71
Seriti Commission
Minister’s Committee
• Mr Thabo Mbeki as Chairman and Deputy President of the Republic of
South Africa;
• Mr Mosiuoa Gerard Patrick Lekota as Minister of Defence (Initially Mr J.
Modise);
• Mr Alec Erwin as Minister of Trade and Industry;
• Mr Trevor Manuel as Minister of Finance; and
• Mr Jeffrey Thamsanqa Radebe as Minister of Public Enterprises (Initially
Ms. S Sigcau).
72
Seriti Commission
Preferred Bidder Recommendation
• Evaluation results and indicated preferred bidders that were presented
to the AASB, AAC, the Minister’s Committee and subsequently to
Cabinet for approval, were all presentations and were not part of the
project governance documentation that would normally be submitted
to structures such as the AASB and AAC.
• Post SOFCOM consolidation, the procurement process outside of
Armscor’s control.
• This action therefore constituted a deviation from Armscor’s standard
procurement processes where Armscor would normally be solely
responsible for authorizing and appointing a preferred bidder
73
Seriti Commission
CONTRACT NEGOTIATIONS AND CONTRACTING AUTHORIZATION
74
Seriti Commission
Contract Negotiations - IONT
• November 1998 - Cabinet announced the preferred suppliers that had
been selected.
• Cabinet approved the establishment of the International Offers
Negotiating Team (IONT) to negotiate the umbrella agreements with each
of the preferred suppliers in respect of the SDPP and to finalize financing
arrangements with financial institutions.
• IONT was led by a chief negotiator and reported to the Minister’s
Committee and directly to the Deputy President as and when required.
75
Seriti Commission
Armscor Contracting Model
76
Seriti Commission
Contract Negotiations
• During the period of approximately 1 year between date of approval of the
preferred suppliers and the date of contract signature, negotiations were
conducted at 2 tiers :
– Negotiations by IONT resulting in
• “Umbrella Agreements” with suppliers.
• financing agreements with financial institutions.
• Alignment of equipment quantities and delivery phasing with the
negotiated funding.
– Negotiations by project teams - resulting in the “Supply Terms” to the
umbrella agreements.
77
Seriti Commission
Negotiated Agreements
• Umbrella agreements
– provided in-principle agreement with regards to certain elements of
the contract at a high level, for instance, including but not limited to
NIP and DIP undertakings, performance guarantees as well as price of
the system.
– the schedules, annexures and appendices to the umbrella agreement
contained detailed specifics of the individual elements agreed to in
the umbrella agreements.
• Supply terms to the umbrella agreements
– contain commercial as well as technical specifications of the product,
• NIP and DIP agreements
78
Seriti Commission
Contract Negotiations
• The 2 tiers of negotiations and subsequent agreements - constituted a deviation from the standard Armscor procurement processes.
• In the ordinary course of Armscor’s standard procurement processes, Armscor would be solely responsible for the negotiations and conclusion of contracts with the preferred suppliers.
• In the case of the SDPP’s, the IONT which was led by an independent chief negotiator who eventually reported to Cabinet,
– negotiated the high level agreements with the prospective preferred suppliers.
– Made eventual submission to Cabinet to obtain approval to enter into the contracts with the respective suppliers
• This process was outside of the area of control of Armscor.
79
Seriti Commission
International Offers Negotiating Team
IONT consisted of the following members:
• Mr Jayendra Naidoo as Chief Negotiator and Chairman;
• Technical and DIP domain addressed by the CEO of Armscor, who
– led the technical and DIP negotiating workgroups
– supported by Chief of Acquisition of the DoD;
• NIP domain addressed by the Acting Director Industrial Participation of
the DTI
• financing domain addressed by the Senior Manager, Budget Office of the
Department of Finance
80
Seriti Commission
SUMMARY OF SDPP ACQUISITION PROCESS
81
Seriti Commission
SDPP Process - RFI
• RFI’s were submitted to embassies of 9 countries for forwarding to
possible suppliers in their countries
– to determine whether they had a product that could satisfy the
requirements.
• 37 responses received on 31 October 1997.
• RFI responses were evaluated according to previously approved value
systems.
• Shortlist of acceptable products determined from RFI response evaluation.
82
Seriti Commission
SDPP Process - RFO
• During February 1998, the RFO's for the short-listed products in 6
equipment categories (excluding LIFT) were submitted via the Military
Attache’s of the respective countries /suppliers.
