Overview & Introduction to the generation plan.
Transcript of Overview & Introduction to the generation plan.
Overview & Introduction to the generation plan. • Master plan . • existing generation system . • Combined cycle.
Overview & Introduction to the transmission network. • Existing network.
• Reinforcement.
Overview & Introduction to the distribution network. • Existing network.
• Energy consumption.
• Challenges.
Renewable energy program. • Generation side
• Solar + Wind sites
• Distribution side.
Issues to be addressed.
Future strategy.
Summary.
The presentation covers a time span extending to the years (2017-2030)
Includes all the major components of electricity sectors (Generation, Transmission, Distribution & Renewable energy).
Gives the urgent needs to be addressed
o 25 Year of war & lack of investment. o Significant damage to power plants, substations & transmission
lines. o 12 Year of sanctions had deprived (M.E) of any assets & resources
to maintain or expand system accompanied by degradation. o These challenges had led (M.E) to prepare a very powerful Master
Plan. o Fast Track gas power units contracts were singed in (2008-2009) o Actual start of Master Plan was 2008 when the Mega Deal to
supply 56/GE F9Es (7000MW) + 18 unit/Siemens (3200MW) was actually budgeted and signed December 2008.
o Installation of Mega Deal power units was delayed to 2010 due to the need for EPC contracts formulation consultations and
assignment of budget.
13000 MW (2012-2015)
7000 MW (2012-2017)
400 MW (2013-2016)
4000 MW (2013-2017)
1130 MW (2012)
o No more Diesel plants after 2012.
Kirkuk
Steam, Gas turbine & Diesel projects (2012-2015)
Nenawa :6x125MW
Akkaz :2x125MW
Akkaz2 :4x30MW
Khairat :10x125MW Kerbala :2x125MW East Kerbala : 300MW
Hilla :2x125MW
Haydariya :4x125MW
Quds : 4x125MW Taji :4x40MW
Saddir :2x169MW
Rumaila :5x292MW Shat Al-Basra :10x125 MW
Najibiya : 4x125MW
Dewaniya :4x125MW North Dewaniya : 200MW East Dewaniya : 200MW
Dibis : 2x169MW
Dibis2 : 2x169MW Taza :1x292MW
Bazurgan :2x60MW
Amara :4x125MW North Amara :200 MW
Mansuriya : 4x185MW
Samawa :4x125MW
Nassiriya : 4x125MW
Baiji :6x169MW
Al-Shamal :4x350MW
Salah Al-deen :2x630MW
Anbar (CCGT) : 1500 MW
Yousfiya :3x210MW Zubaidiya :2x610MW Zubaidiya2 :4x330MW
Mukhliss Kafi : 230 MW
Plant Type. Capacity (MW)
Steam Turbine + CCGT
6330
Gas Turbine 13420
Diesel 1130
Total 20880
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
2012 2013 2014 2015 Total
1500
7500 7500
3500
20000
Expected capacity Additions (MW) 2012-2015
4.5
9
13.5
18
22.5
27
2012 2013 2014 2015 2016 2017
- Financial Requirements (2012-2017) Excluding the Budget Already Spent/and or Assigned for Mega Deal & EPC Projects Generation: 14 BUSD
Transmission: 5 BUSD Distribution: 8 BUSD
4.5 BUSD/Yr.
• The net power delivered to consumers is around 7000MW due to losses
Power cuts up to 14 hours daily.
9
21
2 2
6
0
5
10
15
20
25
Industrial Domestic Commercial Agricultural Governmental
Cost of economy losses (US billion dollars per year )
according to consumer categories due to power cuts
To be announced
All existing and new gas power plants operated on natural : First stage gas will be converted from simple cycle to combined cycle.
gas power plants operated on crude oil or heavy new All: Second stage fuel oil will be converted to combined cycle when
operated on natural gas.
Combined Cycle conversion
( Nominated Power plants)
Rumaila: 1450+700 MW. Najibiya:500+250MW.
Shat Al-basra:1250+600MW.
