Overview of Mitsubishi Advanced PWR 2... · APWR design to improve economy, safety, reliability,...
Transcript of Overview of Mitsubishi Advanced PWR 2... · APWR design to improve economy, safety, reliability,...
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.8AS-EXP-20130003
Overview of
Mitsubishi Advanced PWR
IAEA INPRO 7th Dialogue Forum in Vienna
Sumio FUJIIActing General Manager,
Nuclear Systems Engineering Department
November 19, 2013
8AS-EXP-20130003
Remarks on proprietary and copyright information
• The data and information in the presentation materials are proprietary of
Mitsubishi Heavy Industries.
• Utilization of the data and information is limited to the purpose of INPRO
7th Dialogue Forum.
• The data and information concerning advanced PWR in the presentation
materials are never permanent. They may be changed in the process of
nuclear power plant construction for individual site.
• Mitsubishi Heavy Industries has the copyright of all figures and photos in
the presentation materials.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 1
8AS-EXP-20130003
Contents
1. Development History of Mitsubishi PWR
2. Advanced PWR for Global Deployment
3. Safety of Mitsubishi Advanced PWR
4. State-of-Art Technology for Digital Instrumentation &
Control System of Mitsubishi Advanced PWR
5. Safety Enhancements for Beyond Design Basis
Accident of Mitsubishi Advanced PWR
6. Construction Management of Mitsubishi Advanced
PWR
7. Operation and Maintenance Management of
Mitsubishi Advanced PWR
8. Conclusion
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 2
8AS-EXP-20130003
Development History
of Mitsubishi PWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 3
8AS-EXP-20130003
Line-up of Mitsubishi PWR for Japanese utilities
Unit C/O Outpt
Mihama1 1970.11 340 MkWe
Mihama2 1972.07 500 MkWe
Genkai1 1975.10 559 MkWe
Ikata1 1977.09 566 MkWe
Genkai2 1981.03 559 MkWe
Ikata2 1982.03 566 MkWe
Tomari1 1989.06 579 MkWe
Tomari2 1991.04 579 MkWe
Unit C/O Output
Takahama1 1974.11 826 MkWe
Takahama2 1975.11. 826 MkWe
Mihama3 1976.12 826 MkWe
Sendai1 1984.07 890 MkWe
Takahama3 1985.01 870 MkWe
Takahama4 1985.06 870 MkWe
Senfai2 1985.11 890 MkWe
Ikata3 1994.12 890 MkWe
Tomari3 2009.12 912 MkWe
Unit C/O Output
Ohi1 1979.03 1175 MkWe Ohi2 1979.12 1175 MkWe
Turuga2 1987.02 1160 MkWe
Ohi3 1991.12 1180 MkWe
Ohi4 1993.02 1180 MkWe Genkai3 1994.03 1180 MkWe
Genkai4 1997.07 1180 MkWe
Tsuruga3 201X~ 1538 MkWe
Tsuruga4 201X~ 1538 MkWe
2Loop((((300-600MWe)))) 3loop((((900-1000 MWe))))4Loop((((1200-1500MWe))))
Tsuruga 3 & 4 are Advanced PWRs.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 4
8AS-EXP-20130003
Development of Advanced PWR (J-APWR)
• The development of the Advanced PWR (APWR) was started in late
1980s as a joint cooperative development project by five Japanese PWR
owner utilities and Mitsubishi Heavy Industries (MHI), financially
supported by the Ministry of International Trade and Industry (Currently
the Ministry of Economy, Trade, and Industry) as a part of the Phase III
Improvement and Standardization Program of Japanese PWR.
• The design of the APWR was based on MHI’s conventional 4-loop plant
technologies, on which MHI has accumulated significant operating
experiences, and was scaled up to achieve higher electrical output.
• In addition to adopting those proven technologies after the first step
development, further modifications were also made on the prototype
APWR design to improve economy, safety, reliability, operability, and
maintainability by incorporating advanced technologies.
• The first APWR plant (Japanese APWR) is Tsuruga-3 producing 1538
MWe operated by the Japan Atomic Power Company. The Tsuruga-3 is
now under safety review for construction permission, which got
suspended due to the Fukushima Daiichi accident.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 5
8AS-EXP-20130003
GⅢ+ Reactors Development
70’s 80’s 90’s 2000’s 2010’s 2020’s
Development & Improvement of PWR
Technology
Enhanced up to APWR
APWR Tsuruga 3, 4licensing process
US-APWRUS NRC Licensing
EU-APWR
US UtilitiesComanche Peak
3, 4
European Utilities
ATMEA1
by ATMEA (Joint Venture)
European and Global Utilities
AREVA
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 6
8AS-EXP-20130003
Development of US-APWR & EU-APWR
• By referring the J-APWR, MHI has designed the US-APWR which meets
regulatory requirements in United States of America as well as Utilities
Requirements Document (URD). The turbine-generator system and all
electric equipment of the US-APWR are designed for 60 Hz electric grid.
