Overview of 10 PRB Sites and Upcoming Projects · Overview of 10 PRB Sites and Upcoming Projects...
Transcript of Overview of 10 PRB Sites and Upcoming Projects · Overview of 10 PRB Sites and Upcoming Projects...
LüneburgBuxtehudeSuderburg
Universityof Applied Sciences
FachhochschuleNordostniedersachsen
ww
ww
ww
.rubi
n.ru
bin --
onlin
e.de
onlin
e.de
PRBs in Germany and AustriaOverview of 10 PRB Sites
and Upcoming Projects
Volker BirkeHarald BurmeierDiana Rosenau
n Two R&D networks(funded by the Federal Government)
“SAFIRA“ (6 Mio $)Basic R&D, semi-technical scalereactive materials for cVOCs/chlorobenzenes/PAHs
“RUBIN“ (4-5 Mio $)R&D and technical implementation of PRBs at different sites across the country
nPublic funds spent ≈ 14 Mio $nDifferent private sites ≈ 6 Mio $
PRBs in Germany
Bernaun High contamination of cVOCs affecting two
aquifers (TCE up to around 100 mg/L)
n Special reactor design capturing bothaquifers by pumping GW and injecting it into a collecting zone and additional tanks
n Closed funnel = containment for the source and serving as a collecting/mixing zone for accumulating lifted GW before it enters the gate
nn RUBIN project, volume: RUBIN project, volume: apprappr. 1.5 Mio $ . 1.5 Mio $ (50 % public funds) (50 % public funds)
Cut-off wall Cut-off wall
Bracing Bracing
2 x 2 2 x 2 2 x 2 2 x 2 2 x 2 2 x 2 2 x 2 Unterwasserbetonsohle
NE SW
Surface level
“Containment”
Inflow
Inflow
Reactor elements (modules) Drain
GWMS
Cut-off wall
18.30 m
2.30 m below s.l.
4.50 m below s.l.
5.50 m below s.l.
8.0 m below s.l.
Re-infil-tra-tion
BernauElevation of the gate system
0 10 20 30 40 50 m
Top view of the funnel-and-gate
system
0
40000
80000
120000
0 400 800 1200
mittlere Aufenthaltszeit [min]
Bernau – PerformanceTCE-Decay in the PRB
c(o)= 96,5 mg/L
0
25
50
75
100
R1 R2 R3 R4 R5 R6 R7 R8 R9 R10
[mg
/L]
Decay of cis-DCE and VC in the PRB; c(o)= 96,5 mg/L
0,00
0,05
0,10
0,15
0,20
0,25
R1 R2 R3 R4 R5 R6 R7 R8 R9 R10
[mg
/L]
c-DCE VC
Konzentrationsverlauf Einzelstoffe- halblogarithmische Darstellung -
0
1
100
R1 R2 R3 R4 R5 R6 R7 R8 R9 R10
[µm
ol/L
]
TCE c-DCE VC PCE
Concentration profiles of single components
- semi-logarithmic display -Field results (appr. after one
pore volume has been
exchanged)
Bitterfeld (“SAFIRA“)n Semi-technical test site for new PRB materials; five shafts (30 m deep, 3.50 m Ø) containing diff. steel reactors, loaded with different media:
n Microaerophilic, anaerobic reactors (aquifer material)
n Combined media, e.g., GAC/microbiol.; ZVI/ORC)
n Membrane- and zeolite-supported Palladium (Pd)
n Catalytic oxidation using metal catalysts; ultrasound
http://safira.ufz.de
Membrane-supported Pd/H2 rapidly dehaloge-nates monochlorobenzene (MCB) to benzene
Denkendorf
n cVOC contamination (TCE, PCE, cis-DCE, 1,1,1-TCA, VC) is treated with GAC
n “Drain-and-Gate” PRB to meet the low hydraulic gradient of 2%:
90 m long and 6 m deep gravel drainage directing the flow right towards a single GAC reactor
n GAC reactor was placed inside a shaft (6 m deep)
street
Köngener Straße
Heerweg
REWE-Markt
Baierl & Braun GdbR
ESA Eppinger GmbH
Fa. Goldmann- Nörenberg
Körsch
Sulzbach verdohlt
GWM12
N
0 50 m 100 m
Lage der Drainage Reaktorbauwerk
Rewe- Supermarkt
LHKW-Verunreinigungen
M2 M3
M6
M8
BGW12 BGW11
GWM8
BGW8
BGW1
BGW10 GWM13
BGW9 GWM2
GWM4 GWM3 BGW3 BGW4 GWM10 GWM9 Spülschacht GWM11
GWM7 GWM6
BGW13 BGW7
GWM5 BGW5
UVB Grundwasserfließrichtung
REWE-Markt
Baierl & Braun GdbR
ESA Eppinger GmbH
Fa. Goldmann- Nörenberg
Körsch (stream)
GWM12
N
0 50 m 100 m
Drainage Reactor (shaft)
Rewe- Supermarkt
Areas of cVOC contamination
M2 M3
M6
M8
BGW12 BGW11
GWM8
BGW8
well
BGW10 GWM13
BGW9 GWM2
GWM4 GWM3 BGW3 BGW4 GWM10 GWM9 Spülschacht GWM11