IRAN
Syria
Power Plant: Single Cycle (MW)+ Combined Cycle (MW)
Diwaniya : 500+250MW.
Al-Anbar :1000+500MW. Al-Mansuriya:740+300MW.
Amara :500+250MW.
Kirkuk (Taza):292+125MW. Kirkuk
Al-Saddir :338+150MW.
Al-Khairat :1250+600MW.
Samawa :500+250MW.
Nassiriya:500+250MW.
Estimated Fuel Burn in 2011
23%
33% 12%
32% Crude Oil
Fuel Oil
Gas Oil
Natural Gas
Major Load Centres
10%
30%
10%
Existing Transmission and
Distribution Network
GenerationGenerationTransmission
Network
Distribution
Network
System
Load
400
kV
11 kV
132 kV
11 kV33 kV11 kV33 kV
GenerationG
G
11 kV 11 kV
LOAD
LOAD LOAD
LOAD
Reinforcement of the Existing
Transmission Network
Exist Under-construction ,future
(2012-2015)
400 kV Substations 25 19
400 kV Overhead Lines 4900 km 1500km
132 kV Substations 210 75
132 kV Overhead Lines 12,500km 2500km
• Plan to implement flexible AC systems (FACTS) is under
development
Long Term Transmission Plan 2016 - 2030
Three Scenarios for Energy Transfer
• Scenario A:
Build Power Plants near Gas Resources and build EHV lines to transfer
power between zones and towards Baghdad
• Scenario B:
Build Power Plants near Demand Centres and supply gas to power
plants by building gas pipe lines
• Scenario C:
Utilizing the MoO Gas and Pipe Lines development but also develop
EHV lines for power transfer. This scenario is midway between A and B.
Which Scenario is the least cost solution for Iraq?
Long Term Transmission Plan Demand ( and availability of )and Fuel (gas) Geography
(Available)G
as
Demand
10%
10%
12%
19%
11%
11%
30%
35% 10%
o 33 kV , 11kV , 0.4 &0.23 kV.
o Very large asset base.
o High proportion of aged equipment.
o Maintenance program likely to be affecting asset life.
o Rapid rise in demand leading to restricted supply
o More investment in both infrastructure & training are required.
Energy Consumption
46% 20%
3%
5% 26%
domestic
industrial
agricultural
commercial
governmental
• The domestic demand is the highest , demand side management program is
under development.
o Distribution investment must be parallel with generation expansion plan (20000 MW).
o Significant investment will be required to maintain existing capacity.
o Large capacity development program required.
o Increase the reliability and efficiency (Demand side management).
1. Rehabilitation of the existing network.
2. Adding 400 (33/11 kV)substation.
3. Energy efficiency programs.
4. Smart meters.
o In 2011 “Renewable energy & Environment
Center” was established.
o Renewable Energy programs have been
approved in both Generation & Distribution
sides.
o Solar Potential in IRAQ:
o 5.7 kWh/Day.
o 2050 kWh/Year.
o Utilize solar & wind power to supply
small isolated locations that cannot
economically be connected to the grid .
o Install “on grid” & concentrated solar
power (CSP) plants in later stages.
o The first stage is to utilize solar and wind
power to supply ten isolated areas:
• Total capacity : 43 MW.
• Total cost ( Estimated ) : 200 MUSD.
• Current status : Tendering
• Expected date of operation : 2013
Renewable Energy program
Phase one:
Solar + Batteries
+Wind turbines
18 hour energy supply
Methodology
Renewable energy sites
Al-waleed border point
Treibeel border point
Al-sheeb
Al-shelamcha
Al-salman
Bssaiya
Al-nekhaib
Al-rahmaniya
IRAN
Syria
Al-rufei
Bazurgan
Al-sa’ad
The renewable energy target is to reach 2% of the
available power by the end of 2016.