• Basic designs of the US-APWR except for the fuel length are same as
those of the J-APWR whose design has completed. The US-APWR has
been developed as a larger-output version of the J-APWR, aiming at
higher electrical outputs and improved economics, by modifying some
design features mainly in the secondary side without increasing core
thermal output.
• The fuel length was changed to 4.2 meters in place of 3.66 meter, and
the electric output was increased to about 1700 MWt.
• EU-APWR is a sister plant of the US-APWR and is aiming to satisfy
European Utilities Requirements (EUR). Nevertheless the turbine-
generator system and all of electric equipment are designed as 50 Hz,
designs of core and other major equipment on the reactor coolant system
are same as those of the US-APWR except the reactor coolant pumps.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 7
8AS-EXP-20130003
Advanced PWR for
Global Deployment
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 8
8AS-EXP-20130003
US-APWR & EU-APWR : Course of Design
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 9
� To contribute toward safe, stable
and flexible power production
through satisfying American
“Utilities Requirements Document”
and “European Utilities
Requirements”.
A course of design for the US-APWR and EU-APWR is to;
�To achieve the best performance in safety, reliability,
operability, and maintainability by incorporating advanced
technologies.
�To provide the world’s largest NPP for large electric grid
utilities aiming at economical production costs.
8AS-EXP-20130003
Major Features on safety and reliability
� Top-mounted ICIS for avoiding penetrations at
the RV bottom
SHSH
SHSH
RWSP
RVACC ACC
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 10
� Full 4-train safety systems
with best-mix of passive
and active systems, which
allows on-power
maintenance
� Full digital I&C technology enabling
one-man operation
8AS-EXP-20130003
Major Features on economy
� Large reactor producing thermal output of 4,466MWt
� 14-ft fuels creating additional thermal margin and flexible core operation
� 14-ft fuels making 24-month operationwithout deterioration in fuel economy
� Enhanced SG heat transfer performance by enlarged heat transfer area with triangular lattice arrangement of SG tubes
� High-performance steam-water separators generating high quality steam in SG
� High performance LP-turbine having last stage blades of 70 inches length
� Secondary system enabling high thermal efficiency over 36%
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 11
8AS-EXP-20130003
Comparison of Major Specifications
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 12
8AS-EXP-20130003
Reactor Vessel and Internals
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 13
8AS-EXP-20130003
Reactor Core
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 14
Fuel and Rod cluster control assemblies
A, B, C, D : Control group bank
SA, SB, SC, SD : Shutdown group bank
Control rod drive
mechanism
Reactor
vessel
Fuel
assembly
Outlet
nozzle
Inlet
nozzle
Reactor Vessel Core design
8AS-EXP-20130003
Major Core Parameters
Design limitsBest estimates
of initial core
Active Core
Active core equivalent diameters (cold) 3.89 m
Active fuel height (cold) 4.2 m
Hydrogen/Uranium atomic ratio (cold) 5.57
Core average linear power density 15.2 kW/m
Maximum linear power density 39.5 kW/m 31.2 kW/m
Nuclear enthalpy rise hot channel factor FN∆H 1.73 1.50
Delayed neutron fraction βeff (%) 0.44 to 0.75 0.50 to 0.69
Prompt neutron lifetime, l* (µsec) 8 to 20 14.0 to 15.3
Reactivity coefficient
Doppler power coefficient (pcm/%power) BOC
EOC
-12.4 to -7.4
-12.1 to -7.6
Moderator temperature coefficient (pcm/℃℃℃℃) -71.1 to -1.4
Moderator density coefficient (pcm/g/cm3) < 0.51x105 < 0.32x105
Boron coefficient (pcm/ppm) - -9.3 to -8.0
Neutron multiplication factor
Maximum core reactivity keff (BOC,cold,noXe) - 1.223
Maximum fresh fuel assembly k∞ - 1.456
Boron concentration (ppm)
Refueling boron concentration > 4000 -
Cold shutdown, BOC, noXe, ARI, keff<0.95 - 1850
Cold shutdown, BOC, noXe, ARO keff=0.99 - 1796
Hot shutdown, BOC, noXe, ARO keff=0.99 - 1706
Hot zero power, BOC, noXe, ARO keff=1.0 - 1579
Hot full power, BOC, noXe, ARO keff=1.0 - 1444
Hot zero power, BOC, equilibrium Xe, ARO - 1086
Shutdown margin
BOC
EOC> 1.6
2.94
2.15
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 15
8AS-EXP-20130003
Major Thermal-Hydraulic Parameters
Design Parameters Design Values
Coolant condition
Primary coolant system pressure (MPa(absolute)) 15.51