GWM7 GWM6
BGW13 BGW7
GWM5 BGW5
UVB GW flow direction
street
creek
(creek)
street
Overviewof the drain-and-gate system
Denkendorf West East South North
Aquitard
app. 90 m app. 60 m
Cohesive material
Filter gravel
Drainage tube (DN100)
Water table
Palladium on zeolite
3 m
Activated carbon
Outlet tube (DN150) Receiving water (Körsch)
Pump Water table 6 m
Denkendorf
RUBIN project:
n Bypass: hydrogenation catalysts like palladium on zeolite are tested
n Addition of hydrogen gas:
fast and complete degradation of cVOCs
(first, small column experiments in the first quarter of 2002: especially VC is effectively degraded, too)
Edenkoben
n cVOCs (20% TCE, 50% cis-DCE, 30% 1,1,1-TCA)
n 1998: pilot-scale F&G 2000: expanded to a full-scale F&G
nGates designed for a diverted, verticalflow insideGroundwater is passively lifted by a vertical drainage (gravel columns) and thus directed through the ZVI bed
Edenkoben
nSix identical gates, each constructed as a sheet pile caisson (open at its bottom)
nFunnel: continuous sheet pile wall, 430 m long, 14 m deep
nFunnel also runs through every gate, thus separating each of them into two chambers
n Inside the gates the sheet pile wall was buried down to 1 m below the lowest groundwater level anticipated = overflow weir between the chambers
Ansicht nach Herstellung
G 3
G 6
Pilot-Test 1998:
Gate: 33 ft.
Funnel: 60 ft.
1.500 ft.
G 2
G 1
G 4
G 6
Full-scale 2001
1.440 ft. length40-50 ft. depth6 gates - (825 t Fe°)
G 5
Edenkoben
PESCHLA + ROCHMES PESCHLA + ROCHMES GMBHGMBH
wwwwww..gprgpr.de.de
ZUSTROMABSTROM
DICHTHORIZONTAQUITARD
GATESheet Pile Caisson
FUNNELSheet Piles
PEA GRAVELColumns
Fe° REACTOR
InfluentEffluent
Position and shapeof the F&G PRB
Gate design
Edenkoben
Validation of cVOC degradation six months after installing the pilot gate
1
10
100
1000
10000
0 10 20 30 40 50 60 70
residence time in the reactor in [h]
conc
entr
atio
n in
µg/
l
PCE TCE cis DCE 111 TCA 11-DCA VC Summe
PCE
TCE
cis DCE
VC
11 DCA
111 TCA VC: 4%
cis: 25%
11 DCA: 71%
Downstream Results:
Karlsruhe
n 2000/2001: full-scale F&G packed with granular activated carbon (GAC, 150 tons) to treat PAHs and BTEX
n Funnel consists of sheet piles (200 m long, 17 m deep)
n Eight gates consisting of specifically perforated steel; cylindrical steel tubes were lowered into previously set up, large diameter boreholes (2.5 m)
Karlsruhe
Overview of the full-scale F&G PRB
Former gas works plant
Karlsruhe
nPea gravel, serving as a filter medium and for homogenizing the flow through the gates, was packed at the inflow and outflow zone
Clay seal Clay seal
Pea gravel
Sheet pile wall Activated
carbon inflow
outflow Perforated steel sheets
nFree space left between the steel tubes and the adjacent funnel segments was sealed off using clay
Karlsruhe
Sheet piles were pressed into the ground using the “silent piler”-technique
Packing the gate with granular activated carbon
Oberurseln cVOC contamination treated with ZVI at
the BOSTIK site (TOTALFINAELF)n L-shaped F&G equipped with one gaten Gate shaped like a wide annulus:uDiameter 3.3 m, 13 m deepuOverlapping boreholes cast with
concrete forming the annulus(at the inflow/outflow zone, permeable concrete was cast)
n Funnel (slurry wall): 175 m long, 4-19 m deep, 0.6 m thick
OberurselGate construction
Oberursel
Gate construction, shape of the F&G
Tübingenn 1998: Installation of a full-scale F&G system at
the BEKA site (Neckar valley)n ZVI to treat a plume of cVOCsn L-shaped funnel (slurry wall, 215 m long, 0.6
m thick, 8-11 m deep) with 3 gates
Tübingen
Gate constructionn upstream and downstream pea gravel filter zones
were emplaced by overlapping boreholes
Tübingen