0
50
100
150
200
250
300
350
400
450
2012 2013 2014 2015 Total
Expected capacity additions from Renewable energy to grid (2013-2016) MW
2013 2014 2015 2016
o Renewable energy (solar & wind) are promising ,
but technical and regulating measures are required
to unleash their potentials.
o Detailed solar atlas of Iraq need to be created.
o Detailed wind atlas of Iraq need to be created.
o Legislation ,incentives should be issued to
promote renewable goals.
o Technical assistance infrastructure of the
center is required.
o Solar water heaters.
o Air-conditioning solar systems.
o Lighting (L.E.D).
o Domestic self generation units (PV).
o It’s Anticipated that the generation will match the demand during the year 2015.
o Two strategies :
o 2012-2015 : o Capacity additions to satisfy the unmet demand.
o 2016-2020 : o Reduce demand (Demand side management). o Large scale conversion of the gas turbines in the plants of the “ Mega Deal” from burning crude oil or HFO to burning Natural gas . o Large scale conversion of the simple cycle gas turbine units to
combined cycle units. o Mapping technical potentials (Solar , Wind , Waste & Bio energy)
Present and future strategies
Strategies for the years (2012-2020)
12000
14000
16000
18000
20000
22000
24000
26000
2012 2013 2014 2015 2016 2017 2018 2019 2020
Load forecast (High) Strategy
G=D
Capacity additions to
meet the demand
• Reduce Demand.
• Conversion of Gt units to burning N.G
• Combined cycle units (CCGT).
• Renewable Energy.
Iraq Interconnection lines with neighbors
132kV tie line
400kV tie line
Under construction
Stopped
Planned
Syria
I.R.Iran
Kuwait
Turkey
Iraq is a member in EIJPLLST electric
inter-connection Project :
o Qa’im- Tayem
(Iraq) (Syria)
o Mosul- Cizre (Under construction)
(Iraq) (Turkey)
A. Electricity
Iraq have three 400kV on going tie lines
with I.R.Iran:
o Diyala4 - Mersad4
o Amara4 - Kerkha4
o Khor Al.zubair - Khorm shaher
A. Electricity
Iraq Plans to connect with Arabian Gulf network through
several Tie lines in future.
As a result of what had been shown in the previous slides
Iraq would be the electricity exchange node among
EIJPLLST countries , Iran , Gulf & Europe networks.
A. Electricity
9
8
6
7
3
5
6
1
Baiji - Mishraq Junction Gas Pipeline 18”
Baiji - K3 - Fertilizer 16”
Strategic Gas Pipeline 24” Under-construction 2011
350 MMscf
Strategic Gas Pipeline 18” 70-150 MMscf (Under-rehabilitation)
Kirkuk- Taji Gas Pipeline 16”
North Gas
K3
PS4
PS3
PS2
G.T.U
On operation Pipeline
Suggested Pipeline Under-construction Pipeline
Damaged Pipeline
Suggested Gas Complex
Natural Gas Compressor
42”=1000 MMscf, Or
48”=1200 MMscf. Planned in 2014-2015
42” Planned in 2014
42” Under-construction
10
2
4
7
B. Oil & N.gas
Iraq have a huge reserve of both :
• Fossil Fuel.
• Natural gas.
Electricity power plants face problems in
availability of natural gas for the moment ,
so it mostly operate depending on fossil
fuel.
B. Oil & N.gas
Ministry of oil implemented a huge plan to build
sufficient infrastructure in both production and
transportation of oil & natural gas through all
country pipelines grid.
Iraq through these two under-construction
pipelines grids can be considered a
transportation node between Arabian Gulf and
I.R.Iran (oil & Natural gas) to Europe.
o A lot of work has been done already.
o M.E have made a lot of progress , but there is still a great work to deal with, but it is setting itself up for the future
o The ministry now has the planning tools and needs training and Consultations to carry-on the planning process
Summary
o Iraq’s economy has started to accelerate.
o (Oil & Gas) output & revenues are increasing
o Major projects are planned.
o Investment in electrical sector in Iraq (2012-2030) estimated to be 75 BUSD:
• Generation 35 BUSD • Transmission 10 BUSD • Distribution 30 BUSD.
Summary