• The closing dates for submission of the best and final offers ranged from
11 May to 15 May 1998 for the 6 categories of equipments.
• The RFO for the LIFT lagged behind the initial six equipment types. The
RFO was sent out on 11 May 1998 and responses received back on 15 June
1998.
83
Seriti Commission
SDPP Process - RFO
• The RFOs required that the final offers should consist of four separated
sections per submission, i.e.
– technical and pricing information,
– economical advantage for the South African defence and non-defence
related industry (DIP and NIP) and
– proposed financing arrangements.
84
Seriti Commission
SDPP Process – Offer Evaluation
• The received proposals were evaluated by 12 (twelve) project teams, i.e.
– 7 (seven) Program-related teams for the technical appraisal,
comprising members from the respective Arm of Service (SANDF),
Armscor and the Defence Secretariat;
– 1 (one) NIP team for the NIP appraisal, comprising members from DTI;
– 3 (three) DIP teams for the DIP appraisal, comprising members from
Armscor, SANDF and the Defence Secretariat; and
– 1 (one) Financial team for the Financing appraisal, comprising
members from Armscor, Defence Secretariat, SANDF, Department of
Finance and Financial Institutions.
85
Seriti Commission
SDPP Process – Consolidation
• The results provided by each project team was normalized to a 100 (one
hundred) point score
• presented individually to the SOFCOM on the 1st and 2nd of July 1998.
• The independent group scores per equipment type were consolidated by
the SOFCOM to arrive at a preferred supplier per equipment type.
86
Seriti Commission
SDPP Process – Recommendation
• a recommendation per program was compiled by the SOFCOM,
• AASB and the AAC were briefed on the results.
• followed by a special Ministerial briefing to the then Deputy President,
Minister of Defence, Minister of Trade and Industry, Minister of Public
Enterprise and the Deputy Minister of Defence on 31 August 1998.
• 18 November 1998 - briefing was presented to full Cabinet
• Cabinet approved the preferred suppliers for each of the equipment types
and authorized that negotiations be entered into with the preferred
suppliers in order to arrive at an affordable contacting position with the
respective suppliers.
87
Seriti Commission
SDPP Process- Preferred Supplier Approval
• Subsequent to Cabinet approval of the preferred suppliers,
– Preferred suppliers notified by letter under the signature of the Chairman of
Armscor of their selection as preferred suppliers,
– unsuccessful bidders were simultaneously notified that they weren’t selected as
preferred suppliers.
• Following on cabinet approval of the preferred suppliers, the IONT was formed,
comprising inter alia members from DoD, Armscor, Department of Finance (Treasury)
and DTI.
• IONT negotiated umbrella contracts and financing arrangements at a high level,
• respective program teams negotiated the technical terms with the respective suppliers
in order to finalize the configuration of each of the equipment types while remaining
within a predetermined cost ceiling.
88
Seriti Commission
SDPP Process – Contract Authorization
• Upon conclusion of the negotiation process - final briefing was presented
to Cabinet on 1 December 1999
• Cabinet authorized the signing of contracts with the suppliers of the
corvettes, submarines, LIFT, ALFA and the LUH.
• These contracts were subsequently signed on the 3rd of December 1999.
89
Seriti Commission
SDPP Process – Deviations from Standard Armscor Processes
• The Department of Finance (Treasury) evaluated the financing component
of the offers.
• deviation from standard Armscor procurement process where the
evaluation did not simply take place on technical, Industrial Participation
and cost grounds.
90
Seriti Commission
SDPP Process – Deviations from Standard Armscor Processes
• After consolidation of evaluation results - the proposed preferred suppliers were
recommended by the SOFCOM to the AASB and subsequently to the AAC and the
Minister’s Committee.
• The next stage was approval by full Cabinet of the contracting decision arrangements
which occurred on or about 1 December 1999.
• The contracts were signed on the 3rd of December 1999.
• In terms of Armscor’s standard tendering and contracting processes - Armscor as the
Tender Board would have been responsible for all phases in this process.
• In the case of the SDPP - the decisions regarding the selection of the preferred bidders
and the awarding of the contract was not made by Armscor Tender Board, but rather
was made by Cabinet
• Signature of the contracts was only subsequently ratified by the Armscor Board.
91
Seriti Commission
ARMSCOR INTERNAL AUDITS INTO PROCESS
92
Seriti Commission
Armscor Audits into SDPP Process
• The SDPP process was the subject-matter of two internal audit reports.
• The 1st (first) internal audit report was carried out over the period 6 to 30
November 1998 (“the first internal audit report”)
• the 2nd (second) internal audit report was produced on 21 July 1999 (“the
second internal audit report”).