n ZVI were emplaced right between the pea gravel filter zones using the same technique
n Within the iron zones, cVOC concentrations decrease to below detection limits
n However, downgradient of one gate a slight increase in cVOC levels compared to the values in the iron zone is found
n Performance of the BEKA PRB will be scrutinized in a member project of the network RUBIN (University of Kiel)
Reichenbach
n 2000: representing the first full-scale adsorptive continuous reactive barrier (CRB) in Germany
n A homogeneously distributed cVOCcontamination of the groundwater had been identified
n Non-overlapping boreholes diameter 0.25 m each aligned in two parallel rowspacked with GAC
CRB (20 m long, 7 m deep) had to be erected directly inside a manufacturing hall (2000)
Reichenbach
Reichenbach - Performance
Rheinen 1998: representing the first installation of a
pilot-scale CRB in Germany (22.5 m long, 6 m deep, 0.6-0.9 m thick, overlapping boreholes), circular steel caisson installation
n Primary contaminants: PCE and cis-DCE,plume: 400 m long, 200 m broad
n Barrier contains two types of ZVI:uGranular iron mixed with gravel at 1:2
(v/v) (69 tons, wall segment 10 m long)u “Iron sponge” (85 tons, 12.5 m long)
RheineThree Three RUBIN-project(s):(“Mull und Partner GmbH”, University of Kiel, Technical University of Berlin)uEffects of precipitation and differences in
the composition of the reactive materialsuScrutinizing the surface properties of the
ZVI typesuCharacterization of microorganismsuGathering more geological and hydrogeo-
logical data due to the heterogeneous and apparently instationary plume
Herstellung mittels Großbohrungen
Rheine
Reactive barrier
Groundwater-flow
ZVI
Monitoringwell
Canal
Monitoringwell
Pilot CRB (1998): overlapping boreholes; two ZVI types (granular and “sponge”), packed apart in two segments
Coring(Nov. 2001)
Rheine
Rheine – Performance
80
82
84
86
88
90
92
94
96
98
100
17.17
.98
30.09
.98
01.10
.98
11.11
.98
03.12
.98
07.01
.99
20.01
.99
04.02
.99
04.03
.99
19.05
.99
17.06
.99
27.09
.99
17.12
.99
22.02
.00
14.08
.00
31.01
.01
23.05
.01
Deg
rad
atio
n o
f P
CE
[%
]
0
10
20
30
40
50
60
70
80
90
100
Inle
t co
nce
ntr
atio
n [
mg
/l]
Inlet granular iron
Inlet iron sponge
Degradation ongranular iron
Degradation oniron sponge
Brunn am Gebirge AUSTRIA
11
www.geol.at technical geology niederbacher
site: former industrial plant
§ tar plant
1878 - 1932
§ linoleum production
1933 – 1965
area 60.000 m²
12
www.geol.at technical geology niederbacher
§ result of more than 100 years of industrial land use
§ solid and liquid residuals of tar
and linoleum production
Site fundamentals
Brunn am Gebirge AUSTRIA
33
www.geol.at technical geology niederbacher
Pannonian shales CONFINING LAYER
g w - p o n d westf o r m e r g r o u n d l e v e l+214rg m SL s i l t y , s d . g r a v e l QUATER-
N A R Y
© NIEDERBACHER 2001 o u t l e t t r e a t e d w a t e rdrainage s h a f t
adsorptive r e a c t o r
cont. G W e n t r yf i l t e r w i n d o w
impermeable b a r r i e r
collector s h a f tmeasurement s h a f t
AC- r e a c t o r
6 3
induced GW-flow towards AR&B
hydraulic barrier
groundwater contamination
man made pond
in-situ adsorptive reactors
Brunn am Gebirge AUSTRIA
38
www.geol.at technical geology niederbacher
confining layer
aquiferjet grouting wall
injection of bentonite –cement suspension
trenchwell
SYSTEM IMPLEMENTATION
barrier construction
length 220marea 1000m²depth 2 – 6m
thickness 1–1,4mmin. thickness 0,5mcut into confininglayer 1-1,5m
Offenbach (upcoming), RUBIN
n Specifically designed F&G (microbiology + GAC), BTEX/PAH plume (former tar processing plant)
n Funnel: 120 m long sealing wall, vertically arranged to the groundwater flow; sheet pile wall intercepts the aquifer flow in front of the reactor