Thermal design flow rate (ton/hr) 76,300
Effective flow rate for core cooling (ton/hr) 69,500
Reactor vessel inlet temperature (℃) 288.1
Average rise temperature in reactor vessel (℃) 36.9
Heat transfer at normal condition
Fraction of heat generated in fuel (%) 97.4
Core average linear heat rate (kW/m) 15.2
Maximum local peak linear heat rate at FQ=2.6 (kW/m) 39.5
Power density (kW/l) 89.2
Specific power (kW/kg uranium) 32.0
Minimum DNBR by WRB-2 correlation
At nominal condition; for typical hot channel
for thimble hot channel
2.05
1.98
During AOO; for typical hot channel
for thimble hot channel
> 1.35
> 1.33
Maximum fuel centerline temperature during AOO (℃℃℃℃) < 2548
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 16
8AS-EXP-20130003
Safety of
Mitsubishi Advanced PWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 17
8AS-EXP-20130003
Structure of Emergency Core Cooling System
Conventional 4-loop PWR US-APWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 18S
pra
y H
ead
er
Sp
ray H
ead
er
Sp
ray H
ead
er
Sp
ray H
ead
er
Sp
ray H
ead
er
Sp
ray H
ead
er
Sp
ray H
ead
er
Sp
ray H
ead
er
RWSP
8AS-EXP-20130003
Features and Strengths in ECCS
� Four independent safety trains
• Four-train mechanical safety systems
• Four-train electrical safety systems
• No inter-connecting piping between trains
� Direct vessel injection (DVI)
• The cooling water from the safety injection pumps is directly injected into
the reactor vessel.
� Refueling water storage pit (RWST) inside the containment
• Operation of changing the suction from the RWST to the containment
recirculation sump is eliminated.
� Advanced accumulator (ACC)
• An advanced accumulator is connected to each cold leg to refill the
reactor vessel lower plenum and down-comer immediately after a LOCA.
� No low-head safety injection system
• Installation of ACCs enabled us to eliminate low-head safety injection
systems, which resulted in reduction of the number of active components.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 19
8AS-EXP-20130003
Schematic Flow Diagram of ECCS
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 20
8AS-EXP-20130003
Advanced Accumulator having two flow rates
Nitrogen
Injection
Water
Flow Damper
High Flow Rate Mode
Injection Water
Nitrogen
Flow Damper
Low Flow Rate Mode
Main stand pipe
Side inlet
Side inlet
• A short while high flow rate of cooling water is required just at early stage
of LOCA, a large volume of water is injected to fill up the down-comer.
After that, the flow rate is reduced to the amount necessary for decay heat
removal. Advanced accumulator system has a longer supplying duration
that can cover the time expected to the low pressure injection system.
• This design makes it possible to eliminate the LPIS, which leads to the
reduction of active components.
Conventional Design
Advanced Accumulator
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 21
8AS-EXP-20130003
State-of-Art Technology
for Digital Instrumentation &
Control System of
Mitsubishi Advanced PWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 22
8AS-EXP-20130003
Full Digital Instrumentation & Control System
• Fully digitalized technology is applied to the instrumentation and control
system (I&C system) for both safety and non-safety functions.
• The reactor protection system and actuation system of engineered
safeguard features (ESF) have 4-time redundancy in the I&C system.
• Conventional operating and monitoring devices such as switches and
indicators have been eliminated, except devices for diverse actuation
system (DAS).
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 23
System Features
Main control board
・Fully computerized
・Visual Display Units (VDU) for safety and non-safety channels
・Limited number of conventional switches and indicators
Safety I&C
・Fully digitalized with Mitsubishi digital controllers
・Four-train redundancy in reactor trip system, ESF actuation system and safety logic
system for component control
Non-safety I&C・Fully digitalized with Mitsubishi digital controllers
・Duplex digital architecture for each control and process monitoring sub-system
Data communication
・Fully multiplexed, including class 1E signals
・Multi-drop data bus and serial data link
・Fiber optics communication networks for noise immunity and required isolation
8AS-EXP-20130003
Full Digital Instrumentation & Control System
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 24
8AS-EXP-20130003
• A large display panel is installed
to display major parameters for
normal and abnormal situations.