• Audits were performed at the request of the General Manager:
Aeronautics and Maritime in order to enquire whether the processes
followed during the valuation of the SDPP were proper and transparent.
• The internal audits were carried out JG Grobbelaar of Internal Audit, Dr. BJ
van Tonder and Mr. W van der Walt from the Quality Engineering Services
Division.
93
Seriti Commission
Armscor Internal Audit Findings
• Audit reports concluded that no evidence of improper conduct was found
on the part of any of the Armscor employees involved in the evaluation of
the various proposals.
• The reports of the teams that evaluated the technical merits of the
proposals were adequate and contained sufficient information to verify
the adequacy of the procedures that were followed and the
appropriateness of the recommendations made to the SOFCOM.
94
Seriti Commission
First Audit Report - Findings
• The first internal audit report concluded that:
– although the evaluation were not performed strictly to A/PROC/097
since the process was influenced by parties outside of Armscor, the
basic principles and rationale in determining best value for money
were applied;
– the MOD policy for dealing with the SDPP stipulated a multi-tier
approach to be followed during the assessment of offers. The policy
outlined a three-order evaluation to be performed and according to
the SOFCOM constitution it managed the second order evaluation
95
Seriti Commission
First Audit Report - Findings
• The calculations of Military Performance Index values were verified by hand
calculations based on data included in the reports -
– were verified to within a few percent in all cases except for the submarine.
– Mr JG Grobler of Internal Audit confirmed the accuracy of the calculations
made for the submarine proposals during a further investigation.
• On instructions of the SOFCOM all final offers were evaluated and no offeror
was excluded due to non-compliance with any critical requirements.
• It must be noted that all offers were considered to meet the Defence Force's
minimum technical requirements.
96
Seriti Commission
First Audit Report - Findings • The evaluations were not performed strictly to A-Proc-097 (Armscor procedure for the
selection of contractual resources)
– the process was influenced by parties outside Armscor,
– the basic principles and the rationale of determining best value for money were
applied.
• The MOD policy for dealing with international Defence Equipment Offers dated 8
August 1997 stipulated a multi-tier approach to be followed during the assessment of
offers.
• The policy outlined a three-order evaluation to be performed and according to the
SOFCOM constitution it managed the second order evaluation.
• No First Order Evaluation in terms of the policy has been performed and it is uncertain
whether some other First order evaluation has been performed that could account for
the change in recommendations regarding the LIFT.
97
Seriti Commission
Second Audit Report - Findings
• even though a number of concerns exist regarding procedures followed,
the role of programme teams, accountability and actions by parties
outside of Armscor no evidence was found that would indicate gross
misconduct within Armscor with regard to the execution of work
• negotiations were conducted professionally and with integrity.
98
Seriti Commission
JIT Report - Recommendations
• The following recommendations of the Joint Investigating Team (“JIT”)
(consisting of the Public Protector, National Prosecution Agency and
Auditor General) into the SDPP process, related to the acquisition policy :
– “(§14.2.1) It is recommended that the policy document, referred to in
paragraph 3.2.5 above (VB1000) be further refined with specific
reference to the lessons learnt from the acquisition process under
investigation as reflected in this report. The staff of DoD and Armscor
involved in procurement should be properly trained to ensure that
they assimilate and fully understand the policy with a view to its
effective implementation.”
99
Seriti Commission
JIT Report - Recommendations
• (§ 14.2.6) Adequate audit trails, with particular emphasis on the visibility
of supervision, decision making and assumption of responsibility should
be in place at appropriate levels in the procurement process.
• “(§ 14.2.11) The guidelines contained in the Defence Review that relate
to the selection and appointment of subcontractors must be followed and
steps taken to ensure that an open and fair process is adhered to for the
selection of subcontractors”
100
Seriti Commission
JIT Report Recommendations - Implementation
• Subsequent to the release of the JIT Report
– a total review of the DoD/Armscor Acquisition Policy was initiated,
amongst others, addressing the recommendations from the JIT.
– Culminated in the promulgation of DODI/ACQ/No 00005/2003 (DAP
1000) on 1 September 2004.
– This document was subsequently reviewed and an updated version
was implemented on 1 July 2010.
101
Seriti Commission
CONCLUSION
102
103
Although there were a number of deviations to the standard Armscor procurement process, Armscor executed on its mandate in respect of the SDPP acquisition - “to meet as effectively and economically as may be feasible the armaments requirements of the Republic, as determined by the Minister, including armaments required for export”.