n Gravel zone in front of the sheet piles, filter pipes for diverting the groundwater flow vertically towards the reactor and for adding required/suitable electron donorsu Microbiological degradation in the 8 m long gravel
zone inward the reactor (1.5 days residence time)u Activated carbon (additional adsorbent for some PAHs
that cannot be readily degraded biologically)
Offenbach (upcoming)
Clay
Gate (cross-section)
Well
G
oundwater flow
Aquitard
Cut
-off
wal
l(te
mpo
rary
dur
ing
con
stru
ctio
n)
Cut
-off
wal
l(t
empo
rary
dur
ing
con
stru
ctio
n)
Sorption
Filter tube Degradation of
Naphtalene, BTEX
Fe precipitation
Water table3 m
Cut
-off
wal
l
Filter gravel
2 m
Filter gravel
8 m
Filter gravel
1 m
InletG
oundwater flow
Outlet
Filter gravel C
ollector
Filter tube
Dosing and mixing ofNitrate and H 2O2
Back-flushing Monitoring sensors
Cut-off wall
Filter gravel D
istributor
Wiesbaden (planned), RUBIN
n Applicant HIM GmbH, ASG, Wiesbadenn Co-operation Partners
- Peschla + Rochmes GmbH- University of Kiel- Technical University of Hamburg-Harburg
n Kind of PollutantsDifferent arsenic compounds
Wiesbaden
As contamination > 7.000 mg/kg
As contamination > 10.000 mg/kg
Groundwater flow
Sampling point
Foot path
Downgradient reactor (pilot gate)
River Rhein
Upgradientreactor
Plan of site
NUpgradient (reactive wall): readily oxidizable Corg-phases, solid phases consistingof sulphate
Downgradient (F&G): iron oxide (adsorptive fixation of arsenate),non-redoxsensitive sorbents
R&D/Spanning RUBIN Projects
University of Kiel, Prof. Dr. A. Dahmkein co-operation with Dr. R. Wienberg, HamburgEvaluation and Further Development of Pre-investigation, Monitoring and Quality Management Regarding Reactive Walls - A Comparative Laboratory and Site Study -
University of Tuebingen, Prof. Dr. G. TeutschComparative Technical and Economical Assessment of In-Situ Permeable Reactive Barriers
University of Applied Sciences of North-East Lower Saxony, Suderburg, Prof. H. BurmeierCo-ordination of the Large Scale R&D Program RUBIN and Making up a Comprehensive Documentation and Manual
Conclusions§ 2002: Germany – 9 PRBs, 2 planned; Austria – 1 PRB
§ PRBs with “directed GW flow“ prevail (7 in total, F&G, “drain-and-gate“ and modified F&G systems (partly applying pumping))
§ Reactors/gates often installed/accessible nearby the surface – Germans and Austrians“love control“?!
§ ZVI and GAC: preferred reactive materials
Conclusions (cont.)
§ The need for new materials to meet complex pollutant mixtures is an important issue; novelmedia are therefore intensively investigated
§ German PRBs: ≈ 14 Mio $ public funds
§ Some German PRBs do not meet remediation goals (e.g., 10 µg/L cVOCs)
§ Some German PRBs are facing hydraulic problems (after 2-3 years of operation)
Special thanks to:§ Peter Hein („INGAAS GmbH“, Berlin, for Bernau)§ Theo Woll, Michael Rochmes („Peschla & RochmesGmbH“, Kaiserlautern, for Edenkoben)§Wilfried Möller, Martin Wegner („Mull und Partner GmbH“, Hanover, for Rheine)§ Kerstin Schmidt, Markus Schleyer („ARCADIS GmbH“, Karlsruhe, and „Stadtwerke Karlsruhe“, resp., for Karlsruhe)§ Peter Hartwiger (for Reichenbach)§ Hermann Schad, Christoph Schüth („I.M.E.S. GmbH“, and University of Tübingen, resp., for Denkendorf)§ Peter Niederbacher (for Brunn am Gebirge)
University of Applied Sciences-NE Lower Saxony, Suderburg
Department of Civil EngineeringWater and Environmental Management
Office Hanover
Prof. Harald Burmeier Dr. Volker Birke Dipl.-Ing. Diana Rosenau
Co-ordination Group of RUBINSteinweg 4, D-30989 Gehrden
voice +49 5108-9217-30
[email protected] [email protected] [email protected]
www.rubin-online.de