Thus, the current status of the
entire plant can be understood by
all crews and their communication
is improved.
• Thus, the digital system provides
significant benefits to the safety of
nuclear power through reduction
in operation works and
maintenance work loads, which
reduces the potential for human
error.
Human Engineering & Control Room Design
• Plant parameters and associated operating switches are displayed on
same screens, and touch screen operations are applied. Thus, the
operator’s work load is reduced and the reliability of operation is
increased.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 25
8AS-EXP-20130003
Diverse Actuation System (DAS)
• Diverse Actuation System (DAS) is installed to
provide back-up actuations for safety and non-
safety components as countermeasures against
common cause failure (CCF) in the software of
the digital I&C system.
• The DAS was designed for beyond design basis
CCF incidents. The DAS consists of diverse
devices from the digital safety system so that a
CCF in the digital system doesn’t impair the DAS
functions.
• The DAS initiates safety functions independent
from the output of the digital safety system.
Manual actuation is provided for all functions.
Automatic actuation is also provided for functions
if the time for manual operator action is
inadequate.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 26
Diverse Human-System-
Interface (HSI) Panel
Switches
Indicators
Alarms
Diverse Human-System-
Interface (HSI) Panel
Switches
Indicators
Alarms
Automatic actuation
system
Automatic actuation
system
Diverse
Trip
Diverse
Trip
Each
Remote
I/O
Each
Remote
I/O
Components
such as pumps, valves
Components
such as pumps, valves
Measured
parameter
signals
8AS-EXP-20130003
Safety Enhancements for
Beyond Design Basis
Accident of
Mitsubishi Advanced PWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 27
8AS-EXP-20130003
Design against Airplane Crash
� Countermeasures against Airplane Crash
• The US-APWR is designed against the airplane crash (APC) by taking
into account the potential effects of the impact of a large commercial
airplane for the building strengths and plant layout.
• The countermeasures for the APC in the US-APWR design:
- Physical / functional separation and segmentation in the layout design
for safety related structures, systems and components (SSCs)
- Reinforcement of structural design of the buildings, which contain
safety related SSCs
• It was confirmed by the assessment that the inherent robustness of the
US-APWR design would be maintained for the followings;
- The reactor core remains cooled or the containment remains intact
- Spent fuel pit integrity is maintained
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 28
8AS-EXP-20130003
� Prevention of severe accidents
1. Reduction of potential precursor of design basis accidents and severe
accidents.
• Reduction of latent LOCA precursors. E.g.;
- Adoption of top-mounted in-core instrumentation system (ICIS) to
eliminate penetrations at the reactor vessel bottom.
- Reduction of reactor vessel welding seams and improvement of
welding methodologies
- Improvement of piping bypassing the containment to a higher rating to
reduce probability of interface LOCA
2. Enhanced reliability in safety functions
• Installation of four-train structure for safety systems
• Installation of refueling water storage pit (RWSP) in the containment
• Installation of advanced accumulators to reduce the number of active
components
• Countermeasures against Anticipated Transient Without Scram (ATWS).
E.g.; Installation of diverse actuation system to cope with common cause
failure in the reactor protection system
Countermeasures against Severe Accidents
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 29
8AS-EXP-20130003
• Countermeasures against station blackout (SBO)
E.g.; Installation of four-train emergency gas turbine generators (GTGs) and
additional alternate power source by two-train GTGs.
• Countermeasures against fire
E.g.; Clear physical separation between the redundant trains of safety
systems
• Countermeasures against the intersystem LOCA
E.g.; Prevention of over-pressurization of the residual heat removal system
� Frequency of severe accidents (PRA result for core damage frequency)
• The result of calculation for US-APWR core damage frequency (CDF)
meets the NRC goal and the Utility Requirements Document (URD) goal.
Countermeasures against Severe Accidents
Requirement NRC URD US-APWR
CDF 1×10-4/RY 1×10-5/RY 3.0×10-6/RY
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 30
8AS-EXP-20130003
� Mitigation of severe accidents (To keep the integrity of the containment
vessel)
• For debris dispersion, reinforcement of depressurization function of the
primary system and an improvement of RV cavity geometry are
considered.
• For quasi-static over pressurization, an usual containment vessel air
recirculation system and an alternative containment spray supplied from
the fire service water system can be used. These systems can be used to
reduce the pressure if the containment spray system is not available.
• As countermeasures to avoid containment vessel damage due to
hydrogen combustion, a hydrogen control system (igniters) is installed to
control the hydrogen concentration.
Countermeasures against Severe Accidents
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 31
8AS-EXP-20130003
Construction Management
of Advanced PWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 32
8AS-EXP-20130003
Total Engineering Capability with “Single Responsibility” in the full areas;
� Conceptual/Basic/Detailed Engineering
� Manufacturing of components
� Erections and installations of structures, systems and components
� Support of human resource development for operation & maintenance
� Technical support after start of commercial operation
Construction Management of Advanced PWR (1)
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 33
8AS-EXP-20130003
Material procurement
and management
CAM*
Welding
inspections
On-site
installation
inspections
Construction
process
management
•CAM : Computer-Aided Manufacturing
Integration
Construction Management of Advanced PWR (2)
� To keep quality and schedule,
MHI’ Data management system
integrates;
� Design
� Procurement
� Manufacturing & Inspection
� Construction
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 34
8AS-EXP-20130003
Construction Management of Advanced PWR (3)
Reactor vessel is
now under processing in
upright installation
position with high-
accuracy & high-quality.
Major Components (Reactor Vessel, Steam Generator, Reactor
Coolant Pump, Reactor Internals, Control Rod Drive Mechanism,
Pressurizer, Turbine, etc.) are manufactured in our hands.
Works and machines have been updated/enlarged and are
prepared for the global deployment.
(Photo)
A reactor vessel is
manufactured by a super-
large combined machine
tool named “Super Miller”.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 35
8AS-EXP-20130003
Construction Management of Advanced PWR (4)
�Rational designs like;• Internal structures using steel plate
reinforced concrete (SC) (left)
• Large modular (prefabricated) block
construction (Right)
�Tools for efficient construction like
Super-large-capacity cranes
which enables on-site welding and
formation of containment vessel.
�Ability for comprehensive coordination
of civil & installation work
40m-dia.
upper
containment
Brilliant Successes
(1st Concrete to Fuel Loading)
2 loop : 34.5 months
3 loop : 37.5 months
4 loop : 40.0 months
Reduction of on-site work volume and construction period
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 36
8AS-EXP-20130003
Operation and Maintenance
Management of
Mitsubishi Advanced PWR
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 37
8AS-EXP-20130003
・・・・Application of world’s first submerged automated guided vehicle with robot・・・・Using a manipulator with 7 shafts
Inspection Technologies for Advanced PWR
Pressurizer
RV
Piping inspection unitUT / ECT for BMI nozzle inspection unit
TOFD-UT ( for sizing )
RV head nozzle inspection unit
ECT probe for J-type welds surfacePhased array type probe for
J-groove welds
SG tubes inspection unit
•Lightweight and compact unit
•Point focus phased array enables high accuracy flaw sizing. (Approx.±±±±3mm)
Censer
Inspections can be done for 4 days by utilizing two units simultaneously. (for 4 loops)
One unit ((((more than 3,000 tubes)))) can be inspected for around 4 days.
RV inspection unit A-UT machine
MHI point focus probe Automated UT unit for piping
Achievement of high accuracy sizing with point focus
capability
Phased array censer
SG
ECT (for detection::::0.5mm)
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 38
8AS-EXP-20130003
Conclusion
MHI developed Advanced PWRs based on accumulation of half-century experiences in construction and operation of conventional PWR power plants.
Proven and advanced technologies have been introduced in APWR to improve economy, safety, reliability, operability and maintainability.
Advanced accumulator was employed to reduce the number of active components, and low pressure injection system was eliminated.
US- and EU-APWR were developed to let them meet regulator’s and user’s requirements including flexible operation. The fuel length was changed to 4.2 meters.
ECCS and supporting systems have 4 divisions in redundancy.
Due to enhancements in safety systems, the total of the CDF is estimated 3.0x10-6 /RY in a PRA calculation.
MHI’s manufacturing and construction management is integrated to one data base system to accomplish them with high quality, high reliability and strict keeping of schedule.
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 39
© 2013 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.8AS-EXP-20130003
Thank you for kind attention!
Design Control Documents of the US-APWR are found on;
http://www.nrc.gov/reactors/new-reactors/design-cert/apwr.html